Slope repair system

By setting up a combination solution of drainage components, backfill support and greening components on the slope, the problem of poor growth environment of green plants in the prior art is solved, the survival rate of green plants is improved, and the stability of slopes is enhanced. Aesthetic.

CN221956750UActive Publication Date: 2024-11-05ZHEJIANG INST OF COMM CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420285076.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-06
Publication Date
2024-11-05
Estimated Expiration
2034-02-06

AI Technical Summary

Technical Problem

While taking into account the low destructiveness and protecting the ecology, existing slope restoration technology is difficult to ensure the growth environment of green plants, resulting in low survival rates of green plants and is susceptible to erosion and damage during heavy rainfall.

Method used

A combination of drainage components, backfill support and greening components is adopted, including setting up drainage components on the slope to drain water, backfill support to repair the surface shape, and setting up step structures and graft grooves on its surface, and implanting water-retaining structures to Provide moisture and growth space to ensure the growth environment of green plants.

Benefits of technology

It effectively improves the survival rate of green plants, avoids the destructiveness and ecological damage of traditional restoration methods, and prevents the green plants from being washed away during heavy rainfall, ensuring the stability and aesthetics of the slope.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221956750U_ABST
    Figure CN221956750U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of slope repair, and discloses a slope repair system. The slope repairing system comprises a drainage assembly, a backfill supporting body and a greening assembly. The drainage assembly is arranged on the side slope and used for draining water in the pit out of the side slope. And the pit is filled with the backfill supporting body so as to repair the surface morphology of the side slope. The greening assembly comprises vegetation grooves and a water retention structure, step structures are arranged on the surface of the backfill supporting body in the inclination direction of the slope, a plurality of vegetation grooves are formed in each layer of step structure at intervals in the extending direction of the step structure, the vegetation grooves in the two ends of each layer of step structure communicate with the outside, and the adjacent vegetation grooves located in the same layer of step structure communicate with each other. Green plants can be planted in the vegetation grooves, and the water retention structures can store water so as to provide water for growth of the green plants. According to the slope restoration system, pits in the slope are restored under the conditions of small destructiveness and ecological protection, meanwhile, a good environment can be provided for growth of green plants, and the survival rate of the green plants is increased.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of slope repair, in particular to a slope repair system. Background Art

[0002] The slopes with a certain slope on both sides of the roadbed are called side slopes. When a geological disaster occurs, local collapse will occur on the slope surface to form pits, which will cause the slope to become unstable and seriously affect the stability of the roadbed. Therefore, the pits on the side slopes need to be repaired. Slope repair can be done by brushing and excavation. This method causes large construction disturbance, takes a long time to complete, is expensive, and damages the ecology. Based on this, a repair method that takes into account both low destructiveness and ecological protection has emerged.

[0003] For example, patent CN218116500U discloses a repair structure for water-damaged pits on the side slopes of highway cuts, which repairs the pits on the side slopes by setting a filling body, and plants a green layer on the filling body to achieve the effect of aesthetics and ecological protection. However, the repair structure directly lays a green layer formed by vegetation bags, flexible protective nets and thick layers of sprayed substrate on the surface of the filling body for greening, which makes it difficult to ensure the water source and growth environment required for the growth of green plants. There is a risk of green plants dying in the later stage, and the green layer on the surface of the supporting body is also easily washed away and damaged during heavy rainfall. Utility Model Content

[0004] The purpose of the utility model is to provide a slope repair system, which can repair pits on the slope while taking into account low destructiveness and ecological protection, and at the same time can provide a good environment for the growth of green plants and improve the survival rate of green plants.

[0005] To achieve this purpose, the utility model adopts the following technical solutions:

[0006] A slope repair system is provided for repairing pits on a slope surface, comprising:

[0007] A drainage assembly, disposed on the side slope, for draining water in the pit to the outside of the side slope;

[0008] Backfilling the support body into the pit to repair the surface morphology of the slope;

[0009] A greening component, the greening component includes a planting groove and a water retention structure arranged in the planting groove, the surface of the backfill support body is provided with a step structure along the inclination direction of the slope, each layer of the step structure is provided with a plurality of the planting grooves at intervals along its extension direction, the planting grooves at both ends of each layer of the step structure are connected to the outside, the planting grooves located on the same layer of the step structure and adjacent to each other are connected, green plants can be planted in the planting grooves, and the water retention structure can store water to provide water for the growth of the green plants.

[0010] Preferably, the water-retaining structure includes a water-retaining pad and a plurality of water-retaining rods, wherein the plurality of water-retaining rods are arranged on the water-retaining pad at intervals, and a plurality of limiting holes are arranged on the bottom wall of the planting groove. The plurality of water-retaining rods can be inserted into the plurality of limiting holes one by one to limit the water-retaining pad in the planting groove.

[0011] Preferably, the water-retaining structure also includes a water-retaining side plate, which is circumferentially arranged on the side of the water-retaining pad facing away from the water-retaining rod, and the water-retaining pad and the water-retaining side plate together form a trough structure with the same shape as the planting trough, the water-retaining pad is in contact with the bottom wall of the planting trough, and the water-retaining side plate is in contact with the side wall of the planting trough.

[0012] Preferably, a first channel is provided at both ends of the step structure, one end of the first channel passes through the side wall of the step structure, and the other end is connected to the planting groove located at the end of the step structure, and a second channel is provided between adjacent planting grooves, and both ends of the second channel are respectively connected to adjacent planting grooves, and the first channel can be connected to an external water source to replenish water into the planting groove.

[0013] Preferably, the height of the connection position between the first hole and the planting groove is higher than the height of the connection position between the second hole and the planting groove.

[0014] Preferably, a plugging piece is provided in each of the first channel and the second channel, and the plugging piece is made of polyurethane sponge.

[0015] Preferably, the drainage component includes a first drainage ditch, a second drainage ditch and a rapids trough, the first drainage ditch is arranged at the foot of the slope, the first drainage ditch is connected to the highway ditch, the second drainage ditch is arranged in the pit and extends along the inclination direction of the slope, the rapids trough extends along the inclination direction of the slope, one end of the rapids trough is connected to the first drainage ditch, and the other end is connected to the second drainage ditch, and the water in the pit can flow into the highway ditch through the second drainage ditch, the rapids trough and the first drainage ditch in sequence.

[0016] Preferably, an anchoring assembly is further included, wherein the anchoring assembly includes a plurality of first anchor rods, wherein the plurality of first anchor rods are arranged at intervals in the pit, and an end of the first anchor rod away from the slope can be embedded in the backfill support body.

[0017] Preferably, the anchoring assembly further comprises a plurality of second anchor rods, the length of the second anchor rods being greater than the length of the first anchor rods, the plurality of second anchor rods being arranged at intervals along the surface of the backfill support body, the second anchor rods being penetrated through the backfill support body and anchored in the bedrock of the slope.

[0018] Preferably, the backfill support body comprises a foam concrete structure and a steel wire mesh embedded in the foam concrete structure.

[0019] Beneficial effects of the utility model:

[0020] The utility model provides a slope repair system, in which the drainage component can drain the water in the pit to the outside of the slope, so as to avoid the water in the pit affecting the stability of the connection between the backfill support and the slope. The pit is filled by the backfill support, so as to repair the surface morphology of the slope, ensure the stability of the roadbed, and avoid the traditional brush excavation treatment method, which is less destructive. A step structure is set on the surface of the backfill support, and a planting groove is set on each step structure to provide sufficient growth space for green plants. Since the planting groove is set on the top surface of the step structure, the green plants can grow in a vertically upward direction, which conforms to the growth law of green plants. The step structure can also provide a buffering effect to avoid the green plants in the planting groove being washed away during heavy rainfall. The planting grooves at both ends of each step structure are connected to the outside world, and the adjacent planting grooves located on the same step structure are connected to ensure the connection of the air at the bottom of the planting groove, that is, the middle planting groove on each step structure is connected to the outside world through the planting grooves at both ends, which ensures the air permeability of the planting groove, and can also prevent excessive water accumulation in the planting groove during long-term rainfall. The water-retaining structure can store water, thereby providing the green plants with the water they need for growth, avoiding their later withering and increasing the survival rate of the green plants. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a three-dimensional schematic diagram of the slope repair system provided by the utility model;

[0022] Figure 2 It is a structural schematic diagram of the water-retaining structure of the slope repair system provided by the utility model;

[0023] Figure 3 It is a schematic diagram of the internal structure of the backfill support body of the slope repair system provided by the utility model;

[0024] Figure 4 This is a schematic diagram of the structure when the backfill support body is poured to half the elevation;

[0025] Figure 5 middle Figure 4 The enlarged view of point A in the middle;

[0026] Figure 6is a partial schematic diagram of a side view of a backfill support body;

[0027] Figure 7 yes Figure 6 The enlarged view of point B in the middle;

[0028] Figure 8 It is a structural schematic diagram of the anchoring assembly of the slope repair system provided by the utility model.

[0029] In the figure:

[0030] 1. Drainage assembly; 11. First drainage ditch; 12. Second drainage ditch; 13. Rapid flow trough;

[0031] 2. Backfilling support body; 21. First channel; 22. Second channel;

[0032] 3. Greening components; 31. Planting trough; 32. Water-retaining structure; 321. Water-retaining pad; 322. Water-retaining rod; 323. Water-retaining side plate; 33. Green plants; 34. Planting bag;

[0033] 4. Blocking parts;

[0034] 5. Anchor assembly; 51. First anchor rod; 52. Second anchor rod; 53. Anchor pier; 54. Fastening nut; 55. Sealing anchor head; 56. Steel pad; 57. Centering bracket;

[0035] 6. The third drainage ditch;

[0036] 7. Filling parts;

[0037] 100. Slope;

[0038] 200. Foam concrete pumping truck. DETAILED DESCRIPTION

[0039] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only the parts related to the present invention, rather than all structures, are shown in the accompanying drawings.

[0040] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0041] In the present utility model, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.

[0042] In the description of this embodiment, the terms "upper", "lower", "right", etc., are based on the directions or positions shown in the drawings, and are only for the convenience of description and simplified operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation of the present invention. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.

[0043] See also Figures 1 to 8 This embodiment provides a slope repair system, which repairs the pits on the slope 100 while taking into account low destructiveness and ecological protection, and at the same time can provide a good environment for the growth of green plants 33 and improve the survival rate of green plants 33. The slope repair system includes a drainage component 1, a backfill support body 2 and a greening component 3. The drainage component 1 is arranged on the slope 100 to drain the water in the pit to the outside of the slope 100. The backfill support body 2 is filled in the pit to repair the surface morphology of the slope 100. The greening component 3 includes a vegetation groove 31 and a water retention structure 32 arranged in the vegetation groove 31. The surface of the backfill support body 2 is provided with a step structure along the inclination direction of the slope 100. Each layer of the step structure is provided with a plurality of vegetation grooves 31 at intervals along its extension direction. The vegetation grooves 31 at both ends of each layer of the step structure are connected to the outside, and adjacent vegetation grooves 31 are connected. Green plants 33 can be planted in the vegetation grooves 31, and the water retention structure 32 can store water to provide water for the growth of the green plants 33.

[0044] In the slope repair system provided in this embodiment, the drainage component 1 can drain the water in the pit to the outside of the slope 100 to prevent the moisture in the pit from affecting the stability of the connection between the backfill support 2 and the slope 100. The pit is filled by the backfill support 2, thereby repairing the surface morphology of the slope and ensuring the stability of the roadbed. At the same time, the traditional brush excavation treatment method is avoided, which is less destructive. A step structure is set on the surface of the backfill support 2, and a vegetation groove 31 is opened on each layer of the step structure to provide sufficient growth space for the green plants 33. Since the vegetation groove 31 is opened on the top surface of the step structure, the green plants 33 can grow in a vertical upward direction, which conforms to the growth law of the green plants 33. The setting of the step structure can also provide a buffering effect to prevent the green plants 33 in the vegetation groove 31 from being washed away during heavy rainfall. The vegetation grooves 31 at both ends of each step structure are connected to the outside world, and the vegetation grooves 31 located on the same step structure and adjacent to each other are connected to ensure the air connection at the bottom of the vegetation grooves 31, that is, the vegetation grooves 31 in the middle of each step structure are connected to the outside world through the vegetation grooves 31 at both ends, which ensures the air permeability of the vegetation grooves 31 and prevents excessive water accumulation in the vegetation grooves 31 during long-term rainfall. The water retention structure 32 can store water, thereby providing the green plants 33 with the water needed for growth, avoiding late withering and improving the survival rate of the green plants 33.

[0045] Optionally, see Figure 5 and Figure 7 A vegetation bag 34 containing a thick layer of substrate and plant seeds is arranged in the vegetation trough 31. The thick layer of substrate is composed of three parts: greening substrate, fiber, and planting soil, so as to provide necessary nutrients for the growth of plant seeds. The combination of the vegetation trough 31 and the vegetation bag 34 can enclose and protect the nutrient soil, etc., to prevent the nutrient soil from being destroyed by heavy rainfall in the traditional method of spraying greening with thick layer of substrate on slope, resulting in poor greening of the slope. In addition, by directly arranging the greening component 3 on the backfill support 2, a large number of other additional measures and other work taken to implement greening can also be omitted. Specifically, the plant seeds should contain drought-resistant vines, such as creepers, ivy, etc. The thick layer of substrate belongs to the prior art and is not described in detail in this embodiment.

[0046] Optionally, see Figure 2 and Figure 5The water-retaining structure 32 includes a water-retaining pad 321 and a plurality of water-retaining rods 322. The plurality of water-retaining rods 322 are arranged at intervals on the water-retaining pad 321. The bottom wall of the planting groove 31 is provided with a plurality of limiting holes. The plurality of water-retaining rods 322 can be inserted into the plurality of limiting holes one by one to limit the water-retaining pad 321 in the planting groove 31. The water-retaining rods 322 can limit the water-retaining structure 32 in the planting groove 31 to prevent the water-retaining structure 32 from being separated from the planting groove 31; the water-retaining structure 32 can store water to provide sufficient water for the growth of the green plants 33 to prevent the green plants 33 from dying later. Preferably, the water-retaining pad 321 is made of polyurethane sponge, which is inexpensive and has good water absorption and air permeability. Furthermore, the water-retaining rod 322 includes a water-retaining rod body and a water-absorbing layer coated on the outer surface of the water-retaining rod body. The water-absorbing layer is made of polyurethane sponge, so that it is easy to insert into the limiting hole while ensuring water absorption.

[0047] Furthermore, the water-retaining structure 32 also includes a water-retaining side plate 323, which is circumferentially arranged on the side of the water-retaining pad 321 that faces away from the water-retaining rod 322. The water-retaining pad 321 and the water-retaining side plate 323 together form a trough structure with the same shape as the planting groove 31. The water-retaining pad 321 fits with the bottom wall of the planting groove 31, and the water-retaining side plate 323 fits with the side wall of the planting groove 31. The water-retaining side plate 323 can increase the contact area between the water-retaining structure 32 and the planting bag 34, and increase the water storage capacity of the water-retaining structure 32. When the planting bag 34 is placed in the planting groove 31, the water-retaining structure 32 can wrap the planting bag 34, so that the water in the water-retaining structure 32 can be better absorbed by the seeds in the planting bag 34. Similarly, the water-retaining side plate 323 is also made of polyurethane sponge.

[0048] Optionally, see Figure 3 , both ends of the step structure are provided with a first channel 21, one end of the first channel 21 penetrates the side wall of the step structure, and the other end is connected to the vegetation groove 31 located at the end of the step structure, and a second channel 22 is provided between adjacent vegetation grooves 31, and both ends of the second channel 22 are respectively connected to adjacent vegetation grooves 31, and the first channel 21 can be connected to an external water source to replenish water into the vegetation groove 31. The vegetation grooves 31 at both ends of the step structure are connected to the outside through the first channel 21, and the adjacent vegetation grooves 31 are connected through the second channel 22, which ensures the air permeability of the vegetation groove 31. At the same time, during long rainfall periods, rainwater in the vegetation groove 31 can flow out through the second channel 22 and the first channel 21 to avoid water accumulation. In addition, by connecting one end of any first channel 21 of each step structure away from the plant groove 31 to an external water source, the external water source can inject water into all the plant grooves 31 of each step structure through the first channel 21 and the second channel 22, thereby providing water for the growth of green plants 33 in extremely dry conditions. Optionally, the external water source is a water supply truck.

[0049] In this embodiment, green plants 33 are not planted in the vegetation grooves 31 at both ends of each step structure, but filling pieces 7 made of polyurethane sponge are placed therein. This arrangement ensures the air permeability of the vegetation grooves 31, and at the same time, water can be replenished into the grooves in extremely dry conditions. The filling pieces 7 can store water, and the replenished water can flow into the middle vegetation groove 31 through the vegetation grooves 31 at both ends, which has a high water replenishment efficiency compared to replenishing water through the first channel 21.

[0050] Preferably, the height of the connection position between the first hole 21 and the vegetation groove 31 is higher than the height of the connection position between the second hole 22 and the vegetation groove 31, so that water can flow better from the first hole 21 into the vegetation groove 31 connected thereto, thereby improving the water replenishment efficiency.

[0051] The vegetation bag 34 is usually made of non-woven fabric and sunshade net, which is air permeable and water permeable. As the use time increases, the thick base auxiliary materials in the vegetation bag 34 may seep out through the vegetation bag 34 and enter the first channel 21 or the second channel 22. Based on this, the first channel 21 and the second channel 22 are both provided with a plugging member 4, and the plugging member 4 is made of polyurethane sponge. The plugging member 4 can prevent the thick base auxiliary materials that seep out of the vegetation bag 34 from entering the first channel 21 or the second channel 22. Since the plugging member 4 is made of polyurethane sponge, it is air permeable and water permeable, and will not affect the air permeability of the vegetation groove 31, nor will it affect the water replenishment into the vegetation groove 31. In this embodiment, plugging members 4 are provided at both ends of the second channel 22, and a plugging member 4 is provided at the end of the first channel 21 away from the vegetation groove 31.

[0052] Optionally, see Figure 1 and Figure 4The drainage component 1 includes a first drainage ditch 11, a second drainage ditch 12 and a rapid flow groove 13. The first drainage ditch 11 is arranged at the foot of the slope 100, and the first drainage ditch 11 is connected with the road ditch. The second drainage ditch 12 is arranged in the pit and extends along the inclination direction of the slope 100. The rapid flow groove 13 extends along the inclination direction of the slope 100. One end of the rapid flow groove 13 is connected with the first drainage ditch 11, and the other end is connected with the second drainage ditch 12. The water in the pit can flow into the road ditch through the second drainage ditch 12, the rapid flow groove 13 and the first drainage ditch 11 in sequence. After cleaning the pit, first build a first drainage ditch 11 at the foot of the slope 100, and build a torrent trough 13 along the inclination direction of the slope 100, and lay a second drainage ditch 12 in the pit, so that the water in the pit flows into the road ditch through the second drainage ditch 12, the torrent trough 13 and the first drainage ditch 11 in sequence, so as to prevent the water in the pit from affecting the stability of the connection between the backfill support 2 and the slope 100. Specifically, the second drainage ditch 12 includes a plastic blind ditch and a geotextile wrapped on the outer wall of the material blind ditch. The plastic blind ditch is fixed in the pit through galvanized iron wire. The geotextile can prevent the plastic blind ditch from being blocked. In this embodiment, two layers of geotextile are provided. Multiple groups of second drainage ditches 12 and torrent troughs 13 can be arranged one by one in a direction perpendicular to the inclination direction of the slope 100. The number and spacing are specifically determined according to the size of the pit, and are not specifically limited in this embodiment.

[0053] Furthermore, it also includes a third drainage ditch 6, which is arranged at the top of the slope 100 to increase the drainage capacity of the slope 100, avoid excessive rainwater from damaging the slope protection system, and ensure the stability of the slope 100.

[0054] Optionally, the backfill support 2 includes a foam concrete structure and a steel wire mesh embedded in the foam concrete structure. Foam concrete can play a backfill counter-pressure role on the rock mass in the pit. The foam concrete has small particles and is in a fluid state during the construction process. It can penetrate into the cracks and gaps of the rock and soil medium around the pit with high fluidity. It can be more closely combined with the surrounding medium than traditional soil or concrete backfill materials, and play a role in reinforcing the surrounding original rock; secondly, the density of foam concrete is much smaller than the commonly used ordinary concrete backfill body, and the weight can be 250kg / m3-1650kg / m3, which has a small loading effect on the slope 100, which is conducive to the stability of the slope 100; at the same time, foam concrete has a certain compressive strength (0.3MPa-8MPa), strong anti-scouring ability, faster solidification, and good self-support after solidification and hardening, and can form a vertical slope surface. The high plasticity of foam concrete during construction ensures rapid repair and reconstruction of the slope 100, providing a working platform for subsequent ecological restoration of the slope. Moreover, because the water absorption rate of foam concrete is lower than that of ordinary concrete, it can ensure the long-term storage of water in the surface vegetation groove 31, providing a long-term water supply for the slope vegetation. In addition, foam concrete produces a large number of bubbles during the solidification stage, and after solidification, a honeycomb-like porous surface can be formed on the surface, which is easy for green plants 33 such as vines to climb and grow. Furthermore, the cement of foam concrete should be general-purpose silicate cement, and its strength grade should be 42.5 or above, and its performance should comply with the provisions of "General-purpose silicate cement". Construction water should comply with the "Standard for Concrete Water" JGJ63. The foaming agent should be a synthetic polymer surfactant, and the appearance of the foaming agent should be uniform and transparent, with no foreign matter precipitation or precipitation under normal temperature conditions, and no peculiar or irritating odor.

[0055] Specifically, when pouring foam concrete, firstly, a step structure template is set up layer by layer from bottom to top along the inclination direction of the slope 100 in the pit, and the foam concrete is filled in the template layer by layer. Figure 4 When pouring to half the elevation, lay a layer of wire mesh horizontally on the foam concrete to enhance the flexibility and structural stability of the backfill support 2, and then continue to pour the foam concrete until the pit is filled. The specifications of the wire mesh are Ф6mm×10cm×10cm, the longitudinal overlap length is 20cm, and the transverse overlap length is 30cm. It should be noted that due to the thermal expansion and contraction of foam concrete, when the unidirectional length of the backfill support 2 exceeds 15m, a settlement joint should be set every 10m along its extension direction, and additional settlement joints should be set at the place where the cross-sectional morphology changes suddenly. The settlement joints use reserved settlement joints that are vertically connected from top to bottom, and 20cm-30cm thick polystyrene boards are placed in the settlement joints for filling to ensure the structural stability of the backfill support 2.

[0056] Optionally, see Figure 4 and Figure 6, and also includes an anchoring assembly 5, which includes a plurality of first anchor rods 51, which are arranged at intervals in the pit, and one end of the first anchor rod 51 away from the slope 100 can be embedded in the backfill support body 2. Specifically, after the drainage assembly 1 is set, the first anchor rod 51 is driven into the pit in a direction perpendicular to the slope surface, so that half of the length of the first anchor rod 51 is anchored in the rock and soil of the bottom wall of the pit, and the other half of the length is suspended out of the bottom wall of the pit; then the foam concrete is poured, and the first anchor rod 51 can drag the foam concrete to improve the anti-overturning ability of the foam concrete. After the backfill foam concrete solidifies, the end of the first anchor rod 51 away from the slope 100 can be embedded in the foam concrete structure, thereby increasing the stability of the connection between the backfill support body 2 and the slope 100. Optionally, the spacing between adjacent first anchor rods 51 is 1m-2m, and the length of the first anchor rod 51 is 1 / 2-1 / 3 of the maximum depth of the pit. Specifically, the drilling diameter of the first anchor rod 51 is 90 mm, the first anchor rod 51 is made of HRB400 steel bars with a diameter of 22 mm, and is poured with cement mortar of M20 or above.

[0057] In order to ensure the connection strength between the backfill support body 2 and the slope 100, the anchor assembly 5 also includes a plurality of second anchor rods 52, the length of the second anchor rods 52 is greater than the length of the first anchor rods 51, and the plurality of second anchor rods 52 are arranged at intervals along the surface of the backfill support body 2, and the second anchor rods 52 are penetrated through the backfill support body 2 and anchored in the bedrock of the slope 100. Specifically, after the foam concrete structure of each layer of the step structure solidifies, a cutting machine is used to perform groove processing at positions at intervals of 20 cm on the top surface of the step structure to increase the connection strength of the upper and lower step structures, and at the same time, the second anchor rods 52 are penetrated through the foam concrete structure of the step structure and anchored into the bedrock of the slope 100 to ensure the stability of the connection between the backfill support body 2 and the slope 100.

[0058] Specifically, see Figure 8An anchor pier 53 is arranged on the outer side of the step structure. The anchor pier 53 includes a foam concrete structure and a steel mesh embedded in the foam concrete structure. A fastening nut 54 is screwed on the end of the second screw away from the slope 100. After the second anchor rod 52 is passed through the step structure, the fastening nut 54 is sleeved on the second anchor rod 52 and the fastening nut 54 is screwed to make the fastening nut 54 pressed against the anchor pier 53. Then, a sealing anchor head 55 is used to seal the end of the second anchor rod 52 away from the slope 100 inside the concrete structure of the sealing anchor head 55, thereby fixing the second anchor rod 52. The setting of the sealing anchor head 55 can prevent the second anchor rod 52 from rusting. More specifically, a steel plate 56 with a size of 20cm×20cm×20cm is provided between the fastening nut 54 and the anchor pier 53. A reserved hole is provided on the steel plate 56 for the second anchor rod 52 to pass through, so as to avoid stress concentration and improve the fastening strength; a wedge-shaped steel pad is provided in the reserved hole to ensure the tension strength of the second anchor rod 52; a centering bracket 57 is provided on the outside of the second anchor rod 52 to stably support the second anchor rod 52. Preferably, the length of the second anchor rod 52 anchored in the bedrock should be greater than 2m. Optionally, the second anchor rod 52 adopts D25PSB830 finely rolled threaded steel bars, the spacing between adjacent second anchor rods 52 is 2m-3m, and the fastening force of the anchor head is not greater than 50kN. Anchoring belongs to the prior art and is not further described in this embodiment.

[0059] The slope repair system provided in this embodiment is used to repair the slope 100, including the following steps:

[0060] S1. Clearing the loose deposits and the partially loose and cracked rock and soil in the pit on the slope 100;

[0061] S2, setting a drainage assembly 1 on the slope 100 to drain the water in the pit to the outside of the slope 100;

[0062] S3, a template of a step structure is set up layer by layer from bottom to top along the inclination direction of the slope 100 in the pit, and the backfill support body 2 is filled in the template layer by layer. After each layer of the step structure is filled, a vegetation groove 31 is opened on the step structure, and adjacent vegetation grooves 31 are connected, and the vegetation grooves 31 at both ends of the step structure are connected to the outside;

[0063] S4. After all the backfilling is completed, a water retention structure 32 is set in the vegetation groove 31, and a vegetation bag 34 containing a thick layer of substrate is placed in the vegetation groove 31. Then, the output end of the external water source is connected to any vegetation groove 31 on each layer of the step structure to water the vegetation groove 31 of each layer of the step structure.

[0064] In step S2, a first drainage ditch 11 and a third drainage ditch 6 are respectively constructed at the foot and the top of the slope 100, and a second drainage ditch 12 is laid on the bottom wall of the pit along the inclination direction of the slope 100, and a torrent trough 13 is constructed on the slope surface along the inclination direction of the slope 100, so that one end of the torrent trough 13 is connected to the second drainage ditch 12, and the other end is connected to the first drainage ditch 11, and the first drainage ditch 11 is connected to the road ditch, so that the water in the pit is drained into the road ditch through the second drainage ditch 12, the torrent trough 13 and the first drainage ditch 11.

[0065] Before step S3, the process also includes: driving the first anchor rod 51 into the bottom wall of the pit along the direction perpendicular to the slope, so that 1 / 2 of the length of the first anchor rod 51 is anchored in the rock and soil of the pit, and the other 1 / 2 of the length hangs out of the bottom wall of the pit. The length of the first anchor rod 51 should be 1 / 2-1 / 3 of the maximum depth of the pit.

[0066] In step S3, a foam concrete pumping truck 200 is used to pour foam concrete; the height of each step structure is 0.8m-1.0m. After each step structure is poured, the outer surface of the mold of the planting groove 31 is wrapped with plastic wrap, and then vertically pressed into the foam concrete structure of the step structure from top to bottom. After the foam concrete is initially set and can stabilize itself, the mold of the planting groove 31 is taken out, and the planting groove 31 can be formed on the step structure; then, holes are punched between adjacent planting grooves 31 to form a second channel 22 to connect two adjacent planting grooves 31, and holes are punched at both ends of the step structure to form a first channel 21 to connect the planting grooves 31 at both ends of the step structure with the outside world.

[0067] In step S4, after all backfilling is completed, the sealing member 4 is first inserted into the first channel 21 and the second channel 22, and then the multiple water-retaining rods 322 of the water-retaining pad 321 are inserted one by one into the multiple limiting holes on the bottom wall of the planting groove 31 to limit the water-retaining structure 32 in the planting groove 31.

[0068] After step S4, the method further includes: after all construction is completed, non-woven fabric is laid on the slope surface, and necessary preliminary maintenance is performed. The preliminary maintenance belongs to the prior art and will not be described in detail in this embodiment.

[0069] Obviously, the above embodiments of the present invention are merely examples for the purpose of clearly illustrating the present invention, and are not intended to limit the implementation methods of the present invention. For those skilled in the art, various obvious changes, readjustments and substitutions can be made without departing from the scope of protection of the present invention. It is not necessary and impossible to list all implementation methods here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention shall be included in the scope of protection of the claims of the present invention.

Claims

1. A slope repair system for repairing pits on the surface of a slope (100), characterized in that: include: A drainage component (1) is arranged on the side slope (100) and is used to drain water in the pit to the outside of the side slope (100); Backfilling the support body (2) into the pit to repair the surface morphology of the slope (100); A greening component (3), the greening component (3) comprising a planting groove (31) and a water-retaining structure (32) arranged in the planting groove (31); a step structure is arranged on the surface of the backfill support body (2) along the inclination direction of the slope (100); a plurality of the planting grooves (31) are arranged at intervals in each layer of the step structure along its extension direction; the planting grooves (31) at both ends of each layer of the step structure are connected to the outside; the adjacent planting grooves (31) located on the same layer of the step structure are connected; green plants (33) can be planted in the planting grooves (31); and the water-retaining structure (32) can store water to provide water for the growth of the green plants (33).

2. The slope repair system according to claim 1, characterized in that: The water-retaining structure (32) comprises a water-retaining pad (321) and a plurality of water-retaining rods (322); the plurality of water-retaining rods (322) are arranged at intervals on the water-retaining pad (321); a plurality of limiting holes are arranged on the bottom wall of the planting groove (31); the plurality of water-retaining rods (322) can be inserted into the plurality of limiting holes in a one-to-one correspondence, so as to limit the water-retaining pad (321) in the planting groove (31).

3. The slope repair system according to claim 2, characterized in that: The water-retaining structure (32) further comprises a water-retaining side plate (323), the water-retaining side plate (323) being circumferentially arranged on a side of the water-retaining pad (321) facing away from the water-retaining rod (322), the water-retaining pad (321) and the water-retaining side plate (323) together forming a groove-shaped structure having the same shape as the planting groove (31), the water-retaining pad (321) being in contact with the bottom wall of the planting groove (31), and the water-retaining side plate (323) being in contact with the side wall of the planting groove (31).

4. The slope repair system according to claim 1, characterized in that: Both ends of the step structure are provided with a first channel (21), one end of the first channel (21) passes through the side wall of the step structure, and the other end is connected to the planting groove (31) located at the end of the step structure, and a second channel (22) is provided between adjacent planting grooves (31), and both ends of the second channel (22) are respectively connected to adjacent planting grooves (31), and the first channel (21) can be connected to an external water source to replenish water into the planting groove (31).

5. The slope repair system according to claim 4, characterized in that: The height of the connection position between the first hole channel (21) and the vegetation groove (31) is higher than the height of the connection position between the second hole channel (22) and the vegetation groove (31).

6. The slope repair system according to claim 4, characterized in that: A blocking piece (4) is provided in each of the first hole (21) and the second hole (22), and the blocking piece (4) is made of polyurethane sponge.

7. The slope repair system according to claim 1, characterized in that: The drainage component (1) comprises a first drainage ditch (11), a second drainage ditch (12) and a rapid flow groove (13); the first drainage ditch (11) is arranged at the foot of the slope (100); the first drainage ditch (11) is connected to the road ditch; the second drainage ditch (12) is arranged in the pit and extends along the inclination direction of the slope (100); the rapid flow groove (13) extends along the inclination direction of the slope (100); one end of the rapid flow groove (13) is connected to the first drainage ditch (11) and the other end is connected to the second drainage ditch (12); water in the pit can flow into the road ditch through the second drainage ditch (12), the rapid flow groove (13) and the first drainage ditch (11) in sequence.

8. The slope repair system according to claim 1, characterized in that: It also includes an anchoring assembly (5), the anchoring assembly (5) including a plurality of first anchor rods (51), the plurality of first anchor rods (51) being arranged at intervals in the pit, and the end of the first anchor rod (51) away from the slope (100) being capable of being embedded in the backfill support body (2).

9. The slope repair system according to claim 8, characterized in that: The anchoring assembly (5) further comprises a plurality of second anchor rods (52), the length of the second anchor rods (52) being greater than the length of the first anchor rod (51), the plurality of second anchor rods (52) being arranged at intervals along the surface of the backfill support body (2), the second anchor rods (52) being penetrated through the backfill support body (2) and anchored in the bedrock of the slope (100).

10. The slope repair system according to any one of claims 1 to 9, characterized in that: The backfill support body (2) comprises a foam concrete structure and a steel wire mesh embedded in the foam concrete structure.

Citation Information

Cited By

  • Slope restoration system and restoration method

    CN117947797A