Assembly type bent cap and pier connecting structure
By using a combination of plug-in steel and shear-resistant steel bars in the bridge structure, the problems of high cut-off and construction accuracy of the cover beam steel bars are solved, the shear resistance and construction tolerance are improved, and the stable connection between the cover beam and the bridge pier is achieved. Rapid construction.
Patent Information
- Application Number
- CN202323366427.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-11
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2033-12-11
AI Technical Summary
In the existing bridge structure, the connection method between the cover beam and the bridge pier can easily lead to the cut-off of the cover beam steel bars, resulting in insufficient local stiffness and high construction accuracy requirements, which limits the promotion and application of the lower structure of the prefabricated bridge.
The plug-in steel is used to embed at the bottom of the cover beam, and the plug-in space is set on the top of the bridge pier. The plug-in steel is inserted into the plug-in space, and shear steel is installed at the connection to improve shear resistance. At the same time, an inflatable inner membrane is installed in the bridge pier. and post-pour concrete to enhance connection stability.
It effectively avoids the cut-off of the steel bars of the cover beam, improves the shear resistance and construction fault tolerance at the connection, improves the local stiffness and overall structural stability of the cover beam, reduces the construction accuracy requirements, and achieves rapid construction.
Smart Images

Figure CN222024874U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of bridge structures, and in particular to an assembled cap beam and bridge pier connection structure. Background Art
[0002] The upper structure of the large-scale and wide-area simply supported beam bridge in highway bridges has basically been assembled, while the assembly of the lower part is still in its infancy. As an important component of the bridge substructure, the cap beam is indispensable for the widely used prefabricated small box beam and T-beam bridge as the main support and force transmission component of the upper structure. The connection between the prefabricated cap beam and the prefabricated bridge pier generally adopts grouting sleeve, grouting bellows connection, or slot connection. Among them, the connection between the grouting sleeve and the grouting bellows requires high construction and installation accuracy, especially when the prefabricated bridge pier and the pile foundation also adopt this connection, the installation accuracy requirements need to be greatly improved. In addition, the above connection generally connects the longitudinal main reinforcement, and the shear resistance of the connection is poor, especially in areas with high seismic requirements, which greatly limits the promotion and application of the assembled bridge substructure. The slot connection generally reserves the pier insertion space at the position of the prefabricated cap beam, and after the prefabricated bridge pier is inserted, the grouting material is poured to form a whole. However, the slot-type connection reserves insertion space, which cuts off the cap beam reinforcement, resulting in insufficient local stiffness of the cap beam. Utility Model Content
[0003] The utility model aims to provide an assembled cap beam and pier connection structure, which can effectively prevent the cap beam reinforcement from being cut off, thereby effectively avoiding the problem of insufficient local rigidity of the cap beam structure, and at the same time has low requirements on construction accuracy and is easy to construct.
[0004] The utility model is realized by the following technical solutions:
[0005] A prefabricated cap beam and pier connection structure comprises a cap beam, a pier and a plug-in steel section, wherein the plug-in steel section is pre-buried at the bottom of the cap beam, a plug-in space is provided at the top of the pier, and the plug-in steel section is inserted into the plug-in space. In order to solve the above technical problems and achieve the corresponding technical effects, the utility model realizes the prefabricated connection between the cap beam and the pier by inserting the plug-in steel section into the plug-in space provided at the top of the pier, and the use of the steel section can effectively ensure the mechanical properties of the connection, and can effectively improve the shear resistance of the connection compared to the traditional grouting sleeve and grouting bellows. At the same time, the construction precision requirement is low, the fault tolerance rate of the construction can be improved, and the construction is fast. By pre-embedding the plug-in steel section on the cap beam, the situation where the cap beam reinforcement is cut off can be effectively avoided, thereby effectively avoiding the problem of insufficient local stiffness of the cap beam structure.
[0006] Further technical solutions;
[0007] The upper half of the plug-in steel is embedded in the cap beam, and the lower half of the plug-in steel passes through the cap beam and extends downward.
[0008] Further: cap beam reinforcement is pre-embedded in the cap beam, and the upper half of the plug-in steel section is connected to the cap beam reinforcement.
[0009] Furthermore: the bridge pier is a hollow bridge pier, and an inflatable inner membrane is arranged in the cavity of the bridge pier, and the cavity above the inflatable inner membrane is the plug-in space.
[0010] Further: when the plug-in steel is inserted into the plug-in space, the inflatable inner membrane is inflated, and the plug-in space is filled with post-cast concrete. Connecting ribs are arranged on the inner side of the pier to ensure reliable connection with the post-cast concrete.
[0011] Further: the lower half of the plug-in steel section is provided with shear-resistant steel bars a, and the shear-resistant steel bars a are horizontally and vertically welded to the plug-in steel section.
[0012] Further: a shear steel bar b is arranged in the insertion space, one end of the shear steel bar b is buried in the inner wall of the insertion space, and the other end of the shear steel bar b extends outward from the side wall.
[0013] Furthermore: the shear steel bars b are arranged in multiple rows, and the multiple shear steel bars b are evenly and evenly spaced along the inner wall of the insertion space.
[0014] Furthermore: the splicing steel is also arranged in multiple rows, and a splicing steel is arranged between two adjacent shear reinforcement bars b.
[0015] Further: the shear reinforcement b is arranged along the direction pointing to the center of the insertion space.
[0016] Compared with the prior art, the utility model has the following advantages and beneficial effects:
[0017] 1. The utility model provides an assembled cap beam and pier connection structure, which can effectively avoid the cap beam reinforcement being cut off by pre-embedding plug-in steel sections on the cap beam, thereby effectively avoiding the problem of insufficient local rigidity of the cap beam structure.
[0018] 2. The utility model provides an assembled cap beam and pier connection structure, which realizes the assembled connection between the cap beam and the pier by inserting the plug-in steel into the plug-in space set on the top of the pier. The use of steel can effectively ensure the mechanical properties of the connection. Compared with the traditional grouting sleeve and grouting bellows, it can effectively improve the shear resistance of the connection. At the same time, the construction precision requirement is low, which can improve the fault tolerance of the construction and the construction is fast. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the technical solutions of the exemplary embodiments of the present utility model, the following is a brief introduction to the drawings required for use in the embodiments. It should be understood that the following drawings only illustrate certain embodiments of the present utility model, and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without creative work. In the drawings:
[0020] Figure 1 It is a schematic diagram of the structure of the utility model;
[0021] Figure 2 This is a cross-sectional view of the structure of the utility model;
[0022] Figure 3 This is a bottom view of the structure of the utility model;
[0023] Figure 4 Schematic diagram of the connection structure between shear reinforcement a and plug-in steel.
[0024] Marks and corresponding parts names in the attached drawings:
[0025] 1- cap beam, 2- pier, 3- plug-in steel, 4- inflatable inner membrane, 5- post-cast concrete, 11- cap beam reinforcement, 21- plug-in space, 22- shear reinforcement b, 31- shear reinforcement a. DETAILED DESCRIPTION
[0026] In order to make the purpose, technical solutions and advantages of the utility model more clearly understood, the utility model is further described in detail below in conjunction with embodiments and drawings. The schematic implementation methods of the utility model and their descriptions are only used to explain the utility model and are not intended to limit the utility model.
[0027] In the following description, a large number of specific details are set forth in order to provide a thorough understanding of the present invention. However, it is apparent to those skilled in the art that these specific details are not necessary to implement the present invention. In other embodiments, in order to avoid confusing the present invention, well-known structures, circuits, materials or methods are not specifically described.
[0028] Throughout the specification, references to "one embodiment," "an embodiment," "an example," or "an example" mean that a particular feature, structure, or characteristic described in conjunction with the embodiment or example is included in at least one embodiment of the present invention. Therefore, the phrases "one embodiment," "an embodiment," "an example," or "an example" appearing in various places throughout the specification do not necessarily all refer to the same embodiment or example. In addition, particular features, structures, or characteristics may be combined in one or more embodiments or examples in any suitable combination and / or sub-combination. In addition, it will be appreciated by those of ordinary skill in the art that the figures provided herein are for illustrative purposes and that the figures are not necessarily drawn to scale. The term "and / or" as used herein includes any and all combinations of one or more of the associated listed items.
[0029] In the description of the present invention, the terms "front", "rear", "left", "right", "up", "down", "vertical", "horizontal", "high", "low", "inside", "outside", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they should not be understood as limiting the scope of protection of the present invention.
[0030] Example
[0031] like Figure 1 to Figure 4 As shown, the utility model is an assembled cap beam and pier connection structure, comprising a cap beam 1, a pier 2 and a plug-in steel 3, wherein the plug-in steel 3 is pre-embedded at the bottom of the cap beam 1, and a plug-in space 21 is provided at the top of the pier 2, and the plug-in steel 3 is inserted into the plug-in space 21. In this embodiment, by pre-embedding the plug-in steel 3 on the cap beam 1, it is possible to effectively avoid the situation where the cap beam reinforcement is cut off, thereby effectively avoiding the problem of insufficient local rigidity of the cap beam 1 structure. At the same time, by inserting the plug-in steel 3 into the plug-in space 21 provided at the top of the pier 2, the assembled connection between the cap beam 1 and the pier 2 is realized, and the use of steel can effectively guarantee the mechanical properties of the connection, and can effectively improve the shear resistance of the connection compared to the traditional grouting sleeve and grouting bellows, and at the same time, the low construction precision requirement can improve the fault tolerance rate of the construction.
[0032] The upper half of the plug-in steel 3 is embedded in the cap beam 1, and the lower half of the plug-in steel 3 passes through the cap beam 1 and extends downward. In this embodiment, the plug-in steel 3 is used as an intermediate component to connect the cap beam 1 and the bridge pier 2. When the cap beam 1 is prefabricated, the upper half of the plug-in steel 3 is embedded in the concrete of the cap beam 1, and then the lower half of the plug-in steel 3 is inserted into the insertion space 21, and after the insertion is in place, concrete is poured into the insertion space 21, so that the assembly work of the cap beam 1 and the bridge pier 2 can be effectively realized.
[0033] The cap beam 1 is pre-embedded with cap beam reinforcement 11, and the upper half of the plug-in steel 3 is connected to the cap beam reinforcement 11. In this embodiment, the integrity of the steel structure is improved by connecting the plug-in steel 3 with the cap beam reinforcement 11, thereby improving the strength and stability of the steel structure, thereby ensuring the stability of the assembly relationship between the cap beam 1 and the pier 2.
[0034] The pier 2 is a hollow pier, and an inflatable inner membrane 4 is provided in the cavity of the pier 2, and the cavity above the inflatable inner membrane 4 is the plug-in space 21. When the plug-in steel 3 is inserted into the plug-in space 21, the inflatable inner membrane 4 is inflated, and the plug-in space 21 is filled with post-cast concrete 5. In this embodiment, the pier 2 adopts a hollow pier to reduce the amount of concrete, thereby reducing the construction cost; the inflatable inner membrane 4 is provided in the cavity in the middle of the pier 2 to isolate the plug-in space 21, so that the concrete structure can be poured, and the integrity of the steel bars and concrete at the connection is improved. At the same time, the pier 2 can also adopt a conventional solid pier, and it can also be achieved by reserving a plug-in space on the top of the solid pier.
[0035] Improve the performance of the steel-concrete combination at the connection, thereby improving the stability of the entire cap beam and pier connection structure. At the same time, the pier can also use a conventional solid pier, and the insertion space 21 can also be realized at the reserved position on the top of the solid pier.
[0036] The lower half of the plug-in steel 3 is provided with a shear steel bar a31, and the shear steel bar a31 is horizontally and vertically welded to the plug-in steel 3. In this embodiment, the provision of the shear steel bar a31 can effectively enhance the shear resistance of the steel-concrete structure after pouring concrete in the plug-in space 21, thereby improving the integrity of the steel bar and concrete.
[0037] The plug-in space 21 is provided with a shear steel bar b22, one end of which is buried in the inner wall of the plug-in space 21, and the other end of which extends outward from the side wall. Similarly, the provision of the shear steel bar b22 can also effectively enhance the integrity of the steel bar and concrete after the concrete is poured in the plug-in space 21. At the same time, in order to further improve the shear resistance, the shear steel bar b22 is provided in multiple channels, and the multiple channels of the shear steel bars b22 are evenly and evenly spaced along the inner wall of the plug-in space 21. Specifically, the plug-in steel 3 is also provided in multiple channels, and a plug-in steel 3 is provided between two adjacent shear steel bars b22. The shear steel bar b22 is provided in a direction pointing to the center of the plug-in space 21.
[0038] The specific implementation methods described above further illustrate the purpose, technical solutions and beneficial effects of the utility model in detail. It should be understood that the above description is only the specific implementation method of the utility model and is not used to limit the protection scope of the utility model. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the utility model should be included in the protection scope of the utility model.
Claims
1. A prefabricated cap beam and bridge pier connection structure, It is characterized in that It comprises a cap beam (1), a bridge pier (2) and a plug-in steel (3), wherein the plug-in steel (3) is pre-buried at the bottom of the cap beam (1), a plug-in space (21) is provided at the top of the bridge pier (2), and the plug-in steel (3) is inserted into the plug-in space (21).
2. The assembled cap beam and pier connection structure according to claim 1, It is characterized in that The upper half of the plug-in steel (3) is pre-buried in the cap beam (1), and the lower half of the plug-in steel (3) passes through the cap beam (1) and extends downward.
3. The assembled cap beam and pier connection structure according to claim 2, It is characterized in that A cap beam reinforcement (11) is pre-buried in the cap beam (1), and the upper half of the plug-in steel (3) is connected to the cap beam reinforcement (11).
4. The assembled cap beam and pier connection structure according to claim 1, It is characterized in that The bridge pier (2) is a hollow bridge pier, and an inflatable inner membrane (4) is arranged in the cavity of the bridge pier (2), and the cavity above the inflatable inner membrane (4) is the insertion space (21).
5. The assembled cap beam and pier connection structure according to claim 4, It is characterized in that When the plug-in steel (3) is inserted into the plug-in space (21), the inflatable inner membrane (4) is in an inflated state, and the plug-in space (21) is filled with post-cast concrete (5).
6. The assembled cap beam and pier connection structure according to claim 2, It is characterized in that A shear-resistant steel bar a (31) is arranged on the lower half of the plug-in steel section (3), and the shear-resistant steel bar a (31) is horizontally and vertically welded to the plug-in steel section (3).
7. The assembled cap beam and bridge pier connection structure according to claim 6, It is characterized in that A shear steel bar b (22) is arranged in the insertion space (21), one end of the shear steel bar b (22) is buried in the inner wall of the insertion space (21), and the other end of the shear steel bar b (22) extends outward from the side wall.
8. The assembled cap beam and pier connection structure according to claim 7, It is characterized in that The shear-resistant steel bars b (22) are arranged in multiple rows, and the multiple rows of shear-resistant steel bars b (22) are evenly and evenly spaced along the inner wall of the insertion space (21).
9. The assembled cap beam and bridge pier connection structure according to claim 8, It is characterized in that The splicing steel (3) is also arranged in multiple rows, and a splicing steel (3) is arranged between two adjacent rows of shear reinforcement bars b (22).