Mine wellhead air conditioning system
By designing a heat pump subsystem and a heat pipe heat exchange subsystem at the mine wellhead, combining explosion-proof heat dissipation fan and low-pressure specific compressor, and using Freon as a refrigerant, the problem that the mine wellhead air conditioning system cannot meet the explosion-proof requirements of coal mine safety regulations is solved, and the explosion-proof requirements of the mine wellhead air conditioning system is realized. It provides safe, energy-saving and efficient air supply effects.
Patent Information
- Application Number
- CN202420424468.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-05
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2034-03-05
AI Technical Summary
The existing technology cannot provide anti-freezing air conditioning systems at the mine wellhead, and at the same time meet the explosion-proof requirements of coal mine safety regulations, which makes it difficult to maintain the inlet temperature of the air supply shaft above 2℃, affecting personnel and equipment safety.
A mine wellhead air conditioning system was designed, using a heat pump subsystem and a heat pipe heat exchange subsystem, including an evaporation section, a condensation section and a power module. Freon is used as a refrigerant and combined with an explosion-proof heat dissipation fan to realize heat exchange and circulation power. Meet the operation needs of low-voltage compressors and ensure the system is safe, energy-saving and environmentally friendly.
It achieves safe, energy-saving and efficient air supply at low ambient temperatures, avoids high energy consumption and maintenance difficulties of traditional systems, meets the explosion-proof requirements of coal mine safety regulations, and reduces the cost of later maintenance.
Smart Images

Figure CN222025810U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of new energy, in particular to a mine wellhead air conditioning system. Background Art
[0002] The outdoor temperature in northern my country is relatively low in winter, and in most areas the outdoor temperature is below 0°C for up to 4-5 months in winter. Some mine air shafts have anti-freeze requirements, and the temperature at the entrance of the air shaft must be maintained above 2°C to ensure the safety of personnel entering and exiting and underground equipment. However, according to the "Coal Mine Safety Regulations", all electrical appliances and lines within 20 meters of the wellhead must meet explosion-proof requirements. Conventional heating methods cannot meet the above regulations. The existing technology urgently needs an air-conditioning system that not only meets the requirements of the "Coal Mine Safety Regulations" but also can realize the wellhead anti-freeze function. Utility Model Content
[0003] In order to solve various problems existing in traditional solutions, the utility model provides a mine wellhead air conditioning system, the system includes a heat pump subsystem and a heat pipe heat exchange subsystem, wherein:
[0004] The heat pipe heat exchange subsystem includes an evaporation section, a condensation section and a power module, wherein the evaporation section, the condensation section and the power module are connected in sequence, the refrigerant absorbs heat and evaporates in the evaporation section, and condenses and releases heat in the condensation section, and the power module provides circulation power for the refrigerant;
[0005] The heat pump subsystem includes an evaporator, a condenser, a compressor and a throttling component, wherein the condenser is a flooded heat exchanger;
[0006] The evaporation section of the heat pump subsystem is the tube section of the full-liquid heat exchanger; in the full-liquid heat exchanger, heat is exchanged to the coolant in the heat pipe subsystem.
[0007] Furthermore, the condensing section is a heat pipe heat exchanger, which has an explosion-proof heat dissipation fan, and the explosion-proof heat dissipation fan provides heated air to the mine wellhead.
[0008] Furthermore, the power module includes a fluorine pump, a first solenoid valve and a second solenoid valve, and the fluorine pump, the first solenoid valve and the second solenoid valve are arranged in parallel.
[0009] Furthermore, a third solenoid valve is provided on the pipeline between the power module and the evaporation section.
[0010] Furthermore, a fourth solenoid valve is provided on the pipeline between the evaporation section and the condensation section.
[0011] Furthermore, the coolant is Freon.
[0012] Furthermore, a liquid wick is provided in the pipeline of the heat pipe heat exchange subsystem.
[0013] Furthermore, the compressor is a low pressure ratio compressor.
[0014] The mine wellhead air conditioning system provided by the utility model can provide hot air for the mine wellhead and meet the explosion-proof requirements of the "Coal Mine Safety Regulations" at the same time. It is a safe, energy-saving and environmentally friendly air conditioning system. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] In order to more clearly illustrate the technical solutions in the specific implementation of the present invention, the following briefly introduces the drawings required for use in the specific implementation or the description of the prior art.
[0016] Figure 1 This is a schematic diagram of the system structure of Example 1 disclosed in the utility model.
[0017] The meanings of the accompanying drawings are as follows: 1—heat pump subsystem; 2—evaporation section; 3—third solenoid valve; 4—fourth solenoid valve; 5—power module; 6—fluorine pump; 7—first solenoid valve; 8—second solenoid valve; 9—explosion-proof cooling fan; 10—condensation section. DETAILED DESCRIPTION
[0018] The structure and operation of the utility model patent will be further described in detail below in conjunction with the accompanying drawings. Obviously, the accompanying drawings are provided only for a better understanding of the utility model patent, and they should not be understood as limitations on the utility model patent. Based on the embodiments of the utility model patent, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0019] In the description of the present invention, it should be noted that if the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the drawings, which is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In addition, if the terms "first" and "second" appear, they are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.
[0020] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0021] Example 1
[0022] Combination Figure 1 As shown, this embodiment discloses a mine wellhead air-conditioning system, the system includes a heat pump subsystem 1 and a heat pipe heat exchange subsystem, wherein: the heat pipe heat exchange subsystem includes an evaporation section 2, a condensation section 10 and a power module 5, the evaporation section 2, the condensation section 10 and the power module 5 are connected in sequence, the refrigerant absorbs heat and evaporates in the evaporation section, and condenses and releases heat in the condensation section, and the power module 5 provides circulation power for the refrigerant.
[0023] The heat pump subsystem includes an evaporator, a condenser, a compressor and a throttling component, wherein the condenser is a flooded heat exchanger;
[0024] The evaporation section 2 of the heat pump subsystem is a pipe section of a full-liquid heat exchanger; in the full-liquid heat exchanger, heat is exchanged to the coolant in the heat pipe subsystem.
[0025] Specifically, the condensing section 10 is a heat pipe heat exchanger, which has an explosion-proof heat dissipation fan 9, and the explosion-proof heat dissipation fan 9 provides heated air to the mine wellhead.
[0026] Specifically, the power module 5 includes a fluorine pump 6, a first solenoid valve 7 and a second solenoid valve 8, and the fluorine pump 6, the first solenoid valve 7 and the second solenoid valve 8 are arranged in parallel.
[0027] Specifically, a third solenoid valve 3 is provided on the pipeline between the power module 5 and the evaporation section 2 .
[0028] Specifically, a fourth solenoid valve 4 is provided on the pipeline between the evaporation section 2 and the condensation section 10 .
[0029] Specifically, the coolant is Freon.
[0030] Specifically, a liquid wick is provided in the pipeline of the heat pipe heat exchange subsystem.
[0031] Specifically, the compressor is a low-pressure ratio compressor. This low-pressure ratio compressor is dedicated to mines and uses ultra-low temperature air source as a heat source. Since the air supply temperature required at the mine wellhead is 2°C, the condensing temperature of the air source heat pump can be 15-25°C, which can ensure that the compressor is in the operating range comfort zone in a low environment, maintain low compression ratio operation, and be safe, energy-saving, and efficient.
[0032] The working principle of the system provided in this embodiment is as follows: the heat pump subsystem utilizes the reverse Carnot cycle principle to absorb heat from the air, and exchanges heat with the refrigerant Freon in the heat pipe subsystem in the full liquid heat exchanger. The refrigerant in the heat pipe subsystem will boil or evaporate after being heated in the evaporation section, generating sensible heat of vaporization, and changing from liquid to gas. The generated high-temperature gas flows to the condensation section 10 under the action of a certain pressure difference in the tube, and after being cooled by the explosion-proof heat dissipation fan 9, the steam encounters the cold wall surface and condenses into liquid, while releasing the latent heat of vaporization. The condensate flows back to the evaporation section and evaporates again under the action of gravity (or liquid absorption core) and the circulation of the power module 5. In this way, the heat transfer and exchange of the external cold and hot media is realized.
[0033] When the system circulation is good, the fluorine pump 6 is closed, and the flow rate of the refrigerant Freon is controlled by adjusting the first solenoid valve 7 and the second solenoid valve 8 to open.
[0034] The main function of the third solenoid valve 3 and the fourth solenoid valve 4 is to collect the refrigerant into the full liquid heat exchanger during system maintenance.
[0035] The utility model can achieve the following technical effects:
[0036] (1) Use a low-pressure ratio compressor dedicated to mines and use ultra-low temperature air source as the heat source. Since the air supply temperature required at the mine wellhead is 2°C, the condensing temperature of the air source heat pump can reach 15-25°C. This can ensure that the compressor is in the comfortable operating range even in low environments, maintain low compression ratio operation, and be safe, energy-saving, and efficient.
[0037] (2) Heat is transferred using heat pipe technology. Because it is a medium to low temperature transfer, the heat loss is low and the energy waste is small;
[0038] (3) Using heat pipe technology, the freon liquid inside the heat pipe absorbs heat and evaporates in the heating section, then transmits heat to the condensing section through the steam riser, and then condenses and flows back to the heating section through the condensate downcomer. The entire cycle does not require external force. Even in some systems with long heat transfer distances, a fluorine pump is added to ensure system circulation. The input power of the fluorine pump is also much smaller than the input power of the water pump when water is used as the coolant, achieving energy-saving and environmental protection effects;
[0039] (4) Using a heat pipe system, the working fluid uses Freon. Compared with water, there is no need to consider pipe scaling and pipe freezing during winter shutdown maintenance. It has high promotion and social and economic significance;
[0040] (5) The heat pipe system uses a movable static sealing structure to facilitate the maintenance and cleaning of the heat pipe; the welding structure is reliably sealed, there is no hidden danger of fluid leakage on both sides, and the subsequent maintenance cost is low.
[0041] The above embodiments are only used to illustrate the present utility model patent, wherein the structure, connection method and manufacturing process of each component can be changed. Any equivalent transformations and improvements based on the present technical solution should not be excluded from the protection scope of the present utility model patent.
Claims
1. A mine wellhead air conditioning system, characterized in that The system includes a heat pump subsystem and a heat pipe heat exchange subsystem, wherein: The heat pipe heat exchange subsystem includes an evaporation section, a condensation section and a power module, wherein the evaporation section, the condensation section and the power module are connected in sequence, the refrigerant absorbs heat and evaporates in the evaporation section, and condenses and releases heat in the condensation section, and the power module provides circulation power for the refrigerant; The heat pump subsystem includes an evaporator, a condenser, a compressor and a throttling component, wherein the condenser is a flooded heat exchanger; The evaporation section of the heat pump subsystem is the tube section of the full-liquid heat exchanger; the heat in the full-liquid heat exchanger is exchanged to the coolant in the heat pipe subsystem; The power module comprises a fluorine pump, a first solenoid valve and a second solenoid valve, and the fluorine pump, the first solenoid valve and the second solenoid valve are arranged in parallel.
2. The system according to claim 1, characterized in that: The condensing section is a heat pipe heat exchanger, which has an explosion-proof heat dissipation fan, and the explosion-proof heat dissipation fan provides heated air to the mine wellhead.
3. The system according to claim 1, characterized in that: A third solenoid valve is arranged on the pipeline between the power module and the evaporation section.
4. The system according to claim 1, characterized in that: A fourth solenoid valve is arranged on the pipeline between the evaporation section and the condensation section.
5. The system according to claim 1, characterized in that: The refrigerant is Freon.
6. The system according to claim 1, characterized in that: A liquid wick is arranged in the pipeline of the heat pipe heat exchange subsystem.
7. The system according to claim 1, characterized in that: The compressor is a low pressure ratio compressor.