Fluidized bed boiler system capable of simultaneously carrying out blending combustion on bulk biomass materials and granular biomass materials
By designing independent feeding devices and speed control in biomass power plants, the blockage and low efficiency problems in the admixture of biomass bulk materials and pellet materials are solved, efficient and low-cost combustion of biomass power generation is achieved, and the boiler is enhanced Load capacity and fuel flexibility of the equipment.
Patent Information
- Application Number
- CN202420281610.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Priority Date
- 2023-07-27
- Filing Date
- 2024-02-05
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2034-02-05
AI Technical Summary
Most existing biomass power plants only burn biomass bulk or pellets, resulting in low combustion calorific value and efficiency of bulk materials and high ash content. The system is easily blocked when the bulk materials and pellets are mixed, and they cannot be flexibly mixed, which increases fuel costs. and the risk of corrosion to boiler equipment.
Design a fluidized bed boiler system to transport the biomass pellets and bulk materials into the fluidized bed through independent biomass pellets and bulk materials, and control the feeding speed using a speed governor and a speed sensor. , avoid mixing and blockage, and achieve flexible mixing.
It improves the combustion efficiency and average calorific value of biomass power generation, reduces fuel costs, enhances the load capacity of boiler equipment, and improves fuel flexibility and economy.
Smart Images

Figure CN222026929U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of biomass power generation, in particular to a fluidized bed boiler system for simultaneously burning biomass bulk materials and granular materials. Background Art
[0002] Bulk biomass refers to unformed biomass fuel, such as straw, rice straw, wood chips, sawdust, etc. The raw materials are widely available and easy to obtain. There is no sulfur emission when burning, which reduces acid rain and greenhouse effect. At the same time, it is low in cost and saves investment. However, the raw material density is low, the volume is large, the combustion calorific value is low, the combustion efficiency is low, and the ash content is high, which has a certain corrosive effect on boiler equipment; biomass pellets have high density, small volume, convenient transportation and storage, high combustion efficiency, low ash content, and no damage to boiler equipment, but require special equipment and technology for processing, so the cost is relatively high. Most of the existing biomass power plants only burn bulk biomass or biomass pellets. Blending biomass bulk with biomass pellets can solve the problem of low calorific value and combustion efficiency of bulk materials and high ash content, and reduce damage to boiler equipment. However, the feeding system of biomass bulk and biomass pellets cannot be universal. If biomass bulk and biomass pellets are directly mixed, it will cause system blockage. Utility Model Content
[0003] In order to solve the problems existing in the prior art, the utility model provides a fluidized bed boiler system for simultaneously burning bulk biomass and granular biomass. The biomass granular biomass and bulk biomass can be respectively introduced into the fluidized bed boiler without changing the boiler body, thereby achieving the purpose of flexible burning of bulk biomass and granular biomass, which helps to reduce the fuel cost of biomass power generation.
[0004] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a fluidized bed boiler system for simultaneously burning biomass bulk and granular materials, comprising a biomass granular material furnace front feeding device, a biomass bulk material furnace front feeding device, and a fluidized bed boiler, the biomass granular material furnace front feeding device comprising a biomass granular material feeder, the outlet of the biomass granular material feeder is connected to the secondary air nozzle of the fluidized bed boiler, the biomass bulk material furnace front feeding device comprises a second biomass bulk material conveying belt, the second biomass bulk conveying belt is connected to the feeding port of the fluidized bed boiler, the biomass granular material feeder and the second biomass bulk conveying belt are both connected to a speed regulator, and the two speed regulators are respectively provided with speed sensors.
[0005] Furthermore, the biomass pellet feeder is a screw feeder.
[0006] Furthermore, the width of the second biomass bulk material transport belt is 1.6 meters.
[0007] Furthermore, the biomass pellet feeding device in front of the furnace also includes a biomass pellet silo, the inlet of the biomass pellet silo is connected to the outlet of the biomass pellet storage silo through a biomass pellet transport belt, and the outlet of the biomass pellet silo is connected to the inlet of the biomass pellet feeder.
[0008] Furthermore, the biomass pellet transport belt has an inclination angle of less than 35° and a width of 1.4 meters.
[0009] Furthermore, the biomass pellet silo stores a biomass pellet material with a combustion amount of 6h-12h.
[0010] Furthermore, the biomass bulk furnace front feeding device also includes a crusher, a first biomass bulk transport belt and a biomass bulk silo. The outlet of the crusher is connected to the inlet of the first biomass bulk transport belt, the outlet of the first biomass bulk transport belt is connected to the inlet of the biomass bulk silo, and the outlet of the biomass bulk silo is connected to the inlet of the second biomass bulk transport belt.
[0011] Furthermore, the first biomass bulk material transport belt and the second biomass bulk material transport belt have the same width.
[0012] Furthermore, the biomass bulk materials include straw bulk materials, crushed engineering board materials, peanut shells, and rice husks.
[0013] Furthermore, the biomass pellets include straw pellets and straw briquettes.
[0014] Compared with the prior art, the utility model has at least the following beneficial effects:
[0015] The utility model provides a fluidized bed boiler system for simultaneously burning biomass bulk and granular materials, and sets an independent biomass granular material furnace front feeding device and a biomass bulk material furnace front feeding device. Without changing the boiler body, the biomass granular material and the biomass bulk material are respectively introduced into the fluidized bed boiler, solving the problem that the feeding systems of the biomass bulk and the biomass granular material cannot be used universally, and the problem that the direct mixing of the biomass bulk and the biomass granular material causes the system to be blocked, and realizes the flexible burning of the biomass bulk and the biomass granular material, and effectively reduces the fuel cost of biomass power generation. The fluidized bed boiler system of the utility model improves the average combustion calorific value and the load-carrying capacity of the furnace by burning biomass granular materials, and further improves the combustion efficiency of the power plant.
[0016] Furthermore, the utility model controls the feeding speed of the biomass pellet feeder and the second biomass bulk material transport belt by setting a speed regulator and a speed sensor, thereby controlling the feeding amount of biomass pellets and biomass bulk material, greatly improving the flexibility of biomass power generation fuel. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 Schematic diagram of the system structure of the utility model;
[0018] In the attached drawings: 1. Biomass pellet storage bin, 2. Biomass pellet transport belt, 3. Biomass pellet silo, 4. Biomass pellet feeder, 5. Crusher, 6. First biomass bulk transport belt, 7. Biomass bulk silo, 8. Second biomass bulk transport belt, 9. Speed regulator, 10 Fluidized bed boiler. DETAILED DESCRIPTION
[0019] The utility model is further described below in conjunction with the accompanying drawings and specific implementation methods.
[0020] like Figure 1 As shown, the utility model provides a system for mixing biomass bulk material with biomass pellets in a fluidized bed boiler, including a biomass bulk material furnace front feeding device, a biomass pellet material furnace front feeding device, and a fluidized bed boiler 10. The biomass bulk material furnace front feeding device includes a second biomass bulk material conveying belt 8, and the second biomass bulk material conveying belt 8 is connected to the feeding port of the fluidized bed boiler. The biomass pellet material furnace front feeding device includes a biomass pellet feeder 4, and the outlet of the biomass pellet feeder 4 is connected to the secondary air nozzle of the fluidized bed boiler 10. The biomass pellets are easy to burn and have a small volume. They can be sprayed in with the secondary air, and the biomass pellets passing through the secondary air can avoid mixing with the biomass bulk material to cause blockage, thereby realizing the mixed combustion of biomass pellets and biomass bulk material.
[0021] The driving device of the biomass pellet feeder 4 and the second biomass bulk transport belt 8 includes a motor and a speed regulator 9. The speed regulator 9 is provided with a speed sensor. The speed sensor measures the motor speeds of the biomass pellet feeder 4 and the second biomass bulk transport belt 8 respectively, and transmits the speeds to the speed regulator. The motor speeds of the biomass pellet feeder 4 and the second biomass bulk transport belt 8 are adjusted by the speed regulator according to demand to adjust the feeding speed, thereby controlling the feeding amount of biomass pellets and biomass bulk materials, greatly improving the flexibility of biomass power generation fuel.
[0022] Preferably, the speed regulator 9 adopts a mechanical speed regulator or an electronic speed regulator;
[0023] Preferably, the feeding speed is adjusted by adjusting the motor speed of the biomass pellet feeder 4 and the belt conveying speed of the second biomass bulk material conveying belt 8 through a speed regulator, thereby adjusting the feeding speed and thus adjusting the blending ratio.
[0024] Preferably, the biomass pellet feeder 4 is a screw feeder, which can break up agglomerated biomass pellets.
[0025] Preferably, the width of the second biomass bulk material transport belt 8 is 1.6 meters.
[0026] Preferably, the biomass pellet feeding device in front of the furnace also includes a biomass pellet storage bin 1, a biomass pellet conveying belt 2 and a biomass pellet silo 3. The outlet of the biomass pellet storage bin 1 is connected to the inlet of the biomass pellet silo 3 through the biomass pellet conveying belt 2. The outlet of the biomass pellet silo 3 is connected to the inlet of the biomass pellet feeder 4 for storing biomass pellets that can be burned for 6h-12h, thereby ensuring the continuity of feeding to the fluidized bed boiler 10 and ensuring the safety of combustion.
[0027] Preferably, the biomass particle transport belt 2 has an inclination angle of less than 35° and a width of 1.4 meters;
[0028] Preferably, the biomass bulk material pre-furnace feeding device also includes a crusher 5, a first biomass bulk material conveying belt 6 and a biomass bulk material silo 7. The outlet of the crusher 5 is connected to the inlet of the first biomass bulk material conveying belt 6 for feeding the bulk material crushed by the crusher 5 into the first biomass bulk material conveying belt 6. The outlet of the first biomass bulk material conveying belt 6 is connected to the inlet of the biomass bulk material silo 7. The setting of the biomass bulk material silo 7 can ensure the continuity of feeding to the fluidized bed boiler 10, thereby ensuring the safety of combustion. The outlet of the biomass bulk material silo 7 is connected to the feeding port of the fluidized bed boiler through the second biomass bulk material conveying belt 8.
[0029] Preferably, the first biomass bulk material conveying belt 6 and the second biomass bulk material conveying belt 8 have the same width.
[0030] When the fluidized bed boiler system of the utility model is used for simultaneously burning bulk biomass and granular materials, the specific steps are as follows:
[0031] In the first step, technicians adjust the optimal blending ratio of bulk biomass and pellet biomass according to different load requirements to pursue the best economic benefits. The selection of the blending ratio is based on the following: the average calorific value of the fuel meets the full load operation of the unit, the unit performance indicators after blending must be able to reach the design parameters, and there must be no problems such as excessive carbon content in ash; when there are multiple types of bulk biomass, the proportion of low-priced bulk materials should be increased as much as possible while meeting the average calorific value requirements of the fuel.
[0032] In the second step, based on the above determined blending ratio, the biomass pellets and the biomass pellets are introduced into the fluidized bed boiler 10 for combustion and power generation. Specifically:
[0033] The bulk raw materials are sent from the crusher 5 to the biomass bulk silo 7 through the first biomass bulk conveyor belt 6, and then are conveyed to the feed port of the fluidized bed boiler 10 through the second biomass bulk conveyor belt 8, and are burned in the furnace;
[0034] The biomass particles in the biomass particle storage bin 1 are conveyed to the biomass particle silo 3 via the biomass particle conveying belt 2. The storage capacity of the biomass storage bin 3 is 6h-12h of the blending amount. Finally, the biomass particles are conveyed into the furnace of the fluidized bed boiler 10 through the secondary air nozzle via the screw feeder, and the combustion is completed in the furnace.
[0035] Although bulk biomass has a large volume, low density and low combustion calorific value, biomass pellets have a high calorific value and can increase the average calorific value of combustion. Therefore, blending biomass pellets can improve the combustion problems of bulk biomass and enhance the load-carrying capacity of the furnace. The utility model combines the combustion advantages of bulk biomass and pellets, solves the problem of low calorific value of pure burning of bulk biomass, and avoids the high cost of pure burning of pellets. It can maximize economic benefits and combustion efficiency, while improving the adaptability to biomass raw materials and expanding the fuel source for biomass power generation.
[0036] Example 1
[0037] The utility model provides a fluidized bed boiler system for simultaneously co-firing biomass bulk and pellets. The biomass bulk uses straw bulk, and the biomass pellets use straw pellets. The average calorific value of the straw bulk is 2700 kcal, and the average calorific value of the straw pellets is 2900 kcal. The comprehensive average calorific value requirement of the power plant for co-firing is 2840 kcal. Under the premise of ensuring performance indicators, the technicians select the biomass bulk: biomass pellets in a ratio of 7:3 for co-firing according to empirical values, and the ratio can be appropriately adjusted by 0.5.
[0038] The straw bulk material is sent from the crusher 5 to the biomass bulk material bin 7 through the first biomass bulk material transport belt 6, and then is transported to the feed port through the second biomass bulk material transport belt 8 to complete combustion in the furnace.
[0039] In the third step, the straw pellets are transported from the biomass pellet storage bin 1 to the biomass pellet bin 3 via the biomass pellet transport belt 2, and finally fed into the furnace through the secondary air nozzle via the screw feeder for combustion.
[0040] Example 2
[0041] The utility model provides a fluidized bed boiler system for simultaneously burning biomass bulk materials and granular materials, and adopts straw briquettes, engineering plate crushed materials and peanut shell fuel for burning. The average calorific value of the straw briquettes is 2900 kcal, the average calorific value of the engineering plate crushed fuel is 3800 kcal, and the average calorific value of the peanut shell fuel is 3200 kcal. The comprehensive average calorific value requirement of the power plant for burning is 2960 kcal. The burning ratio of the straw briquettes, the engineering plate crushed materials and the peanut shell fuel is calculated according to the experimental ratio of 9:0.5:0.5, and the average calorific value of the fuel can meet the full load operation of the unit.
[0042] The engineering board crushed material and peanut shell fuel will be sent to the biomass bulk bin 7 by the crusher 5 through the first biomass bulk conveyor belt 6, and then transferred to the feed port through the second biomass bulk conveyor belt 8 to complete the combustion in the furnace.
[0043] The straw briquettes are transported from the biomass pellet storage bin 1 to the biomass pellet silo 3 via the biomass pellet transport belt 2, and are finally fed into the furnace through the secondary air nozzle via a screw feeder for combustion.
[0044] Example 3
[0045] The utility model provides a fluidized bed boiler system for simultaneously burning biomass bulk materials and granular materials, adopting straw briquettes, rice husks and peanut shell fuels for burning, the average calorific value of the straw briquettes is 2900 kcal, the average calorific value of the rice husk fuel is 3200 kcal, the average calorific value of the peanut shell fuel is 3200 kcal, the comprehensive average calorific value requirement of the power plant for burning is 2930 kcal, the burning ratio of the straw briquettes, rice husks and peanut shell fuels is calculated according to an experimental ratio of 9:0.5:0.5, and the average calorific value of the fuel can meet the full-load operation requirement of the unit.
[0046] The rice husk and peanut shell fuel are sent from the crusher 5 to the biomass bulk bin 7 through the first biomass bulk transport belt 6, and then are sent to the feed port through the second biomass bulk transport belt 8 to complete combustion in the furnace.
[0047] The straw briquettes are transported from the biomass pellet storage bin 1 to the biomass pellet silo 3 via the biomass pellet transport belt 2, and are finally fed into the furnace through the secondary air nozzle via a screw feeder for combustion.
Claims
1. A fluidized bed boiler system for simultaneously burning bulk biomass and granular biomass. It is characterized in that The invention comprises a biomass pellet furnace front feeding device, a biomass bulk material furnace front feeding device, and a fluidized bed boiler (10). The biomass pellet furnace front feeding device comprises a biomass pellet feeder (4), the outlet of the biomass pellet feeder (4) is connected to the secondary air nozzle of the fluidized bed boiler (10), and the biomass bulk material furnace front feeding device comprises a second biomass bulk material conveying belt (8), and the second biomass bulk material conveying belt (8) is connected to the feed port of the fluidized bed boiler.
2. A fluidized bed boiler system for simultaneously burning bulk biomass and granular biomass according to claim 1, It is characterized in that The biomass pellet feeder (4) is a screw feeder.
3. A fluidized bed boiler system for simultaneously burning bulk biomass and granular biomass according to claim 1, It is characterized in that The width of the second biomass bulk material transport belt (8) is 1.6 meters.
4. A fluidized bed boiler system for simultaneously burning bulk biomass and granular biomass according to claim 1, It is characterized in that The biomass pellet feeder in front of the furnace also includes a biomass pellet silo (3), the inlet of the biomass pellet silo (3) is connected to the outlet of the biomass pellet storage silo (1) through a biomass pellet transport belt (2), and the outlet of the biomass pellet silo (3) is connected to the inlet of the biomass pellet feeder (4).
5. A fluidized bed boiler system for simultaneously burning bulk biomass and granular biomass according to claim 4, It is characterized in that The biomass particle transport belt (2) has an inclination angle of less than 35° and a width of 1.4 meters.
6. A fluidized bed boiler system for simultaneously burning bulk biomass and granular biomass according to claim 4, It is characterized in that The biomass pellet silo (3) stores a biomass pellet material in an amount sufficient for combustion for 6 hours to 12 hours.
7. A fluidized bed boiler system for simultaneously burning bulk biomass and granular biomass according to claim 1, It is characterized in that The biomass bulk material furnace front feeding device also includes a crusher (5), a first biomass bulk material conveying belt (6) and a biomass bulk material silo (7); the outlet of the crusher (5) is connected to the inlet of the first biomass bulk material conveying belt (6); the outlet of the first biomass bulk material conveying belt (6) is connected to the inlet of the biomass bulk material silo (7); and the outlet of the biomass bulk material silo (7) is connected to the inlet of the second biomass bulk material conveying belt (8).
8. A fluidized bed boiler system for simultaneously burning bulk biomass and granular biomass according to claim 7, It is characterized in that The first biomass bulk material conveying belt (6) and the second biomass bulk material conveying belt (8) have the same width.
9. A fluidized bed boiler system for simultaneously burning bulk biomass and granular biomass according to claim 1, It is characterized in that The biomass pellet feeder (4) is connected to a speed regulator, and a speed sensor is arranged on the speed regulator.
10. A fluidized bed boiler system for simultaneously burning bulk biomass and granular biomass according to claim 1, It is characterized in that The second biomass bulk material transport belt (8) is connected to a speed regulator, and a speed sensor is arranged on the speed regulator.