Distribution line stay wire bending manufacturing tool
By designing the distribution line bending and making tooling, the power part is used to drive the sliding of the movable components to achieve bending and shaping, which solves the problems of time consumption and quality in traditional methods, and improves efficiency and stability.
Patent Information
- Application Number
- CN202420643109.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-29
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2034-03-29
AI Technical Summary
The traditional wire pull elbow production method takes a lot of time, is difficult to guarantee quality, and manual force consumption is high, making it difficult to maintain a stable output for a long time.
设计了一种配电线路拉线弯曲制作工装,包括工作台和弯曲定型机构,利用动力部带动活动组件沿弧形导向槽滑移,实现拉线的弯曲定型,提供限位导向防止交叉,减少人力施 force demand.
It improves operating efficiency, saves manpower, ensures the quality of bending of wires, and achieves long-term stable force application output.
Smart Images

Figure CN222077829U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of distribution line drawing wire production, in particular to a distribution line drawing wire bending production tool. Background Art
[0002] During the construction process, in order to balance the tower, the construction workers made the guy wires to balance the horizontal wind force on the tower and the tension of the conductor and lightning arrester. The guy wires of the overhead power line tower usually consist of 7 parts: the guy wire reel, the guy wire U-shaped hanging ring, the guy wire rod, the UT type wire clamp, the steel strand, the wedge-shaped wire clamp upper handle, and the guy wire clamp. The main process of guy wire production is the production of the guy wire handle and the lower handle. Among them, the core step that takes the most time and has the highest quality requirements is the production of the guy wire elbow. The traditional method of making a wire elbow is generally manual production at the construction site using simple auxiliary tools such as wrenches. The construction workers use a marker to measure 420-430mm from the steel strand head to mark it, insert the wire clamp into the steel strand, step on the main line with the left foot, hold the wire end with the right hand, and control the steel strand with the left hand to bend it at the marked point. After bending out the angle, the tail of the wire is inserted into the convex belly of the wire clamp; after inserting a wedge and pulling it tightly, use a wooden hammer to knock it so that there is no gap between the steel strand and the tongue plate, and there is no loose strand phenomenon at the bend.
[0003] In response to the above-mentioned problems, the utility model patent with application number 202110260363.9 discloses a distribution line cable elbow maker, which places the steel strand in the wire trough and the first positioning groove, and the staff rotates the pull rods on both sides of the fixed pulley to bring the two pull rods closer to each other. At this time, the fixed pulley serves as a fulcrum, and the force block on the pull rod applies force to the steel strand to bend the steel strand. However, in actual use of the above technical solution, due to the hard texture of the cable, it needs to be maintained for a certain time during the bending process to achieve a certain bending effect. The manual force pressing method consumes a lot of physical energy for the staff, and it is difficult to maintain a long-term stable force output. As the operation time increases, the quality of the cable is also difficult to guarantee. Summary of the invention
[0004] In order to solve the technical problems existing in the above-mentioned technology, it is necessary to provide a distribution line wire bending and manufacturing tooling.
[0005] A distribution line wire bending tool, comprising a workbench and a bending shaping mechanism arranged inside the workbench;
[0006] The workbench is provided with a first fixed wheel and a second fixed wheel, the first fixed wheel and the second fixed wheel are in the same straight line, and arc-shaped guide grooves bent toward one side of the first fixed wheel are symmetrically provided on both sides of the first fixed wheel, one end of the arc-shaped guide groove is located at the first fixed wheel, and the other end of the arc-shaped guide groove is located at the second fixed wheel;
[0007] The bending and shaping mechanism includes a power unit, a first movable component, and a second movable component. The first movable component and the second movable component are respectively slidably installed in the arc guide groove. The output end of the power unit is respectively connected to the first movable component and the second movable component to drive the first movable component and the second movable component to slide synchronously along the arc guide groove to achieve the bending shaping of the pulling wire.
[0008] Preferably, the first movable component and the second movable component have the same structure, and the first movable component includes a swing arm and a pressing part; the pressing part is arranged in an arc-shaped guide groove, the upper end of the pressing part extends out of the workbench, and the lower end of the pressing part extends into the workbench, one end of the swing arm is fixed to the output end of the power part, and the other end of the swing arm is rotatably connected to the lower end of the pressing part, so that the pressing part can rotate circumferentially along its own axis when the swing arm drives the pressing part to move along the arc-shaped guide groove.
[0009] Preferably, the pressing portion is flush with the first fixed wheel and the second fixed wheel.
[0010] Preferably, the pressing part includes a connecting rod and a pressing wheel; the connecting rod is longitudinally arranged in an arc-shaped guide groove, the upper end of the connecting rod extends out of the workbench, the lower end of the connecting rod is rotatably connected to the swing arm, and the pressing wheel is fixedly arranged at the upper end of the connecting rod, and the pressing wheel is flush with the first fixed wheel and the second fixed wheel.
[0011] Preferably, a gear located below the arc-shaped guide groove is fixedly provided on the connecting rod, and an inner gear ring adapted to mesh with the gear is provided inside the workbench, and the inner gear ring is concentrically arranged with the arc-shaped guide groove.
[0012] Preferably, a positioning mechanism for supporting the first fixed wheel is provided on a side of the first fixed wheel away from the second fixed wheel.
[0013] Preferably, the positioning mechanism includes a telescopic part, and an arc-shaped plate fixed to the protruding end of the telescopic part; the telescopic part is arranged on a workbench, and the telescopic part and the first fixed wheel are in the same straight line, the protruding end of the telescopic part faces the first fixed wheel, and the shape of the arc-shaped plate is adapted to the pull wire.
[0014] Preferably, the arc-shaped plate is provided with a groove adapted to the pull wire.
[0015] Preferably, two limiting grooves are arranged side by side on a side of the second fixed wheel away from the first fixed wheel, and the limiting grooves are in the same straight line as the first fixed wheel and the second fixed wheel.
[0016] Preferably, the workbench is provided with mounting holes, and the mounting holes are evenly distributed from the first fixed wheel to the second fixed wheel, and the first fixed wheels are correspondingly arranged in different mounting holes to meet the requirements of making different wire drawing sizes.
[0017] Compared with the prior art, the power distribution line cable bending tool provided by the utility model places the cable in the groove on the first fixed wheel, and keeps the cable in contact between the first movable component and the first fixed wheel, and between the second movable component and the first fixed wheel, and uses the power unit to drive the first movable component and the second movable component to move synchronously along the arc guide groove, so that the first movable component and the second movable component can roll and squeeze the cable while moving along the arc guide groove toward the second fixed wheel, thereby realizing the bending of the cable. During the bending process, the second fixed wheel can be used to provide a limiting guide for the cable to prevent the cable from crossing when bending, so as to facilitate subsequent binding. When the utility model is in use, there is no need for manpower to apply force to the cable, and only one person is required to operate it, which not only saves manpower and improves work efficiency, but also can provide a long-term stable force output, thereby ensuring the cable bending quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for describing the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0019] Figure 1 It is a schematic diagram of the top structure of the utility model.
[0020] Figure 2 It is a schematic diagram of the structure of the utility model when viewed from above.
[0021] Figure 3 It is a structural schematic diagram of the utility model from another angle.
[0022] Figure 4 For this utility model Figure 3 Schematic diagram of the cross-sectional structure.
[0023] Figure 5 It is a structural schematic diagram of the top pressing part of the utility model.
[0024] Figure 6 It is a structural schematic diagram of the workbench of the utility model.
[0025] In the figure: workbench 01, first fixed wheel 11, second fixed wheel 12, arc guide groove 13, inner gear ring 14, mounting hole 15, bending and shaping mechanism 02, power unit 21, first movable component 22, swing arm 221, top pressing part 222, connecting rod 2221, pressure wheel 2222, gear 2223, second movable component 23, positioning mechanism 03, telescopic part 31, arc plate 32, groove 33, limit groove 04. DETAILED DESCRIPTION
[0026] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0027] In the description of the present invention, it should be understood that the terms "upper", "middle", "outer", "inner", "lower" and the like indicating directions or positional relationships are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the components or elements referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as limitations on the present invention.
[0028] Please see Figures 1 to 6The utility model provides a distribution line wire bending tool, including a workbench 01 and a bending shaping mechanism 02 arranged inside the workbench 01; a first fixed wheel 11 and a second fixed wheel 12 are arranged on the workbench 01, the first fixed wheel 11 and the second fixed wheel 12 are in the same straight line, and arc-shaped guide grooves 13 bent toward one side of the first fixed wheel 11 are symmetrically arranged on both sides of the first fixed wheel 11, one end of the arc-shaped guide groove 13 is located at the first fixed wheel 11, and the other end of the arc-shaped guide groove 13 is located at the second fixed wheel 12. The bending and shaping mechanism 02 includes a power unit 21, a first movable component 22, and a second movable component 23. The first movable component 22 and the second movable component 23 are respectively and correspondingly slidably installed in the arc guide groove 13. The output end of the power unit 21 is respectively connected to the first movable component 22 and the second movable component 23 to drive the first movable component 22 and the second movable component 23 to slide synchronously along the arc guide groove 13 to achieve the bending shaping of the tension wire; wherein, the power unit 21 can use a variable frequency motor to drive a single-input and dual-output reducer, so that the power unit 21 can synchronously drive the first movable component 22 and the second movable component 23. When in use, by placing the pull wire in the groove 33 on the first fixed wheel 11, since the pull wire will stretch outward, the pull wire will interfere between the first movable component 22 and the first fixed wheel 11, and between the second movable component 23 and the first fixed wheel 11. We can use the power unit 21 to drive the first movable component 22 and the second movable component 23 to move synchronously along the arc guide groove 13, so that the first movable component 22 and the second movable component 23 can roll and squeeze the pull wire while moving along the arc guide groove 13 toward the second fixed wheel 12, thereby realizing the bending of the pull wire. During the bending process, the second fixed wheel 12 can be used to provide a limiting guide for the pull wire to prevent the pull wire from crossing when bending, so as to facilitate subsequent binding. During the entire pull wire bending process, there is no need for manpower to apply force to the pull wire, and only one person is needed to operate it, which not only saves manpower and improves work efficiency, but also can provide a long-term stable force output, thereby ensuring the bending quality of the pull wire.
[0029] In one embodiment, the first movable assembly 22 and the second movable assembly 23 adopt the same structure. The first movable assembly 22 includes a swing arm 221 and a pressing portion 222; the pressing portion 222 is arranged in the arc-shaped guide groove 13, the upper end of the pressing portion 222 extends out of the workbench 01, and the lower end of the pressing portion 222 extends into the workbench 01. One end of the swing arm 221 is fixed to the output end of the power unit 21, usually in a key connection manner; and the other end of the swing arm 221 is rotatably connected to the lower end of the pressing portion 222. When the swing arm 221 is driven by the power unit 21, the swing arm 221 will drive the pressing part 222 to move along the arc guide groove 13. At the same time, since the end of the swing arm 221 is rotatably connected to the pressing part 222, the pressing part 222 can rotate circumferentially along its own axis. The pressing part 222 can be used to form a rolling extrusion on the pull wire, which can not only avoid greater wear on the outer wall of the pull wire after hard contact, but also reduce the resistance when extruding the pull wire to save power consumption.
[0030] Specifically, in order to ensure the quality of the cable when it is bent and prevent the cable from being bent, the pressing portion 222 is flush with the first fixed wheel 11 and the second fixed wheel 12 .
[0031] Specifically, the pressing part 222 includes a connecting rod 2221 and a pressing wheel 2222; the connecting rod 2221 is longitudinally arranged in the arc guide groove 13, the upper end of the connecting rod 2221 extends out of the workbench 01, the lower end of the connecting rod 2221 is rotatably connected to the swing arm 221, and the pressing wheel 2222 is fixedly arranged at the upper end of the connecting rod 2221, and the pressing wheel 2222 is flush with the first fixed wheel 11 and the second fixed wheel 12.
[0032] Specifically, a gear 2223 located below the arc-shaped guide groove 13 is fixedly provided on the connecting rod 2221, and an inner gear ring 14 is provided inside the workbench 01 to mesh with the gear 2223, and the inner gear ring 14 is arranged concentrically with the arc-shaped guide groove 13. When the power unit 21 drives the swing arm 221 to rotate, the swing arm 221 will drive the connecting rod 2221 to not only move along the arc-shaped guide groove 13, but also assist the connecting rod 2221 to achieve self-rotation through the meshing of the gear 2223 and the inner gear ring 14, and at this time, the pressure wheel 2222 can form a stable rolling extrusion on the wire.
[0033] In one embodiment, a positioning mechanism 03 is provided on the side of the first fixed wheel 11 away from the second fixed wheel 12. The positioning mechanism 03 is used to support the pull wire in the groove 33 of the first fixed wheel 11 to prevent the pull wire from bulging at the end when bending, thereby ensuring the bending quality of the pull wire.
[0034] Specifically, the positioning mechanism 03 includes a telescopic portion 31 and an arc plate 32 fixed to the extended end of the telescopic portion 31; the telescopic portion 31 is disposed on the workbench 01, and the telescopic portion 31 is in the same straight line as the first fixed wheel 11, the extended end of the telescopic portion 31 faces the first fixed wheel 11, and the shape of the arc plate 32 matches the pull wire. The telescopic portion 31 can be any one of an electric telescopic rod, a pneumatic telescopic rod, and a hydraulic cylinder.
[0035] The arc plate 32 is provided with a groove 33 adapted to the pull wire.
[0036] In one embodiment, two limiting grooves 04 are arranged side by side on the side of the second fixed wheel 12 away from the first fixed wheel 11, and the limiting groove 04 is in the same straight line as the first fixed wheel 11 and the second fixed wheel 12. When the pull wire is rolled and squeezed to achieve bending, the pull wire can be placed in the limiting groove 04 to ensure that the pull wire is straight, thereby facilitating subsequent binding.
[0037] In one embodiment, mounting holes 15 are provided on the workbench 01, and the mounting holes 15 are evenly distributed from the first fixed wheel 11 to the second fixed wheel 12. The first fixed wheel 11 is correspondingly arranged in different mounting holes 15 to meet the requirements of making different wire sizes.
[0038] The above disclosure is only a preferred embodiment of the present invention, and it certainly cannot be used to limit the scope of the present invention. A person skilled in the art can understand that all or part of the processes of the above embodiments and equivalent changes made according to the claims of the present invention still fall within the scope of the present invention.
Claims
1. A tool for bending and manufacturing distribution line wires, characterized in that: It includes a workbench and a bending and shaping mechanism arranged inside the workbench; The workbench is provided with a first fixed wheel and a second fixed wheel, the first fixed wheel and the second fixed wheel are in the same straight line, and arc-shaped guide grooves bent toward one side of the first fixed wheel are symmetrically provided on both sides of the first fixed wheel, one end of the arc-shaped guide groove is located at the first fixed wheel, and the other end of the arc-shaped guide groove is located at the second fixed wheel; The bending and shaping mechanism includes a power unit, a first movable component, and a second movable component. The first movable component and the second movable component are respectively slidably installed in the arc guide groove. The output end of the power unit is respectively connected to the first movable component and the second movable component to drive the first movable component and the second movable component to slide synchronously along the arc guide groove to achieve the bending shaping of the pulling wire.
2. The power distribution line wire bending tool according to claim 1 is characterized in that: The structures of the first movable component and the second movable component are the same. The first movable component includes a swing arm and a pressing part. The pressing part is arranged in an arc-shaped guide groove, the upper end of the pressing part extends out of the workbench, and the lower end of the pressing part extends into the workbench. One end of the swing arm is fixed to the output end of the power part, and the other end of the swing arm is rotatably connected to the lower end of the pressing part, so that when the swing arm drives the pressing part to move along the arc-shaped guide groove, the pressing part can rotate circumferentially along its own axis.
3. The power distribution line wire bending tool according to claim 2 is characterized in that: The pressing portion is flush with the first fixed wheel and the second fixed wheel.
4. The power distribution line wire bending tool according to claim 3 is characterized in that: The pressing part includes a connecting rod and a pressing wheel; the connecting rod is longitudinally arranged in an arc-shaped guide groove, the upper end of the connecting rod extends out of the workbench, the lower end of the connecting rod is rotatably connected to the swing arm, and the pressing wheel is fixedly arranged at the upper end of the connecting rod, and the pressing wheel is flush with the first fixed wheel and the second fixed wheel.
5. The power distribution line wire bending tool according to claim 4 is characterized in that: A gear located below the arc-shaped guide groove is fixedly arranged on the connecting rod, and an inner gear ring meshing with the gear is arranged inside the workbench, and the inner gear ring is concentrically arranged with the arc-shaped guide groove.
6. The distribution line wire bending tool according to claim 1 is characterized in that: A positioning mechanism for supporting the first fixed wheel is arranged on a side of the first fixed wheel away from the second fixed wheel.
7. The power distribution line wire bending tool according to claim 6, characterized in that: The positioning mechanism includes a telescopic part and an arc plate fixed to the extended end of the telescopic part; the telescopic part is arranged on a workbench, and the telescopic part and the first fixed wheel are in the same straight line, the extended end of the telescopic part faces the first fixed wheel, and the shape of the arc plate is adapted to the pull wire.
8. The power distribution line wire bending tool according to claim 7, characterized in that: The arc plate is provided with a groove adapted to the pull wire.
9. The power distribution line wire bending tool according to claim 1, characterized in that: Two limiting grooves are arranged side by side on a side of the second fixed wheel away from the first fixed wheel, and the limiting grooves are in the same straight line as the first fixed wheel and the second fixed wheel.
10. The distribution line wire bending tool according to claim 1, characterized in that: The workbench is provided with mounting holes, which are evenly distributed from the first fixed wheel to the second fixed wheel. The first fixed wheel is correspondingly arranged in different mounting holes to meet the requirements of making different wire sizes.