Reinforcing system for soil body at inlet and outlet of jacking pipe

By setting up a water stop curtain, bottom cover reinforcement and stirring and solidification at the entrances of the top pipe, combined with fiber adhesive to make the sand and soil cohesive, the problem of water and sand gushing in high-pressure water head areas is solved, and effective The soil and water closure and construction costs are reduced.

CN222120286UActive Publication Date: 2024-12-06CHINA RAILWAY 24TH BUREAU GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420769196.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-15
Publication Date
2024-12-06
Estimated Expiration
2034-04-15

AI Technical Summary

Technical Problem

In high-pressure water-head sandy soil areas, there is a risk of water gushing and sand gushing when the head pipe enters the hole. Unilateral soil improvement cannot completely avoid this risk because the sandy soil has no adhesion to the water, resulting in soil and water flow Entering the well causes economic losses.

Method used

Using a combination of water stop curtain, back cover reinforcement and stirring solids, a water stop curtain and back cover reinforcement are installed on one side of the caisson, and fiber adhesive is added to the soil to make the sand and soil sticky through stirring construction. Gather force to form mud film to prevent water and soil from flowing in.

Benefits of technology

Effectively seal the water barrier to avoid the risk of water and sand gushing, reduce construction investment costs, and the modified sand and soil are closely fitted with the top pipe pipe to prevent soil and water from flowing in.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222120286U_ABST
    Figure CN222120286U_ABST
Patent Text Reader

Abstract

The utility model relates to a reinforcing system for soil mass at the entrance and exit of a pipe jacking, which comprises a waterproof curtain, a bottom sealing reinforcing body and a stirring reinforcing body, the waterproof curtain is arranged on the periphery of the entrance and exit of an open caisson and forms an enclosed structure with the open caisson, the bottom sealing reinforcing body is arranged in an enclosed area of the waterproof curtain, and a pile top is positioned below the entrance and exit of the open caisson; the stirring reinforcing body is located above the bottom sealing reinforcing body and located in an enclosure area of the waterproof curtain, and the height of the stirring reinforcing body covers the opening position of the open caisson. The open caisson has the advantages that the open caisson opening soil body is modified, and the modified sandy soil has the performance of clay; when the jacking pipe penetrates through the reinforcing area, a jacking pipe pipeline is tightly attached to the modified sandy soil, the modified sandy soil has the cohesive force characteristic, a mud film is formed between the modified sandy soil and the pipe wall of the jacking pipe, water and soil outside the reinforcing area can be prevented from flowing into a well, and therefore the risk of water gushing and sand gushing is avoided; and the construction investment cost is low, and the risks of water gushing and sand gushing are avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a soil reinforcement system at a top pipe inlet and outlet hole. Background Art

[0002] With the rapid development of urbanization, the growing population has put forward higher demands on the infrastructure of most cities in my country. The tap water supply pipeline project is one of the more common projects in municipal engineering, and its construction quality is related to the drinking water problem of people's livelihood. The construction of the jacking project is to design two foundation pits at the starting point and receiving point of the pipeline, and the foundation pit at the receiving point of the pipeline adopts a caisson sinking system. In water-rich sandy soil areas, there is a general risk of water and sand gushing when the jacking pipe enters the cave. In general, the designer improves the soil in the inlet and outlet area during the design, and most of them use deep mixing piles to reinforce the soil. This method has a certain effect in actual engineering. However, when the pipeline is located in the confined water layer, under the action of high confined water head, the water and soil outside the reinforcement area will flow along the gap between the pipe wall and the soil, and flow into the well when the jacking pipe enters the cave. If the water cannot be stopped, it will bring huge economic losses.

[0003] In summary, when the jacking pipe enters the cave in the sandy soil area with high pressure head, the risk of water and sand gushing cannot be completely avoided by unilateral soil improvement. The key problem is that the sandy soil will flow with the water when it encounters water, and there is no adhesion between the soil bodies of this type of soil. To solve this kind of problem, the soil body is essentially replaced, but the buried position of the jacking pipe is generally deep, and large-scale soil replacement is very uneconomical. Therefore, it is necessary to develop a soil reinforcement system at the entrance and exit of the jacking pipe, which is the key to solving the above technical problems. Summary of the invention

[0004] The purpose of the utility model is to provide a soil reinforcement system at the entrance and exit of the caisson in response to the above-mentioned deficiencies of the prior art. By arranging a water-stop curtain, a bottom reinforcement body and a stirring reinforcement body on one side of the caisson, the soil at the entrance and exit of the caisson is reinforced to achieve a water-proof and sealed effect. At the same time, when the jacking pipe passes through the reinforced area, the jacking pipe and the modified sand are tightly fitted. The modified sand has cohesive properties and forms a mud film between the jacking pipe wall, which can prevent water and soil outside the reinforcement area from flowing into the well, thereby avoiding the risk of water and sand gushing.

[0005] The purpose of this utility model is achieved by the following technical solutions:

[0006] A soil reinforcement system at the entrance and exit of a jacking pipe is arranged on the other side of the jacking direction of a caisson, and is characterized in that it includes a water-stop curtain, a bottom reinforcement body and a mixing reinforcement body, wherein the water-stop curtain is arranged at the periphery of the entrance and exit of the caisson and forms an enclosure structure with the caisson, the bottom reinforcement body is arranged in the enclosure area of ​​the water-stop curtain and the pile top is located below the entrance and exit of the caisson, the mixing reinforcement body is located above the bottom reinforcement body and in the enclosure area of ​​the water-stop curtain, and the height of the mixing reinforcement body covers the entrance and exit position of the caisson.

[0007] The water-stop curtain is an MJS pile, the pile bottom depth of which is located below the bottom of the entrance and exit opening of the caisson, and the pile top is located at the original ground.

[0008] The bottom sealing water-stopping body is an MJS method pile, and the pile top is located below the bottom of the entrance and exit opening of the caisson.

[0009] The mixing reinforcement body is constructed by mixing.

[0010] The advantages of the utility model are: the soil at the caisson hole entrance is modified, and the modified sand has the properties of clay; when the jacking pipe passes through the reinforced area, the jacking pipe and the modified sand fit tightly, and the modified sand has cohesive properties, forming a mud film between the jacking pipe wall, which can prevent water and soil outside the reinforced area from flowing into the well, thereby avoiding the risk of water and sand gushing; the construction investment cost is relatively small, and the risk of water and sand gushing is avoided. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is the elevation layout diagram of the utility model;

[0012] Figure 2 This is a plan layout diagram of the utility model. DETAILED DESCRIPTION

[0013] The following is a further detailed description of the features of the present invention and other related features through embodiments in conjunction with the accompanying drawings to facilitate understanding by technicians in the same industry:

[0014] like Figure 1-2 As shown, the marks 1-4 in the figure respectively represent: caisson 1, soil reinforcement area of ​​the cave entrance 2, water-stop curtain 3, and bottom water-stop body 4.

[0015] Example: Figure 1 and Figure 2 As shown, the soil reinforcement system for the entrance and exit of the jacking pipe in this embodiment is used to reinforce the soil at the entrance and exit positions of the caisson 1.

[0016] Specifically, combined Figure 1 and Figure 2As shown, after the construction of the caisson 1 is completed, the soil at the entrance and exit of the caisson 1 is further reinforced. First, the three-side water-stop curtains 3 outside the soil reinforcement area 2 at the entrance are constructed, and each side is connected to the shaft of the caisson 1, so that a closed loop is formed around the soil reinforcement area 2 at the entrance. In this embodiment, the water-stop curtain 3 uses MJS construction method piles, the depth of the pile bottom reaches no less than 5m below the bottom of the entrance, and the pile top is located at the original ground.

[0017] Then, the bottom sealing water stop body 4 is constructed on the bottom of the hole soil processing area 2, so that the surrounding of the hole soil reinforcement area 2 corresponding to the hole entrance and exit position of the caisson 1 is completely closed to achieve the effect of water-proof sealing. In this embodiment, the bottom sealing water stop body 4 also uses MJS construction method piles for bottom sealing water stop construction, the pile top is located at least 2m below the bottom of the hole, and the pile length is 2-3m.

[0018] After the MJS construction piles serving as the bottom water stop 4 reach a certain strength, the soil in the tunnel entrance reinforcement area 2 is modified. The modified sand is constructed by mixing piles. Fiber adhesives are added to the sandy soil to make the sandy soil have cohesion, so that the sand has the properties of clay. The amount of fiber adhesive added is 40%-60%.

[0019] When in use, the soil at the entrance and exit of the caisson 1 is closed-loop and stirred and reinforced by the water-stop curtain 3 and the bottom water-stop body 4, so as to achieve the effect of water-proof sealing; at the same time, when the jacking pipe passes through the reinforced area from the entrance and exit of the caisson 1, the jacking pipe and the modified sand in the reinforced area 2 of the soil at the entrance are tightly fitted. The modified sand has cohesive properties and forms a mud film between the jacking pipe wall, which can prevent water and soil outside the reinforced area from flowing into the well, thereby avoiding the risk of water and sand gushing.

[0020] Although the above embodiments have described the concepts and embodiments of the purpose of the utility model in detail with reference to the accompanying drawings, ordinary technicians in this field can recognize that various improvements and modifications can still be made to the utility model without departing from the scope of the claims, so they are not described one by one here.

Claims

1. A soil reinforcement system at the entrance and exit of the jacking pipe, arranged on the other side of the caisson jacking direction, characterized in that: It includes a water-stop curtain, a bottom reinforcement body and a mixing reinforcement body, wherein the water-stop curtain is arranged at the periphery of the entrance and exit hole of the caisson and forms an enclosure structure with the caisson, the bottom reinforcement body is arranged in the enclosure area of ​​the water-stop curtain and the pile top is located below the entrance and exit hole of the caisson, the mixing reinforcement body is located above the bottom reinforcement body and in the enclosure area of ​​the water-stop curtain, and the height of the mixing reinforcement body covers the entrance and exit hole position of the caisson.

2. A soil reinforcement system at the entrance and exit of a jacking pipe according to claim 1, characterized in that: The water-stop curtain is an MJS pile, the pile bottom depth of which is located below the bottom of the entrance and exit opening of the caisson, and the pile top is located at the original ground.

3. A soil reinforcement system at the entrance and exit of a jacking pipe according to claim 1, characterized in that: The bottom sealing water-stopping body is an MJS method pile, and the pile top is located below the bottom of the entrance and exit opening of the caisson.