By designing the sample preparation device of automatic metering sand filling body test block, the problem of low automation of preparation of tailing sand cement filling body test blocks is solved, and efficient research on the mechanical properties of tailing sand cement filling body is achieved, and sample preparation efficiency and measurement are improved. Accuracy avoids moisture volatility and labor intensity during tailing sand transportation.
Patent Information
- Application Number
- CN202420589763.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-26
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-03-26
AI Technical Summary
The existing tailings sand cemented filling test block preparation process has low degree of automation, low production efficiency and high labor intensity, and the viscosity of tailings sand is not high in metrology accuracy, so it is impossible to achieve automated research on the mechanical properties of tailings sand cemented filling.
An automatic metering tailings filling body sample preparation device was designed. By setting up weighing sensors and motor-driven twisting dragons in the tailings sand chamber, gelling material chamber and water chamber, combining valves and discharge pipes to achieve the accuracy of raw materials. Measuring and automatic input, stirring and slurry distribution are used to use a stirring pot and buffer chamber, and automated test block preparation is achieved through a test mold clamp.
Improve the automation degree of the mechanical properties of tailings sand cement filling body and sample preparation work efficiency, ensure the accuracy of slurry ratio, avoid the problem of moisture volatility during tailings sand transportation, and realize the self-cleaning of the device, improve the filling Measuring accuracy and test accuracy of the material.
Smart Images

Figure CN222124893U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a tailings filling body test block sample preparation device. Background Art
[0002] As environmental protection issues are becoming more and more important and deep-mine mining operations are putting forward higher and higher safety requirements, backfill mining is being adopted by more and more mines, and backfill mining has developed into the mainstream mining method for mineral resource exploitation. In order to better play the technical advantages of high-concentration (paste) cemented backfilling technology of tailings, mastering and regulating the mechanical properties of cemented backfills is also receiving more and more attention. The research carrier of the mechanical properties of cemented backfills of tailings is mainly the backfill test block.
[0003] At present, the preparation of tailings cemented filling body test blocks is mainly done by manual operation, which generally has the disadvantages of low automation, low production efficiency and high labor intensity. The Chinese invention patent application with publication number CN115875074A discloses a "low-cost and high-quality mining cemented filling method", which involves a method for preparing slurry into test blocks. In order to improve the slurry ratio accuracy, it adopts a static metering method, and the filling materials, filter tailings, cement solids, and water are metered and fed respectively, and a vertical multi-axis activation stirring method is adopted. After stirring, the slurry enters a secondary stirring tank to obtain a slurry. Then, according to the slurry ratio, the slurry is prepared into a test block, and a 7.07cm×7.07cm×7.07cm standard triple test mold is used. In order to ensure that the slurry does not precipitate during the casting process of the test block, a test block casting method of stirring and casting the mold is adopted. The static metering and feeding process of the filling material filter press tailings is as follows: the filter press tailings are loaded by a loader to the filter press tailings feeding metering equipment, which includes a filter press tailings feeder, a weighing sensor, a hopper, a belt, and a control system. After the filter press tailings enters the hopper of the filter press tailings feeder, the weighing sensor measures the weight, and then the material is sent out through the belt. The control system will set the delivery amount. When the set value is reached, the control system stops the belt feeding, and the measured filter press tailings enters the vertical multi-axis activated mixer through the inclined belt.
[0004] Although the patent application technology can improve the slurry ratio accuracy to a certain extent, the tailings need to be sent out through the belt after being measured by the weighing sensor. On the one hand, because the tailings have strong viscosity, they are easy to stick to the belt, and when the control system sends a signal to stop the belt feeding, the tailings on the conveyor belt will still fall by inertia. Therefore, the use of belt feeding after measurement will still result in insufficient accuracy of the tailings entering the mixer. On the other hand, this method cannot automatically prepare tailings cemented filling body test blocks. It is necessary to take the prepared slurry separately and transfer it to the triple test mold. The test block preparation link still has the disadvantages of low automation, low production efficiency and high labor intensity. Utility Model Content
[0005] The problem to be solved by the utility model is to provide a device for automatically measuring tailings filling body test block sample preparation, which further improves the automation degree of the sample preparation process on the basis of accurate batching and improves the sample preparation work efficiency.
[0006] The technical solution of the utility model is as follows:
[0007] An automatic metering tailings filling body test block sample preparation device comprises a box body, wherein a tailings chamber, a cementitious material chamber and a water tank are arranged in parallel on the upper end surface of the box body, wherein the tailings chamber, the cementitious material chamber and the water tank are respectively connected to a first weighing sensor, a second weighing sensor and a third weighing sensor; a tailings discharge pipe with a first valve is connected to the lower end of the tailings chamber, a cementitious material discharge pipe with a second valve is connected to the lower end of the cementitious material chamber, and a water discharge pipe with a third valve is connected to the lower end of the water tank; a stirring pot with an open upper end and a buffer chamber located below the stirring pot and open at the upper end are installed inside the box body, and a fourth weighing sensor is installed below the buffer chamber; a buffer chamber discharge pipe with a fifth valve is installed in the buffer chamber; The stirring pot is provided with a discharge pipe at the lower end, and a fourth valve is installed on the discharge pipe; the outlets of the tailings discharge pipe, the cementitious material discharge pipe and the water discharge pipe are located directly above the upper port of the stirring pot; the discharge pipe outlet at the lower end of the stirring pot is located directly above the upper port of the buffer chamber; the sample preparation device also includes a test mold fixture arranged inside the box body and horizontally running below the discharge pipe outlet of the buffer chamber, and a triple test mold is installed in the test mold fixture; a slider is installed at the bottom of the test mold fixture, and the slider is slidably installed on the slide rail; the sample preparation device also includes a nut fixedly installed on the test mold fixture and a lead screw transmission-connected to the nut; the lead screw is connected to a power mechanism for driving the lead screw to rotate.
[0008] Preferably, a first auger driven by a first motor is installed in the tailings chamber, and a second auger driven by a second motor is installed in the cementitious material chamber.
[0009] Preferably, the stirring pot is connected to the box body via a first bracket.
[0010] Preferably, the cache chamber is connected to the box body via a second bracket.
[0011] Preferably, the fourth weighing sensor is mounted on a third bracket, and the third bracket is connected to the box.
[0012] Preferably, the trial mold fixture is also equipped with a cleaning trough.
[0013] Compared with the prior art, the utility model has the following beneficial effects:
[0014] First, the utility model uses weighing sensors respectively arranged under the tailings chamber, cementitious material chamber, water tank and buffer chamber to accurately measure the proportion of tailings, cementitious materials and water, as well as the amount of tailings cementing filling materials distributed to each test mold. It can ensure that in the mechanical property research test of tailings cementing filling body, the adjustment of the proportion of ingredients is more convenient and accurate. The whole process operation from raw material input to test block output is realized through valve opening and closing and motor opening and closing control, and the degree of automation and sample preparation efficiency are higher.
[0015] Second, since the utility model can realize the whole process from raw material input to test block output, it avoids the trouble of transporting tailings cementing filling materials in the prior art, and avoids the problem of water volatilization of tailings cementing filling materials during transportation. It further improves the metering accuracy of filling materials and the accuracy of the test.
[0016] Third, the utility model can utilize the water in the water tank to self-clean the stirring pot, the stirring pot stirrer, the buffer chamber and the buffer chamber discharge pipe without the need for an attached cleaning mechanism. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a structural schematic diagram of an embodiment of the utility model.
[0018] In the figure, 1. box body, 2. control panel, 3. water tank, 4. cementitious material chamber, 5. second motor, 6. second auger, 7. first motor, 8. tailings chamber, 9. first auger, 10. first weighing sensor, 11. second weighing sensor, 12. third weighing sensor, 13. tailings discharge pipe, 14. first valve, 15. cementitious material discharge pipe, 16. second valve, 17, water discharge pipe, 18. third valve, 19. first bracket, 20. fourth valve, 21. second bracket, 22. third bracket, 23. trial mold fixture, 24. lead screw, 25. slider, 26. nut, 27. bearing mechanism, 28. fourth motor, 29. cache chamber discharge pipe, 30. fifth valve, 31. cache chamber, 32. stirring pot agitator, 33. stirring pot, 34. third motor, 35. fourth weighing sensor. DETAILED DESCRIPTION
[0019] The utility model is described in detail below in conjunction with the embodiments and drawings.
[0020] like Figure 1The embodiment of the utility model comprises a box body 1, wherein a tailings chamber 8, a cementing material chamber 4 and a water tank 3 are arranged in parallel on the upper end surface of the box body 1, and a first weighing sensor 10, a second weighing sensor 11 and a third weighing sensor 12 are respectively installed between the tailings chamber 8, the cementing material chamber 4 and the water tank 3 and the upper end surface of the box body 1. A first auger 9 driven by a first motor 7 is installed in the tailings chamber 8, and a second auger 6 driven by a second motor 5 is installed in the cementing material chamber 4. A tailings discharge pipe 13 with a first valve 14 is connected to the lower end of the tailings chamber 8, a cementing material discharge pipe 15 with a second valve 16 is connected to the lower end of the cementing material chamber 4, and a water discharge pipe 17 with a third valve 18 is connected to the lower end of the water tank 3. The tailings discharge pipe 13, the cementing material discharge pipe 15 and the water discharge pipe 17 respectively pass through the through holes opened on the upper end plate of the box body 1 from top to bottom. The through hole has a relatively large inner diameter to prevent the tubes from contacting the hole wall and interfering with the operation of the weighing sensor.
[0021] The box 1 is provided with a stirring pot 33 with an open top and a buffer chamber 31 located below the stirring pot 33 and with an open top, and a fourth weighing sensor 35 is provided below the buffer chamber 31. A buffer chamber discharge pipe 29 with a fifth valve 30 is provided at the lower end of one side of the buffer chamber 31. A stirring pot stirrer 32 driven by a third motor 34 is provided in the stirring pot 33. A discharge pipe is provided at the lower end of the stirring pot 33, and a fourth valve 20 is provided on the discharge pipe.
[0022] The outlets of the tailings discharge pipe 13, the gelling material discharge pipe 15 and the water discharge pipe 17 are located just above the upper port of the stirring pot 33. The outlet of the discharge pipe at the lower end of the stirring pot 33 is located just above the upper port of the buffer chamber 31.
[0023] This embodiment further comprises a test mold fixture 23 running horizontally below the outlet of the buffer chamber discharge pipe 29, wherein a triple test mold is installed in the test mold fixture 23. A slider 25 is installed at the bottom of the test mold fixture 23, and the slider 25 is slidably installed on a slide rail.
[0024] This embodiment further includes a nut 26 fixedly mounted on the bottom side of the trial mold fixture 23 and a lead screw 24 drivingly connected to the nut 26 , wherein the lead screw 24 is mounted on a bearing mechanism 27 .
[0025] This embodiment also includes a power mechanism disposed outside the box 1 and used to drive the lead screw 24 to rotate. The power mechanism is generally a reduction motor or a motor and a reducer connected to each other in a transmission manner. In this embodiment, it is a fourth motor 28 and a reducer connected to each other in a transmission manner. The power output shaft of the reducer is connected to the lead screw 24 through a coupling. The forward and reverse rotation of the fourth motor 28 is controlled to achieve the advance and retreat of the test mold fixture 23.
[0026] The stirring pot 33 is connected to the box body 1 through the first bracket 19. The buffer chamber 31 is connected to the box body 1 through the second bracket 21. The fourth weighing sensor 35 is located and installed on the third bracket 22, and the third bracket 22 is connected to the box body 1.
[0027] The first motor 7, the second motor 5 and the third motor 3 are all reduction motors. The trial mold fixture 23 is also equipped with a cleaning trough for containing the stirring pot and the buffer chamber cleaning liquid.
[0028] This embodiment further includes a control panel 2 installed on the outside of the box 1, and the control panel 2 is connected to a controller, and the controller is respectively connected to the first motor 7, the second motor 5, the third motor 3, the fourth motor 28, the first valve 14, the second valve 16, the third valve 18, the fourth valve 20, the fifth valve 30, the first weighing sensor 10, the second weighing sensor 11, the third weighing sensor 12 and the fourth weighing sensor 35. The controller collects the weighing sensor data and controls the opening and closing of the motor and the valve, and controls the forward and reverse switching of the fourth motor 28.
[0029] The test parameters include tailings density r t , water density r w , density of cementitious materials r b 、 Lime-sand ratio n (tailings: cementitious material = 1:n), triple mold size (for example: 70.7mm×70.7mm×70.7mm), stirring slurry mass M, stirring slurry concentration w, stirring time T. The controller completes the calculation of tailings, cementitious material, water volume and filling slurry density required for one block making according to the input parameters, and realizes the metering of related materials by controlling the start and stop of the reduction motor.
[0030] The working process of the device is as follows:
[0031] (1) Add tailings, cementitious materials and water to the tailings chamber 8, cementitious materials chamber 4 and water tank 3 respectively; enter the tailings density r t , water density r w , density of cementitious materials r b 、 Lime-sand ratio n (tailings: cementitious material = 1:n), triple test mold size (70.7 mm × 70.7 mm × 70.7 mm), stirring slurry mass M, stirring slurry concentration w, stirring time T and other related parameters; put the triple test mold into the test mold fixture 23 and fix it, and start the main power supply of the device.
[0032] (2) The third valve 18 is opened, and water flows to the stirring pot 33. The third weighing sensor 12 records the mass change of the water tank 3. When the amount of water discharged from the water tank is equal to the required amount of water, the third valve 18 is closed; the first motor 7 and the second motor 5 are turned on, and the first motor 7 and the second motor 5 drive the first auger 9 and the second auger 6 to rotate respectively. The tailings and the cementitious material are respectively measured by the first weighing sensor 10 and the second weighing sensor 11 and enter the stirring pot 33.
[0033] (3) When the third valve 18 is opened, the third motor 34 is started. When the tailings and the cementitious material are added, the timing starts, and the stirring time is T min.
[0034] (4) After stirring for T min, open the fourth valve 20 and the slurry enters the buffer chamber 31. Close the third motor 34 and the fourth valve 20, start the fourth motor 28, and the test mold fixture 23 moves below the outlet of the discharge pipe 29 of the buffer chamber. Open the fifth valve 30 and put the slurry into the triple test mold in sequence.
[0035] (5) After the loading is completed, the test mold fixture 23 is withdrawn and the triple test mold is removed for maintenance.
[0036] (6) Place the cleaning material tank into the trial mold fixture 23, and move the trial mold fixture 23 toward the lower side of the outlet of the buffer chamber discharge pipe 29. Open the third valve 18 to clean the stirring pot 33, stirring pot stirrer 32, buffer chamber 31 and buffer chamber discharge pipe 29.
Claims
1. An automatic measuring tailings filling body test block sample preparation device, comprising a box body (1), wherein a tailings chamber (8), a cementitious material chamber (4) and a water tank (3) are arranged in parallel on the upper end surface of the box body (1), characterized in that: The tailings chamber (8), the cementitious material chamber (4) and the water tank (3) are respectively connected to a first weighing sensor (10), a second weighing sensor (11) and a third weighing sensor (12); the lower end of the tailings chamber (8) is connected to a tailings discharge pipe (13) with a first valve (14); the lower end of the cementitious material chamber (4) is connected to a cementitious material discharge pipe (15) with a second valve (16); the lower end of the water tank (3) is connected to a water discharge pipe (17) with a third valve (18); a stirring pot (33) with an open top and a buffer chamber (31) located below the stirring pot (33) and open at the top are installed inside the box body (1); a fourth weighing sensor (35) is installed below the buffer chamber (31); a buffer chamber discharge pipe (29) with a fifth valve (30) is installed in the buffer chamber (31); a discharge pipe is provided at the lower end of the stirring pot (33), and a valve (29) is provided on the discharge pipe. A fourth valve (20) is installed; the outlets of the tailings discharge pipe (13), the cementitious material discharge pipe (15) and the water discharge pipe (17) are located directly above the upper port of the stirring pot (33); the outlet of the discharge pipe at the lower end of the stirring pot (33) is located directly above the upper port of the buffer chamber (31); the sample preparation device also includes a test mold fixture (23) arranged inside the box body (1) and horizontally running below the outlet of the discharge pipe (29) of the buffer chamber, and a triple test mold is installed in the test mold fixture (23); a slider (25) is installed at the bottom of the test mold fixture (23), and the slider (25) is slidably installed on a slide rail; the sample preparation device also includes a nut (26) fixedly installed on the test mold fixture (23) and a lead screw (24) drivingly connected to the nut (26); the lead screw (24) is connected to a power mechanism for driving the lead screw (24) to rotate.
2. The automatic measuring tailings filling body test block sample preparation device according to claim 1, characterized in that: A first auger (9) driven by a first motor (7) is installed in the tailings chamber (8), and a second auger (6) driven by a second motor (5) is installed in the cementitious material chamber (4).
3. The automatic measuring tailings filling body test block sample preparation device according to claim 1, characterized in that: The stirring pot (33) is connected to the box (1) via a first bracket (19).
4. The automatic measuring tailings filling body test block sample preparation device according to claim 1, characterized in that: The cache chamber (31) is connected to the box body (1) via a second bracket (21).
5. The automatic measuring tailings filling body test block sample preparation device according to claim 1, characterized in that: The fourth weighing sensor (35) is mounted on a third bracket (22), and the third bracket (22) is connected to the box (1).
6. The automatic measuring tailings filling body test block sample preparation device according to claim 1, characterized in that: The trial mold fixture (23) is also equipped with a cleaning trough.
Citation Information
Cited By
Tailing filling body test block sample preparation device and sample preparation method
CN120907922A