Scaffold steel pedal
By designing a fixed frame and transmission system on the scaffolding steel pedals and fixing them on the scaffolding with hooks and jamming grooves, the gap problem caused by the movement of traditional steel pedals from left to right is solved, and the walking safety of construction workers is improved.
Patent Information
- Application Number
- CN202420880256.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-25
- Publication Date
- 2024-12-20
- Estimated Expiration
- 2034-04-25
AI Technical Summary
Traditional scaffolding steel pedals are easily moved left and right after installation, resulting in gaps between the pedals and pedals. Construction workers are prone to step on empty space when walking, causing leg injuries.
A steel pedal including a fixing frame, connecting rod, hook, transmission rod, gear, screw rod and ball nut block is designed. It is fixed to the scaffolding through the hook, and the gear and transmission rod are used to drive the screw rod and ball nut block to rotate. , the jamming groove is clamped with the scaffolding to prevent the fixed frame from shaking left and right.
It effectively prevents gaps between the pedals, ensures the safety of construction workers when walking, and avoids air stomping and leg injuries.
Smart Images

Figure CN222207208U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of steel pedals, in particular to a scaffolding steel pedal. Background Art
[0002] Steel pedals are an important part of the scaffolding and their function is to allow construction workers to walk on them.
[0003] Traditional scaffolding steel pedals are generally composed of steel plates and hooks. After the steel pipes of the scaffolding are assembled, the hooks fixed on both sides of the steel plates are installed on the scaffolding to allow construction workers to walk on them.
[0004] At present, in the prior art, the hooks fixed on both sides of the steel plate are directly installed on the scaffolding to allow construction workers to walk. However, the steel pedals usually move left and right after being hung on the scaffolding, resulting in gaps between the pedals. Construction workers may easily step on empty space when walking on it without paying attention, resulting in leg injuries, etc.
[0005] Therefore, a scaffold steel pedal is proposed in view of the above problems. Utility Model Content
[0006] In order to make up for the deficiencies of the prior art and solve the above-mentioned problems, a scaffolding steel pedal is proposed.
[0007] The technical solution adopted by the utility model to solve its technical problems is: the utility model describes a scaffolding steel pedal, comprising a fixed frame; a fixed component is connected through the interior of the fixed frame; the fixed component comprises a connecting rod and a hook; fixed grooves are provided on both sides of the fixed frame; bearings are rotatably connected to the fixed grooves; a transmission rod is fixedly connected to the bearings; screw rods are fixedly connected to both ends of the transmission rod; a gear is fixedly connected to the middle of the transmission rod; an operating hole is provided in the middle of the fixed frame; the gear passes through the operating hole; a ball nut block is threadedly connected to the screw rod; the ball nut block is fixedly connected to a first fixed block; two first fixed blocks are provided, and are symmetrically arranged on the first fixed block; a clamping groove is provided on the first fixed block.
[0008] Preferably, a sliding groove is provided in the fixing groove; a sliding column is movably connected in the sliding groove; and a side of the sliding column not connected to the sliding groove is fixedly connected to the first fixing block.
[0009] Preferably, both ends of the connecting rod pass through the fixed frame; both ends of the connecting rod are fixedly connected to the hooks; and two groups of the fixing components are symmetrically arranged on the fixed frame.
[0010] Preferably, a drainage hole is opened on the top of the fixed frame; a plurality of the drainage holes are provided, and the drainage holes are arranged in an array.
[0011] Preferably, a connecting column is fixedly connected to the connecting rod; a rotating groove is provided on the connecting column; a rotating column is rotatably connected in the rotating groove; a rotating block is fixedly connected to the rotating column; and a second fixed block is fixedly connected to the rotating block.
[0012] Preferably, the connecting columns are provided in four groups and are distributed on the inner side of the hook.
[0013] Beneficial effects of the utility model:
[0014] 1. The utility model provides a scaffolding steel pedal, which fixes the fixed frame on the scaffolding through a fixed component hook on the fixed frame, and then rotates the gear fixedly connected to the middle part of the transmission rod through an operation hole opened on the fixed frame. The gear drives the transmission rod to rotate, and the transmission rod drives the lead screw at the end to rotate. The rotation of the lead screw will move the ball nut block forward and the first fixed block fixedly connected to the ball nut block forward, so that the clamping groove opened on the first fixed block is clamped on the scaffolding, so as to prevent the fixed frame from shaking left and right, resulting in a gap. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of the present application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention. In the drawings:
[0016] Figure 1 It is a three-dimensional diagram of the utility model;
[0017] Figure 2 It is a cross-sectional view of the utility model;
[0018] Figure 3 The utility model Figure 2 A partial enlarged view of
[0019] Figure 4 It is a cross-sectional view of the utility model;
[0020] Legend:
[0021] 1. Fixed frame; 2. Connecting rod; 3. Snap-in groove; 4. First fixed block; 5. Screw rod; 6. Drain hole; 7. Connecting column; 8. Gear; 9. Operating hole; 10. Fixed groove; 11. Ball nut block; 13. Bearing; 14. Transmission rod; 15. Rotating block; 16. Rotating groove; 17. Rotating column; 18. Second fixed block; 19. Sliding column; 20. Sliding groove; 21. Hook. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] Specific examples are given below.
[0024] See also Figure 1-Figure 4 The utility model provides a scaffolding steel pedal, including a fixed frame 1; a fixed assembly is connected through the interior of the fixed frame 1; the fixed assembly includes a connecting rod 2 and a hook 21; fixed grooves 10 are provided on both sides of the fixed frame 1; a bearing 13 is rotatably connected to the fixed groove 10; a transmission rod 14 is fixedly connected to the bearing 13; screw rods 5 are fixedly connected to both ends of the transmission rod 14; a gear 8 is fixedly connected to the middle of the transmission rod 14; an operating hole 9 is provided in the middle of the fixed frame 1; the gear 8 passes through the operating hole 9; a ball nut block 11 is threadedly connected to the screw rod 5; the ball nut block 11 is fixedly connected to a first fixed block 4; two first fixed blocks 4 are provided, and are symmetrically arranged on the first fixed block 4; a clamping groove 3 is provided on the first fixed block 4. The traditional scaffolding steel pedal is generally composed of a steel plate and a hook. After the steel pipe of the scaffold is assembled, the hooks fixedly connected to the two sides of the steel plate are installed on the scaffold so that the construction workers can walk. At present, in the prior art, the hooks fixed on both sides of the steel plate are directly installed on the scaffolding. The scaffolding can be placed on the scaffolding so that construction workers can walk. However, generally, the steel pedals will move left and right after being hung on the scaffolding, resulting in gaps between the pedals. Construction workers walking on the scaffolding may easily step on empty space if they are not careful, resulting in leg injuries, etc. In order to prevent such incidents from happening, during work, the fixed frame 1 is fixed to the scaffolding through the fixed component hook 21 on the fixed frame 1, and then the gear 8 fixedly connected to the middle part of the transmission rod 14 is rotated through the operation hole 9 opened on the fixed frame 1, and the gear 8 drives the transmission rod 14 to rotate, and the fixed frame 14 is fixed. Fixed grooves 10 are provided on both sides of the fixed frame 1, and bearings 13 are movably connected to the fixed grooves 10. The transmission rod 14 is fixedly connected to the bearings 13. When the transmission rod 14 rotates, the screw rods 5 fixedly connected to the ends on both sides rotate accordingly. When the screw rods 5 rotate, they will push the ball nut block 11 to move forward. Because the first fixed block 4 is fixedly connected to the ball nut block 11, it moves forward together with the ball nut block 11. When it moves to a certain position, the clamping groove 3 provided on the first fixed block 4 will be clamped with the scaffolding to prevent the fixed frame 1 from shaking left and right.
[0025] Further, such as Figure 4As shown, a sliding groove 20 is provided in the fixed groove 10; a sliding column 19 is movably connected in the sliding groove 20; the side of the sliding column 19 not connected to the sliding groove 20 is fixedly connected to the first fixed block 4. When working, the sliding groove 20 provided in the fixed groove 10, the sliding groove 20 is movably connected with the sliding column 19, and the sliding column 19 is fixedly connected to the first fixed block 4, so that the first fixed block 4 remains fixed and does not rotate up and down to ensure that the clamping groove 3 on the first fixed block 4 can be clamped with the scaffold.
[0026] Further, such as Figure 1 and Figure 2 As shown, both ends of the connecting rod 2 pass through the fixed frame 1; both ends of the connecting rod 2 are fixedly connected with hooks 21; the fixing components are symmetrically arranged in two groups on the fixed frame 1. When working, the fixed frame 1 needs to be connected to the scaffolding, and the hooks 21 fixedly connected on both sides of the connecting rod 2 are hung on the scaffolding to fix the entire fixed frame 1 on the scaffolding.
[0027] Further, such as Figure 1 As shown, a drainage hole 6 is opened on the top of the fixed frame 1; there are multiple drainage holes 6, and the drainage holes 6 are arranged in an array. During work, when it is thunderstorm weather, in order to prevent water from accumulating on the fixed frame 1 and causing construction workers to slip when walking on it, a drainage hole 6 is opened on the top of the fixed frame 1 to allow rainwater to flow out of the drainage hole 6.
[0028] Further, such as Figure 3 As shown, a connecting column 7 is fixedly connected to the connecting rod 2; a rotating groove 16 is provided on the connecting column 7; a rotating column 17 is rotatably connected in the rotating groove 16; a rotating block 15 is fixedly connected to the rotating column 17; and a second fixed block 18 is fixedly connected to the rotating block 15. During operation, when the hook 21 needs to be connected to the scaffold, the rotating column 17 in the rotating groove 16 rotates to move the rotating block 15 upward, and at the same time, the second fixed block 18 fixedly connected to the rotating block 15 also moves upward together, and the steel pipe of the scaffold is placed in the hook 21. When the scaffold steel pipe is placed in the hook 21, the rotating column 17 is rotated again to allow the rotating block 15 and the second fixed block 18 to move downward, so that the second fixed block 18 and the end of the hook 21 remain horizontal to prevent the steel pipe of the scaffold from falling off.
[0029] Further, such as Figure 1 As shown, the connecting columns 7 are provided in four groups and are distributed on the inner side of the hook 21 . When working, the connecting columns 7 are provided in four groups and are distributed on the inner side of the hook 21 to prevent the steel pipes of the scaffolding from falling off from the hook 21 .
[0030] Working principle: The hooks fixed on both sides of the steel plate are installed on the scaffolding, so that construction workers can walk. However, the steel pedals will move left and right after being hung on the scaffolding, resulting in gaps between the pedals. Construction workers may easily step on empty space when walking on them without paying attention, resulting in leg injuries, etc. In order to prevent such incidents from happening, during work, the fixed frame 1 is fixed to the scaffolding through the fixed component hook 21 on the fixed frame 1, and then the gear 8 fixedly connected in the middle of the transmission rod 14 is rotated through the operating hole 9 opened on the fixed frame 1, and the gear 8 drives the transmission The movable rod 14 rotates, and fixed grooves 10 are opened on both sides of the fixed frame 1. Bearings 13 are movably connected to the fixed grooves 10. The transmission rod 14 is fixedly connected to the bearings 13. When the transmission rod 14 rotates, the screw rods 5 fixedly connected to the ends on both sides rotate accordingly. When the screw rods 5 rotate, they will push the ball nut block 11 to move forward. Because the first fixed block 4 is fixedly connected to the ball nut block 11, it moves forward with the ball nut block 11. When it moves to a certain position, the clamping groove 3 opened on the first fixed block 4 will be clamped with the scaffolding to prevent the fixed frame 1 from shaking left and right.
[0031] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments, and the above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, and these changes and improvements fall within the scope of the utility model to be protected.
Claims
1. A scaffolding steel pedal, characterized in that: The invention comprises a fixing frame (1); a fixing assembly is connected through the inside of the fixing frame (1); the fixing assembly comprises a connecting rod (2) and a hook (21); fixing grooves (10) are provided on both sides of the fixing frame (1); a bearing (13) is rotatably connected to the fixing groove (10); a transmission rod (14) is fixedly connected to the bearing (13); a screw rod (5) is fixedly connected to both ends of the transmission rod (14); a gear (8) is fixedly connected to the middle of the transmission rod (14); an operating hole (9) is provided in the middle of the fixing frame (1); the gear (8) passes through the operating hole (9); a ball nut block (11) is threadedly connected to the screw rod (5); the ball nut block (11) is fixedly connected to a first fixing block (4); two first fixing blocks (4) are provided and are symmetrically arranged on the first fixing block (4); a clamping groove (3) is provided on the first fixing block (4).
2. A scaffolding steel pedal according to claim 1, characterized in that: A sliding groove (20) is provided in the fixed groove (10); a sliding column (19) is movably connected in the sliding groove (20); and the side of the sliding column (19) not connected to the sliding groove (20) is fixedly connected to the first fixed block (4).
3. A scaffolding steel pedal according to claim 2, characterized in that: Both ends of the connecting rod (2) pass through the fixed frame (1); both ends of the connecting rod (2) are fixedly connected to the hooks (21); and two groups of the fixing components are symmetrically arranged on the fixed frame (1).
4. A scaffolding steel pedal according to claim 3, characterized in that: A drainage hole (6) is provided on the top of the fixed frame (1); a plurality of the drainage holes (6) are provided, and the drainage holes (6) are arranged in an array.
5. A scaffolding steel pedal according to claim 4, characterized in that: A connecting column (7) is fixedly connected to the connecting rod (2); a rotating groove (16) is provided on the connecting column (7); a rotating column (17) is rotatably connected in the rotating groove (16); a rotating block (15) is fixedly connected to the rotating column (17); and a second fixed block (18) is fixedly connected to the rotating block (15).
6. A scaffolding steel pedal according to claim 5, characterized in that: The connecting posts (7) are provided in four groups and are distributed on the inner side of the hook (21).