Pile foundation bearing capacity detector

By introducing sliding and rotating structures into the pile foundation detection device, the clamps are adjusted to adapt to pile foundations of different shapes, which solves the problem that existing clamps cannot be adjusted, and improves detection accuracy and use flexibility.

CN222227389UActive Publication Date: 2024-12-24SHENZHEN TIEKE INSPECTION & TESTING ENG CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202420219622.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-30
Publication Date
2024-12-24
Estimated Expiration
2034-01-30

AI Technical Summary

Technical Problem

In the existing pile foundation detection devices, the slug plate is arc-shaped and cannot be adjusted, resulting in the inability to adapt to pile foundations of different shapes, and needs to be frequently disassembled, assembled and replaced.

Method used

A pile foundation bearing capacity detector was designed. Through sliding and rotating structure, the limiting plate, return spring, hydraulic rod and threaded rod are used to adjust and fix the clamp, adapt to square and circular pile foundations, and improve the Positioning accuracy and versatility.

Benefits of technology

It realizes stable positioning and extrusion fixation of pile foundations of different sizes and shapes, improves detection accuracy and use flexibility, and reduces the frequency of disassembly and assembly.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222227389U_ABST
    Figure CN222227389U_ABST
Patent Text Reader

Abstract

The utility model discloses a pile foundation bearing capacity detector, which relates to the technical field of building construction and comprises a fixing plate, a first sliding plate is slidably mounted at the top end of the fixing plate, and second sliding plates are slidably mounted at two side end parts of the first sliding plate. At least two clamping plates are slidably mounted at the side end of each second sliding plate, and two guide plates are fixedly mounted at the top end of the fixing plate. According to the pile foundation bearing capacity detector, the rotating rod is rotated to drive the bevel gear at the tail end to rotate, the two threaded rods rotate on the inner side of the first sliding plate and rotate at the side end of the first sliding plate, and the surfaces of the threaded rods are matched with the inner side of the first connecting block; and pushing force is applied to the first connecting block, the second sliding plates slide on the two side ends of the first sliding plate, the distance between the two second sliding plates is adjusted, pile foundations of different sizes can be positioned, and the use universality is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a pile foundation bearing capacity detector. Background Art

[0002] The current pile bearing capacity detection device usually uses a reaction beam and a hydraulic cylinder. One method is the loading method, which is to load a counterweight on the reaction beam after the reaction beam is erected on the pile. The hydraulic cylinder is located between the reaction beam and the pile to apply pressure to the pile.

[0003] At present, the existing pile foundation detection (such as patent number: CN216586704U) discloses a pile foundation vertical bearing capacity detection device for construction engineering. The positioning rod and the positioning groove cooperate to keep the installed jack and the test pile coaxial, so that the test pile is evenly stressed, thereby improving the detection accuracy of the pile foundation vertical bearing capacity.

[0004] However, in the process of implementing the above technical solution, it was found that there are at least the following technical problems: the pile foundation is positioned by assembling multiple pallets, but the pallets are arc-shaped in design, and the pile foundations have different shapes such as square and circular. The shape of the pallets cannot be adjusted. During use, the positioned pile foundation needs to be disassembled and replaced. Utility Model Content

[0005] 1. Technical issues to be solved

[0006] In view of the deficiencies in the prior art, the utility model provides a pile foundation bearing capacity tester, which solves the problem of positioning the pile foundation by assembling multiple clips. However, the clips are of arc-shaped design, and the pile foundations have different shapes such as square and round. The shape of the clips cannot be adjusted. During use, the positioned pile foundation needs to be disassembled, assembled and replaced.

[0007] (II) Technical solution

[0008] In order to achieve the above objectives, the present invention is implemented through the following technical solutions:

[0009] A pile foundation bearing capacity detector, comprising a fixed plate, a first slide plate being slidably mounted on the top of the fixed plate, a second slide plate being slidably mounted on both side ends of the first slide plate, at least two clamping plates being slidably mounted on each side end of the second slide plate, two guide plates being fixedly mounted on the top of the fixed plate, and a driving rod being fixedly mounted on the inner side of each guide plate;

[0010] Preferably: a hydraulic rod is fixedly installed on the top of each of the second slide plates, the same push plate is fixedly installed on the tops of the two hydraulic rods, a bottom plate is fixedly installed on the bottom end of each of the first slide plates, a rotating rod is rotatably installed on the top of each of the first slide plates, a threaded rod is rotatably installed on the two side ends of each of the first slide plates, and a first connecting block is slidably installed on the surface of each of the threaded rods.

[0011] Preferably: a second connecting block is fixedly installed on the side end of each of the splints, a second return spring is fixedly installed on the side end of each of the second connecting blocks, a mounting plate is fixedly installed on the side end of each of the second slide plates, a first return spring is fixedly installed on the bottom end of each of the mounting plates, and a limiting plate is fixedly installed on the end of each of the first return springs.

[0012] (III) Beneficial effects

[0013] 1. By pushing the limit plate, the limit plate slides downward at the bottom end of the second slide plate, and the top end of the limit plate applies a pulling force to the first return spring, allowing the first return spring to expand and contract to a certain extent. At the same time, one end of the limit plate leaves the bottom end of the multiple clamps, and the top end of the limit plate leaves the slot at the bottom end of the clamp, releasing the fixation of the clamp. At this time, under the reverse force of the second return spring, the top end of the second return spring pushes the second connecting block, allowing the second connecting block to slide outward from one side of the second slide plate, pushing the clamps to move synchronously, and by pushing the top ends of the multiple clamps, the multiple clamps are adjusted to a stepped shape, or the clamps are adjusted to a horizontal shape, and the circular or square pile foundations are squeezed and fixed.

[0014] 2. By rotating the rotating rod, the rotating rod drives the bevel gear at the end to rotate, and the two threaded rods rotate on the inner side of the first slide plate. At the same time, the threaded rods rotate on the side ends of the first slide plate. The surface of the threaded rods fits with the inner side of the first connecting block, and a thrust is applied to the first connecting block to slide the second slide plate on the two side ends of the first slide plate. By adjusting the distance between the two second slide plates, pile foundations of different sizes can be positioned, thereby increasing the versatility of use. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] The above description is only an overview of the technical solution of the utility model. In order to more clearly understand the technical means of the utility model and implement it according to the contents of the specification, the following is a detailed description of the preferred embodiments of the utility model in conjunction with the accompanying drawings.

[0016] Figure 1 This is a structural diagram of the fixed plate of the utility model;

[0017] Figure 2 This is a structural diagram of the skateboard of the utility model;

[0018] Figure 3This is a structural diagram of the regulating device of the utility model;

[0019] Figure 4 It is the structural diagram of the splint of the utility model.

[0020] Legend: 1. Fixed plate; 11. First slide plate; 12. Second slide plate; 13. Driving rod; 14. Hydraulic rod; 15. Push plate; 16. Bottom plate; 17. Guide plate; 18. Rotating rod; 19. Threaded rod; 21. First connecting block; 22. Clamp plate; 23. Mounting plate; 24. First return spring; 25. Limiting plate; 26. Second connecting block; 27. Second return spring. DETAILED DESCRIPTION

[0021] The embodiment of the present application provides a pile foundation bearing capacity tester, which effectively solves the problem of positioning the pile foundation by assembling multiple clamping plates. However, the clamping plates are of arc-shaped design, and the pile foundations have different shapes such as square and round. The shape of the clamping plates cannot be adjusted. During use, the positioned pile foundation needs to be disassembled, assembled and replaced, and the limiting plate is pushed to slide downward at the bottom end of the second slide plate. The top end of the limiting plate applies a pulling force to the first return spring, allowing the first return spring to expand and contract to a certain extent. At the same time, one end of the limiting plate leaves the bottom ends of the multiple clamping plates, and the top end of the limiting plate leaves the clamping groove at the bottom end of the clamping plate, releasing the fixation of the clamping plate. At this time, under the reverse action force of the second return spring, the top end of the second return spring pushes the second connecting block, allowing the second connecting block to slide outward from one side of the second slide plate, pushing the clamping plates to move synchronously, and by pushing the top ends of the multiple clamping plates, the multiple clamping plates are adjusted to a stepped shape, or the clamping plates are adjusted to a horizontal shape, so as to squeeze and fix the circular or square pile foundation.

[0022] Example

[0023] like Figure 1 , Figure 2 , Figure 3 and Figure 4 As shown, the technical solution in the embodiment of the present application effectively solves the problem of positioning the pile foundation by assembling multiple pallets, but the pallet is designed in an arc shape, and the pile foundation has different shapes such as square and round. The shape of the pallet cannot be adjusted. In use, the technical problem that the positioned pile foundation needs to be disassembled and replaced is solved. The overall idea is as follows:

[0024] In view of the problems existing in the prior art, the utility model provides a pile foundation bearing capacity tester, which includes a fixed plate 1, a first slide plate 11 is slidably installed on the top of the fixed plate 1, and second slide plates 12 are slidably installed on the two side ends of the first slide plate 11, and a placement groove is provided on the top of the fixed plate 1, which is located between the two first slide plates 11, and at least two clamping plates 22 are slidably installed on the side ends of each second slide plate 12, and two guide plates 17 are fixedly installed on the top of the fixed plate 1, and a driving rod 13 is fixedly installed on the inner side of each guide plate 17. By driving the driving rod 13, the driving rod 13 applies a thrust to the first slide plate 11, and the first slide plate 11 drives the bottom plate 16 to slide along the top of the guide plate 17, so that the two second slide plates 12 apply compression to the pile foundation to ensure the stability of the pile foundation sinking downward.

[0025] A hydraulic rod 14 is fixedly installed on the top of each second slide plate 12, and the same push plate 15 is fixedly installed on the top of the two hydraulic rods 14. The push plate 15 is of V-shaped design and is connected to the hydraulic rod 14 at both ends. A bottom plate 16 is fixedly installed on the bottom end of each first slide plate 11, and a rotating rod 18 is rotatably installed on the top of each first slide plate 11. Threaded rods 19 are rotatably installed on the two side ends of each first slide plate 11. The threaded rods 19 rotate on the side ends of the first slide plate 11, and the surface of the threaded rods 19 fits with the inner side of the first connecting block 21, applying a thrust to the first connecting block 21 to allow the second slide plate 12 to slide on the two side ends of the first slide plate 11, and adjust the spacing between the two second slide plates 12. The surface of each threaded rod 19 is slidably installed with the first connecting block 21.

[0026] A second connecting block 26 is fixedly installed on the side end of each splint 22, and a second return spring 27 is fixedly installed on the side end of each second connecting block 26. A mounting plate 23 is fixedly installed on the side end of each second slide plate 12, and a first return spring 24 is fixedly installed on the bottom end of each mounting plate 23. A limiting plate 25 is fixedly installed on the end of each first return spring 24. By pushing the limiting plate 25, the limiting plate 25 slides downward at the bottom end of the second slide plate 12, and the top end of the limiting plate 25 applies a pulling force to the first return spring 24, allowing the first return spring 24 to expand and contract to a certain extent. At the same time, one end of the limiting plate 25 leaves the bottom end of the multiple splints 22, and the top end of the limiting plate 25 leaves the slot at the bottom end of the splint 22, thereby releasing the fixation of the splint 22.

[0027] Working principle:

[0028] The first step is to push the limit plate 25 to allow the limit plate 25 to slide downward at the bottom end of the second slide plate 12. The top end of the limit plate 25 applies a pulling force to the first return spring 24, allowing the first return spring 24 to expand and contract to a certain extent. At the same time, one end of the limit plate 25 leaves the bottom ends of the plurality of clamping plates 22, and the top end of the limit plate 25 leaves the slot at the bottom end of the clamping plate 22, releasing the fixation of the clamping plate 22. At this time, under the reverse force of the second return spring 27, the top end of the second return spring 27 pushes the second connecting block 26, allowing the second connecting block 26 to slide outward from one side of the second slide plate 12, pushing the clamping plates 22 to move synchronously, and by pushing the top ends of the plurality of clamping plates 22 At the end, multiple clamps 22 are adjusted to a stepped shape, or the clamps 22 are adjusted to be horizontal, and the circular or square pile foundation is squeezed and fixed. Through the different sliding distances of multiple clamps 22, the top of the clamp 22 is close to the surface of the pile foundation. At the same time, under the pulling force of the first return spring 24, the limit plate 25 slides toward the second slide plate 12, and one end of the limit plate 25 is stuck into the bottom end of the clamp 22 to fix the clamp 22. Then, by driving the driving rod 13, the driving rod 13 applies a thrust to the first slide plate 11, and the first slide plate 11 drives the bottom plate 16 to slide along the top of the guide plate 17, so that the two second slide plates 12 squeeze the pile foundation to ensure the stability of the pile foundation sinking downward.

[0029] In the second step, the push plate 15 is driven by the hydraulic rod 14 to slide downward, and pressure is applied to the top of the pile foundation. The pile foundation slides downward inside the fixed plate 1. Due to the support of the two second slide plates 12, the pile foundation sinks vertically downward. At the same time, the rotating rod 18 is rotated to drive the bevel gear at the end to rotate, so that the two threaded rods 19 are rotated on the inner side of the first slide plate 11. At the same time, the threaded rod 19 rotates at the side end of the first slide plate 11, and the surface of the threaded rod 19 fits with the inner side of the first connecting block 21, applying a thrust to the first connecting block 21, so that the second slide plate 12 slides on the two side ends of the first slide plate 11. The spacing between the two second slide plates 12 can be adjusted to position pile foundations of different sizes, thereby increasing the versatility of use.

[0030] Finally, it should be noted that: Obviously, the above embodiments are only examples for clearly explaining the present invention, and are not intended to limit the implementation methods. For ordinary technicians in the relevant field, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived from this are still within the scope of protection of the present invention.

Claims

1. A pile foundation bearing capacity detector, characterized in that: The pile foundation detector comprises a fixed plate (1), a first slide plate (11) is slidably mounted on the top of the fixed plate (1), second slide plates (12) are slidably mounted on both side ends of the first slide plate (11), at least two clamping plates (22) are slidably mounted on the side ends of each second slide plate (12), two guide plates (17) are fixedly mounted on the top of the fixed plate (1), and a driving rod (13) is fixedly mounted on the inner side of each guide plate (17); The end of the driving rod (13) is connected to the first slide plate (11), and the two first slide plates (11) and the second slide plate (12) are installed opposite to each other. At the same time, a placement groove is provided at the top of the fixing plate (1) and is located between the two first slide plates (11).

2. A pile foundation bearing capacity detector as claimed in claim 1, characterized in that: A hydraulic rod (14) is fixedly mounted on the top of each of the second slide plates (12), and a same push plate (15) is fixedly mounted on the tops of the two hydraulic rods (14); The push plate (15) is of V-shaped design, and its two ends are connected to the hydraulic rod (14).

3. A pile foundation bearing capacity detector as claimed in claim 1, characterized in that: A bottom plate (16) is fixedly mounted on the bottom end of each of the first slide plates (11), and a rotating rod (18) is rotatably mounted on the top end of each of the first slide plates (11); Wherein, a bevel gear is installed at the end of the rotating rod (18).

4. A pile foundation bearing capacity detector as claimed in claim 1, characterized in that: A threaded rod (19) is rotatably mounted on the two side ends of each of the first slide plates (11), and a first connecting block (21) is slidably mounted on the surface of each of the threaded rods (19); The side end of the first connecting block (21) is integrally connected to the second sliding plate (12).

5. A pile foundation bearing capacity detector as claimed in claim 1, characterized in that: A second connecting block (26) is fixedly mounted on the side end of each clamping plate (22), and a second return spring (27) is fixedly mounted on the side end of each second connecting block (26); The bottom end of the clamping plate (22) is provided with a plurality of slots arranged at equal intervals.

6. A pile foundation bearing capacity detector as claimed in claim 1, characterized in that: A mounting plate (23) is fixedly mounted on the side end of each second slide plate (12), a first return spring (24) is fixedly mounted on the bottom end of each mounting plate (23), and a limit plate (25) is fixedly mounted on the end of each first return spring (24).

Citation Information

Patent Citations

  • Pile foundation vertical bearing capacity detection device for constructional engineering

    CN216586704U