Split type prefabricated pump station

Through the design of split prefabricated pump stations, the combination of concrete and H-shaped steel has been used to solve the problem of fixed design and planning of existing pump stations, flexible adjustment and transportation are achieved, easy equipment installation, reduced cost and weight, and improved adaptability and Mechanical strength.

CN222227439UActive Publication Date: 2024-12-24SHANDONG SURVEY & DESIGN INST OF WATER CONSERVANCY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422849555.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-11-22
Publication Date
2024-12-24
Estimated Expiration
2034-11-22

AI Technical Summary

Technical Problem

The existing integrated prefabricated pump stations in buried pump stations are difficult to adjust after the initial design plan, have poor adaptability, and are inconvenient to transport large-sized pump stations and are costly.

Method used

Designed with split prefabricated pump station, the concrete base, link and top cover are connected through connectors, flexible installation is achieved using H-shaped steel and flower basket screws, the arc-shaped top hoop provides support, the sealing layer is made of fiberglass cloth, and the material is made of concrete and steel bars. Reduce cost and weight.

Benefits of technology

It realizes flexible adjustment and transportation of the pump station, facilitates equipment installation, reduces cost and weight, improves adaptability and mechanical strength, and avoids breakage at the connection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222227439U_ABST
    Figure CN222227439U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of water delivery systems, and particularly relates to a split type prefabricated pump station which comprises a pump station body, and the pump station body comprises a concrete base, a concrete link and a concrete top cover which are vertically fixed through connecting pieces. At least two concrete links are arranged, the end parts of the concrete base, the concrete links and the concrete top cover are all provided with tongue-and-groove structures, the outer sides of the tongue-and-groove structures are provided with sealing layers, and the inner walls of the tongue-and-groove structures are pre-embedded with connecting seats which are circumferentially and uniformly distributed; the upper and lower layers of connecting seats are staggered and are connected up and down one by one through connecting pieces; a water inlet pipe is pre-embedded in the concrete link located at the bottom layer, and a water outlet pipe is pre-embedded in the concrete link located at the top layer. Compared with the prior art, the utility model is formed by installing the split type prefabricated parts, on one hand, the split type installation can be free from the constraint of the early planning and design and can be flexibly adjusted according to the actual situation, on the other hand, the concrete is adopted as the main body material to facilitate the installation of internal equipment, and the adaptability is better.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of water delivery systems, and in particular relates to a split prefabricated pump station. Background Art

[0002] A pump station is a hydraulic facility in a water transmission / supply system. At the beginning of the design and planning, the specifications and location of the pump station need to be determined. Currently, the most common underground pump stations are prefabricated integrated pump stations made of fiberglass. This type of pump station has the advantages of strong corrosion resistance, fast construction speed, little impact on the surrounding environment, and easy maintenance. However, the pump station needs to be customized in advance according to the design requirements, and it is more expensive than other types of pump stations, has poor adaptability, and large-sized pump stations are inconvenient to transport. Utility Model Content

[0003] The utility model aims to provide a split prefabricated pump station, which is installed by split prefabricated parts, so as to meet the requirements of flexible adjustment according to different design requirements and has good adaptability.

[0004] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a split prefabricated pump station, including a pump station body, the pump station body including a concrete base, a concrete link and a concrete top cover fixed up and down by connecting pieces; at least two concrete links are provided, the ends of the concrete base, the concrete link and the concrete top cover are all provided with a tongue-and-groove structure and a sealing layer is provided on the outer side of the tongue-and-groove structure, and the inner wall thereof is pre-buried with connecting seats evenly distributed around the circumference; the upper and lower layers of connecting seats are staggered and connected one by one up and down by the connecting pieces; the concrete link located at the bottom layer is pre-buried with a water inlet pipe, and the concrete link located at the top layer is pre-buried with a water outlet pipe.

[0005] Furthermore, the connecting seat is an H-shaped steel, and its upper and lower wing plates are fixedly connected to one end of the angle seat, and the other end of the angle seat is hingedly connected to the end of the connecting piece.

[0006] Furthermore, the connecting piece is a turnbuckle.

[0007] Furthermore, the pump station body also includes an arc-shaped top hoop, and the arc-shaped top hoop is fixedly connected between the webs of two adjacent connecting seats on the inner wall of the concrete segment.

[0008] Furthermore, the arc-shaped top hoop includes an arc-shaped hoop plate with both ends bent inward to form a connecting portion and an arc-shaped rib plate vertically arranged on the inner side of the arc-shaped hoop plate and connected to the connecting portion.

[0009] Furthermore, the concrete link includes a concrete ring body and a steel cage embedded in the concrete ring body.

[0010] Furthermore, the concrete top cover includes a concrete cover body and a metal cover body embedded in the center of the concrete cover body, the metal cover body is provided with a manhole and a vent, a manhole cover is installed at the manhole, a handrail is installed on one side of the manhole, and a ventilation pipe is installed at the vent.

[0011] Furthermore, the sealing layer is a glass fiber cloth bonding layer.

[0012] Compared with the prior art, the beneficial effects of the utility model are:

[0013] 1. The utility model is installed by split prefabricated parts. On the one hand, the split installation can be free from the constraints of early planning and design and can be flexibly adjusted according to actual conditions, and is easy to transport. On the other hand, the use of concrete as the main material is also convenient for internal equipment installation, and has good adaptability and price advantages.

[0014] 2. The connection seat in the utility model adopts H-shaped steel and is fixed in a pre-buried manner. The material is easy to obtain, low in price, and has good mechanical strength. It cooperates with the basket screws to achieve the purpose of upper and lower layered connection and fixation.

[0015] 3. The arc-shaped top hoop in the utility model can support the inner wall of the concrete link and the connecting seat to avoid breakage at the connection between the two.

[0016] 4. The concrete part in the utility model is cast with reinforced concrete. Under the premise of meeting the strength requirements, the wall thickness is reduced, which helps to control the overall cost and weight. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a structural stereogram of a preferred embodiment of the utility model;

[0018] Figure 2 for Figure 1 A top view of the structure of the illustrated embodiment;

[0019] Figure 3 for Figure 2 Structural cross-section view along the AA axis;

[0020] Figure 4 for Figure 3 A partial enlarged view of point B in the middle;

[0021] Figure 5 for Figure 1 A structural stereogram of the concrete link in the illustrated embodiment;

[0022] Figure 6 for Figure 1 A structural stereogram of the arc-shaped top hoop in the illustrated embodiment;

[0023] Figure 7 for Figure 1 A half-cutaway perspective view of the concrete top cover in the illustrated embodiment;

[0024] Figure 8 for Figure 1 A schematic diagram of the installation structure of the embodiment shown;

[0025] Figure numerals: 1. concrete link; 101. concrete ring; 102. steel cage; 2. concrete top cover; 201. concrete cover; 202. metal cover; 203. manhole; 204. vent; 3. concrete base; 4. ventilation pipe; 5. manhole cover; 6. handrail; 7. water outlet pipe; 8. sealing layer; 9. water inlet pipe; 10. connecting piece; 11. maintenance platform; 12. ladder; 13. arc-shaped top hoop; 1301. arc-shaped hoop plate; 1302. arc-shaped rib plate; 1303. connecting part; 14. angle seat; 15. connecting seat. DETAILED DESCRIPTION

[0026] The technical solutions in the embodiments of the utility model are described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0027] like Figures 1 to 8 As shown, the utility model provides a split prefabricated pump station, including a pump station body. It should be noted that the utility model does not involve improvements to pump station accessories such as pumps, control boxes, and pipelines. The aforementioned accessories are all conventional components and should be selected and installed according to actual design requirements, so the description of these accessories is omitted.

[0028] The pump station body comprises a concrete base 3, a concrete link 1 and a concrete top cover 2 fixed up and down by a connecting piece 10. The concrete base 3, the concrete link 1 and the concrete top cover 2 are all prefabricated concrete parts.

[0029] The bottom of the concrete base 3 is provided with a flange structure for fixing on a base in the foundation pit by anchor bolts. The height of the concrete base 3 is set to 20-30 cm.

[0030] like Figure 5As shown, three concrete segments 1 are provided. As a preferred example, the concrete segment 1 includes a concrete ring body 101 and a steel cage 102 pre-buried inside the concrete ring body 101. The purpose of providing the steel cage 102 is to increase the strength, thereby reducing the wall thickness of the concrete segment 1, thereby reducing the cost and weight. The diameter of the concrete segment 1 is 2-4m, the height is 1.5-2m, and the wall thickness is 5-10cm. The specific number of concrete segments 1 is determined according to the design requirements of the pump station body. The concrete segment 1 located at the bottom layer is pre-buried with an inlet pipe 9, and the concrete segment 1 located at the top layer is pre-buried with an outlet pipe 7. The inlet pipe 9 and the outlet pipe 7 are used to connect the internal pipelines of the pump station.

[0031] like Figure 7 As shown, since the concrete top cover 2 has the lowest bearing force requirement, in order to reduce the amount of concrete, as a preferred example, the concrete top cover 2 includes a concrete cover body 201 and a metal cover body 202 embedded in the center of the concrete cover body 201. That is, an opening is provided in the center of the concrete cover body 201, and the diameter of the opening is 4 / 5-9 / 10 of the diameter of the concrete cover body 201. The metal cover body 202 is fixed at the opening in a pre-embedded manner. The outer edge of the metal cover body 202 is provided with a bent boss structure to improve the bonding force of the pre-embedded connection. The connection between the two is waterproof and sealed, for example, by coating with waterproof paint. The metal cover body 202 is provided with a manhole 203 and a vent 204. A manhole cover 5 is installed at the manhole 203. A handrail 6 is installed on one side of the manhole 203 to cooperate with the ladder 12 in the pump station to realize the entry and exit of personnel. A ventilation pipe 4 is installed at the vent 204.

[0032] The ends of the concrete base 3, the concrete link 1 and the concrete top cover 2 are all provided with a tongue-and-groove structure, which is used for axial positioning, and a sealing layer 8 is provided on the outside of the tongue-and-groove structure for waterproofing. The inner walls of the three main components are pre-buried with connecting seats 15 evenly distributed around the circumference, and each prefabricated component is fixed with three connecting seats 15, and the upper and lower layers of connecting seats 15 are staggered and connected one by one through the connecting piece 10. In other words, the connecting piece 10 and the connecting seat 15 are connected at an angle to form a triangular structure, which can form a stable connection in both the circumferential direction and the axial direction.

[0033] As a preferred example, Figure 4As shown, the connection seat 15 is an H-shaped steel, that is, the H-shaped steel is cut according to the size and processed, and holes are punched on its wing plate and web, and then pre-embedded and cast. The upper and lower wing plates of the connection seat 15 are fixedly connected to one end of the angle seat 14, and the other end of the angle seat 14 is hingedly connected to the end of the connector 10, and the connection method is bolt connection. Specifically, the angle seat 14 has a first connection part and a second connection part. The first connection part is bent, and its horizontal part is connected to the wing plate, and its bent part is connected to the second connection part. The center line of the connection hole on the second connection part is perpendicular to the center line of the connection hole on the first connection part. The second connection part is connected to the connector 10. Through this structure, the connector 10 and the connection seat 15 can be connected at any angle.

[0034] Since the height and diameter of the concrete link 1 are determined according to the design requirements, multiple specifications can be designed to meet the construction requirements of different pipe network systems. Therefore, in order to adapt to the installation of concrete prefabricated parts of different specifications, as a preferred example, the connector 10 is a basket screw. The basket screw can adjust the overall length as required and has good flexibility and adaptability. It should be noted that the use load of the connector 10 should be above 1 t.

[0035] In order to reduce cost and weight, the wall thickness of the concrete segment 1 is lightweight, that is, the wall thickness is reduced, so the length of the connection seat 15 embedded in the concrete ring body 101 is limited. Therefore, in order to improve the firmness of the connection seat 15, all the connection seats 15 of each layer are reinforced by arc-shaped top hoops 13. Specifically, the webs of two adjacent connection seats 15 on the inner wall of the concrete segment 1 are fixedly connected with the arc-shaped top hoops 13, and the connection method is bolt connection.

[0036] like Figure 6 As shown, as a preferred example, the arc-shaped top hoop 13 includes an arc-shaped hoop plate 1301 whose two ends are bent inward to form a connection portion 1303 and an arc-shaped rib plate 1302 vertically arranged inside the arc-shaped hoop plate 1301 and connected to the connection portion 1303. The outer diameter of the arc-shaped hoop plate 1301 matches the inner diameter of the concrete segment 1, so that the outer wall of the arc-shaped hoop plate 1301 is closely attached to the inner wall of the concrete segment 1 to form a support, so that the arc-shaped top hoop 13 is firmly fixed in the concrete segment 1, and at the same time, it also supports the connection seats 15 on both sides to prevent them from being separated from the concrete segment 1.

[0037] It should be noted that another function of the arc-shaped top hoop 13 is to provide an installation basis for other components in the pump station, such as the maintenance platform 11, which can be fixedly installed on the arc-shaped rib plate 1302 of a certain layer of the arc-shaped top hoop 13.

[0038] As a preferred example, the sealing layer 8 is formed by coating glass fiber cloth and adhesive and then curing, and all metal parts are also treated with rust and corrosion prevention.

[0039] Compared with the integrated prefabricated pump station, the split prefabricated pump station in the utility model has lower cost, is easy to manufacture and install, and the prefabricated concrete parts can be easily punched and modified later. In addition, it does not need to be customized by the manufacturer but can be manufactured by the construction party, which has good flexibility and adaptability.

[0040] The matters not described in detail in the present invention are all known technologies to those skilled in the art.

[0041] It should be noted that the above specific implementation methods are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model is described in detail with reference to the embodiments, ordinary technicians in the field should understand that the technical solution of the utility model can be modified and replaced by equivalents without departing from the spirit and scope of the technical solution of the utility model, which should be included in the scope of the claims of the utility model.

Claims

1. A split prefabricated pump station, comprising a pump station body, characterized in that: The pump station body comprises a concrete base (3), a concrete segment (1) and a concrete top cover (2) fixed up and down by a connecting piece (10); at least two concrete segments (1) are provided, and the ends of the concrete base (3), the concrete segment (1) and the concrete top cover (2) are all provided with a tongue-and-groove structure, and a sealing layer (8) is provided on the outer side of the tongue-and-groove structure, and the inner wall thereof is pre-buried with connecting seats (15) uniformly distributed around the circumference; the upper and lower layers of connecting seats (15) are arranged in a staggered manner and are connected one by one up and down by the connecting piece (10); the concrete segment (1) located at the bottom layer is pre-buried with a water inlet pipe (9), and the concrete segment (1) located at the top layer is pre-buried with a water outlet pipe (7).

2. A split prefabricated pump station according to claim 1, characterized in that: The connecting seat (15) is an H-shaped steel, and its upper and lower wing plates are fixedly connected to one end of the angle seat (14), and the other end of the angle seat (14) is hingedly connected to the end of the connecting piece (10).

3. A split prefabricated pump station according to claim 2, characterized in that: The connecting piece (10) is a turnbuckle.

4. A split prefabricated pump station according to claim 2, characterized in that: The pump station body further comprises an arc-shaped top hoop (13), and the arc-shaped top hoop (13) is fixedly connected between the webs of two adjacent connection seats (15) on the inner wall of the concrete segment (1).

5. A split prefabricated pump station according to claim 4, characterized in that: The arc-shaped top hoop (13) comprises an arc-shaped hoop plate (1301) with both ends bent inwardly to form a connecting portion (1303), and an arc-shaped rib plate (1302) vertically arranged on the inner side of the arc-shaped hoop plate (1301) and connected to the connecting portion (1303).

6. A split prefabricated pump station according to claim 1, characterized in that: The concrete segment (1) comprises a concrete ring body (101) and a steel cage (102) pre-buried inside the concrete ring body (101).

7. A split prefabricated pump station according to claim 1, characterized in that: The concrete top cover (2) comprises a concrete cover body (201) and a metal cover body (202) pre-buried in the center of the concrete cover body (201); the metal cover body (202) is provided with a manhole (203) and a vent (204); a manhole cover (5) is installed at the manhole (203); a handrail (6) is installed on one side of the manhole (203); and a ventilation pipe (4) is installed at the vent (204).

8. The split prefabricated pump station according to claim 1, characterized in that: The sealing layer (8) is a glass fiber cloth bonding layer.