Anchor rod lattice beam side slope scaffold
Through the double-row structure of inner and outer poles and the design of wall connecting parts, combined with the use of expansion bolts and wooden wedges, the stability and safety of scaffolding in high steep slope support is solved, achieving more efficient and safer aerial work.
Patent Information
- Application Number
- CN202421429427.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-21
- Publication Date
- 2024-12-24
- Estimated Expiration
- 2034-06-21
AI Technical Summary
The installation and construction of scaffolding during the support process of high steep slopes is complicated, and safety and stability are difficult to guarantee. The operational standardization in the existing technology has insufficient, resulting in the safety of high-altitude operations not being effectively guaranteed.
A double-row structure of inner pole and outer pole is adopted. The inner pole and outer pole are connected by an oblique cross rod, and a wall connecting piece is installed on the inside of the scaffolding, so that the inner pole is embedded in the slope through the wall connecting piece. The anchor bolt knot, combined with the design of expansion bolts and wooden wedges, enhances the stability and safety of the vertical pole, and improves the convenience of the mounting and disassembly through the connecting structure of rotary fasteners and cross fasteners.
It improves the stability and safety of the scaffolding, enhances the guarantee of high-altitude operations, simplifies the process of disassembly and disassembly, and ensures the uniform stress of the vertical pole and the stability of the frame.
Smart Images

Figure CN222227898U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of building construction, and particularly relates to an anchor rod lattice beam slope scaffold. Background Art
[0002] With the development of infrastructure construction in my country, mountain buildings and infrastructure projects are increasing, and high and steep slope construction is becoming more and more common. During the construction of slope support such as anchor lattice beams, the safety and construction of scaffolding are particularly important due to the steep slope. Regarding the installation and construction of scaffolding in the process of high and steep slope support, compared with ordinary scaffolding, the installation of high and steep slope support scaffolding is more complicated. Safety, stability and applicability are the key to the management of this type of project. Most of the existing high and steep slope support scaffolding are single-row frames, and very few use double-row frames. The standardization of operation needs to be improved, and the safety of high-altitude operations cannot be effectively guaranteed. Utility Model Content
[0003] The utility model aims to provide an anchor rod lattice beam slope scaffolding which has simple structural specifications, is easy to assemble and disassemble, has good applicability and high safety.
[0004] The technical solution of the utility model is an anchor lattice beam slope scaffolding, comprising: vertical uprights, oblique cross bars perpendicular to the uprights, and transverse sweeping bars and longitudinal sweeping bars installed on the bottom of the uprights, the uprights comprising inner uprights and outer uprights, the transverse sweeping bars and the longitudinal sweeping bars being connected to the inner uprights and the outer uprights by rotating fasteners, the oblique cross bars being connected to the inner uprights and the outer uprights by cross fasteners; the inner uprights are tied to anchor rods embedded in the slope through wall connecting parts, the wall connecting parts comprise wall connecting part inner rods, wall connecting part outer rods and wall connecting part steel pipes, the wall connecting part inner rods are embedded in the slope and welded to the anchor rods, one end of the wall connecting part outer rod is threadedly connected to the wall connecting part inner rod through a tapered sleeve, the other end of the wall connecting part outer rod is connected to the wall connecting part steel pipe, and the wall connecting part steel pipe is connected to the inner uprights through steel pipe fasteners.
[0005] Preferably, a first pad is provided at each arrangement position of the vertical poles, the first pad is anchored on the concrete foundation by expansion bolts, and the vertical poles abut against the first pad; the angle formed between the bottom end face of the vertical pole and the first pad is tightened by a wooden wedge, and the wooden wedge is fixed to the first pad by cement nails.
[0006] Preferably, one end of the oblique cross bar is connected to a second pad, and the oblique cross bar is vertically pressed against the slope surface of the slope through the second pad; a plurality of nails are provided on the second pad, one end of the nails is inserted into the second pad, and the other end is inserted into the oblique cross bar.
[0007] Preferably, vertical scissors braces are provided every 15 m on the outside of the outer poles, and the width of the scissors braces is not less than 4 spans.
[0008] Preferably, a zigzag diagonal brace is provided at the end of the scaffolding, and the zigzag diagonal brace is connected to the inner upright pole and the outer upright pole located at the end of the scaffolding.
[0009] Preferably, soil nails are pre-buried between the anchor rods to serve as anchor points for the wall ties, and the wall ties located opposite to each other are welded to the soil nails.
[0010] Preferably, horizontal bars are installed on the vertical bars, and the horizontal bars include transverse horizontal bars and longitudinal horizontal bars installed on the transverse horizontal bars, and scaffolding boards are laid on the transverse horizontal bars and the longitudinal horizontal bars.
[0011] Preferably, a handrail is installed on the outer side of the scaffolding board, and when the slope angle θ is greater than 65 degrees, the handrail is installed on the outer pole; when the slope angle θ is less than 65 degrees, guardrail uprights are first added to the inclined cross bar and the outer pole, and then the handrail is installed on the guardrail uprights.
[0012] Preferably, an upper and lower passage is provided in the middle of the scaffolding, and safety belt hanging points are provided on both sides of the scaffolding with a spacing of 1m.
[0013] Preferably, the longitudinal distance of the scaffolding is about 1.5m, the transverse distance is about 1.05m, the height step is between 1.8-2.0m, the diagonal layout is not more than 2.2m, and the total height of the scaffolding is not more than 15m.
[0014] Compared with the prior art, the beneficial effects of the utility model are:
[0015] ⑴ The utility model adopts a double-row structure of inner and outer uprights, which are connected by oblique cross bars, and a wall connecting piece is arranged on the inner side of the scaffolding, so that the inner uprights are connected with the anchor rods embedded in the slope through the wall connecting piece, thereby ensuring the stability of the scaffolding frame and improving the safety of high-altitude operations;
[0016] (2) Since the wall connecting member is constructed as a structure in which the outer rod of the wall connecting member is threadedly connected to the inner rod of the wall connecting member, the wall connecting member is easy to assemble and disassemble, further improving the convenience of scaffolding erection and disassembly;
[0017] ⑶ By setting the first pad at the arrangement position of the scaffolding uprights, the wooden pad is anchored to the concrete foundation with expansion bolts to resist the oblique lateral sliding force of the uprights; the angle between the bottom of the upright and the first pad is tightened with wooden wedges to ensure uniform force on the bottom end of the upright. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1It is a structural schematic diagram of an embodiment of the anchor rod lattice beam slope scaffolding of the utility model;
[0019] Figure 2 This is a schematic diagram of the tie structure between the wall connecting member and the anchor rod of the utility model;
[0020] Figure 3 yes Figure 2 A partial enlarged view of the middle part;
[0021] Figure 4 yes Figure 2 A partial enlarged view of point B in the middle;
[0022] Figure 5 yes Figure 2 A partial enlarged view of point C in the middle;
[0023] Figure 6 yes Figure 2 A partial enlarged view of point D in the middle;
[0024] Figure 7 yes Figure 2 A partial enlarged view of point E in the middle;
[0025] Figure 8 yes Figure 7 Schematic diagram from another angle;
[0026] Fig. 9 yes Figure 2 A schematic structural diagram of another embodiment is shown at E;
[0027] Fig.10 This is a schematic diagram of the tie structure between the wall connecting member and the soil nails of the utility model;
[0028] Fig.11 yes Fig.10 Schematic diagram of the structure of soil nails;
[0029] Fig.12 yes Fig.11 Schematic diagram from another angle;
[0030] Fig.13 It is a structural schematic diagram of another embodiment of the anchor rod lattice beam slope scaffolding of the utility model;
[0031] Main component symbols:
[0032] Scaffold 1; upright pole 11; inner upright pole 111; outer upright pole 112; rotating fastener 113; cross fastener 114; oblique cross bar 12; second pad 121; nail 122; horizontal sweeping rod 13; vertical sweeping rod 14; wall connecting piece 15; inner rod 151 of wall connecting piece; outer rod 152 of wall connecting piece; steel pipe 153 of wall connecting piece; conical sleeve 154; steel pipe fastener 155; zigzag diagonal brace 16; horizontal rod 17; horizontal horizontal rod 171; vertical horizontal rod 172; scaffolding board 18; handrail 19; guardrail upright pole 191;
[0033] Slope 2; anchor rod 21; soil nail 22; steel pipe head 221; barb 222; grouting hole 223; slope 23; template 24; reinforced wooden back rib 25;
[0034] Concrete foundation 3; first pad 31; expansion bolt 32; wooden wedge 33; cement nail 34;
[0035] Lattice beam foundation 4;
[0036] Cement mortar5. DETAILED DESCRIPTION
[0037] The utility model will be further described below in conjunction with the accompanying drawings:
[0038] See also Figures 1 to 13 As shown, the utility model provides an anchor rod lattice beam slope scaffolding 1, comprising: a vertical pole 11, an oblique cross bar 12 perpendicular to the pole 11, and a transverse sweeping rod 13 and a longitudinal sweeping rod 14 installed at the bottom of the pole 11, the pole 11 comprises an inner pole 111 and an outer pole 112, the transverse sweeping rod 13 and the longitudinal sweeping rod 14 are connected to the inner pole 111 and the outer pole 112 through a rotating fastener 113, the oblique cross bar 12 is connected to the inner pole 111 and the outer pole 112 through a cross fastener 114; the inner pole 111 is tied to an anchor rod 21 pre-buried in the slope 2 through a wall connecting member 15, and the wall connecting member 15 comprises a wall connecting member inner rod 151 , an outer rod 152 of the wall connection member and a steel pipe 153 of the wall connection member, an inner rod 151 of the wall connection member is pre-buried in the slope 2 and welded to the anchor rod 21, one end of the outer rod 152 of the wall connection member is threadedly connected to the inner rod 151 of the wall connection member through a tapered sleeve 154, the other end of the outer rod 152 of the wall connection member is connected to the steel pipe 153 of the wall connection member, and the steel pipe 153 of the wall connection member is connected to the inner vertical rod 111 through a steel pipe fastener 155; by setting the tapered sleeve 154 for the connection between the outer rod 152 of the wall connection member and the inner rod 151 of the wall connection member, it is convenient to temporarily remove and restore the outer rod 152 of the wall connection member, and setting the sleeve 154 to a cone also facilitates the installation and removal of the sleeve 154.
[0039] It is worth mentioning that please refer to Figure 3As shown, during the construction of the lattice beam foundation 4, a template 24 for supporting the template before pouring the lattice beam concrete and a reinforcing wood square back rib 25 located outside the template 24 for reinforcing the template before pouring the lattice beam concrete are provided on the slope surface 23, and the outer rod 152 of the wall connecting member avoids the reinforcing wood square back rib 25 and passes through the template 24 and is threadedly connected with the inner rod 151 of the wall connecting member;
[0040] When the template 24 is removed, the outer rod 152 of the wall connecting member is temporarily removed first, and then the outer rod 152 of the wall connecting member is installed on the inner rod 151 of the wall connecting member after the template 24 is removed, so as to form a Figure 4 The lattice girder formwork 24 is shown in a state after being removed.
[0041] When the wall connecting member 15 is removed, the outer rod 152 of the wall connecting member is removed first, and then the conical sleeve 154 is taken out. Finally, the hole left by the conical sleeve 154 is sealed with cement mortar 5, so as to form a Figure 5 The state after the wall connection parts are removed is shown.
[0042] The anchor lattice beam slope scaffolding provided by the utility model adopts a double-row structure of inner uprights and outer uprights, connects the inner uprights and the outer uprights by oblique cross bars, and arranges wall connecting pieces on the inner side of the scaffolding, so that the inner uprights are connected with the anchor rods pre-buried in the slope through the wall connecting pieces, thereby ensuring the stability of the scaffolding frame and improving the safety of high-altitude operations; since the wall connecting pieces are constructed as a structure in which the outer rod of the wall connecting piece is threadedly connected to the inner rod of the wall connecting piece, the wall connecting piece is easy to assemble and disassemble, further improving the convenience of erecting and disassembling the scaffolding.
[0043] Specifically, in this embodiment, the arrangement of the anchor lattice beam slope scaffolding is as follows: Fig.13 The horizontal distance d1 of the scaffold shown is about 1.05m, the height step h is between 1.8-2.0m, the diagonal layout d2 is not greater than 2.2m, the vertical distance is about 1.5m (not shown in the figure), and the total height of the scaffold is not greater than 15m (not shown in the figure).
[0044] As a preference, see Figure 2 , Figure 6 As shown, the arrangement positions of the vertical poles 11 are all provided with first pads 31, which are anchored on the concrete foundation 3 by expansion bolts 32, and the vertical poles 1 abut against the first pads 31. Specifically, the first pads are made of 150*150*18mm plywood, and the first pads are anchored to the concrete foundation 3 by M10 expansion bolts to resist the oblique side sliding force of the vertical poles 1.
[0045] For further information, see Figure 6As shown, the angle formed between the bottom end face of the upright pole 1 and the first pad 31 is tightened by a wooden wedge 33, and the wooden wedge 33 is fixed to the first pad 31 by a cement nail 34. By arranging the wooden wedge 33 between the bottom end face of the upright pole 1 and the first pad 31, it is ensured that the bottom end face of the upright pole 1 is subjected to uniform force.
[0046] It is worth noting that if Fig.10 As shown, the axial force N is calculated by the slope angle θ and the uprights. The calculated axial force N of the uprights can be obtained by calculating the weight of the scaffolding itself. According to the formula F=N*cosθ, the design value of the lateral horizontal force F can be calculated. The uprights and the foundation must maintain balance, and it is necessary to ensure that the actual anti-slip force in the horizontal force direction is greater than the design value of the lateral horizontal force F; therefore, by arranging a first pad at the upright arrangement position and arranging a wooden wedge between the bottom end face of the upright and the first pad, the oblique lateral sliding force of the upright can be effectively resisted and the bottom end face of the upright can be ensured to be evenly stressed.
[0047] As a preference, see Figure 2 , Figure 7 , Fig. 9 As shown, one end of the oblique cross bar 12 is connected to a second pad 121, and the oblique cross bar 12 is vertically supported on the slope surface 23 of the slope 2 through the second pad 121; a plurality of nails 122 are provided on the second pad 121, one end of the nail 122 is inserted into the second pad 121, and the other end is inserted into the oblique cross bar 12.
[0048] Specifically, the second pad 121 is made of 150*150*18mm plywood, such as Figure 7 , Figure 8 Drive three 5 cm nails into the second pad 121 as shown, or Fig. 9 As shown, a 5 cm nail is driven into the middle of the second pad 121, the nail is driven into the second pad 121 by 10-15 mm, and the exposed part of the nail cap is inserted into the oblique cross bar 12, so that the second pad 121 is connected to the oblique cross bar 12 to prevent the second pad 121 from loosening or sliding down.
[0049] Preferably, vertical scissor braces (not shown) are provided at intervals of 15 m on the outside of the outer pole 112 in the longitudinal direction, and the width of the scissor braces is not less than 4 spans.
[0050] As a preference, see Figure 2 As shown, a zigzag diagonal brace 16 is provided at the end of the scaffold 1 , and the zigzag diagonal brace 16 is connected to an inner upright pole 111 and an outer upright pole 112 located at the end of the scaffold 1 .
[0051] As a preference, see Fig.10As shown, soil nails 22, such as steel bar soil nails or steel pipe soil nails, are pre-buried between the anchor rods 21 to serve as the tie points of the wall ties 15, and the wall ties 15 at opposite positions are welded to the soil nails 22. By adding steel bar soil nails or steel pipe soil nails, the anchor rods are replaced as the tie points of the wall ties at the positions where there are no anchor rods 21. The steel bar soil nails or steel pipe soil nails are much smaller than the anchor rods in terms of force performance, and the construction is also simpler.
[0052] Specifically, in one example, the following is used: Fig.11 , Fig.12 The steel flower pipe soil nail 22 shown in the figure has a pointed cone-shaped head welded to the steel pipe head 221 to facilitate driving into the soil. 1 / 2 of the entire length of the steel pipe is welded with a steel bar or angle steel barb 222. The barb 222 is welded symmetrically along the circumference of the steel pipe. The barb 222 is arranged close to one end of the steel pipe head 221, and a grouting circular hole 223 is set behind the barb 222.
[0053] As a preference, see Figure 1 As shown, horizontal rods 17 are installed on the vertical rods 11. The horizontal rods 17 include transverse horizontal rods 171 and longitudinal horizontal rods 172 installed on the transverse horizontal rods 171. Scaffolding boards 18 are laid on the transverse horizontal rods 171 and the longitudinal horizontal rods 172 to form a slope construction operation platform.
[0054] For further information, see Figure 1 As shown, a handrail 19 is installed on the outside of the scaffolding board 18. When the slope angle θ is greater than 65 degrees, the handrail 19 is installed on the outer pole 112; when the slope angle θ is less than 65 degrees, as shown in FIG. Fig.13 As shown, guardrail uprights 191 are firstly added to the oblique crossbar 12 and the outer uprights 112 , and then the handrail 19 is installed on the guardrail uprights 191 .
[0055] Passage entrances and exits are set on both sides of the scaffolding (not shown in the figure), and construction workers enter the passage from the side of the slope; further, up and down passages are set in the middle of the scaffolding, and safety belt hanging points with a spacing of 1m are required on both sides of the scaffolding.
[0056] The above description is only a preferred embodiment of the present invention. All equivalent changes and modifications made within the scope of the claims of the present invention shall fall within the scope of the claims of the present invention.
Claims
1. An anchor lattice beam slope scaffolding, comprising: A vertical pole, an oblique cross pole perpendicular to the pole, and a horizontal sweeping pole and a longitudinal sweeping pole installed on the bottom layer of the pole, characterized in that the pole comprises an inner pole and an outer pole, the horizontal sweeping pole and the longitudinal sweeping pole are connected to the inner pole and the outer pole by rotating fasteners, and the oblique cross pole is connected to the inner pole and the outer pole by a cross fastener; the inner pole is connected to an anchor rod embedded in the slope through a wall connecting member, the wall connecting member comprises an inner rod of a wall connecting member, an outer rod of a wall connecting member and a steel pipe of a wall connecting member, the inner rod of the wall connecting member is embedded in the slope and welded to the anchor rod, one end of the outer rod of the wall connecting member is threadedly connected to the inner rod of the wall connecting member through a tapered sleeve, the other end of the outer rod of the wall connecting member is connected to the steel pipe of the wall connecting member, and the steel pipe of the wall connecting member is connected to the inner pole through a steel pipe fastener.
2. The anchor lattice beam slope scaffold according to claim 1, characterized in that: A first pad is provided at each arrangement position of the vertical poles, the first pad is anchored on the concrete foundation by expansion bolts, and the vertical poles abut against the first pad; the angle formed between the bottom end surface of the vertical pole and the first pad is tightened by a wooden wedge, and the wooden wedge is fixed to the first pad by cement nails.
3. The anchor lattice beam slope scaffold according to claim 1, characterized in that: One end of the oblique cross bar is connected to a second pad, and the oblique cross bar is vertically supported on the slope surface of the slope through the second pad; a plurality of nails are arranged on the second pad, one end of the nails is inserted into the second pad, and the other end is inserted into the oblique cross bar.
4. The anchor lattice beam slope scaffolding according to claim 1, characterized in that: Vertical scissor braces are arranged at intervals of 15m on the outside of the outer poles, and the width of the scissor braces is not less than 4 spans.
5. The anchor lattice beam slope scaffolding according to claim 1, characterized in that: The ends of the scaffolding are provided with zigzag diagonal braces, and the zigzag diagonal braces are connected with inner upright poles and outer upright poles located at the ends of the scaffolding.
6. The anchor lattice beam slope scaffolding according to claim 1, characterized in that: Soil nails are pre-buried between the anchor rods to serve as anchor points for the wall ties, and the wall ties at opposite positions are welded to the soil nails.
7. The anchor lattice beam slope scaffolding according to claim 1, characterized in that: Horizontal bars are installed on the vertical bars. The horizontal bars include transverse horizontal bars and longitudinal horizontal bars installed on the transverse horizontal bars. Scaffolding boards are laid on the transverse horizontal bars and the longitudinal horizontal bars.
8. The anchor lattice beam slope scaffolding according to claim 7, characterized in that: A handrail is installed on the outside of the scaffolding board. When the slope angle θ is greater than 65 degrees, the handrail is installed on the outer pole; when the slope angle θ is less than 65 degrees, guardrail poles are first added to the oblique cross bar and the outer pole, and then the handrail is installed on the guardrail pole.
9. The anchor lattice beam slope scaffolding according to claim 7, characterized in that: There are up and down passages in the middle of the scaffolding, and safety belt hanging points with a spacing of 1m are set on both sides of the scaffolding.
Citation Information
Cited By
Ecological slope protection and green recovery system for steep rock high slope water-intercepting planting belt and construction method of ecological slope protection and green recovery system
CN119913919A
Ecological slope protection and revegetation system and construction method of water intercepting vegetation planting belt for steep rocky high slopes
CN119913919B