Civil construction foundation pile device
By designing the civil building pile device with assembly and sliding locking mechanism, the problem of cumbersome formwork installation during the existing pile filling process is solved, and rapid and simple foundation pile pouring and high-adjustment efficiency is achieved.
Patent Information
- Application Number
- CN202323508608.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-22
- Publication Date
- 2024-12-27
- Estimated Expiration
- 2033-12-22
AI Technical Summary
The existing foundation piles need to use formwork during the pouring process, and the fixing is done by bolts. The installation and loading and unloading process is cumbersome and takes a long time.
A civil building foundation pile device including assembly and sliding locking mechanism is designed. The assembly is connected by a shaft and equipped with a curved groove and a curved bar sliding locking mechanism to simplify the installation and disassembly of the formwork.
Through the sliding locking mechanism, the installation and disassembly of the foundation pile formwork is simplified, the filling efficiency is improved, the complexity of manual operation is reduced, and the pouring height is convenient.
Smart Images

Figure CN222252086U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of civil engineering and construction, in particular to a foundation pile device for civil engineering and construction. Background Art
[0002] The foundation pile is the basis of the foundation pile device of civil engineering, usually made of concrete, used to support and fix the pedestal. There are many types of foundation piles, including prefabricated piles, cast-in-place piles, steel pipe piles, etc. Cast-in-place piles are piles that need to be formed by pouring on site and are suitable for various geological conditions. The existing foundation piles often require a template when pouring. A casting model is formed by fixing four templates together with bolts, and then pouring is performed. However, this casting method needs to be completed by installing and loading and unloading bolts, which is often troublesome. Therefore, a civil engineering foundation pile device is proposed based on the above problem. Utility Model Content
[0003] The purpose of the utility model is to solve the problem that the existing foundation piles often need to use templates when pouring, and the four templates are fixed together with bolts to form a pouring model, and then pouring is carried out. However, this pouring method needs to be completed by installing and unloading bolts, which is often troublesome.
[0004] Therefore, based on the above-mentioned problem, the utility model proposes a civil engineering construction pile foundation device, which includes assembly one and assembly two, one end of which is rotatably connected to each other through an axle rod, and the other end of which is provided with a sliding locking mechanism.
[0005] Preferably: the sliding locking mechanism includes: arc groove 1 and arc groove 2, arc groove 1 is provided at the other end of assembly 1, arc groove 2 is provided at the other end of assembly 2, arc groove 1 and arc groove 2 cooperate with each other to form a circular ring, and the circular ring shape is biased towards one side of assembly 1, the sliding locking mechanism also includes an arc strip, a slidable arc strip is arranged inside arc groove 1, a push block is integrally fixedly connected to one end of the arc strip, a limiting groove is provided on one side of assembly 1, and a push block slides on the limiting groove.
[0006] Preferably: an insert block 1 is integrally fixedly provided on the upper portion of assembly 1, an insert block 2 is integrally fixedly connected to the upper portion of assembly 2, a slot 1 and a slot 2 are respectively provided on the lower portions of assembly 1 and assembly 2, insert block 1 is inserted into slot 1, and insert block 2 is inserted into slot 2.
[0007] Preferably, the length of the arc strip is at least longer than half of the length of the circular ring shape formed by the combination of the arc groove 1 and the arc groove 2.
[0008] Beneficial effect: When it is necessary to cast foundation piles, first fit assembly one and assembly two together, then slide the push block by hand, at this time the arc strip will enter the arc groove one set inside assembly two, and then the arc strip will lock assembly one and assembly two together, thereby forming a template for casting foundation piles, and then plug new assembly one and assembly two into assembly one and assembly two one by one, and the plug block one and plug block two set on assembly one and assembly two are superimposed and inserted into slot one and slot two, and then cement is poured on assembly one and assembly two. BRIEF DESCRIPTION OF THE DRAWINGS
[0009] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0010] Figure 2 This is a schematic diagram of the connection between the shaft rod and the arc strip structure of the second assembly in the utility model;
[0011] Figure 3 This is a use effect diagram of the utility model;
[0012] Figure 4 The use effect of the utility model Figure 2 .
[0013] Figures 1 to 4 The reference numerals are respectively: assembly 1, insert block 101, slot 102, arc groove 103, limit groove 104, assembly 2, insert block 201, slot 202, arc groove 203, shaft rod 3, arc strip 4, push block 401, auxiliary block 5. DETAILED DESCRIPTION
[0014] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.
[0015] Reference Figures 1 to 4 A civil engineering construction pile device comprises an assembly 1 and an assembly 2, wherein one end of the assembly 1 and the assembly 2 are rotatably connected to each other through an axle rod 3, and the other end of the assembly 1 and the assembly 2 is provided with a sliding locking mechanism.
[0016] Preferably, the sliding locking mechanism comprises: arc groove 1 103 and arc groove 2 203, the other end of assembly 1 is provided with arc groove 103, the other end of assembly 2 is provided with arc groove 203, the arc groove 103 and arc groove 2 203 cooperate with each other to form a circular ring, and the circular ring shape is biased towards one side of assembly 1, the sliding locking mechanism also comprises an arc strip 4, the length of the arc strip 4 is at least longer than half of the length of the circular ring shape formed by the combination of arc groove 1 103 and arc groove 2 203, the arc strip 4 is made of steel or an alloy with a hardness greater than that of steel, and the arc groove 103 is provided inside A slidable arc-shaped bar 4 is arranged, one end of which is integrally fixedly connected with a pushing block 401, a limiting groove 104 is arranged on one side of the assembly 1, and a pushing block 401 is slidably arranged on the limiting groove 104. When the staff needs to cast the foundation pile, the assembly 1 and the assembly 2 2 are first matched together, and then the pushing block 401 is slid by hand, and the pushing block 401 will slide along the limiting groove 104, and the pushing block 401 is fixedly connected to the arc-shaped bar 4, so it will also drive the arc-shaped bar 4 to rotate, and at this time the arc-shaped bar 4 will enter the arc-shaped groove 103 arranged inside the assembly 2 2. Figure 3 The arc strip 4 shown will be located between the arc groove 1 103 and the arc groove 2 203. Since the length of the arc strip 4 is at least longer than half of the length of the arc groove 1 103 and the arc groove 2 203 combined to form a circular ring shape, the arc strip 4 will lock the assembly 1 and the assembly 2 2 together, thereby forming a template for pouring foundation piles.
[0017] Preferably: an insert block 101 is integrally fixedly provided on the upper part of assembly 1, and an insert block 201 is integrally fixedly connected to the upper part of assembly 22; a slot 102 and a slot 202 are respectively provided on the lower parts of assembly 1 and assembly 22; the insert block 101 is inserted into the slot 102, and the insert block 201 is inserted into the slot 2 202; when it is necessary to increase the height of the poured foundation piles, new assembly 1 and assembly 2 2 can be plugged into assembly 1 and assembly 2 2 one by one by adjusting the height of the template; the insert blocks 101 and 201 arranged on assembly 1 and assembly 2 2 are overlapped and inserted into the slot 102 and slot 202.
[0018] Preferably: one side of assembly 1 and assembly 2 2 is integrally fixedly connected with an auxiliary block 5. When the staff needs to disassemble, they can gently knock the auxiliary block 5 upward with a tool, which will give an upward force to the auxiliary block 5 and the assembly 1 and assembly 2 2 fixedly connected thereto, thereby facilitating the removal of the plug-in block inserted in the slot.
[0019] Working principle: When the staff needs to cast the foundation pile, first combine the assembly 1 and the assembly 2 2 together, then slide the push block 401 by hand, and the push block 401 will slide along the limit groove 104, and the push block 401 is fixedly connected to the arc strip 4, so it will also drive the arc strip 4 to rotate, and the arc strip 4 will enter the arc groove 1 103 set inside the assembly 2 2. Figure 3 The arc strip 4 shown will be located between the arc groove 1 103 and the arc groove 2 203. Since the length of the arc strip 4 is at least longer than half of the length of the arc groove 1 103 and the arc groove 2 203 combined to form a circular ring shape, the arc strip 4 will lock the assembly 1 and the assembly 2 2 together, thereby forming a template for pouring foundation piles. When it is necessary to increase the height of the pouring foundation piles, the height of the template can be adjusted to plug new assemblies 1 and assemblies 2 2 one by one on the assembly 1 and the assembly 2 2. The plug blocks 101 and 201 set on the assembly 1 and the assembly 2 2 are overlapped and inserted into the slots 1 102 and 202.
[0020] The above description is only a preferred specific implementation manner of the present utility model, but the protection scope of the present utility model is not limited thereto. Any technician familiar with the technical field within the technical scope disclosed by the present utility model can make equivalent substitutions or changes based on the technical scheme and utility model concept of the present utility model, which should be covered by the protection scope of the present utility model.
Claims
1. A foundation pile device for civil engineering construction, comprising a first assembly (1) and a second assembly (2), wherein one end of the first assembly (1) and the second assembly (2) are rotatably connected to each other via a shaft (3), characterized in that: The other ends of assembly one (1) and assembly two (2) are provided with a sliding locking mechanism; The sliding locking mechanism comprises: an arc groove 1 (103) and an arc groove 2 (203), wherein the other end of the assembly 1 (1) is provided with an arc groove 1 (103), and the other end of the assembly 2 (2) is provided with an arc groove 2 (203), and the arc groove 1 (103) and the arc groove 2 (203) cooperate with each other to form a circular ring shape, and the circular ring shape is biased toward one side of the assembly 1 (1); The sliding locking mechanism further comprises an arc-shaped bar (4), a slidable arc-shaped bar (4) is arranged inside the arc-shaped groove (103), one end of the arc-shaped bar (4) is integrally fixedly connected with a push block (401), and a limiting groove (104) is provided on one side of the assembly (1), and a push block (401) slides on the limiting groove (104).
2. The civil engineering construction pile device according to claim 1, characterized in that: The upper part of the assembly one (1) is integrally fixed with an insert block one (101), and the upper part of the assembly two (2) is integrally fixed with an insert block two (201). The lower parts of the assembly one (1) and the assembly two (2) are respectively provided with a slot one (102) and a slot two (202). The insert block one (101) is inserted into the slot one (102), and the insert block two (201) is inserted into the slot two (202).