Building platform for mounting building machine
By introducing adjustable connection components and Bere units into the building machine building platform, the problem that Bere frames cannot be adjusted in the existing technology is solved, flexible adaptation and stable connection of different shapes of floors are achieved, and the construction platform is improved applicability and strength.
Patent Information
- Application Number
- CN202421014863.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-10
- Publication Date
- 2024-12-27
- Estimated Expiration
- 2034-05-10
AI Technical Summary
The existing building machine Beret frame cannot be adjusted according to the floor shape, which limits its adaptability and flexibility in building floors in opposite-shaped shapes.
A construction platform including the first and second connecting mechanisms is designed, through a limited position assembly and an adjustable connecting assembly, allowing the disassembly and reassembly of the Bere unit to achieve angle adjustment and adaptation to floor construction of different shapes.
It improves the scope of application and stability of the construction platform, allows flexible splicing and assembly according to floor size and shape, enhances the stability and strength of the Bere unit, and simplifies the installation and disassembly process.
Smart Images

Figure CN222253042U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building machines, and specifically relates to an erection platform for the installation of building machines. Background Art
[0002] The emergence of the aerial building machine has brought unprecedented innovation to the construction industry. Through automatic mechanical construction, it completes the construction of buildings, thus saving manpower, improving construction efficiency, enhancing safety, etc. In the construction of high-rise building structures, building machines are usually used. For the current building machines, the large operation platform at the top can be built with Bailey frames, which have the advantages of light weight, convenient modular assembly, and high strength.
[0003] Chinese Patent with the authorization announcement number CN216276809U discloses a novel Bailey frame connection component for a building machine. Through the newly designed corner column head, it can quickly connect the Bailey frame units at the corner to form a load-bearing structure in the shape of "L", "T" or "十". Further setting a load-bearing structure with a "田" shaped planar structure can improve the overall strength and is convenient for jacking; setting a walkway board and a guardrail component to prevent people and objects from falling, and further setting a patrol robot for automated inspection.
[0004] However, the above-mentioned disclosed solutions have the following deficiencies: The angle between two adjacent groups of Bailey frame units on the corner column head is fixed, so that the Bailey frame of this building machine can only be spliced and assembled into a specific shape, cannot be adjusted according to the shape of the floor, and cannot adapt to the construction of floors with special shapes, and its use has certain limitations. Summary of the Utility Model
[0005] The purpose of the utility model is to propose an erection platform for the installation of building machines in view of the problems existing in the background art.
[0006] The technical solution of the utility model: An erection platform for the installation of building machines includes several groups of first connection mechanisms and second connection mechanisms, and the adjacent two groups of second connection mechanisms are connected through the first connection mechanism;
[0007] The first connection mechanism includes a mounting seat, the top of which is provided with a limiting component. Four groups of connection components are evenly arranged on the mounting seat. The connection components are rotatably connected to the mounting seat, and the connection components are adjustably connected to the mounting seat through the limiting component. The second connection mechanism is detachably connected to the end of the connection component far away from the mounting seat;
[0008] The second connection mechanism includes Bailey units, and several groups of Bailey units are detachably connected in sequence. The two Bailey units at the head and tail are detachably connected to the connection components in the adjacent first connection mechanism.
[0009] Preferably, the mounting seat includes a top seat, four groups of columns are installed at the bottom end of the top seat, a base is installed between the bottom ends of the three groups of columns, and the connecting assembly is rotatably connected to the corresponding columns.
[0010] Preferably, the connecting assembly includes a rotating seat, which is rotatably connected to the column, and a connecting rod is installed on the other end of the rotating seat; and a docking seat, which is installed on the connecting rod, and four groups of first connecting seats are evenly arranged on the docking seat.
[0011] Preferably, the limit assembly includes a limit rod, which is installed on the connecting rod; and a limit seat, which is provided in four groups. The four groups of limit seats are evenly distributed on the top of the top seat. Four groups of adjustment channels are opened on the top of the top seat. The limit rod passes through the adjustment channel and is connected to the limit seat by bolts. The limit rod is slidably connected to the adjustment channel.
[0012] Preferably, the limit seat and the adjustment channel are both configured to be arc-shaped, and a plurality of groups of adjustment holes are provided on the limit seat, and the adjustment holes are adapted to the bolts.
[0013] Preferably, the Bailey unit includes two groups of Bailey plates A, two groups of Bailey plates B are installed between the two groups of Bailey plates A; four groups of second connecting seats are provided, and the four groups of second connecting seats are respectively installed at the ends of the two groups of Bailey plates A; and four groups of third connecting seats are provided, and the four groups of third connecting seats are respectively installed at the other ends of the two groups of Bailey plates A. The second connecting seat is adapted to the third connecting seat, and the second connecting seat is adapted to the first connecting seat.
[0014] Compared with the prior art, the above-mentioned technical scheme of the utility model has the following beneficial technical effects: the utility model facilitates adjustment of the installation angle of the second connecting mechanism relative to the first connecting mechanism through the connecting component, can adapt to the construction of floors of different shapes, and has a wider range of applications, and can improve the connection stability between the second connecting mechanism and the first connecting mechanism through the limiting component; the stability and strength of the second connecting mechanism are improved through the setting of Bailey plate A and Bailey plate B, and the second connecting seat and the third connecting seat are convenient for splicing and assembling into a second connecting mechanism of appropriate size according to the floor size, and the second connecting seat facilitates splicing of the second connecting mechanism with the first connecting mechanism, and disassembly and assembly are convenient and quick. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0016] Figure 2 This is a schematic diagram of the structure of the first connecting mechanism of the utility model;
[0017] Figure 3 This is a schematic diagram of the structure of the connection assembly of the utility model;
[0018] Figure 4It is a schematic diagram of the structure of the second connecting mechanism of the utility model.
[0019] Figure numerals: 1. first connecting mechanism; 2. second connecting mechanism; 3. top seat; 301. adjustment channel; 302. limit seat; 303. adjustment hole; 304. base; 305. column; 4. rotating seat; 401. connecting rod; 402. docking seat; 403. limit rod; 404. first connecting seat; 5. Bailey piece A; 501. Bailey piece B; 502. second connecting seat; 503. third connecting seat. DETAILED DESCRIPTION
[0020] Embodiment 1
[0021] like Figures 1 to 4 As shown, the utility model provides a building platform for installing a building construction machine, which includes a plurality of groups of first connecting mechanisms 1 and second connecting mechanisms 2 , and two adjacent groups of second connecting mechanisms 2 are connected via the first connecting mechanism 1 .
[0022] The first connecting mechanism 1 includes a mounting seat; a limiting component is arranged at the top of the mounting seat, and four groups of connecting components are evenly arranged on the mounting seat. The connecting component is rotatably connected to the mounting seat, and the connecting component is adjustably connected to the mounting seat through the limiting component. The second connecting mechanism 2 is detachably connected to the end of the connecting component away from the mounting seat.
[0023] The second connecting mechanism 2 includes Bailey units; the Bailey units are arranged in several groups, and the several groups of Bailey units are detachably connected in sequence, and the two groups of Bailey units located at the head and the tail are detachably connected to the connecting components in the adjacent first connecting mechanism 1.
[0024] Furthermore, the mounting base includes a top base 3 ; four groups of columns 305 are installed at the bottom end of the top base 3 , a base 304 is installed between the bottom ends of the three groups of columns 305 , and the connecting assembly is rotatably connected to the corresponding column 305 .
[0025] Furthermore, the connecting assembly includes a rotating seat 4 and a docking seat 402; the rotating seat 4 is rotated to connect the column 305, and a connecting rod 401 is installed on the other end of the rotating seat 4; the docking seat 402 is installed on the connecting rod 401, and four groups of first connecting seats 404 are evenly arranged on the docking seat 402, and the first connecting seat 404 is detachably connected to the second connecting seat 502 in the second connecting mechanism 2.
[0026] In this embodiment, the angle of the connecting assembly relative to the mounting seat is adjusted according to actual installation needs, that is, the rotating seat 4 is rotated to any angle along the column 305, thereby driving the docking seat 402 to rotate along the mounting seat to a suitable position, and then the rotating seat 4 and the connecting rod 401 are fixedly connected to the mounting seat through the limiting assembly to improve the installation stability, and then according to the size of the floor, a suitable number of Bailey units are spliced and assembled into a second connecting mechanism 2, and the second connecting mechanism 2 is fixedly connected to the first connecting seat 404 on the docking seat 402 by bolts, and can be spliced and assembled according to the shape and size of the floor, which is more flexible to use and has a wider range of applications.
[0027] Embodiment 2
[0028] like Figure 2 and Figure 3 As shown, the utility model proposes a building platform for installing a building construction machine. Compared with the first embodiment, the limiting assembly includes a limiting rod 403 and a limiting seat 302; the limiting rod 403 is installed on the connecting rod 401; the limiting seat 302 is provided with four groups, and the four groups of limiting seats 302 are evenly distributed on the top of the top seat 3, and the top of the top seat 3 is provided with four groups of adjustment channels 301, the limiting rod 403 passes through the adjustment channel 301 and is connected to the limiting seat 302 by bolts, and the limiting rod 403 is slidably connected to the adjustment channel 301.
[0029] Furthermore, the limiting seat 302 and the adjusting channel 301 are both arc-shaped, and the limiting seat 302 is provided with a plurality of adjusting holes 303, which are matched with the bolts, so as to facilitate adjusting the angle of the limiting rod 403 relative to the mounting seat, and then adjusting the angle of the docking seat 402 relative to the mounting seat, thereby adjusting the angle between two adjacent sets of second connecting mechanisms 2.
[0030] In this embodiment, after the rotating seat 4 drives the connecting rod 401 to rotate along the column 305 to an appropriate angle, the connecting rod 401 simultaneously drives the limiting rod 403 to rotate along the adjustment channel 301 to an appropriate position, and the limiting rod 403 is fixedly connected to the adjustment hole 303 at an appropriate position on the limiting seat 302 by bolts, and then the limiting rod 403 is fixedly connected to the mounting seat, so that the docking seat 402 is stably connected to the mounting seat, thereby improving the installation stability of the second connecting mechanism 2 and the first connecting mechanism 1.
[0031] Embodiment 3
[0032] like Figure 1 , Figure 2 and Figure 4As shown, the utility model proposes a building platform for installing a building construction machine. Compared with the first embodiment, the Bailey unit includes a Bailey sheet A5, a second connecting seat 502 and a third connecting seat 503; two groups of Bailey sheets A5 are provided, and two groups of Bailey sheets B501 are installed between the two groups of Bailey sheets A5; four groups of second connecting seats 502 are provided, and the four groups of second connecting seats 502 are respectively installed at the ends of the two groups of Bailey sheets A5; four groups of third connecting seats 503 are provided, and the four groups of third connecting seats 503 are respectively installed at the other ends of the two groups of Bailey sheets A5. The second connecting seat 502 is adapted to the third connecting seat 503, and the second connecting seat 502 is adapted to the first connecting seat 404.
[0033] In this embodiment, the stability of the Bailey unit is improved by connecting two groups of Bailey plates A5 and two groups of Bailey plates B501, and the second connecting seat 502 is inserted into the third connecting seat 503 and fixedly connected by bolts, thereby completing the splicing of two adjacent groups of Bailey units, thereby completing the splicing of the second connecting mechanism 2, and can be spliced into different lengths according to installation requirements, and the second connecting seat 502 is connected to the first connecting seat 404, and the second connecting mechanism 2 can be connected to the connecting component in the first connecting mechanism 1, thereby completing the connection between the second connecting mechanism 2 and the first connecting mechanism 1.
[0034] The implementation modes of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited thereto, and various changes can be made within the knowledge scope of technicians in the relevant technical field without departing from the purpose of the present invention.
Claims
1. A construction platform for installing a building construction machine, characterized in that: It comprises a plurality of groups of first connecting mechanisms (1) and second connecting mechanisms (2), wherein two adjacent groups of second connecting mechanisms (2) are connected via the first connecting mechanisms (1); The first connecting mechanism (1) comprises A mounting seat, a limiting assembly is arranged at the top thereof, four groups of connecting assemblies are evenly arranged on the mounting seat, the connecting assemblies are rotatably connected to the mounting seat, the connecting assemblies are adjustably connected to the mounting seat via the limiting assembly, and the second connecting mechanism (2) is detachably connected to an end of the connecting assembly away from the mounting seat; The second connecting mechanism (2) comprises The Bailey units are provided in a plurality of groups, and the plurality of groups of Bailey units are detachably connected in sequence. The two groups of Bailey units located at the head and the tail are detachably connected to the connecting components in the adjacent first connecting mechanism (1).
2. A construction platform for installing a building construction machine according to claim 1, characterized in that: Mount Included The top seat (3) has four groups of columns (305) installed at its bottom end, a base (304) is installed between the bottom ends of the three groups of columns (305), and the connecting components are rotatably connected to the corresponding columns (305).
3. A construction platform for installing a building construction machine according to claim 2, characterized in that: Connectivity components include A rotating seat (4) is rotatably connected to the column (305), and a connecting rod (401) is installed at the other end of the rotating seat (4); And a docking seat (402) is installed on the connecting rod (401), and four groups of first connecting seats (404) are evenly arranged on the docking seat (402).
4. A construction platform for installing a building construction machine according to claim 3, characterized in that: The limiter components include A limiting rod (403) mounted on the connecting rod (401); And a limit seat (302), which is provided with four groups, the four groups of limit seats (302) are evenly distributed on the top of the top seat (3), the top of the top seat (3) is provided with four groups of adjustment channels (301), the limit rod (403) passes through the adjustment channel (301) and is connected to the limit seat (302) by bolts, and the limit rod (403) is slidably connected to the adjustment channel (301).
5. A construction platform for installing a building construction machine according to claim 4, characterized in that: The limiting seat (302) and the adjusting channel (301) are both designed to be arc-shaped, and a plurality of groups of adjusting holes (303) are provided on the limiting seat (302), and the adjusting holes (303) are adapted to the bolts.
6. A construction platform for installing a building construction machine according to claim 5, characterized in that: Bailey unit includes Bailey plates A (5), which are provided in two groups, and two groups of Bailey plates B (501) are installed between the two groups of Bailey plates A (5); The second connecting seats (502) are provided in four groups, and the four groups of second connecting seats (502) are respectively installed at the ends of the two groups of Bailey plates A (5); And a third connecting seat (503), which is provided with four groups, and the four groups of third connecting seats (503) are respectively installed at the other ends of the two groups of Bailey plates A (5). The second connecting seat (502) is adapted to the third connecting seat (503), and the second connecting seat (502) is adapted to the first connecting seat (404).