Electric hoist fixing device for ALC wallboard construction

By designing fixtures in ALC wall panel construction, using counterweight blocks and universal wheels on the base to fix the load bearing frame, and supporting the pulley set through the support frame and pulley set, the problem of sliding and overturning of the floor-standing support frame is solved, and the construction is improved Safety and continuity.

CN222253191UActive Publication Date: 2024-12-27CHINA CONSTR SCI & TECH (BEIJING) HLDG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420974059.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-07
Publication Date
2024-12-27
Estimated Expiration
2034-05-07

AI Technical Summary

Technical Problem

During the construction of existing ALC wall panels, the bottom end of the floor-standing support frame is not fixed, causing sliding and overturning, causing safety hazards, and not easy to dismantle, affecting the continuity of construction.

Method used

A fixing device including a base, a load-bearing frame, an electric hoist fixing frame, a support frame and a universal wheel is designed. By setting counterweights and universal wheels on the base, the fixing of the load-bearing frame and the stability of the device are ensured, and The pulley set is supported by the support frame and pulley set, and the device is stable and easy to turn around.

Benefits of technology

Effectively prevent the support frame from overturning, improve construction safety and efficiency, and ensure the continuity and construction quality of ALC wall panel construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222253191U_ABST
    Figure CN222253191U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of ALC wall plate construction, and discloses an ALC wall plate construction electric hoist fixing device which comprises a base, an electric hoist fixing device and an electric hoist fixing device. The bearing frame is connected with the base and extends upwards in the vertical direction; the electric hoist fixing frame is connected with the bearing frame, and the electric hoist fixing frame is suitable for fixing an electric hoist; the supporting frame is connected with the top of the bearing frame, and the supporting frame is suitable for supporting a pulley block; and the universal wheels are connected with the base. The bearing frame is arranged on the base, and the balancing weight is arranged on the base, so that the bearing frame can be effectively fixed and is not prone to sliding displacement, potential safety hazards caused by overturning of the supporting frame are prevented, meanwhile, the universal wheels are arranged on the base, turnover of the ALC wall plate after vertical plate installation work is completed is facilitated, and the ALC wall plate is convenient to use. And the construction continuity of the ALC wallboard is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of ALC wall panel construction, in particular to an electric hoist fixing device for ALC wall panel construction. Background Art

[0002] In ALC wall panel projects, the existing electric hoist fixing device is a floor-standing steel structure support frame. The bottom of the floor-standing support frame is usually not fixed but directly stands on the floor surface, which may slide and jump, and is prone to overturning, causing safety hazards. At the same time, the floor-standing support frame standing upright on the floor surface is not easy to dismantle for turnover, which is not conducive to the continuous construction of ALC wall panels. Utility Model Content

[0003] In view of this, the utility model provides an electric hoist fixing device for ALC wall panel construction to solve the problems in the prior art that the bottom end of the floor-standing support frame is not fixed and is prone to sliding, causing safety hazards, and is difficult to dismantle, causing turnover difficulties, which is not conducive to the continuous construction of ALC wall panels.

[0004] The utility model provides an electric hoist fixing device for ALC wall panel construction, comprising: a base, on which a counterweight block is arranged; a load-bearing frame, which is connected to the base and extends vertically upward; an electric hoist fixing frame, which is connected to the load-bearing frame and is suitable for fixing the electric hoist; a supporting frame, which is connected to the top of the load-bearing frame and is suitable for supporting a pulley block; and a universal wheel, which is connected to the base.

[0005] Beneficial effect: By setting the load-bearing frame on the base and arranging a counterweight block on the base, the load-bearing frame can be effectively fixed, and it is not easy to slide and displace, so as to prevent the support frame from overturning and causing safety hazards. At the same time, universal wheels are arranged on the base to facilitate the turnover after the installation of the vertical panels of the ALC wall panels, thereby ensuring the continuity of the ALC wall panel construction.

[0006] In an optional embodiment, the load-bearing frame includes a first load-bearing frame, a second load-bearing frame and a third load-bearing frame, wherein a plurality of first load-bearing frames are provided, and a plurality of first load-bearing frames are extended vertically upward along the base, and a plurality of second load-bearing frames are provided, and a first end of a plurality of second load-bearing frames is connected to the base, a second end of a plurality of second load-bearing frames is connected to an end of the first load-bearing frame away from the base, and each end of the third load-bearing frame is connected to an end of the first load-bearing frame away from the base and a second end of the second load-bearing frame.

[0007] Beneficial effect: By setting the first load-bearing frame, the second load-bearing frame and the third load-bearing frame, the overall structure of the electric hoist fixing device for ALC wall panel construction is more stable, thereby improving the construction efficiency and safety.

[0008] In an optional embodiment, the support frame includes a first support frame, a second support frame, a third support frame and a fourth support frame, and several first support frames are provided. The first end of the first support frame is connected to the first load-bearing frame, and the second end of the first support frame is horizontally away from the load-bearing frame. The second support frame is simultaneously connected to an end of the first load-bearing frame away from the base and the second end of the first support frame, the third support frame is simultaneously connected to the first ends of several first support frames, and the fourth support frame is simultaneously connected to the second ends of several first support frames.

[0009] Beneficial effect: By setting the first support frame, the second support frame and the third support frame, the connection between the support frame and the load-bearing frame is more stable, the support of the pulley block is more stable, and the safety of the construction is improved during the ALC wall panel hoisting construction, avoiding safety hazards caused by the ALC wall panel falling.

[0010] In an optional embodiment, a plurality of the electric hoist fixing frames are provided, and the plurality of the electric hoist fixing frames are arranged between the first load-bearing frame and the second load-bearing frame and are arranged at intervals along the vertical direction, and / or the plurality of the electric hoist fixing frames are arranged between a plurality of the second load-bearing frames and are arranged at intervals along the extension direction of the second load-bearing frame.

[0011] In an optional embodiment, the electric hoist fixing device for ALC wall panel construction also includes an electric hoist fixing template, the electric hoist fixing template is simultaneously connected to a plurality of the electric hoist fixing frame bolts, and the electric hoist is suitable for being arranged on the electric hoist fixing template.

[0012] In an optional embodiment, the base includes a bottom frame and a plate body, and a plurality of the plate bodies are provided. The plurality of the plate bodies are cross-arranged to form a plurality of accommodating areas on the bottom frame, and the plurality of the accommodating areas accommodate the counterweight blocks.

[0013] In an optional embodiment, a plurality of the universal wheels are provided, and the plurality of the universal wheels are arranged at intervals on the bottom surface of the base.

[0014] In an optional embodiment, the load-bearing frame is connected to the base by bolts.

[0015] In an optional implementation, the load-bearing frame and the electric hoist fixing frame are connected by bolts.

[0016] In an optional embodiment, the support frame is bolted to the load-bearing frame. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the specific implementation methods of the utility model or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0018] Figure 1 It is a left view of the electric hoist fixing device for ALC wall panel construction according to an embodiment of the utility model;

[0019] Figure 2 It is a structural schematic diagram of an electric hoist fixing device for ALC wall panel construction according to an embodiment of the utility model.

[0020] Description of reference numerals:

[0021] 1. Base; 101. Underframe; 102. Plate; 2. Load-bearing frame; 201. First load-bearing frame; 202. Second load-bearing frame; 203. Third load-bearing frame; 3. Electric hoist fixing frame; 4. Support frame; 401. First support frame; 402. Second support frame; 403. Third support frame; 404. Fourth support frame; 5. Counterweight; 6. Pulley block; 7. Electric hoist fixing template; 8. Electric hoist; 9. Universal wheel. DETAILED DESCRIPTION

[0022] In order to make the purpose, technical solution and advantages of the embodiment of the utility model clearer, the technical solution in the embodiment of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiment of the utility model. Obviously, the described embodiment is a part of the embodiment of the utility model, not all the embodiments. Based on the embodiment of the utility model, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the utility model.

[0023] Combine the following Figure 1 to Figure 2 , describing an embodiment of the utility model.

[0024] According to the embodiments of the present utility model, Figure 1 and Figure 2 As shown, an electric hoist fixing device for ALC wall panel construction is provided, comprising: a base 1, a load-bearing frame 2, an electric hoist fixing frame 3, a support frame 4 and a universal wheel 9. A counterweight 5 is arranged on the base 1. The load-bearing frame 2 is connected to the base 1 and extends vertically upward. The electric hoist fixing frame 3 is connected to the load-bearing frame 2, and the electric hoist fixing frame 3 is suitable for fixing the electric hoist 8. The support frame 4 is connected to the top of the load-bearing frame 2, and the support frame 4 is suitable for supporting a pulley block 6. The universal wheel 9 is connected to the base 1.

[0025] By arranging the load-bearing frame 2 on the base 1 and arranging a counterweight block 5 on the base 1, the load-bearing frame 2 can be effectively fixed, and is not prone to sliding displacement, thereby preventing the support frame 4 from overturning and causing safety hazards. At the same time, universal wheels 9 are arranged on the base 1 to facilitate the turnover after the installation of the vertical panels of the ALC wall panels, thereby ensuring the continuity of the ALC wall panel construction.

[0026] Specifically, the counterweight block 5 is a concrete counterweight block 5 , and a plurality of counterweight blocks 5 are provided, which can be increased or decreased according to the counterweight required for on-site construction.

[0027] Specifically, the overall height of the load-bearing frame 2 can be adjusted according to the actual on-site construction conditions.

[0028] It should be noted that, usually, several ALC wall panels need to be installed in parallel on the wall at the construction location. Therefore, when installing the ALC wall panels on one wall, the continuity of the ALC wall panel installation construction needs to be considered. Therefore, the position of the electric hoist fixing device for the ALC wall panel construction can be quickly adjusted through the universal wheel 9 to ensure the continuity of the ALC wall panel construction, which is conducive to improving the construction quality.

[0029] It should be noted that the load-bearing frame 2, the electric hoist fixing frame 3, and the support frame 4 are all steel pipes. The required steel pipes can be selected at the construction site and connected by steel pipes with suitable strength, which improves the economy of the electric hoist fixing device for ALC wall panel construction, realizes the secondary utilization of materials on the construction site, and saves costs.

[0030] In one embodiment, Figure 2 As shown, the load-bearing frame 2 includes a first load-bearing frame 201, a second load-bearing frame 202 and a third load-bearing frame 203. A plurality of first load-bearing frames 201 are provided, and a plurality of first load-bearing frames 201 are vertically extended upward along the base 1. A plurality of second load-bearing frames 202 are provided, and a first end of a plurality of second load-bearing frames 202 is connected to the base 1, and a second end of a plurality of second load-bearing frames 202 is connected to an end of the first load-bearing frame 201 away from the base 1. Each end of the third load-bearing frame 203 is connected to an end of the first load-bearing frame 201 away from the base 1 and a second end of the second load-bearing frame 202. By providing the first load-bearing frame 201, the second load-bearing frame 202 and the third load-bearing frame 203, the overall structure of the electric hoist fixing device for ALC wall panel construction is more stable, and the construction efficiency and safety are improved.

[0031] In one embodiment, Figure 2As shown, the support frame 4 includes a first support frame 401, a second support frame 402, a third support frame 403 and a fourth support frame 404. There are several first support frames 401. The first end of the first support frame 401 is connected to the first load-bearing frame 201, and the second end of the first support frame 401 is away from the load-bearing frame 2 in the horizontal direction. The second support frame 402 is simultaneously connected to the end of the first load-bearing frame 201 away from the base 1 and the second end of the first support frame 401. The third support frame 403 is simultaneously connected to the first ends of several first support frames 401, and the fourth support frame 404 is simultaneously connected to the second ends of several first support frames 401. By providing the first support frame 401, the second support frame 402 and the third support frame 403, the connection between the support frame 4 and the load-bearing frame 2 is more stable, and the support of the pulley block 6 is more stable. When the ALC wall panel is hoisted, the safety of the construction is improved, and the potential safety hazard caused by the ALC wall panel falling is avoided.

[0032] In one embodiment, Figure 1 and Figure 2 As shown, there are several electric hoist fixing frames 3, several electric hoist fixing frames 3 are arranged between the first load-bearing frame 201 and the second load-bearing frame 202 and are arranged at intervals along the vertical direction, and / or several electric hoist fixing frames 3 are arranged between several second load-bearing frames 202 and are arranged at intervals along the extension direction of the second load-bearing frame 202.

[0033] In one embodiment, Figure 1 and Figure 2 As shown, the electric hoist fixing device for ALC wall panel construction also includes an electric hoist fixing template 7, which is bolted to a plurality of electric hoist fixing frames 3 at the same time, and the electric hoist 8 is suitable for being arranged on the electric hoist fixing template 7.

[0034] Specifically, the electric hoist 8 and the pulley block 6 are connected by a steel cable, and the height of the ALC wall panel hoisted by the pulley block 6 is adjusted by adjusting the length of the steel cable through the electric hoist 8.

[0035] Specifically, in this embodiment, the electric hoist fixing template 7 is bolted to the electric hoist fixing frame 3 arranged between several second load-bearing frames 202, so that the steel cable connected to the electric hoist 8 is on the same axis as the pulley block 6 and the ALC wall panel, thereby preventing the ALC wall panel from swinging and rotating after hoisting, which affects the installation of the vertical panels of the ALC wall panel.

[0036] It is worth noting that the height of the electric hoist fixing frame 3 only needs to satisfy the convenience of operation for construction workers, that is, the construction workers can operate the electric hoist 8 while standing on the ground. At this time, the positions of the electric hoist fixing template 7 and the electric hoist fixing frame 3 can be determined.

[0037] In one embodiment, Figure 2As shown, the base 1 includes a base frame 101 and a plate body 102 . A plurality of plate bodies 102 are provided. The plurality of plate bodies 102 are cross-arranged to form a plurality of accommodating areas on the base frame 101 . The plurality of accommodating areas accommodate the counterweights 5 .

[0038] It should be noted that in order to prevent the electric hoist fixing device for ALC wall panel construction from tipping over, the counterweight blocks 5 need to be evenly distributed according to demand, so the accommodating area is also an area evenly distributed on the base frame 101.

[0039] In one embodiment, Figure 1 and Figure 2 As shown, a plurality of universal wheels 9 are provided, and the plurality of universal wheels 9 are arranged at intervals on the bottom surface of the base 1. By arranging the universal wheels 9 on the lower surface of the base 1, the electric hoist fixing device for ALC wall panel construction can be moved and circulated, which speeds up the construction progress and improves the efficiency of erecting the ALC wall panel.

[0040] Specifically, the universal wheel 9 includes a locking function, that is, when the position of the electric hoist fixing device for ALC wall panel construction is determined, the universal wheel 9 is locked and the universal wheel 9 cannot rotate, thereby improving the stability and safety during construction. When the electric hoist fixing device for ALC wall panel construction needs to be turned around, it only needs to unlock the universal wheel 9 to push the device to the next installation position.

[0041] In one embodiment, the load-bearing frame 2 is connected to the base 1 with bolts.

[0042] In one embodiment, the load-bearing frame 2 and the electric hoist fixing frame 3 are connected by bolts.

[0043] In one embodiment, the support frame 4 is connected to the load-bearing frame 2 by bolts.

[0044] When using the electric hoist fixing device for ALC wall panel construction of the utility model, first, determine the support position, place the base 1 at the support position through the universal wheel 9 and lock the universal wheel 9; then, place the counterweight 5 on the base frame 101; then, calculate the required height of the load-bearing frame 2 according to the actual support height and install it; then, connect the top support frame 4 and the pulley block 6; then, install the electric hoist fixing frame 3 and the electric hoist fixing template 7; finally, fix the electric hoist 8 and pass the steel cable through the pulley block 6 to install the vertical plate of the ALC wall panel; after the construction is completed, disconnect the power supply of the electric hoist 8, release the lock of the universal wheel 9, push the electric hoist fixing device for ALC wall panel construction to the position of the next ALC wall panel vertical plate and repeat the above operation until the installation of the ALC wall panel vertical plate is completed, and then turn around again.

[0045] Although the embodiments of the present invention are described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.

Claims

1. An electric hoist fixing device for ALC wall panel construction, characterized in that: include: A base (1), wherein a counterweight (5) is arranged on the base (1); A load-bearing frame (2) connected to the base (1) and extending vertically upward; An electric hoist fixing frame (3) connected to the load-bearing frame (2), the electric hoist fixing frame (3) being suitable for fixing the electric hoist (8); A support frame (4) connected to the top of the load-bearing frame (2), wherein the support frame (4) is suitable for supporting a pulley block (6); A universal wheel (9) is connected to the base (1).

2. The electric hoist fixing device for ALC wall panel construction according to claim 1 is characterized in that: The load-bearing frame (2) comprises a first load-bearing frame (201), a second load-bearing frame (202) and a third load-bearing frame (203), wherein a plurality of the first load-bearing frames (201) are provided, and the plurality of the first load-bearing frames (201) are vertically extended upward along the base (1), and a plurality of the second load-bearing frames (202) are provided, and the first ends of the plurality of the second load-bearing frames (202) are connected to the base (1), and the second ends of the plurality of the second load-bearing frames (202) are connected to an end of the first load-bearing frame (201) away from the base (1), and each end of the third load-bearing frame (203) is connected to an end of the first load-bearing frame (201) away from the base (1) and to the second end of the second load-bearing frame (202).

3. The electric hoist fixing device for ALC wall panel construction according to claim 2 is characterized in that: The support frame (4) comprises a first support frame (401), a second support frame (402), a third support frame (403) and a fourth support frame (404), wherein a plurality of the first support frames (401) are provided, a first end of the first support frame (401) is connected to the first load-bearing frame (201), a second end of the first support frame (401) is away from the load-bearing frame (2) in a horizontal direction, the second support frame (402) is simultaneously connected to an end of the first load-bearing frame (201) away from the base (1) and a second end of the first support frame (401), the third support frame (403) is simultaneously connected to the first ends of a plurality of the first support frames (401), and the fourth support frame (404) is simultaneously connected to the second ends of a plurality of the first support frames (401).

4. The electric hoist fixing device for ALC wall panel construction according to claim 2 or 3, characterized in that: A plurality of the electric hoist fixing frames (3) are provided, and the plurality of the electric hoist fixing frames (3) are provided between the first load-bearing frame (201) and the second load-bearing frame (202) and are arranged at intervals along the vertical direction, and / or the plurality of the electric hoist fixing frames (3) are provided between the plurality of the second load-bearing frames (202) and are arranged at intervals along the extension direction of the second load-bearing frame (202).

5. The electric hoist fixing device for ALC wall panel construction according to claim 4 is characterized in that: The electric hoist fixing device for ALC wall panel construction also includes an electric hoist fixing template (7), the electric hoist fixing template (7) is simultaneously bolted to a plurality of the electric hoist fixing frames (3), and the electric hoist (8) is suitable for being arranged on the electric hoist fixing template (7).

6. The electric hoist fixing device for ALC wall panel construction according to any one of claims 1 to 3, characterized in that: The base (1) comprises a base frame (101) and a plate body (102), wherein a plurality of the plate bodies (102) are provided, and the plurality of the plate bodies (102) are cross-arranged to form a plurality of accommodating areas on the base frame (101), and the plurality of the accommodating areas accommodate the counterweight blocks (5).

7. The electric hoist fixing device for ALC wall panel construction according to claim 6 is characterized in that: A plurality of universal wheels (9) are provided, and the plurality of universal wheels (9) are arranged at intervals on the bottom surface of the base (1).

8. The electric hoist fixing device for ALC wall panel construction according to any one of claims 1 to 3, characterized in that: The load-bearing frame (2) is bolted to the base (1).

9. The electric hoist fixing device for ALC wall panel construction according to any one of claims 1 to 3, characterized in that: The load-bearing frame (2) and the electric hoist fixing frame (3) are connected by bolts.

10. The electric hoist fixing device for ALC wall panel construction according to any one of claims 1 to 3, characterized in that: The support frame (4) is bolted to the load-bearing frame (2).