Bridge row pile type abutment supporting structure
Through the support structure of bridge pile pile bridge, the combination of reinforced concrete and plain concrete piles is used to solve the problem of complex and high cost of traditional bridge construction methods, and achieve a convenient construction, environmental protection, and beauty effect.
Patent Information
- Application Number
- CN202420678097.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-03
- Publication Date
- 2025-01-28
- Estimated Expiration
- 2034-04-03
AI Technical Summary
The traditional bridge construction method is to excavate first and then build. The process is complicated and the cost is increased. Especially when the construction of the current roadbed is under construction, it is impossible to excavate and fill, making it difficult to carry out traditional methods.
Adopt a bridge pile -type bridge support structure, including reinforced concrete pile piles and plain concrete piles. The combination of reinforced concrete walls and crown beams forms an integrated pile bridge structure to meet the requirements of support and water -stop requirements. Simplify the construction process.
The cost of engineering has been reduced, the construction period has been shortened, the limited construction space has been adapted, the construction convenience and aesthetics have been improved, and the optimization of economy, environmental protection, and progress has been achieved.
Smart Images

Figure CN222412599U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of building engineering construction, in particular to a bridge pile-row abutment supporting structure. Background Art
[0002] In the Chinese utility model patent: the authorization announcement number CN204551242U, the utility model relates to a novel semi-rigid abutment structure, including supporting piles, abutments are arranged above the supporting piles, a supporting belt is arranged between the abutments and the supporting piles, at least one row of force transmission rods are arranged at intervals along the length direction of the abutments and the supporting piles, and the force transmission rods penetrate the supporting belts and connect the supporting piles and the abutments up and down. The utility model changes the rigid connection form of the traditional seamless bridge at the connection between the piles and the abutments. By setting force transmission rods, the connection between the abutments and the pile foundation is designed to be rotatable and hinged, which effectively avoids the problem of plastic hinges formed in the high stress area at the connection caused by cyclic loads in traditional seamless bridges, avoids large lateral displacement of the pile foundation and affects the bearing capacity of the pile foundation, and also avoids the problem of fatigue fracture of steel bars caused by incomplete hinge connection between the piles and the abutments, effectively improving the safety performance of seamless bridges.
[0003] With the increasing efforts in infrastructure construction, the construction of bridges or underground spaces has been accelerated. The implementation of many bridge projects requires both support for the existing soil and construction of abutments at corresponding locations. The traditional approach is to excavate first and then construct, which has complicated procedures and increased costs. This is especially difficult to implement for new and reconstruction projects that require the construction of bridges on the existing roadbed and cannot be done through large-scale excavation and filling. Utility Model Content
[0004] The utility model provides a bridge pile abutment support structure, aiming to solve the problem that the traditional method is to excavate first and then construct, which is complicated in process and increases in cost. In particular, it is difficult to carry out the traditional method for constructing bridges on the existing roadbed and for new construction and reconstruction projects where large excavation and large filling are not possible. The utility model is implemented as follows: the bridge pile abutment support structure includes reinforced concrete piles: the outer wall of the reinforced concrete piles has plain concrete piles, the tops of the reinforced concrete piles and the plain concrete piles are provided with crown beams, and one side of the reinforced concrete piles and the plain concrete piles is provided with a reinforced concrete retaining wall;
[0005] Wherein, a lower channel is arranged on one side of the reinforced concrete retaining wall.
[0006] Preferably, a bridge beam body is arranged on the top of the crown beam, and a backfill layer is arranged on one side of the crown beam.
[0007] Preferably, there are multiple rows of reinforced concrete piles and rows of plain concrete piles, and the multiple rows of reinforced concrete piles and rows of plain concrete piles are arranged to interlock with each other.
[0008] Compared with the prior art, the embodiments of the present application have the following beneficial effects:
[0009] 1. The design of the utility model avoids the large-scale excavation and filling required by the commonly used abutment types of bridges, has a small impact range, a short construction period, and saves engineering costs, thereby solving the problem of material waste in existing construction methods and being more environmentally friendly and energy-saving.
[0010] 2. The design of the utility model has high utilization efficiency of reinforced concrete interlocking pile components, meets the relevant requirements such as backfill and water stopping behind the support platform, and the exterior finishing surface is coordinated with the surrounding environment, meeting the aesthetic requirements.
[0011] 3. With the help of limited construction space, the use of integrated pile abutments greatly shortens the construction time, eases traffic capacity, facilitates construction, and shortens the construction period.
[0012] In summary, the utility model of a bridge pile abutment support structure at a roadbed or underground space can achieve: economically reducing the project cost, shortening the project period, environmentally conducive to aesthetic requirements, and functionally serving two purposes with one pile. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is the front view of the utility model;
[0014] Figure 2 It is a side view of the utility model;
[0015] Figure 3 It is a front view of the utility model;
[0016] Figure 4 It is the right view of the utility model.
[0017] In the figure: 1. Reinforced concrete piles; 2. Plain concrete piles; 3. Fill layer behind the platform; 4. Lower passage; 5. Reinforced concrete retaining wall; 6. Crown beam; 7. Bridge beam. DETAILED DESCRIPTION
[0018] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by technicians in the technical field of this application; the terms used in the specification of the application herein are only for the purpose of describing specific embodiments and are not intended to limit this application; the terms "including" and "having" and any variations thereof in the specification and claims of this application and the above-mentioned drawings are intended to cover non-exclusive inclusions. The terms "first", "second", etc. in the specification and claims of this application or the above-mentioned drawings are used to distinguish different objects, not to describe a specific order.
[0019] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0020] The utility model provides a bridge pile abutment support structure, such as Figure 1-4 As shown, it comprises a reinforced concrete pile row 1: the outer wall of the reinforced concrete pile row 1 has a plain concrete pile row 2, a cap beam 6 is arranged on the top of the reinforced concrete pile row 1 and the plain concrete pile row 2, and a reinforced concrete retaining wall 5 is arranged on one side of the reinforced concrete pile row 1 and the plain concrete pile row 2;
[0021] Among them, a lower channel 4 is arranged on one side of the reinforced concrete retaining wall 5 .
[0022] Preferably, a bridge beam body 7 is provided on the top of the crown beam 6 , and a backfill layer 3 is provided on one side of the crown beam 6 .
[0023] Preferably, there are multiple reinforced concrete piles 1 and plain concrete piles 2, and the multiple reinforced concrete piles 1 and plain concrete piles 2 are arranged to interlock with each other.
[0024] It should be noted that since the traditional approach is to excavate first and then construct, the process is complicated and the cost is increased. This is particularly difficult to implement for new construction and reconstruction projects where bridges are constructed on existing roadbeds and large-scale excavation and filling are not possible.
[0025] Specifically, in this embodiment, this scheme mainly sets the reinforced concrete meat-and-vegetable interlocking pile rows at the abutment position. The reinforced concrete meat-and-vegetable interlocking pile rows can be used as the supporting structure to support the backfill behind the abutment. The closely arranged meat-and-vegetable piles can also serve as a water-stop curtain. The top crown beam of the pile row also serves as a cap to support the upper bridge beam body. A reinforced concrete retaining wall is set on the outside of the pile row to ensure the beautiful exterior surface of the structure.
[0026] It should be noted that, for the above-mentioned embodiments, for the sake of simplicity, they are all described as a series of action combinations, but those skilled in the art should know that the utility model is not limited by the described action sequence, because according to the utility model, some steps may be performed in other sequences or simultaneously. Secondly, those skilled in the art should also know that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required by the utility model.
[0027] In the several embodiments provided in the present application, it should be understood that the disclosed devices can be implemented in other ways. For example, the device embodiments described above are merely schematic, such as the division of the above-mentioned units. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or communication connection shown or discussed can be through some interfaces, and the indirect coupling or communication connection between devices or units can be in the form of telecommunication or other forms.
[0028] The units described above as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0029] The above embodiments are only used to illustrate the technical solutions of the utility model, rather than to limit the protection scope of the utility model. Obviously, the described embodiments are only some embodiments of the utility model, rather than all embodiments. Based on these embodiments, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model. Although the utility model has been described in detail with reference to the above embodiments, ordinary technicians in this field can still combine, add, delete or make other adjustments to the features in the various embodiments of the utility model according to the circumstances without conflict, without making creative work, so as to obtain different other technical solutions that do not deviate from the concept of the utility model in essence, and these technical solutions also belong to the scope of protection of the utility model.
Claims
1. The bridge pile abutment support structure is characterized by: It comprises a reinforced concrete pile row (1), wherein the outer wall of the reinforced concrete pile row (1) is provided with a plain concrete pile row (2), the tops of the reinforced concrete pile row (1) and the plain concrete pile row (2) are provided with a cap beam (6), and one side of the reinforced concrete pile row (1) and the plain concrete pile row (2) is provided with a reinforced concrete retaining wall (5); Wherein, a lower channel (4) is provided on one side of the reinforced concrete retaining wall (5).
2. The bridge pile abutment support structure according to claim 1, characterized in that: A bridge beam body (7) is arranged on the top of the crown beam (6), and a backfill layer (3) is arranged on one side of the crown beam (6).
3. The bridge pile abutment support structure according to claim 1, characterized in that: The number of the reinforced concrete piles (1) and the plain concrete piles (2) is multiple, and the multiple reinforced concrete piles (1) and the plain concrete piles (2) are arranged in an interlocking manner.
Citation Information
Patent Citations
Novel semi-rigid abutment structure
CN204551242U