Water treatment machine and control valve for water treatment machine
By designing an innovative control valve, the problem of high manufacturing costs, large occupation space and high failure rate caused by multiple control valves in the existing water treatment system, and realized the multi -level treatment and improving the rinse efficiency of raw water. Effect.
Patent Information
- Application Number
- CN202420952211.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Priority Date
- 2024-03-19
- Filing Date
- 2024-05-02
- Publication Date
- 2025-01-28
- Estimated Expiration
- 2034-05-02
AI Technical Summary
Multiple control valves in existing water treatment systems lead to high manufacturing costs, large space occupancy, and high failure rate. At the same time, the filter canister cannot be flushed in reverse or forward direction alone, resulting in poor flushing effect.
Design a innovative control valve that can control the three water treatment devices in series to perform multi -level treatment when the water treatment machine is in water treatment state. Filtering materials or softening resin are scrubbed in reverse or forward.
Multi -level treatment of raw water is achieved, water quality is obtained, and water quality is obtained. At the same time, it improves the rinse efficiency, prevent sewage pollution from other water treatment devices, and reduce the system's failure rate and maintenance costs.
Smart Images

Figure CN222416150U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a water treatment machine, in particular to a water treatment machine capable of performing multi-stage treatment on raw water (eg, tap water) to obtain treated water with expected water quality. The utility model further relates to a control valve for the water treatment machine. Background Art
[0002] In modern industrial production, many industries require water with high cleanliness or low hardness. However, the cleanliness and hardness of many water sources, whether surface water or groundwater, do not meet the standards for industrial water. In order to obtain water with the expected water quality, the water from the water source (or raw water) needs to be treated. To treat raw water, generally, the raw water from the water source is first coarsely filtered to filter out larger particulate pollutants to obtain coarsely filtered water, and then the coarsely filtered water is further filtered using materials such as activated carbon to obtain cleaner purified water. Finally, the purified water is softened (or ultrafiltration or RO membrane filtration) to obtain softened water (or purified water with extremely high purity). Finally, the raw water undergoes multi-stage treatment (three or more stages of treatment) to obtain treated water with the expected water quality. For example, raw water is filtered and then ultrafiltered using water filtration equipment (using filter media such as quartz sand, activated carbon, or PP cotton) and ultrafiltration equipment (typically using ultrafiltration membrane fibers). Alternatively, raw water is filtered, ultrafiltered, and then treated with RO membranes using water filtration equipment, ultrafiltration equipment, and RO membrane purification equipment. Alternatively, raw water is coarsely filtered, filtered, and then softened using a prefilter, water filtration equipment, and a water softener. Furthermore, with the increasing improvement of living standards and a growing emphasis on health, people's demands for the quality of their domestic water are becoming increasingly stringent. Waterworks' extensive treatment of water received from the source is insufficient to remove all impurities, such as particulate contaminants (flocculated gels, silt, and even bacteria), which is increasingly insufficient to meet people's needs. Furthermore, the aging of the tap water supply network can introduce new contamination into tap water. Therefore, to further purify tap water and improve its cleanliness, a variety of water treatment methods are required.
[0003] However, most of the existing water treatment systems or water treatment equipment that can perform multi-stage treatment on raw water include multiple water treatment devices and multiple control valves that control the flow of water inside the corresponding water treatment devices. Because each water treatment device has a corresponding control valve, each control valve controls the water treatment function and flushing function of the corresponding water treatment device. Therefore, multiple control valves are connected in series. The multiple control valves of the water treatment system lead to high manufacturing costs and large space occupation. At the same time, since the control valve is a relatively complex device, the multiple control valves cause the failure rate of the entire water treatment system to be high. The utility model patent with application number CN202022865712.3 discloses a water treatment system having three filter material tanks connected in series, and controlling the flow direction of water and performing three-stage treatment on water by a single control valve, which solves the problem of too many control valves in the water treatment system. However, the structure of the water treatment system disclosed by the utility model patent is very simple. Although it can use three filter material tanks connected in series to perform multi-stage treatment on raw water, it cannot perform reverse flushing or forward flushing on the filter material tanks separately and individually. The structure of the water treatment system disclosed in this utility model patent means that when the three filter canisters connected in series are forward-flushed, the sewage generated by forward-flushing the first filter canister will flow into the second filter canister, and the sewage generated by forward-flushing the second filter canister will flow into the third filter canister. When the three filter canisters connected in series are reverse-flushed, the sewage generated by reverse-flushing the third filter canister will flow into the second filter canister, and the sewage generated by reverse-flushing the second filter canister will flow into the first filter canister. In other words, when the three filter canisters connected in series are forward-flushed, only the first filter canister may be cleaned, while the second and third filter canisters may not only not be cleaned, but may be further contaminated; and when the three filter canisters connected in series are reverse-flushed, only the third filter canister may be cleaned, while the second and first filter canisters may not only not be cleaned, but may be further contaminated. In particular, considering the effect of the three filter canisters connected in series in the water treatment system on the cascade reduction of the raw water pressure, the cleaning effect of forward-flushing and reverse-flushing the three filter canisters connected in series may be worse. In other words, the functional deficiencies of existing water treatment systems present a certain inconvenience to users. Finally, generally speaking, the control valve of a water treatment system utilizes a traditional dual-valve disc structure, requiring at least one diversion blind hole in the moving valve disc to provide treated water and redirect the water flow. However, as the water flows through the diversion blind hole, its direction changes 360 degrees, resulting in significant resistance and kinetic energy loss, significantly reducing the flow rate. Utility Model Content
[0004] The main advantage of the present invention is to provide a water treatment machine, wherein the control valve of the water treatment machine of the present invention has an innovative design so that when the water treatment machine of the present invention is in the water treatment state, it can control the three water treatment devices of the water treatment machine of the present invention to be connected in series, so as to perform multi-stage treatment on the raw water and obtain treated water of the expected water quality; and when the water treatment machine of the present invention is in the flushing state, it can control the raw water to separately and individually perform reverse or forward flushing on the filter material or softening resin of the corresponding water treatment device, and control the sewage generated by the reverse flushing or forward flushing to flow out separately, so as to prevent the sewage from contaminating other water treatment devices. Accordingly, the water treatment machine of the present invention and the control valve for the water treatment machine both have a brand-new and unique spatial structure, which is a unique innovative design in the world, thereby creatively solving the difficult problem of using a single control valve to separately and individually perform reverse or forward flushing on three water treatment devices used in series.
[0005] Another advantage of the present invention is that it provides a control valve for a water treatment machine, wherein the control valve for a water treatment machine of the present invention is configured to control the three water treatment devices of the water treatment machine of the present invention to be connected in series, so that raw water flows through the three water treatment devices of the water treatment machine of the present invention in sequence and the raw water is subjected to multi-stage treatment; and controls the raw water to reversely or forwardly flush the filter material or softening resin of the corresponding water treatment device, and controls the sewage generated by the reverse flushing or forward flushing to flow out separately, so as to prevent the sewage from contaminating other water treatment devices.
[0006] Another advantage of the present invention is that it provides a control valve for a water treatment machine, wherein the control valve for a water treatment machine of the present invention is configured to control the regeneration solution to regenerate the softening resin in the third water treatment device of the water treatment machine of the present invention (if the third water treatment device is a water softening device), and when controlling the regeneration solution to regenerate the softening resin in the third water treatment device of the water treatment machine of the present invention, it does not affect the other two water treatment devices of the water treatment machine of the present invention.
[0007] Other purposes and features of the present invention are fully reflected in the following detailed description.
[0008] According to one aspect of the present invention, a control valve for a water treatment machine of the present invention that can achieve the aforementioned objects and other objects and advantages includes:
[0009] a drive element;
[0010] an ejector;
[0011] a valve body; and
[0012] A valve core, wherein the valve body forms a valve cavity, a first opening, a second opening, a third opening, a fourth opening, a fifth opening, a first fluid opening, a second fluid opening, a sewage opening and a first jet opening, wherein the valve core is arranged in the valve cavity, wherein the second fluid opening of the valve body is suitable for being connected to a raw water source, wherein the ejector has an ejection port suitable for being connected to the first jet opening and a salt absorption port being connected to the ejection port, wherein the control valve for the water treatment machine is a plane valve, the valve core further includes a first fixed valve disc, a movable valve disc and a second fixed valve disc, the driving element is arranged to drive the movable valve disc of the plane valve to rotate relative to the first fixed valve disc and the second fixed valve disc, wherein the first fixed valve disc has a first fluid control surface, the movable valve disc has a second fluid control surface and a third fluid control surface, the second fixed valve disc has a fourth fluid control surface. body control surface, wherein the first fixed valve plate, the movable valve plate and the second fixed valve plate of the valve core are all arranged in the valve cavity, wherein the second fluid control surface and the third fluid control surface of the movable valve plate are respectively formed on opposite sides of the movable valve plate, wherein the second fluid control surface of the movable valve plate is arranged on the first fluid control surface of the first fixed valve plate, and the fourth fluid control surface of the second fixed valve plate is arranged on the third fluid control surface of the movable valve plate, and the movable valve plate is arranged to be able to rotate relative to the first fixed valve plate and the second fixed valve plate, wherein when the movable valve plate rotates relative to the first fixed valve plate and the second fixed valve plate, so that the plane valve is in a water treatment working position, the valve core of the plane valve forms a first water treatment flow channel respectively connected to the second fluid opening and the first opening, a second water treatment flow channel respectively connected to the third opening and the fourth opening, and a third water treatment flow channel respectively connected to the fifth opening and the first fluid opening.
[0013] According to another aspect of the present invention, the present invention further provides a water treatment machine, comprising:
[0014] a control valve;
[0015] a first water treatment unit;
[0016] a second water treatment unit; and
[0017] A third water treatment device, wherein the control valve for the water treatment machine includes a drive element, an ejector, a valve body and a valve core, wherein the valve body forms a valve cavity, a first opening, a second opening, a third opening, a fourth opening, a fifth opening, a first fluid opening, a second fluid opening, a sewage opening and a first ejection opening, the first water treatment device has a first water inlet and a first water outlet, the second water treatment device has a second water inlet and a second water outlet, the third water treatment device has a third water inlet and a third water outlet, wherein the valve core is arranged in the valve cavity, wherein the valve body The first opening is suitable for being connected to the first water inlet of the first water treatment device, the second opening is suitable for being connected to the first water outlet of the first water treatment device and the second water inlet of the second water treatment device respectively, the third opening is suitable for being connected to the second water outlet of the second water treatment device, the fourth opening is suitable for being connected to the third water inlet of the third water treatment device, the fifth opening is suitable for being connected to the third water outlet of the third water treatment device, the second fluid opening of the valve body is suitable for being connected to the raw water source, the ejector has an ejection port suitable for being connected to the first ejection opening and a salt absorption port connected to the ejection port, wherein the ejector for water treatment machine The control valve is a plane valve, and the valve core further includes a first fixed valve disc, a movable valve disc and a second fixed valve disc, and the driving element is configured to drive the movable valve disc of the plane valve to rotate relative to the first fixed valve disc and the second fixed valve disc, wherein the first fixed valve disc has a first fluid control surface, the movable valve disc has a second fluid control surface and a third fluid control surface, and the second fixed valve disc has a fourth fluid control surface, wherein the first fixed valve disc, the movable valve disc and the second fixed valve disc of the valve core are all arranged in the valve cavity, wherein the second fluid control surface and the third fluid control surface of the movable valve disc are respectively formed on opposite sides of the movable valve disc, wherein the second fluid control surface of the movable valve disc The body control surface is arranged on the first fluid control surface of the first fixed valve plate, the fourth fluid control surface of the second fixed valve plate is arranged on the third fluid control surface of the movable valve plate, and the movable valve plate is arranged to be able to rotate relative to the first fixed valve plate and the second fixed valve plate, wherein when the movable valve plate rotates relative to the first fixed valve plate and the second fixed valve plate, so that the planar valve is in a water treatment working position, the valve core of the planar valve forms a first water treatment flow channel respectively connected to the second fluid opening and the first opening, a second water treatment flow channel respectively connected to the third opening and the fourth opening, and a third water treatment flow channel respectively connected to the fifth opening and the first fluid opening.
[0018] These and other purposes, features and advantages of the present invention are fully reflected by the following detailed description and accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a front view of the water treatment machine according to the first embodiment of the utility model.
[0020] Figure 2 This is an assembly diagram of the water treatment machine according to the first embodiment of the present utility model.
[0021] Figure 3A It is a cross-sectional view of the first water treatment device of the water treatment machine according to the first and second embodiments of the utility model, which shows the direction of water flow from the first water inlet to the first water outlet when the first water treatment device is used for water treatment or forward flushing.
[0022] Figure 3B It is a cross-sectional view of the first water treatment device of the water treatment machine according to the first embodiment and the second embodiment of the utility model, which shows the water flow direction from the first water outlet to the first water inlet when the first water treatment device is reversely flushed.
[0023] Figure 3C It is a cross-sectional view of the second water treatment device of the water treatment machine according to the first and second embodiments of the utility model, which shows the flow direction of water from the second water inlet to the second water outlet when the second water treatment device is used for water treatment or forward flushing.
[0024] Figure 3D It is a cross-sectional view of the second water treatment device of the water treatment machine according to the first embodiment and the second embodiment of the present invention, which shows the direction of water flow from the second water outlet to the second water inlet when the second water treatment device is reversely flushed.
[0025] Figure 3E It is a cross-sectional view of the third water treatment device of the water treatment machine according to the first and second embodiments of the utility model, which shows the direction of water flow from the third water inlet to the third water outlet when the third water treatment device is used for water treatment, forward flushing, or as a softening filter element for downstream salt absorption and regeneration.
[0026] Figure 3F It is a cross-sectional view of the third water treatment device of the water treatment machine according to the first and second embodiments of the utility model, which shows the direction of water flow from the third water outlet to the third water inlet when the third water treatment device is reversely flushed or used as a softening filter element for countercurrent salt absorption regeneration.
[0027] Figure 3G It is a cross-sectional view of the water treatment machine according to the first embodiment of the present invention.
[0028] Figure 4 It is a three-dimensional view of the control valve of the water treatment machine according to the first embodiment of the present invention.
[0029] Figure 5 1 is an assembly diagram of the control valve of the water treatment machine according to the first embodiment of the present invention.
[0030] Figure 6A It is a three-dimensional view of the first valve body portion of the valve body of the control valve of the water treatment machine according to the first embodiment of the utility model, wherein the view shows the valve cavity of the valve body, the first opening, the second opening and the third opening of the first valve body portion.
[0031] Figure 6B This is another stereoscopic view of the first valve body portion of the control valve of the water treatment machine according to the first embodiment of the present invention, wherein the view shows the valve cavity of the valve body, the first opening, the second opening, the third opening, the first jet opening and the second jet opening of the first valve body portion.
[0032] Figure 6C It is another three-dimensional view of the first valve body of the control valve of the water treatment machine according to the first embodiment of the present utility model.
[0033] Figure 6D This is another stereoscopic view of the first valve body portion of the control valve of the water treatment machine according to the first embodiment of the present invention, wherein the view shows the first opening, the second opening, the third opening, the fourth opening, the fifth opening, the first jet opening and the second jet opening of the first valve body portion.
[0034] Figure 6E This is a cross-sectional view of the first valve body portion of the control valve of the water treatment machine according to the first embodiment of the utility model. The control valve is a planar valve, wherein the figure shows that the first channel of the planar valve is connected to the first opening, the second channel is connected to the second opening, the third channel is connected to the third opening, the twelfth channel is connected to the first jet opening, and the thirteenth channel is connected to the second jet opening.
[0035] Figure 6F It is a cross-sectional view of the first valve body and the ejector of the planar valve of the water treatment machine according to the first embodiment of the present utility model.
[0036] Figure 6GThis is another cross-sectional view of the first valve body of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the figure shows that the fourth channel and the eleventh channel of the planar valve are respectively connected to the fourth opening.
[0037] Figure 6H This is another cross-sectional view of the first valve body of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the figure shows that the fifth channel and the fourteenth channel of the planar valve are respectively connected to the fifth opening.
[0038] Figure 6I This is another cross-sectional view of the first valve body of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the figure shows that the fifteenth channel of the planar valve is connected to the fifth opening.
[0039] Figure 6J This is a three-dimensional view of the second valve body portion of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the view shows the first fluid opening and the sewage opening of the second valve body portion, and the second fluid opening is arranged in the second valve body portion of the valve body.
[0040] Figure 6K This is another stereoscopic view of the second valve body portion of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the view shows the sewage opening of the second valve body portion, and the second fluid opening is arranged on the second valve body portion of the valve body.
[0041] Figure 6L It is another three-dimensional view of the second valve body of the planar valve of the water treatment machine according to the first embodiment of the present utility model.
[0042] Figure 6M This is a cross-sectional view of the second valve body portion of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the figure shows that the second fluid opening is connected to the valve cavity.
[0043] Figure 6N This is another cross-sectional view of the second valve body portion of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the figure shows that the sixth channel of the planar valve is connected to the first fluid opening, the second fluid opening is connected to the valve cavity, and the tenth channel is connected to the sewage opening.
[0044] Figure 6O It is a three-dimensional view of the first valve body portion and the first fixed valve plate of the valve body of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the first fixed valve plate is arranged in the valve cavity of the planar valve.
[0045] Figure 6PIt is a three-dimensional view of the first valve body portion, the first fixed valve plate and the movable valve plate of the valve body of the planar valve of the water treatment machine according to the first embodiment of the utility model, wherein the movable valve plate is arranged in the valve cavity of the planar valve.
[0046] Figure 6Q It is a three-dimensional view of the second valve body portion and the second fixed valve plate of the valve body of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the second fixed valve plate is arranged in the valve cavity of the planar valve.
[0047] Figure 6R 1 is a cross-sectional view of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the figure shows that the tenth channel of the planar valve is connected to the sewage discharge opening.
[0048] Figure 6S It is a cross-sectional view of the valve body of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the figure shows that the valve body includes the first valve body portion and the second valve body portion.
[0049] Figure 6T This is another cross-sectional view of the valve body of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the figure shows that the valve body includes the first valve body portion and the second valve body portion.
[0050] Figure 6U This is another cross-sectional view of the valve body of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the figure shows that the valve body includes the first valve body portion and the second valve body portion.
[0051] Figure 7A It is a three-dimensional view of the first fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model.
[0052] Figure 7B It is a three-dimensional view of the movable valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model.
[0053] Figure 7C It is a three-dimensional view of the second fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model.
[0054] Figure 7D It is a top view of the first fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model.
[0055] Figure 7E It is another three-dimensional view of the first fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model.
[0056] Figure 7FIt is a top view of the movable valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model.
[0057] Figure 7G It is a bottom view of the movable valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model.
[0058] Figure 7H It is a top view of the second fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model.
[0059] Figure 7I It is another three-dimensional view of the second fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model.
[0060] Figure 8A It is a structural schematic diagram of the first fixed valve plate of the plane valve of the water treatment machine according to the first embodiment of the utility model.
[0061] Figure 8B 1 is a structural diagram of the movable valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the dotted lines in the figure indicate the conducting blind hole and the seventh channel of the movable valve plate.
[0062] Figure 8C It is a structural schematic diagram of the second fixed valve plate of the plane valve of the water treatment machine according to the first embodiment of the utility model.
[0063] Figure 9A It is a schematic diagram of the equal division of the first fluid control surface of the first fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the utility model, wherein the figure shows the specific equal division positions of the first fluid control surface of the first fixed valve plate at which the various channels are arranged.
[0064] Figure 9B It is a schematic diagram of the second fluid control surface of the movable valve plate of the planar valve of the water treatment machine according to the first embodiment of the utility model, wherein the figure shows the specific equally divided positions of the various channels on the second fluid control surface of the movable valve plate.
[0065] Figure 9C This is a schematic diagram of an equal division of the third fluid control surface of the movable valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the figure shows the specific equal division positions of the various channels arranged on the third fluid control surface of the movable valve plate.
[0066] Figure 9D It is a schematic diagram of the equal division of the fourth fluid control surface of the second fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the figure shows the specific equal division positions of the various channels arranged on the fourth fluid control surface of the second fixed valve plate.
[0067] Figure 10A This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the utility model when the planar valve is in its water treatment working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0068] Figure 10B This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model when it is in its water treatment working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0069] Figure 10C This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model when the planar valve is in its first backwash working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0070] Figure 10D This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model when the planar valve is in its first backwash working position, wherein the oblique line shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0071] Figure 10E This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the utility model when the planar valve is in its second backwash working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0072] Figure 10F This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model when the planar valve is in its second backwash working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0073] Figure 10G This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the utility model when the planar valve is in its third backwash working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0074] Figure 10H This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model when the planar valve is in its third backwash working position, wherein the oblique line shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0075] Figure 10I This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the utility model when the planar valve is in its first positive flushing working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0076] Figure 10J This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the above-mentioned utility model when the planar valve is in its first positive flushing working position, wherein the oblique line shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0077] Figure 10K This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the utility model when the planar valve is in its second positive flushing working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0078] Figure 10L This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model when the planar valve is in its second positive flushing working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0079] Figure 10M This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the utility model when the planar valve is in its third positive flushing working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0080] Figure 10N This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the above-mentioned utility model when the planar valve is in its third positive flushing working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0081] Figure 10O This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the utility model when the planar valve is in its regeneration working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0082] Figure 10P This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the present utility model when the planar valve is in its regeneration working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0083] Figure 10Q This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the first embodiment of the utility model when the planar valve is in its water replenishing working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0084] Figure 10R This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the plane valve of the water treatment machine according to the first embodiment of the present utility model when the plane valve is in its water replenishing working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the plane valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the plane valve and the channel of the second fixed valve plate are not connected.
[0085] Figure 11AThis is a cross-sectional view of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the planar valve shown in the figure is in the water treatment working position.
[0086] Figure 11B This is another cross-sectional view of the planar valve of the water treatment machine according to the first embodiment of the present invention, wherein the planar valve shown in this figure is in the water treatment working position.
[0087] Figure 12 This is another cross-sectional view of the planar valve of the water treatment machine according to the first embodiment of the present invention, wherein the planar valve shown in this figure is in the first backwashing working position.
[0088] Figure 13 This is another cross-sectional view of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the planar valve shown in this figure is in the second backwashing working position.
[0089] Figure 14 This is another cross-sectional view of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the planar valve shown in this figure is in the third backwashing working position.
[0090] Figure 15 This is another cross-sectional view of the planar valve of the water treatment machine according to the first embodiment of the present invention, wherein the planar valve shown in this figure is in the first positive flushing working position.
[0091] Figure 16 This is another cross-sectional view of the planar valve of the water treatment machine according to the first embodiment of the present invention, wherein the planar valve shown in this figure is in the second positive flushing working position.
[0092] Figure 17 This is another cross-sectional view of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the planar valve shown in the figure is in the third positive flushing working position.
[0093] Figure 18A This is a cross-sectional view of the planar valve of the water treatment machine according to the first embodiment of the present invention, wherein the planar valve shown in the figure is in the regeneration working position.
[0094] Figure 18B This is another cross-sectional view of the planar valve of the water treatment machine according to the first embodiment of the present invention, wherein the planar valve shown in this figure is in the regeneration working position.
[0095] Figure 19 This is another cross-sectional view of the planar valve of the water treatment machine according to the first embodiment of the present utility model, wherein the planar valve shown in the figure is in the water replenishing working position.
[0096] Figure 20AThis is a structural diagram of a water treatment machine according to the first embodiment of the utility model, wherein the plane valve of the water treatment machine shown in the figure is in the water treatment working position, the water treatment machine is controlled to be in its water treatment working state, and the arrow in the figure points to the direction of water flow.
[0097] Figure 20B This is another structural schematic diagram of the water treatment machine according to the first embodiment of the utility model, wherein the plane valve of the water treatment machine shown in the figure is in the first backwash working position, the water treatment machine is controlled to be in its first backwash working state, and the arrow in the figure points to the direction of water flow.
[0098] Figure 20C This is another structural schematic diagram of the water treatment machine according to the first embodiment of the utility model, wherein the plane valve of the water treatment machine shown in the figure is in the second backwash working position, the water treatment machine is controlled to be in its second backwash working state, and the arrow in the figure points to the direction of water flow.
[0099] Figure 20D This is another structural schematic diagram of the water treatment machine according to the first embodiment of the utility model, wherein the plane valve of the water treatment machine shown in the figure is in the third backwash working position, the water treatment machine is controlled to be in its third backwash working state, and the arrow in the figure points to the direction of water flow.
[0100] Figure 20E This is another structural schematic diagram of the water treatment machine according to the first embodiment of the utility model, wherein the plane valve of the water treatment machine shown in the figure is in the first positive flushing working position, the water treatment machine is controlled to be in its first positive flushing working state, and the arrow in the figure points to the direction of water flow.
[0101] Figure 20F This is another structural schematic diagram of the water treatment machine according to the first embodiment of the utility model, wherein the plane valve of the water treatment machine shown in the figure is in the second positive flushing working position, the water treatment machine is controlled to be in its second positive flushing working state, and the arrow in the figure points to the direction of water flow.
[0102] Figure 20G This is another structural schematic diagram of the water treatment machine according to the first embodiment of the utility model, wherein the plane valve of the water treatment machine shown in the figure is in the third positive flushing working position, the water treatment machine is controlled to be in its third positive flushing working state, and the arrow in the figure points to the direction of water flow.
[0103] Figure 20H This is another structural schematic diagram of the water treatment machine according to the first embodiment of the utility model, wherein the plane valve of the water treatment machine shown in the figure is in the regeneration working position, the water treatment machine is controlled to be in its regeneration working state, and the arrow in the figure points to the direction of water flow.
[0104] Figure 20I This is another structural schematic diagram of the water treatment machine according to the first embodiment of the utility model, wherein the plane valve of the water treatment machine shown in the figure is in the water replenishment working position, the water treatment machine is controlled to be in its water replenishment working state, and the arrow in the figure points to the direction of water flow.
[0105] Figure 21A This is a three-dimensional diagram of an optional implementation of the control valve of the water treatment machine according to the first embodiment of the utility model, wherein the diagram shows that the second fluid opening is arranged on the first valve body portion of the valve body.
[0106] Figure 21B 1 is a cross-sectional view of the optional implementation of the control valve of the water treatment machine according to the first embodiment of the present utility model, wherein the figure shows that the second fluid opening is provided in the first valve body portion of the valve body.
[0107] Figure 22 It is a front view of the water treatment machine according to the second embodiment of the above-mentioned utility model.
[0108] Figure 23 This is an assembly diagram of a water treatment machine according to the second embodiment of the present invention.
[0109] Figure 24 It is a cross-sectional view of the water treatment machine according to the second embodiment of the present invention.
[0110] Figure 25 It is a perspective view of a control valve of a water treatment machine according to the second embodiment of the present invention.
[0111] Figure 26 1 is an assembly diagram of the control valve of the water treatment machine according to the second embodiment of the present invention.
[0112] Figure 27A It is a three-dimensional view of the first valve body portion of the valve body of the control valve of the water treatment machine according to the second embodiment of the present utility model, wherein the view shows the valve cavity of the valve body, the first opening, the second opening and the third opening of the first valve body portion.
[0113] Figure 27B This is another stereoscopic view of the first valve body portion of the control valve of the water treatment machine according to the second embodiment of the present invention, wherein the view shows the valve cavity of the valve body, the first opening, the second opening, the third opening, the first jet opening and the second jet opening of the first valve body portion.
[0114] Figure 27C It is another three-dimensional view of the first valve body of the control valve of the water treatment machine according to the second embodiment of the present invention.
[0115] Figure 27DThis is another stereoscopic view of the first valve body portion of the control valve of the water treatment machine according to the second embodiment of the present invention, wherein the view shows the first opening, the second opening, the third opening, the fourth opening, the fifth opening, the first jet opening and the second jet opening of the first valve body portion.
[0116] Figure 27E This is a cross-sectional view of the first valve body portion of the control valve of the water treatment machine according to the second embodiment of the utility model. The control valve is a planar valve, wherein the figure shows that the first channel of the planar valve is connected to the first opening, the second channel is connected to the second opening, the third channel is connected to the third opening, the twelfth channel is connected to the first jet opening, and the thirteenth channel is connected to the second jet opening.
[0117] Figure 27F It is a cross-sectional view of the first valve body and the ejector of the planar valve of the water treatment machine according to the second embodiment of the present invention.
[0118] Figure 27G This is another cross-sectional view of the first valve body of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the figure shows that the fourth channel of the planar valve is connected to the fourth opening.
[0119] Figure 27H This is another cross-sectional view of the first valve body of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the figure shows that the fifth channel of the planar valve is connected to the fifth opening.
[0120] Figure 27I This is another cross-sectional view of the first valve body of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the figure shows that the eleventh channel of the planar valve is connected to the fourth opening.
[0121] Figure 27J This is a three-dimensional view of the second valve body portion of the planar valve of the water treatment machine according to the second embodiment of the present utility model, wherein the view shows the first fluid opening and the sewage opening of the second valve body portion, and the second fluid opening is arranged in the second valve body portion of the valve body.
[0122] Figure 27K This is another stereoscopic view of the second valve body portion of the planar valve of the water treatment machine according to the second embodiment of the present utility model, wherein the view shows the sewage opening of the second valve body portion, and the second fluid opening is arranged on the second valve body portion of the valve body.
[0123] Figure 27L It is another three-dimensional view of the second valve body of the planar valve of the water treatment machine according to the second embodiment of the present invention.
[0124] Figure 27M 1 is a cross-sectional view of the second valve body of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the figure shows that the second fluid opening is connected to the valve cavity.
[0125] Figure 27N This is another cross-sectional view of the second valve body portion of the planar valve of the water treatment machine according to the second embodiment of the present utility model, wherein the figure shows that the sixth channel of the planar valve is connected to the first fluid opening, the second fluid opening is connected to the valve cavity, and the tenth channel is connected to the sewage opening.
[0126] Figure 27O It is a three-dimensional view of the first valve body portion and the first fixed valve plate of the valve body of the planar valve of the water treatment machine according to the second embodiment of the present utility model, wherein the first fixed valve plate is arranged in the valve cavity of the planar valve.
[0127] Figure 27P It is a three-dimensional view of the first valve body portion, the first fixed valve plate and the movable valve plate of the valve body of the planar valve of the water treatment machine according to the second embodiment of the present utility model, wherein the movable valve plate is arranged in the valve cavity of the planar valve.
[0128] Figure 27Q It is a three-dimensional view of the second valve body portion and the second fixed valve plate of the valve body of the planar valve of the water treatment machine according to the second embodiment of the present utility model, wherein the second fixed valve plate is arranged in the valve cavity of the planar valve.
[0129] Figure 27R 1 is a cross-sectional view of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the figure shows that the tenth channel of the planar valve is connected to the sewage discharge opening.
[0130] Figure 27S It is a cross-sectional view of the valve body of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the figure shows that the valve body includes the first valve body portion and the second valve body portion.
[0131] Figure 27T This is another cross-sectional view of the valve body of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the figure shows that the valve body includes the first valve body portion and the second valve body portion.
[0132] Figure 27U This is another cross-sectional view of the valve body of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the figure shows that the valve body includes the first valve body portion and the second valve body portion.
[0133] Figure 28AIt is a three-dimensional view of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model.
[0134] Figure 28B It is a three-dimensional view of the movable valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model.
[0135] Figure 28C It is a three-dimensional view of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model.
[0136] Figure 28D It is a top view of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model.
[0137] Figure 28E It is another three-dimensional view of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model.
[0138] Figure 28F It is a top view of the movable valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model.
[0139] Figure 28G It is a bottom view of the movable valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model.
[0140] Figure 28H It is a top view of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model.
[0141] Figure 28I It is another three-dimensional view of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model.
[0142] Figure 29A It is a structural schematic diagram of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model.
[0143] Figure 29B 1 is a structural diagram of the movable valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model, wherein the dotted lines in the figure indicate the conducting blind hole and the seventh channel of the movable valve plate.
[0144] Figure 29C 1 is a structural diagram of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model.
[0145] Figure 30AIt is a schematic diagram of the equal division of the first fluid control surface of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the utility model, wherein the figure shows the specific equal division positions of the first fluid control surface of the first fixed valve plate at which the various channels are arranged.
[0146] Figure 30B This is a schematic diagram of an equal division of the second fluid control surface of the movable valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model, wherein the figure shows the specific equal division positions of the respective channels arranged on the second fluid control surface of the movable valve plate.
[0147] Figure 30C This is a schematic diagram of an equal division of the third fluid control surface of the movable valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model, wherein the figure shows the specific equal division positions of the various channels arranged on the third fluid control surface of the movable valve plate.
[0148] Figure 30D It is a schematic diagram of the equal division of the fourth fluid control surface of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model, wherein the figure shows the specific equal division positions of the various channels arranged on the fourth fluid control surface of the second fixed valve plate.
[0149] Figure 31A This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the utility model when the planar valve is in its water treatment working position, wherein the oblique line shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0150] Figure 31B This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model when it is in its water treatment working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0151] Figure 31C This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model when the planar valve is in its first backwash working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0152] Figure 31DThis is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model when the planar valve is in its first backwash working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0153] Figure 31E This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model when the planar valve is in its second backwash working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0154] Figure 31F This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model when the planar valve is in its second backwash working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0155] Figure 31G This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the utility model when the planar valve is in its third backwash working position, wherein the oblique line shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0156] Figure 31H This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model when the planar valve is in its third backwash working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0157] Figure 31I This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the utility model when the planar valve is in its first positive flushing working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0158] Figure 31JThis is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model when the planar valve is in its first positive flushing working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0159] Figure 31K This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model when the planar valve is in its second positive flushing working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0160] Figure 31L This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model when the planar valve is in its second positive flushing working position, wherein the oblique line shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0161] Figure 31M This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the utility model when the planar valve is in its third positive flushing working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0162] Figure 31N This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model when the planar valve is in its third positive flushing working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0163] Figure 31O This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model when the planar valve is in its regeneration working position, wherein the oblique shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0164] Figure 31PThis is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model when the planar valve is in its regeneration working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0165] Figure 31Q This is a schematic diagram of the communication between the channel of the movable valve plate and the channel of the first fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the utility model when the planar valve is in its water replenishing working position, wherein the oblique line shaded portion in the figure shows the mutually communicating channels between the movable valve plate and the first fixed valve plate of the planar valve.
[0166] Figure 31R This is a schematic diagram of the connection between the channel of the movable valve plate and the channel of the second fixed valve plate of the planar valve of the water treatment machine according to the second embodiment of the present utility model when the planar valve is in its water replenishing working position, wherein the oblique shaded portion in the figure shows the mutually connected channels of the movable valve plate and the second fixed valve plate of the planar valve, and the grid shaded portion in the figure shows that the channel of the movable valve plate of the planar valve and the channel of the second fixed valve plate are not connected.
[0167] Figure 32A This is a cross-sectional view of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the planar valve shown in the figure is in the water treatment working position.
[0168] Figure 32B This is another cross-sectional view of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the planar valve shown in this figure is in the water treatment working position.
[0169] Figure 33 This is another cross-sectional view of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the planar valve shown in this figure is in the first backwashing working position.
[0170] Figure 34 This is another cross-sectional view of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the planar valve shown in this figure is in the second backwashing working position.
[0171] Figure 35 This is another cross-sectional view of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the planar valve shown in this figure is in the third backwashing working position.
[0172] Figure 36This is another cross-sectional view of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the planar valve shown in this figure is in the first positive flushing working position.
[0173] Figure 37 This is another cross-sectional view of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the planar valve shown in this figure is in the second positive flushing working position.
[0174] Figure 38 This is another cross-sectional view of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the planar valve shown in this figure is in the third positive flushing working position.
[0175] Figure 39A This is a cross-sectional view of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the planar valve shown in the figure is in the regeneration working position.
[0176] Figure 39B This is another cross-sectional view of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the planar valve shown in this figure is in the regeneration working position.
[0177] Figure 40 This is another cross-sectional view of the planar valve of the water treatment machine according to the second embodiment of the present invention, wherein the planar valve shown in the figure is in the water replenishing working position.
[0178] Figure 41A This is a structural diagram of a water treatment machine according to the second embodiment of the present invention, wherein the plane valve of the water treatment machine shown in the figure is in the water treatment working position, the water treatment machine is controlled to be in its water treatment working state, and the arrow in the figure points to the direction of water flow.
[0179] Figure 41B This is another structural schematic diagram of the water treatment machine according to the second embodiment of the above-mentioned utility model, wherein the plane valve of the water treatment machine shown in the figure is in the first backwash working position, the water treatment machine is controlled to be in its first backwash working state, and the arrow in the figure points to the direction of water flow.
[0180] Figure 41C This is another structural schematic diagram of the water treatment machine according to the second embodiment of the above-mentioned utility model, wherein the plane valve of the water treatment machine shown in the figure is in the second backwash working position, the water treatment machine is controlled to be in its second backwash working state, and the arrow in the figure points to the direction of water flow.
[0181] Figure 41DThis is another structural schematic diagram of the water treatment machine according to the second embodiment of the above-mentioned utility model, wherein the plane valve of the water treatment machine shown in the figure is in the third backwash working position, and the water treatment machine is controlled to be in its third backwash working state. The arrow in the figure points to the direction of water flow.
[0182] Figure 41E This is another structural schematic diagram of the water treatment machine according to the second embodiment of the above-mentioned utility model, wherein the plane valve of the water treatment machine shown in the figure is in the first positive flushing working position, the water treatment machine is controlled to be in its first positive flushing working state, and the arrow in the figure points to the direction of water flow.
[0183] Figure 41F This is another structural schematic diagram of the water treatment machine according to the second embodiment of the above-mentioned utility model, wherein the plane valve of the water treatment machine shown in the figure is in the second positive flushing working position, the water treatment machine is controlled to be in its second positive flushing working state, and the arrow in the figure points to the direction of water flow.
[0184] Figure 41G This is another structural schematic diagram of the water treatment machine according to the second embodiment of the above-mentioned utility model, wherein the flat valve of the water treatment machine shown in the figure is in the third positive flushing working position, and the water treatment machine is controlled to be in its third positive flushing working state. The arrow in the figure points to the direction of water flow.
[0185] Figure 41H This is another structural schematic diagram of the water treatment machine according to the second embodiment of the above-mentioned utility model, wherein the plane valve of the water treatment machine shown in the figure is in the regeneration working position, the water treatment machine is controlled to be in its regeneration working state, and the arrow in the figure points to the direction of water flow.
[0186] Figure 41I This is another structural schematic diagram of the water treatment machine according to the second embodiment of the above-mentioned utility model, wherein the flat valve of the water treatment machine shown in the figure is in the water replenishing working position, the water treatment machine is controlled to be in its water replenishing working state, and the arrow in the figure points to the direction of water flow.
[0187] Figure 42A This is a three-dimensional view of an optional implementation of the control valve of the water treatment machine according to the second embodiment of the present utility model, wherein the view shows that the second fluid opening is arranged on the first valve body portion of the valve body.
[0188] Figure 42B 4 is a cross-sectional view of the optional implementation of the control valve of the water treatment machine according to the second embodiment of the present invention, wherein the figure shows that the second fluid opening is provided in the first valve body portion of the valve body. DETAILED DESCRIPTION
[0189] The following description is intended to disclose the present invention and enable those skilled in the art to implement the present invention. The preferred embodiments described below are provided for illustrative purposes only, and those skilled in the art will readily appreciate other obvious variations. The basic principles of the present invention as defined in the following description may be applied to other embodiments, variations, improvements, equivalents, and other technical solutions that do not depart from the spirit and scope of the present invention.
[0190] Those skilled in the art should understand that, in the disclosure of the present invention, the terms "longitudinal", "transverse", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like to indicate directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and are not intended to indicate or imply that the devices or elements referred to must have a specific direction, be constructed and operate in a specific direction. Therefore, the above terms should not be understood as limiting the present invention. It should be understood that the term "one" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element can be one, while in another embodiment, the number of the element can be multiple, and the term "one" should not be understood as limiting the quantity.
[0191] Reference to the accompanying drawings Figures 1 to 3G, a water treatment machine according to a first embodiment of the present invention is illustrated, wherein the water treatment machine of the present invention includes a control valve 1, a first water treatment device 51, a second water treatment device 52 and a third water treatment device 53, wherein the first water treatment device 51 has a first water inlet 511 and a first water outlet 512, so that water can flow into the first water inlet 511 of the first water treatment device 51 and flow out through the first water outlet 512 or can flow into the first water outlet 512 of the first water treatment device 51 and flow out through the first water inlet 511; the second water treatment device 52 has a second water inlet 521 and a second water outlet 522, so that water can flow into the second water inlet 521 of the second water treatment device 52 and flow out through the second water outlet 522 Or it can flow into through the second water outlet 522 of the second water treatment device 52 and flow out through the second water inlet 521; the third water treatment device 53 has a third water inlet 531 and a third water outlet 532, so that water can flow into through the third water inlet 531 of the third water treatment device 53 and flow out through the third water outlet 532, or can flow into through the third water outlet 532 of the third water treatment device 53 and flow out through the third water inlet 531, and the control valve 1 is configured to control the flow of water, such as controlling the water flow provided to the first water treatment device 51, the second water treatment device 52 and / or the third water treatment device 53, controlling the flow of water in the first water treatment device 51, the second water treatment device 52 and the third water treatment device 53, and controlling the supply of treated water. It can be understood that the control valve 1 of the water treatment machine of the present invention is suitable for being connected to a water source. For example, the control valve 1 of the water treatment machine of the present invention can be connected to a tap water pipe. In other words, the control valve 1 controls raw water (e.g., tap water) to be provided to the first water treatment device 51, the second water treatment device 52 and / or the third water treatment device 53.
[0192] As shown in the attached figure Figure 3A and Figure 3BAs shown, exemplarily, the first water treatment device 51 of the water treatment machine according to the first embodiment of the present utility model includes a first outer shell 513, a first central tube 514 and a first water treatment material 515, the first outer shell 513 has a first end 5131 and a first shell body 5132 extending from the first end 5131, the first central tube 514 has a first tube upper end 5141 and a first tube lower end 5142, the first water inlet 511 is formed between the first end 5131 and the first tube upper end 5141, the first tube upper end 5141 forms the first water outlet 512, the first water treatment material 515 is arranged between the first outer shell 513 and the first central tube 514, wherein the first central tube 514 is arranged so that the primary treated water generated after the raw water is treated by the first water treatment material 515 can be collected by the first central tube 514. It is understood that the first water treatment material 515 of the first water treatment device 51 of the water treatment machine of the first embodiment of the present invention can be a filter material, such as activated carbon, PP cotton or quartz sand. It is understood that the first water treatment material 515 of the first water treatment device 51 of the water treatment machine of the first embodiment of the present invention can be a dispersed filter material, or a molded filter material obtained by various molding techniques. The first water treatment material 515 of the first water treatment device 51 of the water treatment machine of the first embodiment of the present invention can also be a softening material, such as a softening resin. Those skilled in the art can understand that the first water treatment device 51 of the water treatment machine of the present invention can also be any other water treatment device having a water inlet and a water outlet.
[0193] As shown in the attached figure Figure 3C and Figure 3DAs shown, for example, the second water treatment device 52 of the water treatment machine according to the first embodiment of the present invention includes a second shell 523, a second central tube 524 and a second water treatment material 525, the second shell 523 has a second end 5231 and a second shell body 5232 extending from the second end 5231, the second central tube 524 has a second tube upper end 5241 and a second tube lower end 5242 extending downward from the second tube upper end 5241, the second inlet The water inlet 521 is formed between the second end 5231 of the second housing 523 and the upper end 5241 of the second tube. The upper end 5241 of the second tube forms the second water outlet 522. The second water treatment material 525 is disposed between the second housing 523 and the second central tube 524. The second central tube 524 is configured so that the secondary treated water generated by the primary treated water flowing in from the second water inlet 521 and treated by the second water treatment material 525 can be collected by the second central tube 524. It is understood that the second water treatment material 525 of the second water treatment device 52 of the water treatment machine of the first embodiment of the present invention can be a filter material, such as activated carbon, PP cotton, or quartz sand. It is understood that the second water treatment material 525 of the second water treatment device 52 of the water treatment machine of the first embodiment of the present invention can be a dispersed filter material or a shaped filter material obtained through various molding techniques. The second water treatment material 525 of the second water treatment device 52 of the water treatment machine of the first embodiment of the present invention may also be a softening material, such as a softening resin. Those skilled in the art will appreciate that the second water treatment device 52 of the water treatment machine of the present invention may also be any other water treatment device having a water inlet and a water outlet.
[0194] As shown in the attached figure Figure 3E and Figure 3FAs shown, exemplarily, the third water treatment device 53 of the water treatment machine according to the first embodiment of the present utility model includes a third outer shell 533, a third central tube 534 and a third water treatment material 535, the third outer shell 533 has a third end 5331 and a third shell body 5332 extending from the third end 5331, the third central tube 534 has a third tube upper end 5341 and a third tube lower end 5342 extending downward from the third tube upper end 5341, the third water inlet 531 is formed between the third end 5331 and the third tube upper end 5341, the third tube upper end 5341 forms the third water outlet 532, the third water treatment material 535 is arranged between the third outer shell 533 and the third central tube 534, wherein the third central tube 534 is arranged so that the secondary treated water flowing in from the third water inlet 531 is treated by the third water treatment material 535 and the tertiary treated water generated can be collected by the third central tube 534. It is understood that the third water treatment material 535 of the third water treatment device 53 of the water treatment machine of the first embodiment of the present invention can be a filter material, such as activated carbon, PP cotton, or quartz sand. It is understood that the third water treatment material 535 of the third water treatment device 53 of the water treatment machine of the first embodiment of the present invention can be a dispersed filter material, or it can be a molded filter material obtained through various molding techniques. Preferably, the third water treatment material 535 of the third water treatment device 53 of the water treatment machine of the first embodiment of the present invention is a softening material, such as a softening resin. Those skilled in the art will understand that the third water treatment device 53 of the water treatment machine of the present invention can also be any other water treatment device having a water inlet and a water outlet.
[0195] As shown in the attached figure Figure 3A As shown, when the first water treatment device 51 of the water treatment machine according to the first embodiment of the present invention is used for water treatment (for example, filtration) or the first water treatment device 51 is forward flushed (positive flushing), water flows into the first water treatment device 51 from the first water inlet 511, and then flows through the first end 5131, the first water treatment material 515, the first tube lower end 5142, the first central tube 514 and the first tube upper end 5141 in sequence and flows out from the first water outlet 512; as shown in the accompanying drawings Figure 3B As shown, when the first water treatment device 51 of the water treatment machine according to the first embodiment of the present invention is backwashed (backwashed), water flows into the first water treatment device 51 from the first water outlet 512, and then flows through the first tube upper end 5141, the first central tube 514, the first tube lower end 5142, the first water treatment material 515 and the first end 5131 in sequence and flows out from the first water inlet 511.
[0196] As shown in the attached figure Figure 3CAs shown, when the second water treatment device 52 of the water treatment machine according to the first embodiment of the present invention is used for water treatment or the second water treatment device 52 is forwardly flushed (positively flushed), water flows into the second water treatment device 52 from the second water inlet 521, and then flows through the second end 5231, the second water treatment material 525, the second tube lower end 5242, the second center tube 524 and the second tube upper end 5241 in sequence and flows out from the second water outlet 522; as shown in the accompanying drawings Figure 3D As shown, when the second water treatment device 52 of the water treatment machine according to the first embodiment of the present invention is backwashed (backwashed), water flows into the second water treatment device 52 from the second water outlet 522, and then flows through the second tube upper end 5241, the second center tube 524, the second tube lower end 5242, the second water treatment material 525 and the second end 5231 in sequence and flows out from the second water inlet 521.
[0197] As shown in the attached figure Figure 3E As shown, when the third water treatment device 53 of the water treatment machine according to the first embodiment of the present invention is used as a purification filter element to purify water or the third water treatment device 53 is forward flushed (positive flushed), water flows into the third water treatment device 53 from the third water inlet 531, and then flows through the third end 5331, the third water treatment material 535, the third tube lower end 5342, the third center tube 534 and the third tube upper end 5341 and flows out from the third water outlet 532; as shown in the accompanying drawings Figure 3F As shown, when the third water treatment device 53 of the water treatment machine according to the first embodiment of the present invention is backwashed (backwashed) as a purification filter element (or softening filter element), water flows into the third water treatment device 53 from the third water outlet 532, and then flows through the third pipe upper end 5341, the third central pipe 534, the third pipe lower end 5342, the third water treatment material 535 and the third end 5331 in sequence and flows out from the third water inlet 531. Figure 3E As shown, when the third water treatment device 53 of the water treatment machine according to the first embodiment of the present utility model is used as a softening filter element to soften water, the third water treatment device 53 is forward flushed (positive flushing) or the third water treatment device 53 is regenerated by downstream salt absorption, water or regeneration solution flows into the third water treatment device 53 from the third water inlet 531, and then flows through the third end 5331, the third water treatment material 535, the third tube lower end 5342, the third center tube 534 and the third tube upper end 5341 in sequence and flows out from the third water outlet 532.
[0198] As shown in the attached figure Figures 2 to 6UAs shown, the control valve 1 of the water treatment machine according to the first embodiment of the present utility model includes a valve body 10 and a valve core 12, wherein the valve body 10 forms a valve cavity 110, a first opening 1101, a second opening 1102, a third opening 1103, a fourth opening 1104, a fifth opening 1105, a first fluid opening 1106, a second fluid opening 1107 and a sewage discharge opening 11010, wherein the valve core 12 is arranged in the valve cavity 110, wherein the first opening 1101 of the valve body 10 is suitable for connecting with the first water inlet 51 of the first water treatment device 51. 11 is connected, the second opening 1102 is adapted to be connected to the first water outlet 512 of the first water treatment device 51 and the second water inlet 521 of the second water treatment device 52, respectively, the third opening 1103 is adapted to be connected to the second water outlet 522 of the second water treatment device 52, the fourth opening 1104 is adapted to be connected to the third water inlet 531 of the third water treatment device 53, the fifth opening 1105 is adapted to be connected to the third water outlet 532 of the third water treatment device 53, and the second fluid opening 1107 of the valve body 10 is adapted to be connected to a raw water source (e.g., tap water). Preferably, the second opening 1102 of the valve body 10 of the control valve 1 of the water treatment machine of the present invention, the first water outlet 512 of the first water treatment device 51, and the second water inlet 521 of the second water treatment device 52 form a three-way structure 61. Optionally, the second opening 1102 of the valve body 10 of the control valve 1 of the water treatment machine of the present invention is respectively connected to the first water outlet 512 of the first water treatment device 51 and the second water inlet 521 of the second water treatment device 52 through the three-way structure 61.
[0199] As shown in the attached figure Figures 4 to 8CAs shown, more specifically, the control valve 1 of the water treatment machine according to the first embodiment of the utility model is a plane valve, wherein the valve core 12 of the plane valve 1 further includes a first fixed valve disc 121, a movable valve disc 122 and a second fixed valve disc 123, wherein the first fixed valve disc 121 has a first fluid control surface 1210, the movable valve disc 122 has a second fluid control surface 1220 and a third fluid control surface 1223, and the second fixed valve disc 123 has a fourth fluid control surface 1230, wherein the first fixed valve disc 121, the movable valve disc 122 and the second fixed valve disc The plates 123 are all arranged in the valve cavity 110, wherein the second fluid control surface 1220 and the third fluid control surface 1223 of the movable valve plate 122 are respectively formed on the opposite sides of the movable valve plate 122, wherein the second fluid control surface 1220 of the movable valve plate 122 is arranged on the first fluid control surface 1210 of the first fixed valve plate 121, and the fourth fluid control surface 1230 of the second fixed valve plate 123 is arranged on the third fluid control surface 1223 of the movable valve plate 122, and the movable valve plate 122 is arranged to be able to rotate relative to the first fixed valve plate 121 and the second fixed valve plate 123. Accordingly, the first fixed valve disc 121 is disposed between the valve body 10 and the movable valve disc 122, and the second fixed valve disc 123 is disposed between the valve body 10 and the movable valve disc 122. The first fixed valve disc 121 is configured to remain stationary relative to the valve body 10, and the second fixed valve disc 123 is configured to remain stationary relative to the valve body 10. Preferably, the second fluid opening 1107 is in communication with the valve cavity 110 of the valve body 10.
[0200] As shown in the attached figure Figures 4 to 6U 、 Figure 21A and Figure 21B As shown, the valve body 10 of the control valve 1 of the water treatment machine according to the first embodiment of the present invention includes a first valve body portion 11 and a second valve body portion 13, wherein the valve chamber 110 is formed between the first valve body portion 11 and the second valve body portion 13, the first opening 1101, the second opening 1102, the third opening 1103, the fourth opening 1104, and the fifth opening 1105 are formed in the first valve body portion 11, the first fluid opening 1106 and the sewage opening 11010 are formed in the second valve body portion 13, and the second fluid opening 1107 is selectively provided in the first valve body portion 11 or the second valve body portion 13 of the valve body 10. In other words, the second fluid opening 1107 can be provided in either the first valve body portion 11 or the second valve body portion 13 of the valve body 10.
[0201] As shown in the attached figure Figure 11A 、 Figure 11B and Figure 20AAs shown, the control valve 1 of the water treatment machine according to the first embodiment of the present invention has a water treatment working position, wherein when the control valve 1 of the water treatment machine of the present invention is in the water treatment working position, the valve core 12 of the control valve 1 forms a first water treatment flow channel 7001, a second water treatment flow channel 7002 and a third water treatment flow channel 7003, wherein the first water treatment flow channel 7001 is respectively connected to the second fluid opening 1107 and the first opening 1101, the second water treatment flow channel 7002 is respectively connected to the third opening 1103 and the fourth opening 1104, and the third water treatment flow channel 7003 is respectively connected to the fifth opening 1105 and the first fluid opening 1106. Accordingly, when the control valve 1 of the water treatment machine of the present invention is in the water treatment working position, raw water flows in from the second fluid opening 1107 of the valve body 10 of the control valve 1 under the action of water pressure, flows to the first opening 1101 of the first valve body portion 11 through the first water treatment flow channel 7001, and further flows into the first water treatment device 51 from the first water inlet 511 under the action of water pressure. The primary treated water obtained after being treated by the first water treatment device 51 flows out from the first water outlet 512 and further flows into the second water treatment device 52 from the second water inlet 521. The secondary treated water after being treated by the second water treatment device 52 flows out from the second water outlet 522, and under the action of water pressure, further flows into the third opening 1103, and then flows into the fourth opening 1104 through the second water treatment channel 7002, and then flows into the third water treatment device 53 from the third water inlet 531. The tertiary treated water obtained after water treatment (purification or softening treatment) by the third water treatment device 53 flows out from the third water outlet 532 and flows into the fifth opening 1105, and then flows to the first fluid opening 1106 through the third water treatment channel 7003 and is provided. Accordingly, when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the water treatment working position, water flows sequentially through the second fluid opening 1107 of the valve body 10, the first water treatment flow channel 7001, the first opening 1101 of the first valve body portion 11, the first water inlet 511 of the first water treatment device 51, the first water outlet 512 of the first water treatment device 51, the second water inlet 521 of the second water treatment device 52, and the second water outlet 522 of the second water treatment device 52. , the third opening 1103 of the first valve body 11, the second water treatment channel 7002, the fourth opening 1104 of the first valve body 11, the third water inlet 531 of the third water treatment device 53, the third water outlet 532 of the third water treatment device 53, the fifth opening 1105 of the first valve body 11, the third water treatment channel 7003 and the first fluid opening 1106, so that the control valve 1 of the water treatment machine of the utility model can control the three water treatment devices of the water treatment machine of the utility model in series.Preferably, the control valve 1 of the water treatment machine according to the first embodiment of the present invention is configured to prevent the flow of water in the second opening 1102 when the control valve 1 is controlled to the water treatment working position. Furthermore, when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to the water treatment working position, water cannot flow from the first water outlet 512 of the first water treatment device 51 to the second opening 1102, nor can it flow from the second water inlet 521 of the second water treatment device 52 to the second opening 1102, thereby ensuring that raw water can flow through the first water treatment device 51, the second water treatment device 52, and the third water treatment device 53 in sequence and be treated by the first water treatment device 51, the second water treatment device 52, and the third water treatment device 53 in sequence. It can be understood that when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to the water treatment working position, the water treatment machine of the present invention is controlled to be in its water treatment working state.
[0202] As shown in the attached figure Figure 12 and Figure 20BAs shown, the control valve 1 of the water treatment machine according to the first embodiment of the present invention has a first backwash working position, wherein when the control valve 1 of the water treatment machine of the present invention is in the first backwash working position, the valve core 12 of the control valve 1 forms a first backwash flow channel 7101 and a second backwash flow channel 7102, wherein the first backwash flow channel 7101 is respectively connected to the second fluid opening 1107 and the second opening 1102, and the second backwash flow channel 7102 is respectively connected to the sewage opening 11010 and the first opening 1101. Accordingly, when the control valve 1 of the water treatment machine of the present invention is in the first backwash working position, raw water, under the action of water pressure, flows from the second fluid opening 1107 of the valve body 10 of the control valve 1, flows through the first backwash flow channel 7101 to the second opening 1102, and further flows into the first water treatment device 51 from the first water outlet 512. Sewage generated after backwashing the first water treatment device 51 flows out from the first water inlet 511, and is then discharged through the first opening 1101, the second backwash flow channel 7102, and the sewage outlet 11010. Preferably, the control valve 1 of the water treatment machine of the first embodiment of the present invention is configured to prevent raw water from flowing from the second fluid opening 1107 of the valve body 10 of the control valve 1 to the third opening 1103, the fourth opening 1104, and the fifth opening 1105 when the control valve 1 is controlled to be in the first backwash working position. More preferably, when the control valve 1 of the water treatment machine of the present invention is controlled to be in the first backwash working position, the flow of water in the third opening 1103, the fourth opening 1104, and the fifth opening 1105 is blocked, thereby blocking the flow of water in the second water treatment device 52 and the third water treatment device 53. More specifically, when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the first backwash working position, water cannot flow from the second opening 1102 or the third opening 1103 of the first valve body 11 to the second water treatment device 52, water cannot flow from the fourth opening 1104 or the fifth opening 1105 of the first valve body 11 to the third water treatment device 53, and water cannot flow from the first water outlet 512 of the first water treatment device 51 to the second water inlet 521 of the second water treatment device 52, thereby ensuring that raw water can and only can backwash the first water treatment device 51. It can be understood that when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the first backwash working position, the water treatment machine of the present invention is controlled to be in its first backwash working state to backwash the first water treatment device 51 of the water treatment machine of the present invention.
[0203] As shown in the attached figure Figure 13 and Figure 20CAs shown, the control valve 1 of the water treatment machine according to the first embodiment of the present invention has a second backwash working position, wherein when the control valve 1 of the water treatment machine of the present invention is in the second backwash working position, the valve core 12 of the control valve 1 forms a third backwash flow channel 7103 and a fourth backwash flow channel 7104, wherein the third backwash flow channel 7103 is respectively connected to the second fluid opening 1107 and the third opening 1103, and the fourth backwash flow channel 7104 is respectively connected to the sewage opening 11010 and the second opening 1102. Accordingly, when the control valve 1 of the water treatment machine of the present invention is in the second backwash working position, raw water, under the action of water pressure, flows from the second fluid opening 1107 of the valve body 10 of the control valve 1, flows through the third backwash flow channel 7103 to the third opening 1103, and further flows into the second water treatment device 52 from the second water outlet 522. Sewage generated after backwashing the second water treatment device 52 flows out from the second water inlet 521 and is then discharged through the second opening 1102, the fourth backwash flow channel 7104, and the sewage outlet 11010. Preferably, the control valve 1 of the water treatment machine of the first embodiment of the present invention is configured to prevent raw water from flowing from the second fluid opening 1107 of the valve body 10 of the control valve 1 to the first opening 1101, the fourth opening 1104, and the fifth opening 1105 when the control valve 1 is controlled to be in the second backwash working position. More preferably, when the control valve 1 of the water treatment machine of the present invention is controlled to be in the second backwash working position, the flow of water in the first opening 1101, the fourth opening 1104, and the fifth opening 1105 is blocked, thereby blocking the flow of water in the first water treatment device 51 and the third water treatment device 53. More specifically, when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the second backwash working position, water cannot flow from the first opening 1101 or the second opening 1102 of the first valve body 11 to the first water treatment device 51, water cannot flow from the fourth opening 1104 or the fifth opening 1105 of the first valve body 11 to the third water treatment device 53, and water cannot flow from the second water inlet 521 of the second water treatment device 52 to the first water outlet 512 of the first water treatment device 51, thereby ensuring that raw water can and only can backwash the second water treatment device 52. It can be understood that when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the second backwash working position, the water treatment machine of the present invention is controlled to be in its second backwash working state to backwash the second water treatment device 52 of the water treatment machine of the present invention.
[0204] As shown in the attached figure Figure 14 and Figure 20DAs shown, the control valve 1 of the water treatment machine according to the first embodiment of the present invention has a third backwash working position, wherein when the control valve 1 of the water treatment machine of the present invention is in the third backwash working position, the valve core 12 of the control valve 1 forms a fifth backwash flow channel 7105 and a sixth backwash flow channel 7106, wherein the fifth backwash flow channel 7105 is respectively connected to the second fluid opening 1107 and the fifth opening 1105, and the sixth backwash flow channel 7106 is respectively connected to the sewage opening 11010 and the fourth opening 1104. Accordingly, when the control valve 1 of the water treatment machine of the present invention is in the third backwash working position, raw water, under the action of water pressure, flows from the second fluid opening 1107 of the valve body 10 of the control valve 1, flows through the fifth backwash flow channel 7105 to the fifth opening 1105, and further flows into the third water treatment device 53 from the third water outlet 532. Sewage generated after backwashing the third water treatment device 53 flows out from the third water inlet 531, and is then discharged through the fourth opening 1104, the sixth backwash flow channel 7106, and the sewage outlet 11010. Preferably, the control valve 1 of the water treatment machine of the first embodiment of the present invention is configured to prevent raw water from flowing from the second fluid opening 1107 of the valve body 10 of the control valve 1 to the first opening 1101, the second opening 1102, and the third opening 1103 when the control valve 1 is controlled to be in the third backwash working position. More preferably, when the control valve 1 of the water treatment machine of the present invention is controlled to be in the third backwash working position, the flow of water in the first opening 1101, the second opening 1102, and the third opening 1103 is blocked, thereby blocking the flow of water in the first water treatment device 51 and the second water treatment device 52. More specifically, when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the third backwash working position, water cannot flow from the first opening 1101 or the second opening 1102 of the first valve body 11 to the first water treatment device 51; water also cannot flow from the second opening 1102 or the third opening 1103 of the first valve body 11 to the second water treatment device 52, thereby ensuring that raw water can and only can backwash the third water treatment device 53. It can be understood that when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the third backwash working position, the water treatment machine of the present invention is controlled to be in its third backwash working state to backwash the third water treatment device 53 of the water treatment machine of the present invention.
[0205] It can be understood that backwashing in this article refers to the flow direction of the water treatment device (the first water treatment device 51, the second water treatment device 52 or the third water treatment device 53) of the water treatment machine of the present invention when the water flow flushes the water treatment device of the water treatment machine of the present invention, and the flow direction of the raw water flowing through the water treatment device of the water treatment machine of the present invention is opposite to that when the water treatment device of the water treatment machine of the present invention treats the raw water.
[0206] As shown in the attached figure Figure 15 and Figure 20EAs shown, the control valve 1 of the water treatment machine according to the first embodiment of the present invention has a first positive flushing working position, wherein when the control valve 1 of the water treatment machine of the present invention is in the first positive flushing working position, the valve core 12 of the control valve 1 forms a first positive flushing flow channel 7201 and a second positive flushing flow channel 7202, wherein the first positive flushing flow channel 7201 is respectively connected to the second fluid opening 1107 and the first opening 1101, and the second positive flushing flow channel 7202 is respectively connected to the sewage opening 11010 and the second opening 1102. Accordingly, when the control valve 1 of the water treatment machine of the present invention is in the first positive flush working position, raw water, under the action of water pressure, flows from the second fluid opening 1107 of the valve body 10 of the control valve 1, flows through the first positive flush flow channel 7201 to the first opening 1101, and further flows into the first water treatment device 51 from the first water inlet 511. The sewage after positive flushing the first water treatment device 51 flows out from the first water outlet 512, and is then discharged through the second opening 1102, the second positive flush flow channel 7202, and the sewage discharge opening 11010. Preferably, the control valve 1 of the water treatment machine of the first embodiment of the present invention is configured to prevent raw water from flowing from the second fluid opening 1107 of the valve body 10 of the control valve 1 to the third opening 1103, the fourth opening 1104, and the fifth opening 1105 when the control valve 1 is controlled to be in the first positive flush working position. More preferably, when the control valve 1 of the water treatment machine of the present invention is controlled to be in the first positive flushing position, the flow of water in the third opening 1103, the fourth opening 1104, and the fifth opening 1105 is blocked, thereby blocking the flow of water in the second water treatment device 52 and the third water treatment device 53. More specifically, when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the first positive flushing position, water cannot flow from the second opening 1102 or the third opening 1103 of the first valve body 11 to the second water treatment device 52, water cannot flow from the fourth opening 1104 or the fifth opening 1105 of the first valve body 11 to the third water treatment device 53, and water cannot flow from the first water outlet 512 of the first water treatment device 51 to the second water inlet 521 of the second water treatment device 52, thereby ensuring that raw water can and can only forward flush the first water treatment device 51. It can be understood that when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the first positive flushing working position, the water treatment machine of the present invention is controlled to be in its first positive flushing working state to forward flush the first water treatment device 51 of the water treatment machine of the present invention.
[0207] As shown in the attached figure Figure 16 and Figure 20FAs shown, the control valve 1 of the water treatment machine according to the first embodiment of the present invention has a second positive flushing working position, wherein when the control valve 1 of the water treatment machine of the present invention is in the second positive flushing working position, the valve core 12 of the control valve 1 forms a third positive flushing flow channel 7203 and a fourth positive flushing flow channel 7204, wherein the third positive flushing flow channel 7203 is respectively connected to the second fluid opening 1107 and the second opening 1102, and the fourth positive flushing flow channel 7204 is respectively connected to the sewage opening 11010 and the third opening 1103. Accordingly, when the control valve 1 of the water treatment machine of the present invention is in the second positive flush working position, raw water, under the action of water pressure, flows from the second fluid opening 1107 of the valve body 10 of the control valve 1, flows through the third positive flush flow channel 7203 to the second opening 1102, and further flows from the second water inlet 521 into the second water treatment device 52. The sewage after positive flushing the second water treatment device 52 flows out from the second water outlet 522, and is then discharged through the third opening 1103, the fourth positive flush flow channel 7204, and the sewage discharge opening 11010. Preferably, the control valve 1 of the water treatment machine of the first embodiment of the present invention is configured to prevent raw water from flowing from the second fluid opening 1107 of the valve body 10 of the control valve 1 to the first opening 1101, the fourth opening 1104, and the fifth opening 1105 when the control valve 1 is controlled to be in the second positive flush working position. More preferably, when the control valve 1 of the water treatment machine of the present invention is controlled to be in the second positive flushing position, the flow of water in the first opening 1101, the fourth opening 1104, and the fifth opening 1105 is blocked, thereby blocking the flow of water in the first water treatment device 51 and the third water treatment device 53. More specifically, when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the second positive flushing position, water cannot flow from the first opening 1101 or the second opening 1102 of the first valve body 11 to the first water treatment device 51, water cannot flow from the fourth opening 1104 and the fifth opening 1105 of the first valve body 11 to the third water treatment device 53, and water cannot flow from the second water inlet 521 of the second water treatment device 52 to the first water outlet 512 of the first water treatment device 51, thereby ensuring that raw water can and can only forward flush the second water treatment device 52. It can be understood that when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the second positive flushing working position, the water treatment machine of the present invention is controlled to be in its second positive flushing working state to positively flush the second water treatment device 52 of the water treatment machine of the present invention.
[0208] As shown in the attached figure Figure 17 and Figure 20GAs shown, the control valve 1 of the water treatment machine according to the first embodiment of the present invention has a third positive flushing working position, wherein when the control valve 1 of the water treatment machine of the present invention is in the third positive flushing working position, the valve core 12 of the control valve 1 forms a fifth positive flushing flow channel 7205 and a sixth positive flushing flow channel 7206, wherein the fifth positive flushing flow channel 7205 is respectively connected to the second fluid opening 1107 and the fourth opening 1104, and the sixth positive flushing flow channel 7206 is respectively connected to the sewage opening 11010 and the fifth opening 1105. Accordingly, when the control valve 1 of the water treatment machine of the present invention is in the third positive flush working position, raw water, under the action of water pressure, flows from the second fluid opening 1107 of the valve body 10 of the control valve 1, flows through the fifth positive flush flow channel 7205 to the fourth opening 1104, and further flows into the third water treatment device 53 from the third water inlet 531. The sewage after positive flushing the third water treatment device 53 flows out from the third water outlet 532, and is then discharged through the fifth opening 1105, the sixth positive flush flow channel 7206, and the sewage discharge opening 11010. Preferably, the control valve 1 of the water treatment machine of the first embodiment of the present invention is configured to prevent raw water from flowing from the second fluid opening 1107 of the valve body 10 of the control valve 1 to the first opening 1101, the second opening 1102, and the third opening 1103 when the control valve 1 is controlled to be in the third positive flush working position. More preferably, when the control valve 1 of the water treatment machine of the present invention is controlled to be in the third positive flushing working position, the flow of water in the first opening 1101, the second opening 1102, and the third opening 1103 is blocked, thereby blocking the flow of water in the first water treatment device 51 and the second water treatment device 52. More specifically, when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the third positive flushing working position, water cannot flow from the first opening 1101 or the second opening 1102 of the first valve body 11 to the first water treatment device 51, and water cannot flow from the second opening 1102 or the third opening 1103 of the first valve body 11 to the second water treatment device 52, thereby ensuring that raw water can and can only forward flush the third water treatment device 53. It can be understood that when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the third positive flushing working position, the water treatment machine of the present invention is controlled to be in its third positive flushing working state to forward flush the third water treatment device 53 of the water treatment machine of the present invention.
[0209] It can be understood that the forward flushing in this article refers to the flow direction of the water treatment device (the first water treatment device 51, the second water treatment device 52 or the third water treatment device 53) of the water treatment machine of the present invention when the water flow is flushing the water treatment device of the water treatment machine of the present invention, and the flow direction of the raw water through the water treatment device of the water treatment machine of the present invention when the water treatment device of the water treatment machine of the present invention treats the raw water is the same. Generally, the time for forward flushing the water treatment device of the water treatment machine of the present invention by using water flow is after backwashing, so as to flush away the wastewater generated by backwashing remaining in the water treatment device of the water treatment machine of the present invention. In addition, if the filter material (or softening material) of the water treatment device of the water treatment machine of the present invention is a granular filter material, the forward flushing can also play a role in compacting the filter material (or softening material) so that it has a better water treatment effect.
[0210] As shown in the attached figure Figures 11A to 17 and Figures 20A to 20G As shown, the control valve 1 of the water treatment machine according to the first embodiment of the present invention, more specifically, the control valve 1 of a single water treatment machine of the present invention, is configured to control the first water treatment device 51, the second water treatment device 52 and the third water treatment device 53 of the water treatment machine of the present invention to be connected in series and perform three-stage treatment on the raw water, and control the raw water to respectively and individually perform reverse flushing and forward flushing on the first water treatment device 51, the second water treatment device 52 and the third water treatment device 53 of the water treatment machine of the present invention.
[0211] As shown in the attached figure Figures 1 to 6FAs shown, the third water treatment device 53 of the water treatment machine according to the first embodiment of the present utility model is a water softening device, the control valve 1 further has an ejector 18, and the valve body 10 of the control valve 1 further forms a first jet opening 11012, and the first jet opening 11012 is formed in the first valve body portion 11 of the valve body 10 of the control valve 1. Furthermore, the valve body 10 of the control valve 1 further forms a second jet opening 11013, and the second jet opening 11013 is formed in the first valve body portion 11 of the valve body 10 of the control valve 1, wherein the ejector 18 has an ejection port 182 suitable for communicating with the first jet opening 11012 of the first valve body portion 11, an ejection port 183 suitable for communicating with the second jet opening 11013 of the first valve body portion 11, and a salt absorption port 181 respectively connected with the ejection port 182 and the ejection port 183. When water flow, such as raw water flow, flows from the ejection port 182 of the ejector 18 to the ejection port 183 of the ejector 18, negative pressure occurs at the salt absorption port 181 of the ejector 18, so that the regeneration solution can flow from the salt absorption port 181 of the ejector 18 to the ejection port 183 of the ejector 18. Correspondingly, the salt absorption port 181 of the ejector 18 is communicated with the ejection port 182 and the ejection port 183 of the ejector 18 respectively.
[0212] As shown in the attached figure Figure 1 、 Figure 2 and Figure 5 As shown, the water treatment machine according to the first embodiment of the present invention further includes a regeneration solution tank 31, wherein the salt intake port 181 is connected to the regeneration solution tank 31, so that the salt solution is provided to the salt intake port 181. It can be understood that the regeneration solution is generally a salt solution. Figure 1 、 Figure 2 and Figure 5 As shown, the water treatment machine according to the first embodiment of the present utility model further includes a salt absorption pipe 184, one end of the salt absorption pipe 184 is connected to the salt absorption port 181, and the other end of the salt absorption pipe 184 is connected to the regeneration solution tank 31, so that the salt solution can be provided to the salt absorption port 181 through the salt absorption pipe 184 or the water flow can flow from the salt absorption port 181 and flow through the salt absorption pipe 184 to the regeneration solution tank 31 to replenish the regeneration solution tank 31.
[0213] As shown in the attached figure Figure 18A 、 Figure 18B and Figure 20HAs shown, the control valve 1 of the water treatment machine according to the first embodiment of the present invention has a regeneration working position, wherein when the control valve 1 of the water treatment machine of the present invention is in the regeneration working position, the valve core 12 of the control valve 1 forms a first regeneration flow channel 7301, a second regeneration flow channel 7302 and a third regeneration flow channel 7303, wherein the first regeneration flow channel 7301 is respectively connected to the second fluid opening 1107 and the first jet opening 11012 of the valve body 10, the second regeneration flow channel 7302 is respectively connected to the second jet opening 11013 and the fourth opening 1104, and the third regeneration flow channel 7303 is respectively connected to the fifth opening 1105 and the sewage opening 11010. Accordingly, when the control valve 1 of the water treatment machine of the present invention is in the regeneration working position, the raw water flows into the second fluid opening 1107 of the valve body 10 of the control valve 1 under the action of water pressure, flows through the first regeneration flow channel 7301 to the first jet opening 11012 of the first valve body 11, and then flows into the ejection port 182 of the ejector 18. After the ejection of the ejector 18, the salt solution (such as sodium chloride solution) from the salt absorption port 181 is mixed to form a regeneration solution. The regeneration solution passes through the ejection port 182 of the ejector 18. 3 flows into the second jet opening 11013 of the first valve body 11, and then flows into the fourth opening 1104 of the first valve body 11 through the second regeneration flow channel 7302. The regeneration solution flows into the third water treatment device 53 from the third water inlet 531, regenerates the third water treatment material 535 downstream, and after softening the resin, the wastewater generated after regeneration flows out from the third water outlet 532, and then flows out through the fifth opening 1105 of the first valve body 11, the third regeneration flow channel 7303 and the sewage opening 11010 in sequence. Preferably, the control valve 1 of the water treatment machine according to the first embodiment of the present invention is configured to prevent the regeneration solution from flowing toward the first opening 1101, the second opening 1102, and the third opening 1103 when the control valve 1 is controlled to be in the regeneration operating position, and to prevent raw water from flowing from the second fluid opening 1107 of the valve body 10 of the control valve 1 to the first opening 1101, the second opening 1102, and the third opening 1103. More preferably, when the control valve 1 of the water treatment machine of the present invention is controlled to be in the regeneration operating position, the flow of water in the first opening 1101, the second opening 1102, and the third opening 1103 is prevented, thereby preventing the flow of water in the first water treatment device 51 and the second water treatment device 52.More specifically, when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the regeneration working position, water cannot flow from the first opening 1101 or the second opening 1102 of the first valve body 11 to the first water treatment device 51, and water cannot flow from the second opening 1102 or the third opening 1103 of the first valve body 11 to the second water treatment device 52, thereby ensuring that the regeneration solution can and can only flow to the third water treatment device 53. The forward regeneration herein means that when in the regeneration working position, the flow direction of the regeneration solution in the third water treatment device 53 is the same as the flow direction of the water in the third water treatment device 53 when the control valve 1 is in the water treatment working position. It can be understood that when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the regeneration working position, the water treatment machine of the present invention is controlled to be in its regeneration working state.
[0214] As shown in the attached figure Figure 19 and Figure 20IAs shown, the control valve 1 of the water treatment machine according to the first embodiment of the present invention further has a water replenishment position. When the control valve 1 is in the water replenishment position, the valve core 12 of the control valve 1 forms a water replenishment channel 7401, wherein the water replenishment channel 7401 is respectively connected to the second fluid opening 1107 and the second jet opening 11013. Accordingly, when the control valve 1 is in the water replenishment position, raw water, under the action of water pressure, flows from the second fluid opening 1107 of the valve body 10 of the control valve 1, flows through the water replenishment channel 7401 to the second jet opening 11013 of the first valve body 11, and then flows into the regeneration solution tank 31 through the injection port 183 of the ejector 18, the salt absorption port 181, and the salt absorption pipe 184 in sequence to replenish the water. Preferably, the control valve 1 of the water treatment machine according to the first embodiment of the present invention is configured to prevent raw water from flowing from the second fluid opening 1107 of the valve body 10 of the control valve 1 to the first opening 1101, the second opening 1102, the third opening 1103, the fourth opening 1104, and the fifth opening 1105 when the control valve 1 is controlled to the water replenishment operating position. More preferably, when the control valve 1 of the water treatment machine according to the present invention is controlled to the water replenishment operating position, the flow of water in the first opening 1101, the second opening 1102, the third opening 1103, the fourth opening 1104, and the fifth opening 1105 is prevented, thereby preventing the flow of water in the first water treatment device 51, the second water treatment device 52, and the third water treatment device 53. More specifically, when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the water replenishment working position, water cannot flow from the first opening 1101 or the second opening 1102 of the first valve body 11 to the first water treatment device 51, water cannot flow from the second opening 1102 or the third opening 1103 of the first valve body 11 to the second water treatment device 52, and water cannot flow from the fourth opening 1104 or the fifth opening 1105 to the third water treatment device 53. It can be understood that when the control valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the water replenishment working state, the water treatment machine of the present invention is controlled to be in its water replenishment working state.
[0215] As shown in the attached figure Figures 5 to 8CAs shown, the plane valve 1 of the water treatment machine according to the first embodiment of the present utility model has a first channel 101, a second channel 102, a third channel 103, a fourth channel 104, a fifth channel 105, a sixth channel 106, a seventh channel 107, an eighth channel 108, a ninth channel 109, a tenth channel 1010, an eleventh channel 1011, a twelfth channel 1012, a thirteenth channel 1013, a fourteenth channel 1014 and a fifteenth channel 1015, wherein the first channel 101 1. The second channel 102, the third channel 103, the fourth channel 104, the fifth channel 105, the eleventh channel 1011, the twelfth channel 1012, the thirteenth channel 1013, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively provided on the first fixed valve disc 121 and extend from the first fluid control surface 1210 of the first fixed valve disc 121; the seventh channel 107, the eighth channel 108 and the ninth channel 109 are respectively provided on the movable valve disc 122, wherein the seventh channel 107 and the eighth channel 108 are respectively extended from the movable valve disc 121. 22 extends from the second fluid control surface 1220 of the movable valve plate 122, the ninth channel 109 extends from the second fluid control surface 1220 of the movable valve plate 122 to the third fluid control surface 1223; the sixth channel 106 and the tenth channel 1010 are respectively provided on the second fixed valve plate 123 and respectively extend from the fourth fluid control surface 1230 of the second fixed valve plate 123, wherein the first channel 101 is connected to the first opening 1101, the second channel 102 is connected to the second opening 1102, the third channel 103 is connected to the third opening 1103, and the fourth channel 104 is connected to the third opening 1104. The eleventh channel 1011 is respectively connected to the fourth opening 1104. The fifth channel 105, the fourteenth channel 1014, and the fifteenth channel 1015 are respectively connected to the fifth opening 1105. The sixth channel 106 is connected to the first fluid opening 1106. The seventh channel 107 is connected to the second fluid opening 1107. The tenth channel 1010 is connected to the sewage opening 11010. The twelfth channel 1012 is connected to the first jet opening 11012. The thirteenth channel 1013 is connected to the second jet opening 11013. Preferably, the eighth channel 108 is a conductive blind hole. Preferably, the ninth channel 109 is a conductive through hole. Preferably, the seventh channel 107 is connected to the valve cavity 110 and further connected to the second fluid opening 1107 through the valve cavity 110.
[0216] As shown in the attached figure Figure 10A 、 Figure 10B 、 Figure 11A 、 Figure 11B and Figure 20AAs shown, according to the first embodiment of the present invention, the movable valve disc 122 of the plane valve 1 of the water treatment machine can rotate relative to the first fixed valve disc 121 and the second fixed valve disc 123 so that the plane valve 1 has a water treatment working position. When the plane valve 1 of the water treatment machine of the present invention is in the water treatment working position, the seventh channel 107 of the plane valve 1 is connected to the first channel 101, thereby forming channels connected to the second fluid opening 1107 and the first opening 1101 respectively. The first water treatment channel 7001 and the eighth channel 108 are respectively connected to the third channel 103 and the fourth channel 104, thereby forming the second water treatment channel 7002 respectively connected to the third opening 1103 and the fourth opening 1104, and the ninth channel 109 is respectively connected to the fifth channel 105 and the sixth channel 106, thereby forming the third water treatment channel 7003 respectively connected to the fifth opening 1105 and the first fluid opening 1106. In other words, when the plane valve 1 of the water treatment machine of the present invention is in the water treatment working position, the water flows under the action of water pressure, in sequence, through the second fluid opening 1107 of the plane valve 1, the seventh channel 107, the first channel 101, the first opening 1101, the first water inlet 511 of the first water treatment device 51, the first water outlet 512 of the first water treatment device 51, the second water inlet 521 of the second water treatment device 52, the second water treatment device 53, the second water outlet 513 of the second water treatment device 53, the second water outlet 514 of the second water treatment device 53, the second water outlet 515 of the second water treatment device 53, the second water outlet 516 of the second water treatment device 53, the second water outlet 517 of the second water treatment device 53, the second water outlet 518 of the second water treatment device 53, the second water outlet 519 of the second water treatment device 53. 52, the second water outlet 522 of the plane valve 1, the third opening 1103 of the plane valve 1, the third channel 103, the eighth channel 108, the fourth channel 104, the fourth opening 1104, the third water inlet 531 of the third water treatment device 53, the third water outlet 532 of the third water treatment device 53, the fifth opening 1105 of the plane valve 1, the fifth channel 105, the ninth channel 109, the sixth channel 106 and the first fluid opening 1106. As shown in the accompanying drawings 7A to 7I 、 Figure 10A 、 Figure 10B and Figure 20A As shown, exemplarily, when the planar valve 1 of the water treatment machine of the utility model is in the water treatment working position, the second channel 102, the eleventh channel 1011, the twelfth channel 1012, the thirteenth channel 1013, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the tenth channel 1010 is blocked by the third fluid control surface 1223 of the movable valve plate 122.
[0217] It is worth noting that when the planar valve 1 of the water treatment machine of the present invention is in the water treatment working position, the second opening 1102 is respectively connected to the first water outlet 512 of the first water treatment device 51 and the second water inlet 521 of the second water treatment device 52, and the second channel 102 is blocked by the second fluid control surface 1220 of the movable valve plate 122. That is to say, when the plane valve 1 of the water treatment machine of the present invention is in the water treatment working position, no water flows out or in through the second opening 1102. At this time, the first water outlet 512 of the first water treatment device 51 and the second water inlet 521 of the second water treatment device 52 form a series structure; the eighth channel 108 is connected with the third channel 103 and the fourth channel 104 respectively, the third opening 1103 is connected with the second water outlet 522 of the second water treatment device 52, the fourth opening 1104 is connected with the third water inlet 531 of the third water treatment device 53, and the second water outlet 512 of the second water treatment device 52 is connected with the fourth opening 1104. The first water treatment device 51 is connected to the second water treatment device 52 and the third water inlet 531 of the third water treatment device 53. When the plane valve 1 is in the water treatment working position, the first water treatment device 51, the second water treatment device 52, and the third water treatment device 53 form a three-stage series structure. The first water treatment material 515 of the first water treatment device 51, the second water treatment material 525 of the second water treatment device 52, and the third water treatment material 535 of the third water treatment device 53 will sequentially treat the raw water entering the second fluid opening 1107 of the plane valve 1. The treated water flows out of the first fluid opening 1106 and is provided. It can be understood that the three-stage series structure can better perform deep treatment on the raw water. In particular, the first water treatment material 515 of the first water treatment device 51, the second water treatment material 525 of the second water treatment device 52 and the third water treatment material 535 of the third water treatment device 53 can be set to different materials. For example, the first water treatment material 515 can be set to quartz sand as a coarse filtration material, the second water treatment material 525 can be set to granular activated carbon as an adsorption material, and the third water treatment material 535 can be set to softening resin for softening treatment.
[0218] As shown in the attached figure Figure 11A 、 Figure 11B and Figure 20AAs shown, exemplarily, when the plane valve 1 of the water treatment machine according to the first embodiment of the present invention is controlled to be in the water treatment working position, the raw water from the plane valve 1 flows into the valve chamber 110 from the second fluid opening 1107 of the valve body 10 under the action of water pressure, and then flows into the first opening 1101 through the seventh channel 107 and the first channel 101, and then flows into the first water treatment device 51 from the first water inlet 511 of the first water treatment device 51. Under the action of water pressure, the raw water is treated (for example, purified) by the first water treatment material 515. The generated primary treated water is collected by the first central pipe 514 and flows out from the first water outlet 512 of the first water treatment device 51, further flows to the second water inlet 521 of the second water treatment device 52 and flows into the second water treatment device 52, and then is treated (for example, purified) by the second water treatment material 525 under the action of water pressure. For example, after purification treatment), the generated secondary treated water is collected by the second central pipe 524 and flows out from the second water outlet 522 of the second water treatment device 52, and then, under the action of water pressure, further passes through the third opening 1103 of the plane valve 1, the third channel 103, the eighth channel 108, the fourth channel 104, the fourth opening 1104, flows to the third water inlet 531 of the third water treatment device 53 and flows into the third water treatment device 53, and under the action of water pressure, is treated by the third water treatment material 535 (for example, softening treatment), and the generated tertiary treated water is collected by the third central pipe 534, and flows out from the third water outlet 532 of the third water treatment device 53 and flows to the fifth opening 1105 of the plane valve 1, and then is provided through the fifth channel 105, the ninth channel 109, the sixth channel 106 and the first fluid opening 1106.
[0219] As shown in the attached figure Figure 10C 、 Figure 10D 、 Figure 12 and Figure 20B As shown, the plane valve 1 of the water treatment machine according to the first embodiment of the present invention further has a first backwash working position. When the plane valve 1 of the water treatment machine of the present invention is in the first backwash working position, the seventh channel 107 of the plane valve 1 is connected with the second channel 102, thereby forming the first backwash flow channel 7101 connected with the second fluid opening 1107 and the second opening 1102 respectively, and the ninth channel 109 is connected with the tenth channel 1010 and the first channel 101 respectively, thereby forming the second backwash flow channel 7102 connected with the sewage opening 11010 and the first opening 1101 respectively. As shown in the accompanying drawings 7A to 7I 、 Figure 10C 、 Figure 10D and Figure 20BAs shown, when the plane valve 1 of the water treatment machine of the utility model is in the first backwash working position, the eighth channel 108 is respectively connected to the fifth channel 105 and the eleventh channel 1011, the third channel 103, the fourth channel 104, the twelfth channel 1012, the thirteenth channel 1013, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122. Therefore, when the plane valve 1 is in the first backwash working position, although the eighth channel 108 of the plane valve 1 is connected to the fifth channel 105 and the eleventh channel 1011 respectively, the eighth channel 108 is a conducting blind hole, and the third channel 103, the fourth channel 104, the twelfth channel 1012, the thirteenth channel 1013, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, so that the raw water can only flow out from the second fluid opening 1220 of the plane valve 1. 107 flows into the seventh channel 107, and further flows through the second channel 102 and the second opening 1102 to the first water outlet 512 of the first water treatment device 51 and flows into the first water treatment device 51. The wastewater generated by backwashing the first water treatment device 51 flows from the first water inlet 511 of the first water treatment device 51 to the first opening 1101 of the plane valve 1, and is further discharged through the first channel 101, the ninth channel 109, the tenth channel 1010 and the sewage opening 11010 of the plane valve 1 under the action of water pressure. In other words, although the eighth channel 108 is connected to the fifth channel 105 and the eleventh channel 1011 respectively, since the fourth channel 104, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the eighth channel 108 is a conductive blind hole, the water does not flow through the flow channel formed by them.Correspondingly, when the plane valve 1 is in the first backwash working position, the third channel 103 of the plane valve 1 is blocked by the second fluid control surface 1220 of the movable valve plate 122, thereby preventing water from flowing through the third opening 1103 of the plane valve 1, so that the flow of water from the second opening 1102 to the second water inlet 521 of the second water treatment device 52 is blocked; the eighth channel 108 is connected to the fifth channel 105 and the eleventh channel 1011 respectively. Since the eighth channel 108 is a conducting blind hole, and the fourth channel 104 and the fourteenth channel 1 014 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and since the fourth channel 104 and the eleventh channel 1011 are respectively connected to the fourth opening 1104, the fifth channel 105, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively connected to the fifth opening 1105, thereby preventing water from flowing through the fourth opening 1104 and the fifth opening 1105 of the plane valve 1, thereby preventing the flow of water in the second water treatment device 52 and the third water treatment device 53. In other words, although the eighth channel 108 is respectively connected to the fifth channel 105 and the eleventh channel 1011, the movable valve plate 122 blocks the raw water from flowing to the third channel 103, the fourth channel 104, the twelfth channel 1012, the thirteenth channel 1013, the fourteenth channel 1014 and the fifteenth channel 1015, thereby ensuring that only the first water treatment device 51 is reverse flushed.
[0220] It is worth noting that when the planar valve 1 is in the first backwash working position, the third channel 103, the fourth channel 104, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively blocked by the movable valve plate 122. Although the eighth channel 108 is respectively connected to the fifth channel 105 and the eleventh channel 1011, the eighth channel 108 is a conducting blind hole, so that the third opening 1103, the fourth opening 1104 and the fifth opening 1105 are all blocked. That is, the third opening 1103, the fourth opening 1104, and the fifth opening 1105 are all blocked by the movable valve plate 122, so that no water flows in the second water treatment device 52. The third water treatment device 53 is isolated from the water flow, ensuring that only the first water treatment device 51 is backwashed. This increases the intensity of the raw water backwashing the first water treatment device 51 while preventing the generated sewage from flowing into the second water treatment device 52 and / or the third water treatment device 53. Therefore, when the flat valve 1 is in the first backwashing working position, the first water treatment device 51 of the water treatment machine of the present invention is backwashed alone.
[0221] As shown in the attached figure Figure 12 and Figure 20BAs shown, exemplarily, when the plane valve 1 of the water treatment machine according to the first embodiment of the present utility model is controlled to be in the first backwash working position, the raw water from the plane valve 1 flows into the first water treatment device 51 from the first water outlet 512 of the first water treatment device 51 under the action of water pressure, and then flows from the first central pipe 514 to the first water treatment material 515 and backwashes the first water treatment material 515 under the action of water pressure. The generated sewage flows out from the first water inlet 511 of the first water treatment device 51, and under the action of water pressure, flows to the first opening 1101 of the plane valve 1, and then flows to the sewage opening 11010 through the second backwash channel 7102 and is discharged.
[0222] As shown in the attached figure Figure 10E 、 Figure 10F 、 Figure 13 and Figure 20C As shown, the plane valve 1 of the water treatment machine according to the first embodiment of the present invention further has a second backwash working position. When the plane valve 1 of the water treatment machine of the present invention is in the second backwash working position, the seventh channel 107 of the plane valve 1 is connected with the third channel 103, thereby forming the third backwash flow channel 7103 connected with the second fluid opening 1107 and the third opening 1103 respectively, and the ninth channel 109 is connected with the tenth channel 1010 and the second channel 102 respectively, thereby forming the fourth backwash flow channel 7104 connected with the sewage opening 11010 and the second opening 1102 respectively. As shown in the accompanying drawings 7A to 7I 、 Figure 10E 、 Figure 10F and Figure 20C As shown, when the plane valve 1 of the water treatment machine of the present invention is in the second backwash working position, the eighth channel 108 is connected to the fifth channel 105 and the twelfth channel 1012 respectively, the first channel 101, the fourth channel 104, the eleventh channel 1011, the thirteenth channel 1013, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122. As shown in the accompanying drawings 7A to 7I 、 Figure 10E 、 Figure 10F and Figure 20CAs shown, specifically, when the plane valve 1 is in the second backwash working position, although the eighth channel 108 is connected to the fifth channel 105 and the twelfth channel 1012 respectively, since the eighth channel 108 is a conducting blind hole, and the first channel 101, the fourth channel 104, the eleventh channel 1011, the thirteenth channel 1013, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, so that the raw water can only flow out from the second fluid opening 1220 of the plane valve 1. 107 flows into the seventh channel 107, and further flows through the third channel 103 and the third opening 1103 to the second water outlet 522 of the second water treatment device 52 and flows into the second water treatment device 52. The wastewater generated by backwashing the second water treatment device 52 flows from the second water inlet 521 of the second water treatment device 52 to the second opening 1102 of the plane valve 1, and is further discharged through the second channel 102, the ninth channel 109, the tenth channel 1010 and the sewage opening 11010 of the plane valve 1 under the action of water pressure. In other words, although the eighth channel 108 of the planar valve 1 is respectively connected to the fifth channel 105 and the twelfth channel 1012, since the eighth channel 108 is a conductive blind hole, and the fourth channel 104, the eleventh channel 1011, the thirteenth channel 1013, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, the water does not flow through the flow channel formed by them. Therefore, when the plane valve 1 is in the second backwash working position, the first channel 101 of the plane valve 1 is blocked by the second fluid control surface 1220 of the movable valve disc 122, thereby preventing water from flowing through the first opening 1101 of the plane valve 1, so that the flow of water from the second water inlet 521 of the second water treatment device 52 to the first water outlet 512 of the first water treatment device 51 is blocked; although the eighth channel 108 is connected to the fifth channel 105 and the twelfth channel 1012 respectively, since the eighth channel 108 is a conducting blind hole, and the fourth channel 104 and the eleventh channel 1011 are respectively blocked by the second fluid control surface 1220 of the movable valve disc 122 The fluid control surface 1220 is blocked, and since the fourth channel 104 and the eleventh channel 1011 are respectively connected to the fourth opening 1104, water is prevented from flowing through the fourth opening 1104 of the planar valve 1, so that no water flows in the fifth opening 1105. Therefore, the flow of water in the first water treatment device 51 and the third water treatment device 53 is blocked, and no water flows in the first jet opening 11012 connected to the twelfth channel 1012. Since the thirteenth channel 1013 is blocked by the second fluid control surface 1220 of the movable valve plate 122, no water flows in the second jet opening 11013.Accordingly, when the plane valve 1 is in the second backwash working position, the flow of water in the first water inlet 511 and the first water outlet 512 of the first water treatment device 51, and the third water inlet 531 and the third water outlet 532 of the third water treatment device 53 is also blocked, to ensure that only the second water treatment device 52 is backwashed, thereby increasing the intensity of the water flow for backwashing the second water treatment device 52 while preventing the generated sewage from flowing into the first water treatment device 51 and / or the third water treatment device 53. Therefore, when the plane valve 1 is in the second backwash working position, the second water treatment device 52 of the water treatment machine of the present invention is backwashed alone.
[0223] It is worth noting that when the planar valve 1 is in the second backwash working position, the first channel 101, the fourth channel 104, the eleventh channel 1011, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively blocked by the movable valve plate 122, so that the first opening 1101 and the fourth opening 1104 are both blocked. Although the eighth channel 108 is respectively connected to the fifth channel 105 and the twelfth channel 1012, the eighth channel 108 is a conductive blind hole, so that no water flows in the fifth opening 1105. That is, no water flows through the first opening 1101, the fourth opening 1104, and the fifth opening 1105, so that no water flows through the first water treatment device 51 and the third water treatment device 53, ensuring that only the second water treatment device 52 is backwashed. This increases the intensity of the flow of raw water backwashing the second water treatment device 52 while preventing the generated sewage from flowing into the first water treatment device 51 and / or the third water treatment device 53. Therefore, when the plane valve 1 is in the second backwashing working position, the second water treatment device 52 of the water treatment machine of the present invention is backwashed alone.
[0224] As shown in the attached figure Figure 13 and Figure 20C As shown, exemplarily, when the plane valve 1 of the water treatment machine according to the first embodiment of the present utility model is controlled to be in the second backwash working position, the raw water from the plane valve 1 flows into the second water treatment device 52 from the second water outlet 522 of the second water treatment device 52 under the action of water pressure, and then flows from the second central pipe 524 to the second water treatment material 525 and backwashes the second water treatment material 525 under the action of water pressure. The generated sewage flows out from the second water inlet 521 of the second water treatment device 52, and under the action of water pressure, flows to the second opening 1102 of the first valve body 11 of the plane valve 1, and then flows to the sewage opening 11010 through the fourth backwash channel 7104 and is discharged.
[0225] As shown in the attached figure Figure 10G 、 Figure 10H 、 Figure 14 and Figure 20D As shown, the plane valve 1 of the water treatment machine according to the first embodiment of the present invention further has a third backwash working position. When the plane valve 1 of the water treatment machine of the present invention is in the third backwash working position, the seventh channel 107 is connected to the fourteenth channel 1014, thereby forming the fifth backwash flow channel 7105 connected to the second fluid opening 1107 and the fifth opening 1105 respectively, and the ninth channel 109 is connected to the tenth channel 1010 and the eleventh channel 1011 respectively, thereby forming the sixth backwash flow channel 7106 connected to the sewage opening 11010 and the fourth opening 1104 respectively. As shown in the accompanying drawings 7A to 7I 、 Figure 10G 、 Figure 10H and Figure 20D As shown, when the flat valve 1 of the water treatment machine of the present invention is in the third backwash working position, the eighth channel 108 is connected to the second channel 102 and the third channel 103 respectively, the first channel 101, the fourth channel 104, the fifth channel 105, the twelfth channel 1012, the thirteenth channel 1013 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122. As shown in the accompanying drawings 7A to 7I 、 Figure 10G 、 Figure 10H and Figure 20DAs shown, specifically, when the plane valve 1 is in the third backwash working position, although the eighth channel 108 is connected to the second channel 102 and the third channel 103 respectively, since the eighth channel 108 is a conducting blind hole, and the first channel 101, the fourth channel 104, the fifth channel 105, the twelfth channel 1012, the thirteenth channel 1013 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, so that the raw water can only flow from the second fluid opening 1107 of the plane valve 1. The wastewater flows into the seventh channel 107, and further flows through the fourteenth channel 1014 and the fifth opening 1105 to the third water outlet 532 of the third water treatment device 53 and flows into the third water treatment device 53. The wastewater generated by backwashing the third water treatment device 53 flows from the third water inlet 531 of the third water treatment device 53 to the fourth opening 1104 of the plane valve 1, and is further discharged through the eleventh channel 1011, the ninth channel 109, the tenth channel 1010 and the sewage opening 11010 of the plane valve 1 under the action of water pressure. In other words, although the eighth channel 108 is respectively connected to the second channel 102 and the third channel 103, the eighth channel 108 is a conducting blind hole, and since the first channel 101 is blocked by the movable valve plate 122, the first channel 101, the first opening 1101, the first water treatment device 51, the second opening 1102 (and the second channel 102), the second water treatment device 52, the third opening 1103, the third channel 103, the eighth channel 108 and the second channel 102 form a closed connecting channel isolated from the raw water, and water cannot flow freely therein. In other words, when the planar valve 1 is in the third backwashing position, the flow of water in the first opening 1101, the second opening 1102, and the third opening 1103 of the first valve body 11 of the planar valve 1 is blocked. Therefore, even if the eighth passage 108 of the planar valve 1 is connected to the second passage 102 and the third passage 103, respectively, no flow path is formed to allow water to flow through. Therefore, the flow of water in the first water treatment device 51 and the second water treatment device 52 is blocked. Accordingly, when the plane valve 1 is in the third backwashing working position, the flow of water in the first water inlet 511 and the first water outlet 512 of the first water treatment device 51, and the second water inlet 521 and the second water outlet 522 of the second water treatment device 52 is also blocked, to ensure that only the third water treatment device 53 is backwashed, and while increasing the intensity of the water flow for backwashing the third water treatment device 53, the generated sewage is prevented from flowing into the first water treatment device 51 and / or the second water treatment device 52. Therefore, when the plane valve 1 is in the third backwashing working position, the third water treatment device 53 of the water treatment machine of the present invention is backwashed alone.
[0226] It is worth noting that when the plane valve 1 is in the third backwash working position, the first channel 101 is blocked by the movable valve plate 122, so that the first opening 1101 is blocked. Even if the eighth channel 108 is connected to the second channel 102 and the third channel 103 respectively, the eighth channel 108 is a conducting blind hole, thereby isolating the first water treatment device 51 and the second water treatment device 52 from the water flow, and no water flows out or in through the first opening 1101, the second opening 1102 and the third opening 1103, so as to ensure that only the third water treatment device 53 is backwashed, thereby increasing the intensity of the raw water flow for backwashing the third water treatment device 53 while preventing the generated sewage from flowing into the first water treatment device 51 and / or the second water treatment device 52. Therefore, when the plane valve 1 is in the third backwash working position, the third water treatment device 53 of the water treatment machine of the present invention is backwashed separately.
[0227] As shown in the attached figure Figure 14 and Figure 20D As shown, exemplarily, when the plane valve 1 of the water treatment machine according to the first embodiment of the present utility model is controlled to be in the third backwash working position, the raw water from the plane valve 1 flows into the third water treatment device 53 from the third water outlet 532 of the third water treatment device 53 under the action of water pressure, and then flows from the third central pipe 534 to the third water treatment material 535 and backwashes the third water treatment material 535 under the action of water pressure. The generated sewage flows out from the third water inlet 531 of the third water treatment device 53, and under the action of water pressure, flows to the fourth opening 1104 of the first valve body 11 of the plane valve 1, and then flows to the sewage opening 11010 through the sixth backwash channel 7106 and is discharged.
[0228] As shown in the attached figure Figure 10I 、 Figure 10J 、 Figure 15 and Figure 20E As shown, the plane valve 1 of the water treatment machine according to the first embodiment of the present invention further has a first positive flushing working position. When the plane valve 1 of the water treatment machine of the present invention is in the first positive flushing working position, the seventh channel 107 of the plane valve 1 is connected with the first channel 101, thereby forming the first positive flushing flow channel 7201 connected with the second fluid opening 1107 and the first opening 1101 respectively, and the ninth channel 109 is connected with the tenth channel 1010 and the second channel 102 respectively, thereby forming the second positive flushing flow channel 7202 connected with the sewage opening 11010 and the second opening 1102 respectively. As shown in the accompanying drawings 7A to 7I 、 Figure 10I 、 Figure 10J and Figure 20EAs shown, when the flat valve 1 of the water treatment machine of the present invention is in the first positive flushing working position, the eighth channel 108 is connected to the first channel 101 and the fourteenth channel 1014 respectively, the third channel 103, the fourth channel 104, the fifth channel 105, the eleventh channel 1011, the twelfth channel 1012, the thirteenth channel 1013 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122. As shown in the accompanying drawings 7A to 7I 、 Figure 10I 、 Figure 10J and Figure 20EAs shown, when the plane valve 1 is in the first positive flushing working position, although the eighth channel 108 of the plane valve 1 is connected to the first channel 101 and the fourteenth channel 1014 respectively, since the eighth channel 108 is a conducting blind hole, and the third channel 103, the fourth channel 104, the fifth channel 105, the eleventh channel 1011, the twelfth channel 1012, the thirteenth channel 1013 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, so that the raw water can only flow from the first channel 101 to the fourth channel 1014 of the plane valve 1. The second fluid opening 1107 flows into the seventh channel 107, and further flows through the first channel 101 and the first opening 1101 to the first water inlet 511 of the first water treatment device 51 and flows into the first water treatment device 51. The wastewater generated by forward flushing the first water treatment device 51 flows from the first water outlet 512 of the first water treatment device 51 to the second opening 1102 of the plane valve 1, and is further discharged through the second channel 102, the ninth channel 109, the tenth channel 1010 and the sewage opening 11010 of the plane valve 1 under the action of water pressure. In other words, although the eighth channel 108 of the plane valve 1 is connected to the first channel 101 and the fourteenth channel 1014 respectively, since the eighth channel 108 is a conducting blind hole, and the fourth channel 104, the fifth channel 105, the eleventh channel 1011 and the fifteenth channel 1015 are blocked by the second fluid control surface 1220 of the movable valve plate 122, and since the fourth channel 104 and the eleventh channel 1011 are connected to the fourth opening 1104 respectively, the fifth channel 105 is blocked by the second fluid control surface 1220 of the movable valve plate 122. , the fourteenth channel 1014 and the fifteenth channel 1015 are respectively connected to the fifth opening 1105, thereby preventing water from flowing through the fourth opening 1104 and the fifth opening 1105 of the plane valve 1; because the third channel 103 is blocked by the second fluid control surface 1220 of the movable valve plate 122, the wastewater generated by forward flushing the first water treatment device 51 is prevented from flowing out of the first water outlet 512 of the first water treatment device 51 to the second water inlet 521 of the second water treatment device 52. Correspondingly, when the planar valve 1 is in the first positive flushing working position, the eighth channel 108 is connected to the first channel 101 and the fourteenth channel 1014 respectively, and the third channel 103, the fourth channel 104, the fifth channel 105, the eleventh channel 1011 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, thereby preventing water from flowing through the third opening 1103, the fourth opening 1104 and the fifth opening 1105 of the planar valve 1. Therefore, the water flow is prevented from flowing through the third opening 1103, the fourth opening 1104 and the fifth opening 1105 of the planar valve 1, thereby preventing the flow of water in the second water treatment device 52 and the third water treatment device 53.In other words, although the eighth channel 108 is respectively connected to the first channel 101 and the fourteenth channel 1014, the movable valve plate 122 blocks the raw water from flowing to the third channel 103, the fourth channel 104, the fifth channel 105, the eleventh channel 1011 and the fifteenth channel 1015, so that the water flows only to the first water treatment device 51 and the first water treatment device 51 is flushed forward.
[0229] It is worth noting that when the planar valve 1 is in the first positive flushing working position, the third channel 103, the fourth channel 104, the fifth channel 105, the eleventh channel 1011 and the fifteenth channel 1015 are respectively blocked by the movable valve plate 122. Although the eighth channel 108 is respectively connected to the first channel 101 and the fourteenth channel 1014, the eighth channel 108 is a conductive blind hole, so that no water flows out or in through the third opening 1103, the fourth opening 1104 and the fifth opening 1105, so that no water flows in the second water treatment device 52 and the third water treatment device 53, to ensure that only the first water treatment device 51 is positively flushed, thereby increasing the intensity of the water flow of the raw water for positive flushing the first water treatment device 51, and preventing the generated sewage from flowing into the second water treatment device 52 and / or the third water treatment device 53. Therefore, when the plane valve 1 is in the first positive flushing working position, the first water treatment device 51 of the water treatment machine of the present invention is flushed forward alone.
[0230] As shown in the attached figure Figure 15 and Figure 20E As shown, exemplarily, when the plane valve 1 of the water treatment machine according to the first embodiment of the present utility model is controlled to be in the first positive flushing working position, the raw water from the plane valve 1 flows into the first water treatment device 51 from the first water inlet 511 of the first water treatment device 51 under the action of water pressure, and then positively flushes the first water treatment material 515 under the action of water pressure. The generated sewage is collected by the first central pipe 514 and flows out from the first water outlet 512 of the first water treatment device 51, and flows to the second opening 1102 of the plane valve 1 under the action of water pressure, and then flows to the sewage opening 11010 through the second positive flushing channel 7202 and is discharged.
[0231] As shown in the attached figure Figure 10K 、 Figure 10L 、 Figure 16 and Figure 20FAs shown, the plane valve 1 of the water treatment machine according to the first embodiment of the present invention further has a second positive flushing working position. When the plane valve 1 of the water treatment machine of the present invention is in the second positive flushing working position, the seventh channel 107 of the plane valve 1 is connected with the second channel 102, thereby forming the third positive flushing flow channel 7203 connected with the second fluid opening 1107 and the second opening 1102 respectively, and the ninth channel 109 is connected with the tenth channel 1010 and the third channel 103 respectively, thereby forming the fourth positive flushing flow channel 7204 connected with the sewage opening 11010 and the third opening 1103 respectively. As shown in the accompanying drawings 7A to 7I 、 Figure 10K 、 Figure 10L and Figure 20F As shown, when the flat valve 1 of the water treatment machine of the present invention is in the second positive flushing working position, the eighth channel 108 is connected to the first channel 101 and the fifteenth channel 1015 respectively, the fourth channel 104, the fifth channel 105, the eleventh channel 1011, the twelfth channel 1012, the thirteenth channel 1013 and the fourteenth channel 1014 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122. As shown in the accompanying drawings 7A to 7I 、 Figure 10K 、 Figure 10L and Figure 20FAs shown, specifically, when the plane valve 1 is in the second positive flushing working position, although the eighth channel 108 of the plane valve 1 is connected to the first channel 101 and the fifteenth channel 1015 respectively, since the eighth channel 108 is a conducting blind hole, and the fourth channel 104, the fifth channel 105, the eleventh channel 1011, the twelfth channel 1012, the thirteenth channel 1013 and the fourteenth channel 1014 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, so that the raw water can only flow from the second fluid control surface 1220 of the plane valve 1. The opening 1107 flows into the seventh channel 107, and further flows through the second channel 102 and the second opening 1102 to the second water inlet 521 of the second water treatment device 52 and into the second water treatment device 52. The wastewater generated by forward flushing the second water treatment device 52 flows from the second water outlet 522 of the second water treatment device 52 to the third opening 1103 of the plane valve 1, and is further discharged through the third channel 103, the ninth channel 109, the tenth channel 1010, and the sewage opening 11010 of the plane valve 1 under the action of water pressure. In other words, although the eighth channel 108 is connected to the first channel 101 and the fifteenth channel 1015 respectively, because the eighth channel 108 is a conductive blind hole, the water does not flow through the flow channel formed by them. Accordingly, when the plane valve 1 is in the second positive flushing working position, because the eighth channel 108 is connected to the first channel 101 and the fifteenth channel 1015 respectively, the second channel 102, the second opening 1102, the first water treatment device 51, the first opening 1101, the first channel 101, the eighth channel 108, the fifteenth channel 1015, the fifth opening 1105, the third water treatment device 53, the fourth opening 1104 and the fourth channel 104 (the eleventh channel 1011) form a flow channel, but due to the fourth channel The fourth channel 104, the fifth channel 105, the eleventh channel 1011 and the fourteenth channel 1014 are all blocked by the movable valve disc 122, so that the fourth opening 1104 is blocked, so that the water flow cannot flow through the flow path formed by the second channel 102, the second opening 1102, the first water treatment device 51, the first opening 1101, the first channel 101, the eighth channel 108, the fifteenth channel 1015, the fifth opening 1105, the third water treatment device 53, the fourth opening 1104 and the fourth channel 104 (the eleventh channel 1011). Further, when the plane valve 1 is in the second positive flushing working position, the fourth channel 104 and the eleventh channel 1011 are all blocked by the movable valve disc 122, so that the water flow cannot flow from the fourth opening 1104 to the third water treatment device 53, or from the third water treatment device 53 to the fourth opening 1104.In other words, the flow of flushing water flowing out of the second opening 1102 to the first water outlet 512 of the first water treatment device 51 is blocked, so that the water flow is blocked from flowing through the first water treatment device 51 and the third water treatment device 53, thereby ensuring that only the second water treatment device 52 is flushed in the forward direction.
[0232] It is worth noting that when the planar valve 1 is in the second positive flushing working position, the fourth channel 104, the fifth channel 105, the eleventh channel 1011 and the fourteenth channel 1014 are respectively blocked by the movable valve plate 122. Although the eighth channel 108 is respectively connected to the first channel 101 and the fifteenth channel 1015, the eighth channel 108 is a conductive blind hole, so that no water flows out or in through the first opening 1101, the fourth opening 1104 and the fifth opening 1105. That is to say, there is no water flowing in the first water treatment device 51 and the third water treatment device 53 to ensure that only the second water treatment device 52 is positively flushed, thereby increasing the intensity of the water flow of the raw water for positive flushing the second water treatment device 52, while also preventing the generated sewage from flowing into the first water treatment device 51 and / or the third water treatment device 53. Therefore, when the plane valve 1 is in the second positive flushing working position, the second water treatment device 52 of the water treatment machine of the present invention is flushed forward alone.
[0233] As shown in the attached figure Figure 16 and Figure 20F As shown, exemplarily, when the plane valve 1 of the water treatment machine according to the first embodiment of the present utility model is controlled to be in the second positive flushing working position, the raw water from the plane valve 1 flows into the second water treatment device 52 from the second water inlet 521 of the second water treatment device 52 under the action of water pressure, and then positively flushes the second water treatment material 525 under the action of water pressure. The generated sewage is collected by the second central pipe 524 and flows out from the second water outlet 522 of the second water treatment device 52, and flows to the third opening 1103 of the plane valve 1 under the action of water pressure, and then flows to the sewage opening 11010 through the fourth positive flushing channel 7204 and is discharged.
[0234] As shown in the attached figure Figure 10M 、 Figure 10N 、 Figure 17 and Figure 20GAs shown, the plane valve 1 of the water treatment machine according to the first embodiment of the present invention further has a third positive flushing working position. When the plane valve 1 of the water treatment machine of the present invention is in the third positive flushing working position, the seventh channel 107 of the plane valve 1 is connected to the eleventh channel 1011, thereby forming the fifth positive flushing flow channel 7205 connected to the second fluid opening 1107 and the fourth opening 1104 respectively, and the ninth channel 109 is connected to the tenth channel 1010 and the fourteenth channel 1014 respectively, thereby forming the sixth positive flushing flow channel 7206 connected to the sewage opening 11010 and the fifth opening 1105 respectively. As shown in the accompanying drawings 7A to 7I 、 Figure 10M 、 Figure 10N and Figure 20G As shown, when the flat valve 1 of the water treatment machine of the present invention is in the third positive flushing working position, the eighth channel 108 is connected to the first channel 101 and the second channel 102 respectively, the third channel 103, the fourth channel 104, the fifth channel 105, the twelfth channel 1012, the thirteenth channel 1013 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122. As shown in the accompanying drawings 7A to 7I 、 Figure 10M 、 Figure 10N and Figure 20GAs shown, specifically, when the plane valve 1 is in the third positive flushing working position, although the eighth channel 108 is connected to the first channel 101 and the second channel 102 respectively, since the eighth channel 108 is a conducting blind hole, and the third channel 103, the fourth channel 104, the fifth channel 105, the twelfth channel 1012, the thirteenth channel 1013 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, so that the raw water can only flow from the second fluid opening 1107 of the plane valve 1. The wastewater flows into the seventh channel 107, and further flows through the eleventh channel 1011 and the fourth opening 1104 to the third water inlet 531 of the third water treatment device 53 and flows into the third water treatment device 53. The wastewater generated by forward flushing the third water treatment device 53 flows from the third water outlet 532 of the third water treatment device 53 to the fifth opening 1105 of the plane valve 1, and is further discharged through the fourteenth channel 1014, the ninth channel 109, the tenth channel 1010 and the sewage opening 11010 of the plane valve 1 under the action of water pressure. In other words, although the eighth channel 108 is respectively connected to the first channel 101 and the second channel 102, the eighth channel 108 is a conducting blind hole, and since the third channel 103 is blocked by the movable valve plate 122, the eighth channel 108, the first channel 101, the first opening 1101, the first water treatment device 51, the second opening 1102 (the second channel 102, the eighth channel 108), the second water treatment device 52, the third opening 1103 and the third channel 103 form a closed connecting channel isolated from the raw water, and water cannot flow freely therein. Accordingly, when the plane valve 1 is in the third positive flushing position, the flow of water in the first opening 1101, the second opening 1102, and the third opening 1103 of the first valve body 11 of the plane valve 1 is blocked, so that even if the eighth channel 108 of the plane valve 1 is connected to the first channel 101 and the second channel 102, respectively, no flow path is formed to allow water to flow. Therefore, the flow of water in the first water treatment device 51 and the second water treatment device 52 is blocked. Accordingly, when the plane valve 1 is in the third positive flushing position, the flow of water in the first water inlet 511 and the first water outlet 512 of the first water treatment device 51, and the second water inlet 521 and the second water outlet 522 of the second water treatment device 52 is also blocked, to ensure that only the third water treatment device 53 is forward flushed, and while increasing the intensity of the water flow for forward flushing the third water treatment device 53, prevent the generated sewage from flowing into the first water treatment device 51 and / or the second water treatment device 52. Therefore, when the plane valve 1 is in the third positive flushing position, the third water treatment device 53 of the water treatment machine of the present invention is forward flushed alone.
[0235] It is worth noting that when the plane valve 1 is in the third positive flushing working position, the third channel 103 is blocked by the movable valve plate 122, so that the third opening 1103 is blocked. Even if the eighth channel 108 is connected to the first channel 101 and the second channel 102 respectively, the eighth channel 108 is a conductive blind hole, thereby isolating the first water treatment device 51 and the second water treatment device 52 from the water flow, and no water flows out or in through the first opening 1101, the second opening 1102 and the third opening 1103, so as to ensure that only the third water treatment device 53 is positively flushed, thereby increasing the intensity of the raw water flow for positively flushing the third water treatment device 53, and preventing the generated sewage from flowing into the first water treatment device 51 and / or the second water treatment device 52. Therefore, when the plane valve 1 is in the third positive flushing working position, the third water treatment device 53 of the water treatment machine of the utility model is separately positively flushed.
[0236] As shown in the attached figure Figure 17 and Figure 20G As shown, exemplarily, when the plane valve 1 of the water treatment machine according to the first embodiment of the present utility model is controlled to be in the third positive flushing working position, the raw water from the plane valve 1 flows into the third water treatment device 53 from the third water inlet 531 of the third water treatment device 53 under the action of water pressure, and then positively flushes the third water treatment material 535 under the action of water pressure. The generated sewage is collected by the third central pipe 534 and flows out from the third water outlet 532 of the third water treatment device 53, and flows to the fifth opening 1105 of the plane valve 1 under the action of water pressure, and then flows to the sewage opening 11010 through the sixth positive flushing channel 7206 and is discharged.
[0237] As shown in the attached figure Figure 10O 、 Figure 10P 、 Figure 18A 、 Figure 18B and Figure 20H As shown, the flat valve 1 of the water treatment machine according to the first embodiment of the present invention further has a regeneration working position. When the flat valve 1 is in the regeneration working position, the seventh channel 107 is connected to the twelfth channel 1012, thereby forming the first regeneration flow channel 7301 connected to the second fluid opening 1107 and the first jet opening 11012 respectively. The eighth channel 108 is connected to the thirteenth channel 1013 and the eleventh channel 1011 respectively, thereby forming the second regeneration flow channel 7302 connected to the second jet opening 11013 and the fourth opening 1104 respectively. The ninth channel 109 is connected to the tenth channel 1010 and the fifteenth channel 1015 respectively, thereby forming the third regeneration flow channel 7303 connected to the sewage opening 11010 and the fifth opening 1105 respectively. As shown in the accompanying drawings 7A to 7I 、 Figure 10O 、 Figure 10P and Figure 20H As shown, when the planar valve 1 is in the regeneration working position, the first channel 101, the second channel 102, the third channel 103, the fourth channel 104, the fifth channel 105 and the fourteenth channel 1014 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122. Therefore, when the plane valve 1 of the water treatment machine of the present invention is in the regeneration working position, the raw water flows into the second fluid opening 1107 of the valve body 10 of the plane valve 1 under the action of water pressure, flows through the first regeneration flow channel 7301 (the seventh channel 107 and the twelfth channel 1012) to the first jet opening 11012 of the first valve body 11, and then flows into the ejection port 182 of the ejector 18. After the ejection of the ejector 18, the salt solution (such as sodium chloride solution) from the salt absorption port 181 is mixed to form a regeneration solution. The regeneration solution flows into the second jet opening 111 of the first valve body 11 through the ejection port 183 of the ejector 18. 013, then flows into the fourth opening 1104 of the first valve body 11 through the second regeneration flow channel 7302 (the thirteenth channel 1013, the eighth channel 108 and the eleventh channel 1011), and the regeneration solution flows into the third water treatment device 53 from the third water inlet 531, regenerating the third water treatment material 535 downstream, such as after softening the resin. The wastewater generated after regeneration flows out from the third water outlet 532, and then flows out through the fifth opening 1105 of the first valve body 11, the third regeneration flow channel 7303 (the fifteenth channel 1015, the ninth channel 109 and the tenth channel 1010) and the sewage outlet 11010 in sequence. As shown in the accompanying drawings 7A to 7I 、 Figure 10O 、 Figure 10P and Figure 20HAs shown, specifically, when the plane valve 1 is in the regeneration working position, the first channel 101, the second channel 102, the third channel 103, the fourth channel 104, the fifth channel 105 and the fourteenth channel 1014 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, so that the raw water can only flow into the seventh channel 107 from the second fluid opening 1107 of the plane valve 1, and further through the twelfth channel 1012, the first jet opening 11012, the ejector 18, the second jet opening 11013, the thirteenth channel 101 3. The eighth channel 108, the eleventh channel 1011 and the fourth opening 1104 flow toward the third water inlet 531 of the third water treatment device 53 and into the third water treatment device 53, regenerating the softening material (for example, softening resin) of the third water treatment device 53 downstream, and the generated wastewater flows from the third water outlet 532 of the third water treatment device 53 to the fifth opening 1105 of the plane valve 1, and is further discharged through the fifteenth channel 1015, the ninth channel 109, the tenth channel 1010 and the sewage opening 11010 of the plane valve 1 under the action of water pressure. Correspondingly, when the planar valve 1 is in the regeneration working position, the first channel 101, the second channel 102 and the third channel 103 are all blocked by the movable valve plate 122, thereby preventing water from flowing through the first opening 1101, the second opening 1102 and the third opening 1103 of the planar valve 1; the water flow is prevented from flowing through the first opening 1101, the second opening 1102 and the third opening 1103 of the planar valve 1, thereby preventing the flow of water in the first water treatment device 51 and the second water treatment device 52, thereby ensuring that only the third water treatment device 53 is regenerated downstream.
[0238] It is worth noting that when the planar valve 1 is in the regeneration working position, the first channel 101, the second channel 102, and the third channel 103 are respectively blocked by the movable valve plate 122, so that the first opening 1101, the second opening 1102 and the third opening 1103 are blocked, that is, the first water treatment device 51 and the second water treatment device 52 are isolated from the water flow to ensure that only the third water treatment device 53 is regenerated downstream, thereby increasing the intensity of the water flow of the regeneration solution for downstream regeneration of the third water treatment device 53, while also preventing the generated sewage from flowing to the first water treatment device 51 and / or the second water treatment device 52. In particular, it is necessary to prevent the regeneration salt solution (or the sewage wastewater after the regeneration resin, because the sewage wastewater has a higher salt content) from entering the first water treatment device 51 and / or the second water treatment device 52, because in actual use, the first water treatment device 51 or the second water treatment device 52 is often other adsorbent filter materials such as activated carbon, and the regeneration salt solution will contaminate the filter materials such as activated carbon, thereby weakening the purification capacity of the first water treatment device 51 or the second water treatment device 52. This is also a major reason why the multi-stage purification and softening water treatment equipment cannot simply use the activated carbon water treatment device and the softening resin water treatment device directly in series. Therefore, when the plane valve 1 is in the regeneration working position, the third water treatment device 53 of the water treatment machine of the present invention is regenerated separately downstream.
[0239] As shown in the attached figure Figure 18A 、 Figure 18B and Figure 20H As shown, exemplarily, when the plane valve 1 of the water treatment machine according to the first embodiment of the present utility model is controlled to be in the regeneration working position, the raw water from the plane valve 1 is mixed with the salt solution from the ejector 18 under the action of water pressure to form a regeneration solution, which flows into the third water treatment device 53 from the third water inlet 531 of the third water treatment device 53, and then regenerates the third water treatment material 535 downstream under the action of water pressure. The generated sewage is collected by the third central pipe 534 and flows out from the third water outlet 532 of the third water treatment device 53, and flows to the fifth opening 1105 of the plane valve 1 under the action of water pressure, and then flows to the sewage opening 11010 through the third regeneration flow channel 7303 and is discharged.
[0240] As shown in the attached figure Figure 10Q 、 Figure 10R 、 Figure 19 and Figure 20I As shown, the plane valve 1 of the water treatment machine according to the first embodiment of the present invention further has a water replenishment working position. When the plane valve 1 is in the water replenishment working position, the seventh channel 107 is connected to the thirteenth channel 1013, thereby forming the water replenishment flow channel 7401 connected to the second fluid opening 1107 and the second jet opening 11013 respectively. 7A to 7I 、 Figure 10Q 、 Figure 10R and Figure 20I As shown, when the planar valve 1 is in the water replenishment working position, the eighth channel 108 is respectively connected to the first channel 101 and the fifteenth channel 1015, the ninth channel 109 is respectively connected to the tenth channel 1010 and the fourth channel 104, the second channel 102, the third channel 103, the fifth channel 105, the eleventh channel 1011, the twelfth channel 1012 and the fourteenth channel 1014 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122. Therefore, when the plane valve 1 of the water treatment machine of the present invention is in the water replenishment working position, the raw water flows into the second fluid opening 1107 of the valve body 10 of the plane valve 1 under the action of water pressure, flows into the second jet opening 11013 through the seventh channel 107 and the thirteenth channel 1013, and then flows into the regeneration solution tank 31 through the injection port 183 of the ejector 18, the salt absorption port 181 and the salt absorption pipe 184 in sequence for water replenishment. Although the eighth channel 108 is connected to the first channel 101 and the fifteenth channel 1015 respectively, and the ninth channel 109 is connected to the tenth channel 1010 and the fourth channel 104 respectively, since the second channel 102, the third channel 103, the fifth channel 105, the eleventh channel 1011, the twelfth channel 1012 and the fourteenth channel 1014 are blocked by the movable valve plate 122 respectively, the eighth channel 108 is a conducting blind hole, and the ninth channel 109 is a conducting through hole, so that the tenth channel 1010, the ninth channel 109, the fourth channel 104 (the eleventh channel 1011), the fourth open hole The opening 1104, the third water treatment device 53, the fifth opening 1105, the fifteenth channel 1015 (the fifth channel 105, the fourteenth channel 1014), the eighth channel 108, the first channel 101, the first opening 1101, the first water treatment device 51, the second opening 1102, the second channel 102, the second water treatment device 52, the third opening 1103, and the third channel 103 form a flow channel isolated from the raw water, so that water cannot flow through the first opening 1101, the second opening 1102, the third opening 1103, the fourth opening 1104, and the fifth opening 1105. In other words, although the eighth channel 108 is connected to the first channel 101 and the fifteenth channel 1015 respectively, and the ninth channel 109 is connected to the tenth channel 1010 and the fourth channel 104 respectively, they cannot form a flow channel that allows water to flow.
[0241] It is worth noting that conventional planar valves utilize a valve core structure with a single movable valve disc and a single fixed valve disc. The movable valve disc often requires a conducting blind hole to guide the water flow toward the outlet. When water flows through the guiding blind hole, the flow direction changes 360 degrees, causing significant resistance to the water flow and a significant loss of kinetic energy, resulting in a significant reduction in the water flow rate. The planar valve 1 of the water treatment machine of the present invention utilizes a three-valve disc structure. Water flowing toward the outlet flows upward from the lower valve disc (first fixed valve disc 121), with the outlet located on the upper valve disc (second fixed valve disc 123). This results in a relatively small (approximate) change in the water flow direction, and the water flow encounters relatively little resistance during the change in direction, significantly reducing the loss of water flow rate. Furthermore, in existing planar valves with a single fixed valve disc, the channel for controlling the flow direction of the water flow, which is provided on the fixed valve disc, can only be provided on the single fixed valve disc. To ensure the water flow rate, the diameter of the fixed valve disc of the planar valve and the overall volume of the planar valve are large. The larger the diameter of a planar valve, the more difficult it is to ensure the stability of the movable valve disc during rotation. To ensure the stability of the entire planar valve, the cross-sectional area of the planar valve increases, requiring a thicker valve body and a corresponding increase in the thickness of the movable valve disc. This not only increases the manufacturing cost of the planar valve, but also makes the entire planar valve heavier and more difficult to operate.
[0242] As shown in the attached figure Figures 6C to 10RAs shown, the first channel 101 of the planar valve 1 of the water treatment machine according to the first embodiment of the present utility model has a first connecting portion 10101 and a second connecting portion 10102, wherein the first connecting portion 10101 of the first channel 101 is connected to the first opening 1101, and the second connecting portion 10102 of the first channel 101 is connected to the first opening 1101. Preferably, the first channel 101 of the planar valve 1 further has a third communication portion 10103 extending between the first communication portion 10101 and the second communication portion 10102. The first communication portion 10101 of the first channel 101 is connected to the first opening 1101, and the second communication portion 10102 of the first channel 101 is connected to the first communication portion 10101 via the third communication portion 10103. In other words, the second communication portion 10102 of the first channel 101 is connected to the first opening 1101 via the third communication portion 10103 and the first communication portion 10101. Preferably, the fifteenth channel 1015 of the planar valve 1 is disposed outside the third communication portion 10103. The second channel 102 of the planar valve 1 has a first conducting portion 10201 and a second conducting portion 10202 , wherein the first conducting portion 10201 of the second channel 102 is connected to the second opening 1102 , and the second conducting portion 10202 of the second channel 102 is connected to the second opening 1102 . Preferably, the second channel 102 of the planar valve 1 further has a third conducting portion 10203 extending between the first conducting portion 10201 and the second conducting portion 10202. The first conducting portion 10201 of the second channel 102 is connected to the second opening 1102, and the second conducting portion 10202 of the second channel 102 is connected to the first conducting portion 10201 via the third conducting portion 10203. In other words, the second conducting portion 10202 of the second channel 102 is connected to the second opening 1102 via the third conducting portion 10203 and the first conducting portion 10201. Preferably, the twelfth channel 1012, the fifth channel 105, the eleventh channel 1011, and the thirteenth channel 1013 of the planar valve 1 are disposed outside the third conducting portion 10203.When the plane valve 1 is in the water treatment working position, the seventh channel 107 of the plane valve 1 is connected to the first connecting portion 10101 of the first channel 101, the eighth channel 108 is connected to the third channel 103 and the fourth channel 104 respectively, the ninth channel 109 is connected to the fifth channel 105 and the sixth channel 106 respectively, the eleventh channel 1011, the twelfth channel 1012, the thirteenth channel 1013, the fourteenth channel 1014 and the tenth channel 106 are connected. The five channels 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, the second connecting part 10102, the third connecting part 10103 of the first channel 101, the first conductive part 10201, the second conductive part 10202 and the third conductive part 10203 of the second channel 102 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the tenth channel 1010 is blocked by the third fluid control surface 1223 of the movable valve plate 122. When the plane valve 1 is in the first backwash working position, the seventh channel 107 of the plane valve 1 is connected to the second conducting portion 10202 of the second channel 102, the ninth channel 109 is connected to the tenth channel 1010 and the second communicating portion 10102 of the first channel 101, the eighth channel 108 is connected to the fifth channel 105 and the eleventh channel 1011, the third channel 103, the fourth channel 104, the twelfth channel 1012, the thirteenth channel 1013, the 013, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, the first connecting portion 10101 of the first channel 101, the third connecting portion 10103, the first conducting portion 10201 and the third conducting portion 10203 of the second channel 102 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122.When the plane valve 1 is in the second backwash working position, the seventh channel 107 of the plane valve 1 is connected to the third channel 103, the ninth channel 109 is connected to the tenth channel 1010 and the first conducting portion 10201 of the second channel 102, the eighth channel 108 is connected to the fifth channel 105 and the twelfth channel 1012, the fourth channel 104, the eleventh channel 1011, the thirteenth channel 1013, the fourteenth channel 1014 and the fourth channel 105 are connected. The fifteen channels 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, the first connecting part 10101, the second connecting part 10102, the third connecting part 10103 of the first channel 101, the second conducting part 10202 and the third conducting part 10203 of the second channel 102 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122. When the plane valve 1 is in the third backwash working position, the seventh channel 107 is connected to the fourteenth channel 1014, the ninth channel 109 is connected to the tenth channel 1010 and the eleventh channel 1011 respectively, the eighth channel 108 is connected to the second conducting portion 10202 of the second channel 102 and the third channel 103 respectively, the fourth channel 104, the fifth channel 105, the twelfth channel 1012, the thirteenth channel 1013 and the fifteenth channel The sixth channel 1015 is respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, the first connecting part 10101, the second connecting part 10102, the third connecting part 10103 of the first channel 101, the first conducting part 10201 and the third conducting part 10203 of the second channel 102 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122.When the plane valve 1 is in the first positive flushing working position, the seventh channel 107 of the plane valve 1 is connected to the second communicating portion 10102 of the first channel 101, the ninth channel 109 is connected to the tenth channel 1010 and the second conducting portion 10202 of the second channel 102, the eighth channel 108 is connected to the first communicating portion 10101 of the first channel 101 and the fourteenth channel 1014, respectively, the third channel 103, the fourth channel 104, the fifth channel 105, the fourth channel 106, the fifth channel 107 and the fifth channel 108 are connected to the tenth channel 1010 and the second conducting portion 10202 of the second channel 102, respectively. The eleventh channel 1011, the twelfth channel 1012, the thirteenth channel 1013 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, the third connecting portion 10103 of the first channel 101, the first conducting portion 10201 and the third conducting portion 10203 of the second channel 102 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122. When the plane valve 1 is in the second positive flushing working position, the seventh channel 107 of the plane valve 1 is connected to the first conducting portion 10201 of the second channel 102, the ninth channel 109 is connected to the tenth channel 1010 and the third channel 103 respectively, the eighth channel 108 is connected to the first communicating portion 10101 of the first channel 101 and the fifteenth channel 1015 respectively, the fourth channel 104, the fifth channel 105, the eleventh channel 1011, the twelfth channel 101 012, the thirteenth channel 1013 and the fourteenth channel 1014 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, the second connecting portion 10102, the third connecting portion 10103 of the first channel 101, the second conducting portion 10202 and the third conducting portion 10203 of the second channel 102 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122.When the plane valve 1 is in the third positive flushing working position, the seventh channel 107 of the plane valve 1 is connected to the eleventh channel 1011, the ninth channel 109 is connected to the tenth channel 1010 and the fourteenth channel 1014 respectively, the eighth channel 108 is connected to the second communicating portion 10102 of the first channel 101 and the first conducting portion 10201 of the second channel 102 respectively, the third channel 103, the fourth channel 104, the fifth channel 105, the twelfth channel 106 and the like. 012, the thirteenth channel 1013 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, the first connecting part 10101 of the first channel 101, the third connecting part 10103, the second conducting part 10202 and the third conducting part 10203 of the second channel 102 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122. When the plane valve 1 is in the regeneration working position, the seventh channel 107 is connected to the twelfth channel 1012, the eighth channel 108 is connected to the thirteenth channel 1013 and the eleventh channel 1011 respectively, the ninth channel 109 is connected to the tenth channel 1010 and the fifteenth channel 1015 respectively, and the third channel 103, the fourth channel 104, the fifth channel 105 and the fourteenth channel 1014 are respectively connected to the first channel 1013 of the movable valve plate 122. The second fluid control surface 1220 is blocked, the first connecting part 10101, the second connecting part 10102, the third connecting part 10103 of the first channel 101, the first conductive part 10201, the second conductive part 10202 and the third conductive part 10203 of the second channel 102 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122. When the plane valve 1 is in the water replenishing working position, the seventh channel 107 is connected to the thirteenth channel 1013, the eighth channel 108 is connected to the second connecting portion 10102 of the first channel 101 and the fifteenth channel 1015 respectively, the ninth channel 109 is connected to the tenth channel 1010 and the fourth channel 104 respectively, the third channel 103, the fifth channel 105, the eleventh channel 1011, the twelfth channel 1012 and the fourteenth channel 1014 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, the first connecting part 10101, the third connecting part 10103 of the first channel 101, the first conducting part 10201, the second conducting part 10202 and the third conducting part 10203 of the second channel 102 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122.Preferably, the third communication portion 10103 of the first channel 101 is disposed on the first fluid control surface 1210 of the first fixed valve disc 121 of the planar valve 1. Optionally, the third communication portion 10103 of the first channel 101 is disposed inside the first fixed valve disc 121 of the planar valve 1. Optionally, the third communication portion 10103 of the first channel 101 is disposed inside the first valve body 11 of the planar valve 1. Preferably, the third conduction portion 10203 of the second channel 102 is disposed on the first fluid control surface 1210 of the first fixed valve disc 121 of the planar valve 1. Optionally, the third conduction portion 10203 of the second channel 102 is disposed inside the first fixed valve disc 121 of the planar valve 1. Optionally, the third conduction portion 10203 of the second channel 102 is disposed inside the first valve body 11 of the planar valve 1.
[0243] As shown in the attached figure 7A to 9DAs shown, the first fluid control surface 1210 of the first fixed valve plate 121 of the plane valve 1 of the water treatment machine according to the first embodiment of the present utility model forms a central portion 12101, an edge portion 12102 extending outward from the central portion 12101, the first communicating portion 10101 of the first channel 101 of the plane valve 1, the fourteenth channel 1014, the fourth channel 104, the third channel 103, the second conducting portion 10202 of the second channel 102, the twelfth channel 1012, the fifth channel 105, the eleventh channel 1011, the thirteenth channel 1013, the The first conducting portion 10201 of the second channel 102, the second connecting portion 10102 of the first channel 101 and the fifteenth channel 1015 are arranged clockwise in this order on the edge portion 12102 of the first fluid control surface 1210 of the first fixed valve plate 121, the seventh channel 107, the eighth channel 108 and the ninth channel 109 of the plane valve 1 are arranged clockwise in this order on the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 and the tenth channel 1010 of the plane valve 1 are arranged on the fourth fluid control surface 1230 of the second fixed valve plate 123. Optionally, the first connecting portion 10101 of the first channel 101 of the planar valve 1, the fourteenth channel 1014, the fourth channel 104, the third channel 103, the second conducting portion 10202 of the second channel 102, the twelfth channel 1012, the fifth channel 105, the eleventh channel 1011, the thirteenth channel 1013, the first conducting portion 10201 of the second channel 102, the second connecting portion 10102 of the first channel 101 and the fifteenth channel 1015 are arranged counterclockwise in this order on the edge portion 12102 of the first fluid control surface 1210 of the first fixed valve plate 121, and the seventh channel 107, the eighth channel 108 and the ninth channel 109 of the planar valve 1 are arranged counterclockwise in this order on the second fluid control surface 1220 of the movable valve plate 122. Preferably, the first channel 101, the fourteenth channel 1014, the fourth channel 104, the third channel 103, the second channel 102, the twelfth channel 1012, the fifth channel 105, the eleventh channel 1011, the thirteenth channel 1013 and the fifteenth channel 1015 are separately arranged on the first fluid control surface 1210 of the first fixed valve plate 121; the seventh channel 107, the eighth channel 108 and the ninth channel 109 of the plane valve 1 are separately arranged on the second fluid control surface 1220 of the movable valve plate 122; the sixth channel 106 and the tenth channel 1010 of the plane valve 1 are separately arranged on the fourth fluid control surface 1230 of the second fixed valve plate 123.Preferably, the third communication portion 10103 of the first channel 101 and the third conducting portion 10203 of the second channel 102 are provided at the central portion 12101 of the first fluid control surface 1210 of the first fixed valve plate 121 .
[0244] As shown in the attached figure 7A to 9DAs shown, the first fluid control surface 1210 of the first fixed valve disc 121 of the plane valve 1 of the water treatment machine according to the first embodiment of the present invention has the center portion 12101 and the edge portion 12102 shown by the dotted line in the figure, wherein the center portion 12101 and the edge portion 12102 are arranged at the top end portion 1214 of the first fixed valve disc 121, and the edge portion 12102 of the first fluid control surface 1210 (or the portion outside the center portion 12101) is equally divided into a first portion 1201, a second portion 1202, and a a third portion 1203, a fourth portion 1204, a fifth portion 1205, a sixth portion 1206, a seventh portion 1207, an eighth portion 1208, a ninth portion 1209, a tenth portion 12010, an eleventh portion 12011, and a twelfth portion 12012; the second fluid control surface 1220 of the movable valve plate 122 of the planar valve 1 has a lower end central area 12201 shown by a dotted line in the figure and a lower end edge area 12202 extending outward from the lower end central area 12201. , wherein the lower end center area 12201 and the lower end edge area 12202 are provided at the lower end portion 1221 of the movable valve plate 122, and the lower end edge area 12202 of the second fluid control surface 1220 (the portion outside the lower end center area 12201) is equally divided into a first lower end area 2001, a second lower end area 2002, a third lower end area 2003, a fourth lower end area 2004, a fifth lower end area 2005, a sixth lower end area 2006, a seventh lower end area 2007, and a an eighth lower end region 2008, a ninth lower end region 2009, a tenth lower end region 20010, an eleventh lower end region 20011, and a twelfth lower end region 20012; the third fluid control surface 1223 of the movable valve disc 122 of the planar valve 1 has an upper end central region 12231 shown by a dotted line in the figure and an upper end edge region 12232 extending outward from the upper end central region 12231, wherein the upper end central region 12231 and the upper end edge region 12232 are provided at the upper end portion 1222 of the movable valve disc 122,The upper edge area 12232 of the third fluid control surface 1223 (the portion outside the upper center area 12231) is equally divided into a first upper area 3001, a second upper area 3002, a third upper area 3003, a fourth upper area 3004, a fifth upper area 3005, a sixth upper area 3006, a seventh upper area 3007, an eighth upper area 3008, a ninth upper area 3009, a tenth upper area 30010, an eleventh upper area 30011 and a twelfth upper area 30012 as shown by dotted lines; wherein the first lower area 2001 is opposite to the first upper area 3001, and the second lower area 3003 is opposite to the first upper area 3003. The first lower end region 2002 is opposite to the second upper end region 3002, the third lower end region 2003 is opposite to the third upper end region 3003, the fourth lower end region 2004 is opposite to the fourth upper end region 3004, the fifth lower end region 2005 is opposite to the fifth upper end region 3005, the sixth lower end region 2006 is opposite to the sixth upper end region 3006, the seventh lower end region 2007 is opposite to the seventh upper end region 3007, the eighth lower end region 2008 is opposite to the eighth upper end region 3008, the ninth lower end region 2009 is opposite to the ninth upper end region 3009, the tenth lower end region 20010 is opposite to the tenth upper end region 30010, and the eleventh lower end region 20011 is opposite to the eleventh upper end region 30 011, the twelfth lower end area 20012 is opposite to the twelfth upper end area 30012; the fourth fluid control surface 1230 of the second fixed valve plate 123 of the planar valve 1 has a central partition 12301 shown by a dotted line in the figure and an edge partition 12302 extending outward from the central partition 12301, wherein the central partition 12301 and the edge partition 12302 are arranged at the bottom end 1231 of the second fixed valve plate 123, and the edge partition 12302 of the fourth fluid control surface 1230 (the part outside the central partition 12301) is equally divided into a first partition 4001, a second partition 4002, a third partition 4003, and a fourth partition 4004 shown by a dotted line. , a fifth partition 4005, a sixth partition 4006, a seventh partition 4007, an eighth partition 4008, a ninth partition 4009, a tenth partition 40010, an eleventh partition 40011 and a twelfth partition 40012; wherein the first channel 101 extends downward from the first portion 1201 and the eleventh portion 12011 of the first fluid control surface 1210 of the first fixed valve disc 121, the fourteenth channel 1014 extends downward from the second portion 1202 of the first fluid control surface 1210 of the first fixed valve disc 121, and the fourth channel 104 extends downward from the third portion 1203 of the first fluid control surface 1210 of the first fixed valve disc 121,The third channel 103 extends downward from the fourth portion 1204 of the first fluid control surface 1210 of the first fixed valve disc 121, the second channel 102 extends downward from the fifth portion 1205 and the tenth portion 12010 of the first fluid control surface 1210 of the first fixed valve disc 121, the twelfth channel 1012 extends downward from the sixth portion 1206 of the first fluid control surface 1210 of the first fixed valve disc 121, the fifth channel 105 extends downward from the first fluid control surface 1210 of the first fixed valve disc 121, and the tenth channel 1012 extends downward from the sixth portion 1206 of the first fluid control surface 1210 of the first fixed valve disc 121. 0 extends downwardly from the seventh portion 1207 of the first fixed valve disc 121, the eleventh channel 1011 extends downwardly from the eighth portion 1208 of the first fluid control surface 1210 of the first fixed valve disc 121, the thirteenth channel 1013 extends downwardly from the ninth portion 1209 of the first fluid control surface 1210 of the first fixed valve disc 121, the fifteenth channel 1015 extends downwardly from the twelfth portion 12012 of the first fluid control surface 1210 of the first fixed valve disc 121, the seventh channel 107 extends downwardly from the second portion 12013 of the movable valve disc 122, The first lower end region 2001 of the fluid control surface 1220 extends upward and outward, the eighth channel 108 extends upward from the third lower end region 2003 and the fourth lower end region 2004 of the second fluid control surface 1220 of the movable valve disc 122, the ninth channel 109 extends from the seventh lower end region 2007 of the second fluid control surface 1220 of the movable valve disc 122 to the seventh upper end region 3007 of the third fluid control surface 1223 of the movable valve disc 122, and the sixth channel 106 extends from the second fixed valve disc 1220 to the seventh upper end region 3007 of the third fluid control surface 1223 of the movable valve disc 122. The seventh partition 4007 of the fourth fluid control surface 1230 of the second fixed valve plate 123 extends upward, and the tenth channel 1010 extends upward from the first partition 4001, the second partition 4002, the third partition 4003, the fourth partition 4004, the fifth partition 4005, the sixth partition 4006, the eighth partition 4008, the ninth partition 4009, the tenth partition 40010, the eleventh partition 40011 and the twelfth partition 40012 of the fourth fluid control surface 1230 of the second fixed valve plate 123. More specifically, the first communication portion 10101 of the first channel 101 extends downward from the first portion 1201 of the first fluid control surface 1210 of the first fixed valve disc 121, the second communication portion 10102 of the first channel 101 extends downward from the eleventh portion 12011 of the first fluid control surface 1210 of the first fixed valve disc 121, the first conduction portion 10201 of the second channel 102 extends downward from the tenth portion 12010 of the first fluid control surface 1210 of the first fixed valve disc 121, and the second conduction portion 10202 of the second channel 102 extends downward from the fifth portion 1205 of the first fluid control surface 1210 of the first fixed valve disc 121. Preferably,The third communication portion 10103 of the first channel 101 and the third conducting portion 10203 of the second channel 102 extend downward from the central portion 12101 of the first fluid control surface 1210 of the first fixed valve plate 121 .
[0245] As shown in the attached figure 7A to 9DAs shown, preferably, the edge portion 12102 of the first fluid control surface 1210 of the first fixed valve plate 121 of the plane valve 1 is divided into the first part 1201, the second part 1202, the third part 1203, the fourth part 1204, the fifth part 1205, the sixth part 1206, the seventh part 1207, the eighth part 1208, the ninth part 1209, the tenth part 12010, the eleventh part 12011 and the twelfth part 12012 in a clockwise direction, and the plane valve 1 The lower edge area 12202 of the second fluid control surface 1220 of the movable valve plate 122 is divided into the first lower end area 2001, the second lower end area 2002, the third lower end area 2003, the fourth lower end area 2004, the fifth lower end area 2005, the sixth lower end area 2006, the seventh lower end area 2007, the eighth lower end area 2008, the ninth lower end area 2009, the tenth lower end area 20010, the eleventh lower end area 20011 and the twelfth lower end area 200 12, the upper edge area 12232 of the third fluid control surface 1223 of the movable valve plate 122 of the planar valve 1 is divided into the first upper end area 3001, the second upper end area 3002, the third upper end area 3003, the fourth upper end area 3004, the fifth upper end area 3005, the sixth upper end area 3006, the seventh upper end area 3007, the eighth upper end area 3008, the ninth upper end area 3009, the tenth upper end area 30010, the eleventh upper end area 30011 and The twelfth upper end area 30012, the edge partition 12302 of the fourth fluid control surface 1230 of the second fixed valve plate 123 of the planar valve 1 is divided clockwise into the first partition 4001, the second partition 4002, the third partition 4003, the fourth partition 4004, the fifth partition 4005, the sixth partition 4006, the seventh partition 4007, the eighth partition 4008, the ninth partition 4009, the tenth partition 40010, the eleventh partition 40011 and the twelfth partition 40012.Optionally, the edge portion 12102 of the first fluid control surface 1210 is divided into the first portion 1201, the second portion 1202, the third portion 1203, the fourth portion 1204, the fifth portion 1205, the sixth portion 1206, the seventh portion 1207, the eighth portion 1208, the ninth portion 1209, the tenth portion 12010, the eleventh portion 12011 and the twelfth portion 12012 in a counterclockwise direction, and the second fluid control portion 1210 of the movable valve plate 122 of the planar valve 1 The lower edge area 12202 of the surface 1220 is divided into the first lower end area 2001, the second lower end area 2002, the third lower end area 2003, the fourth lower end area 2004, the fifth lower end area 2005, the sixth lower end area 2006, the seventh lower end area 2007, the eighth lower end area 2008, the ninth lower end area 2009, the tenth lower end area 20010, the eleventh lower end area 20011 and the twelfth lower end area 20012 in a counterclockwise direction. The upper edge area 12232 of the third fluid control surface 1223 of the movable valve plate 122 is divided into the first upper end area 3001, the second upper end area 3002, the third upper end area 3003, the fourth upper end area 3004, the fifth upper end area 3005, the sixth upper end area 3006, the seventh upper end area 3007, the eighth upper end area 3008, the ninth upper end area 3009, the tenth upper end area 30010, the eleventh upper end area 30011 and the twelfth upper end area 30012. In the end area 30012, the edge partition 12302 of the fourth fluid control surface 1230 of the second fixed valve plate 123 of the planar valve 1 is divided counterclockwise into the first partition 4001, the second partition 4002, the third partition 4003, the fourth partition 4004, the fifth partition 4005, the sixth partition 4006, the seventh partition 4007, the eighth partition 4008, the ninth partition 4009, the tenth partition 40010, the eleventh partition 40011 and the twelfth partition 40012. In other words, the first fluid control surface 1210 of the first fixed valve plate 121 of the planar valve 1 forms twelve equal parts, the second fluid control surface 1220 of the movable valve plate 122 of the planar valve 1 forms twelve equal parts, the third fluid control surface 1223 of the movable valve plate 122 of the planar valve 1 forms twelve equal parts, and the fourth fluid control surface 1230 of the second fixed valve plate 123 of the planar valve 1 forms twelve equal parts.It can be understood that the second fixed valve disc 123 of the plane valve 1 remains stationary relative to the first fixed valve disc 121, and the first partition 4001 of the fourth fluid control surface 1230 of the second fixed valve disc 123 is facing the first part 1201 of the first fluid control surface 1210 of the first fixed valve disc 121; the second partition 4002 of the fourth fluid control surface 1230 of the second fixed valve disc 123 is facing the second part 1202 of the first fluid control surface 1210 of the first fixed valve disc 121; the third partition 4003 of the fourth fluid control surface 1230 of the second fixed valve disc 123 is facing the first fixed valve disc 121. 1, the third portion 1203 of the first fluid control surface 1210 of the first fixed valve disc 121; the fourth partition 4004 of the fourth fluid control surface 1230 of the second fixed valve disc 123 is opposite to the fourth portion 1204 of the first fluid control surface 1210 of the first fixed valve disc 121; the fifth partition 4005 of the fourth fluid control surface 1230 of the second fixed valve disc 123 is opposite to the fifth portion 1205 of the first fluid control surface 1210 of the first fixed valve disc 121; the sixth partition 4006 of the fourth fluid control surface 1230 of the second fixed valve disc 123 is opposite to the first fluid control surface 1210 of the first fixed valve disc 121. 10; the seventh partition 4007 of the fourth fluid control surface 1230 of the second fixed valve disc 123 is opposite to the seventh portion 1207 of the first fluid control surface 1210 of the first fixed valve disc 121; the eighth partition 4008 of the fourth fluid control surface 1230 of the second fixed valve disc 123 is opposite to the eighth portion 1208 of the first fluid control surface 1210 of the first fixed valve disc 121; the ninth partition 4009 of the fourth fluid control surface 1230 of the second fixed valve disc 123 is opposite to the ninth portion 1209 of the first fluid control surface 1210 of the first fixed valve disc 121 9; the tenth partition 40010 of the fourth fluid control surface 1230 of the second fixed valve plate 123 is opposite to the tenth part 12010 of the first fluid control surface 1210 of the first fixed valve plate 121; the eleventh partition 40011 of the fourth fluid control surface 1230 of the second fixed valve plate 123 is opposite to the eleventh part 12011 of the first fluid control surface 1210 of the first fixed valve plate 121; the twelfth partition 40012 of the fourth fluid control surface 1230 of the second fixed valve plate 123 is opposite to the twelfth part 12012 of the first fluid control surface 1210 of the first fixed valve plate 121.
[0246] As shown in the attached figure 7A to 9D 、 Figure 10A 、 Figure 10B and Figure 20AAs shown, when the movable valve disc 122 of the plane valve 1 is rotated to the point where the first equal part (the first lower end area 2001) of the second fluid control surface 1220 of the movable valve disc 122 is aligned with the first equal part (the first part 1201) of the first fluid control surface 1210 of the first fixed valve disc 121, the third equal part and the fourth equal part (the third lower end area 2003 and the fourth lower end area 2004) of the second fluid control surface 1220 of the movable valve disc 122 of the plane valve 1 are aligned with the third equal part and the fourth equal part (the third part 1203 and the fourth part 1204) of the first fluid control surface 1210 of the first fixed valve disc 121 respectively. The seventh equal part (the seventh lower end area 2007) of the second fluid control surface 1220 and the seventh equal part (the seventh upper end area 3007) of the third fluid control surface 1223 are respectively aligned with the seventh equal part (the seventh part 1207) of the first fluid control surface 1210 of the first fixed valve plate 121 and the seventh equal part (the seventh partition 4007) of the fourth fluid control surface 1230 of the second fixed valve plate 123, so that the seventh channel 107 of the plane valve 1 is connected with the first channel 101, the eighth channel 108 is respectively connected with the third channel 103 and the fourth channel 104, the ninth channel 109 is respectively connected with the fifth channel 105 and the sixth channel 106, and the seventh equal part (the seventh part 1207) of the fourth fluid control surface 1230 of the second fixed valve plate 123. The second channel 102, the eleventh channel 1011, the twelfth channel 1012, the thirteenth channel 1013, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the tenth channel 1010 is blocked by the third fluid control surface 1223 of the movable valve plate 122, so as to allow raw water to flow from the second fluid opening 1107 of the valve body 10, flow to the first opening 1101 through the seventh channel 107 and the first channel 101, and further flow into the first water treatment device 51 from the first water inlet 511. The primary treated water after being treated by the first water treatment device 51 flows out from the first water outlet 512 and further flows out from the first water outlet 513. The second water inlet 521 flows into the second water treatment device 52. The secondary treated water after treatment by the second water treatment device 52 flows out of the second water outlet 522 and flows into the third opening 1103. Then, it flows through the third channel 103, the eighth channel 108, and the fourth channel 104 into the fourth opening 1104. It further flows into the third water treatment device 53 through the third water inlet 531. The tertiary treated water (e.g., softened water after softening) after treatment by the third water treatment device 53 flows out of the third water outlet 532 and flows into the fifth opening 1105. Then, it flows through the fifth channel 105, the ninth channel 109, the sixth channel 106, and the first fluid opening 1106 and is provided to the user. Accordingly, the water treatment machine is now in the water treatment working state.
[0247] As shown in the attached figure 7A to 9D 、 Figure 10C 、 Figure 10D and Figure 20B As shown, when the movable valve disc 122 of the plane valve 1 is rotated to the point where the first equal part (the first lower end area 2001) of the second fluid control surface 1220 of the movable valve disc 122 is aligned with the fifth equal part (the fifth part 1205) of the first fluid control surface 1210 of the first fixed valve disc 121, the third equal part and the fourth equal part (the third lower end area 2003 and the fourth lower end area 2004) of the second fluid control surface 1220 of the movable valve disc 122 of the plane valve 1 are aligned with the first fluid control surface 1210 of the first fixed valve disc 121 respectively. The seventh and eighth equal parts (the seventh portion 1207 and the eighth portion 1208), the seventh equal part (the seventh lower end area 2007) of the second fluid control surface 1220 of the movable valve disc 122 of the plane valve 1 and the seventh equal part (the seventh upper end area 3007) of the third fluid control surface 1223 are respectively opposite to the eleventh equal part (the eleventh part 12011) of the first fluid control surface 1210 of the first fixed valve disc 121 and the eleventh equal part (the eleventh partition 400) of the fourth fluid control surface 1230 of the second fixed valve disc 123. 11), so that the seventh channel 107 of the plane valve 1 is connected to the second channel 102, the ninth channel 109 is connected to the tenth channel 1010 and the first channel 101 respectively, the eighth channel 108 is connected to the fifth channel 105 and the eleventh channel 1011 respectively, the third channel 103, the fourth channel 104, the twelfth channel 1012, the thirteenth channel 1013, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122, allowing raw water to flow from the second fluid opening 1107 of the valve body 10, flow through the seventh channel 107 and the second channel 102 to the second opening 1102, and further flow into the first water treatment device 51 from the first water outlet 512. The sewage generated after backwashing the first water treatment device 51 flows out from the first water inlet 511, and is then discharged through the first opening 1101, the first channel 101, the ninth channel 109, the tenth channel 1010, and the sewage outlet 11010. Accordingly, the water treatment device is now in the first backwashing working state.
[0248] As shown in the attached figure 7A to 9D 、 Figure 10E 、 Figure 10F and Figure 20CAs shown, when the movable valve disc 122 of the plane valve 1 is rotated to the point where the first equal part (the first lower end area 2001) of the second fluid control surface 1220 of the movable valve disc 122 is aligned with the fourth equal part (the fourth part 1204) of the first fluid control surface 1210 of the first fixed valve disc 121, the third equal part and the fourth equal part (the third lower end area 2003 and the fourth lower end area 2004) of the second fluid control surface 1220 of the movable valve disc 122 of the plane valve 1 are aligned with the first fluid control surface 1210 of the first fixed valve disc 121 respectively. The sixth and seventh equal parts (the sixth portion 1206 and the seventh portion 1207), the seventh equal part (the seventh lower end area 2007) of the second fluid control surface 1220 of the movable valve disc 122 of the planar valve 1 and the seventh equal part (the seventh upper end area 3007) of the third fluid control surface 1223 are respectively opposite to the tenth equal part (the tenth part 12010) of the first fluid control surface 1210 of the first fixed valve disc 121 and the tenth equal part (the tenth partition 40010) of the fourth fluid control surface 1230 of the second fixed valve disc 123. ), so that the seventh channel 107 of the plane valve 1 is connected to the third channel 103, the ninth channel 109 is respectively connected to the tenth channel 1010 and the second channel 102, the eighth channel 108 is respectively connected to the fifth channel 105 and the twelfth channel 1012, the first channel 101, the fourth channel 104, the eleventh channel 1011, the thirteenth channel 1013, the fourteenth channel 1014 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 1 06 is blocked by the third fluid control surface 1223 of the movable valve plate 122, allowing raw water to flow from the second fluid opening 1107 of the valve body 10, flow through the seventh channel 107 and the third channel 103 to the third opening 1103, and further flow into the second water treatment device 52 from the second water outlet 522. The sewage generated after backwashing the second water treatment device 52 flows out from the second water inlet 521, and is then discharged through the second opening 1102, the second channel 102, the ninth channel 109, the tenth channel 1010, and the sewage outlet 11010. Accordingly, the water treatment device is now in the second backwash working state.
[0249] As shown in the attached figure 7A to 9D 、 Figure 10G 、 Figure 10H and Figure 20DAs shown, when the movable valve disc 122 of the plane valve 1 is rotated to the point where the first equal part (the first lower end area 2001) of the second fluid control surface 1220 of the movable valve disc 122 is aligned with the second equal part (the second part 1202) of the first fluid control surface 1210 of the first fixed valve disc 121, the third equal part and the fourth equal part (the third lower end area 2003 and the fourth lower end area 2004) of the second fluid control surface 1220 of the movable valve disc 122 of the plane valve 1 are aligned with the first fluid control surface 1210 of the first fixed valve disc 121 respectively. The fourth and fifth equal parts (the fourth part 1204 and the fifth part 1205), the seventh equal part (the seventh lower end area 2007) of the second fluid control surface 1220 of the movable valve disc 122 of the plane valve 1 and the seventh equal part (the seventh upper end area 3007) of the third fluid control surface 1223 are respectively opposite to the eighth equal part (the eighth part 1208) of the first fluid control surface 1210 of the first fixed valve disc 121 and the eighth equal part (the eighth partition 4008) of the fourth fluid control surface 1230 of the second fixed valve disc 123, The seventh channel 107 of the plane valve 1 is connected to the fourteenth channel 1014, the ninth channel 109 is connected to the tenth channel 1010 and the eleventh channel 1011 respectively, the eighth channel 108 is connected to the second channel 102 and the third channel 103 respectively, the first channel 101, the fourth channel 104, the fifth channel 105, the twelfth channel 1012, the thirteenth channel 1013 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the second fluid control surface 1220 of the movable valve plate 122. The third fluid control surface 1223 of the movable valve plate 122 is blocked, allowing raw water to flow from the second fluid opening 1107 of the valve body 10, flow through the seventh channel 107 and the fourteenth channel 1014 to the fifth opening 1105, and further flow into the third water treatment device 53 from the third water outlet 532. Sewage generated after backwashing the third water treatment device 53 flows out from the third water inlet 531 and is discharged through the fourth opening 1104, the eleventh channel 1011, the ninth channel 109, the tenth channel 1010, and the sewage outlet 11010. Accordingly, the water treatment device is now in the third backwashing operating state.
[0250] As shown in the attached figure 7A to 9D 、 Figure 10I 、 Figure 10J and Figure 20EAs shown, when the movable valve disc 122 of the plane valve 1 is rotated to the point where the first equal part (the first lower end area 2001) of the second fluid control surface 1220 of the movable valve disc 122 is facing the eleventh equal part (the eleventh part 12011) of the first fluid control surface 1210 of the first fixed valve disc 121, the third equal part and the fourth equal part (the third lower end area 2003 and the fourth lower end area 2004) of the second fluid control surface 1220 of the movable valve disc 122 of the plane valve 1 are facing the first fluid control surface 1210 of the first fixed valve disc 121 respectively. The first and second equal parts (the first part 1201 and the second part 1202), the seventh equal part (the seventh lower end area 2007) of the second fluid control surface 1220 of the movable valve disc 122 of the plane valve 1 and the seventh equal part (the seventh upper end area 3007) of the third fluid control surface 1223 are respectively opposite to the fifth equal part (the fifth part 1205) of the first fluid control surface 1210 of the first fixed valve disc 121 and the fifth equal part (the fifth partition 4005) of the fourth fluid control surface 1230 of the second fixed valve disc 123, The seventh channel 107 of the plane valve 1 is connected to the first channel 101, the ninth channel 109 is connected to the tenth channel 1010 and the second channel 102 respectively, the eighth channel 108 is connected to the first channel 101 and the fourteenth channel 1014 respectively, the third channel 103, the fourth channel 104, the fifth channel 105, the eleventh channel 1011, the twelfth channel 1012, the thirteenth channel 1013 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the The sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122, allowing raw water to flow from the second fluid opening 1107 of the valve body 10, through the seventh channel 107 and the first channel 101 to the first opening 1101, and further into the first water treatment device 51 through the first water inlet 511. The wastewater after positively flushing the first water treatment device 51 flows out of the first water outlet 512, and then is discharged through the second opening 1102, the second channel 102, the ninth channel 109, the tenth channel 1010, and the sewage outlet 11010. Accordingly, the water treatment device is now in the first positive flushing operating state.
[0251] As shown in the attached figure 7A to 9D 、 Figure 10K 、 Figure 10L and Figure 20FAs shown, when the movable valve disc 122 of the plane valve 1 is rotated to the point where the first equal part (the first lower end area 2001) of the second fluid control surface 1220 of the movable valve disc 122 is aligned with the tenth equal part (the tenth part 12010) of the first fluid control surface 1210 of the first fixed valve disc 121, the third equal part and the fourth equal part (the third lower end area 2003 and the fourth lower end area 2004) of the second fluid control surface 1220 of the movable valve disc 122 of the plane valve 1 are aligned with the first fluid control surface 1210 of the first fixed valve disc 121 respectively. The twelfth equal part and the first equal part (the twelfth part 12012 and the first part 1201), the seventh equal part (the seventh lower end area 2007) of the second fluid control surface 1220 of the movable valve plate 122 of the plane valve 1 and the seventh equal part (the seventh upper end area 3007) of the third fluid control surface 1223 are respectively opposite to the fourth equal part (the fourth part 1204) of the first fluid control surface 1210 of the first fixed valve plate 121 and the fourth equal part (the fourth partition 4004) of the fourth fluid control surface 1230 of the second fixed valve plate 123. 04), so that the seventh channel 107 of the plane valve 1 is connected to the second channel 102, the ninth channel 109 is connected to the tenth channel 1010 and the third channel 103 respectively, the eighth channel 108 is connected to the first channel 101 and the fifteenth channel 1015 respectively, the fourth channel 104, the fifth channel 105, the eleventh channel 1011, the twelfth channel 1012, the thirteenth channel 1013 and the fourteenth channel 1014 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel The flow channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122, allowing raw water to flow from the second fluid opening 1107 of the valve body 10, flow through the seventh channel 107 and the second channel 102 to the second opening 1102, and further flow into the second water treatment device 52 from the second water inlet 521. The sewage after positive flushing the second water treatment device 52 flows out from the second water outlet 522, and then is discharged through the third opening 1103, the third channel 103, the ninth channel 109, the tenth channel 1010, and the sewage outlet 11010. Accordingly, the water treatment machine is now in the second positive flushing working state.
[0252] As shown in the attached figure 7A to 9D 、 Figure 10M 、 Figure 10N and Figure 20GAs shown, when the movable valve disc 122 of the plane valve 1 is rotated to the point where the first equal part (the first lower end area 2001) of the second fluid control surface 1220 of the movable valve disc 122 is aligned with the eighth equal part (the eighth part 1208) of the first fluid control surface 1210 of the first fixed valve disc 121, the third equal part and the fourth equal part (the third lower end area 2003 and the fourth lower end area 2004) of the second fluid control surface 1220 of the movable valve disc 122 of the plane valve 1 are aligned with the eighth equal part (the eighth part 1208) of the first fluid control surface 1210 of the first fixed valve disc 121 respectively. The tenth and eleventh equal parts (the tenth part 12010 and the eleventh part 12011), the seventh equal part (the seventh lower end area 2007) of the second fluid control surface 1220 of the movable valve disc 122 of the plane valve 1 and the seventh equal part (the seventh upper end area 3007) of the third fluid control surface 1223 are respectively opposite to the second equal part (the second part 1202) of the first fluid control surface 1210 of the first fixed valve disc 121 and the second equal part (the second partition 4002) of the fourth fluid control surface 1230 of the second fixed valve disc 123. ), so that the seventh channel 107 of the plane valve 1 is connected to the eleventh channel 1011, the ninth channel 109 is respectively connected to the tenth channel 1010 and the fourteenth channel 1014, the eighth channel 108 is respectively connected to the first channel 101 and the second channel 102, the third channel 103, the fourth channel 104, the fifth channel 105, the twelfth channel 1012, the thirteenth channel 1013 and the fifteenth channel 1015 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 10 6 is blocked by the third fluid control surface 1223 of the movable valve plate 122, allowing raw water to flow from the second fluid opening 1107 of the valve body 10, flow through the seventh channel 107 and the eleventh channel 1011 to the fourth opening 1104, and further flow into the third water treatment device 53 from the third water inlet 531. The sewage after positive flushing the third water treatment device 53 flows out from the third water outlet 532, and is then discharged through the fifth opening 1105, the fourteenth channel 1014, the ninth channel 109, the tenth channel 1010, and the sewage outlet 11010. Accordingly, the water treatment machine is now in the third positive flushing working state.
[0253] As shown in the attached figure 7A to 9D 、 Figure 10O 、 Figure 10P and Figure 20HAs shown, when the movable valve disc 122 of the plane valve 1 is rotated to the point where the first equal part (the first lower end area 2001) of the second fluid control surface 1220 of the movable valve disc 122 is facing the sixth equal part (the sixth part 1206) of the first fluid control surface 1210 of the first fixed valve disc 121, the third equal part and the fourth equal part (the third lower end area 2003 and the fourth lower end area 2004) of the second fluid control surface 1220 of the movable valve disc 122 of the plane valve 1 are facing the eighth equal part and the ninth equal part (the eighth part 1208 and the ninth part 1209) of the first fluid control surface 1210 of the first fixed valve disc 121, respectively. The seventh equal part (the seventh lower end area 2007) of the second fluid control surface 1220 of the plane valve 1 and the seventh equal part (the seventh upper end area 3007) of the third fluid control surface 1223 are respectively aligned with the twelfth equal part (the twelfth part 12012) of the first fluid control surface 1210 of the first fixed valve plate 121 and the twelfth equal part (the twelfth partition 40012) of the fourth fluid control surface 1230 of the second fixed valve plate 123, so that the seventh channel 107 of the plane valve 1 is connected to the twelfth channel 1012, the eighth channel 108 is respectively connected to the thirteenth channel 1013 and the eleventh channel 1011, and the ninth channel 109 is respectively connected to the The tenth channel 1010 is connected to the fifteenth channel 1015. The first channel 101, the second channel 102, the third channel 103, the fourth channel 104, the fifth channel 105, and the fourteenth channel 1014 are respectively blocked by the second fluid control surface 1220 of the movable valve plate 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve plate 122, so as to allow raw water to flow from the second fluid opening 1107 of the valve body 10, flow through the seventh channel 107 and the twelfth channel 1012 into the first jet opening 11012, and then flow into the jet port 182 of the ejector 18, pass through the jet of the ejector 18, and mix with the salt intake port 181. After the salt solution (such as sodium chloride solution) is added, a regeneration solution is formed. The regeneration solution flows into the second jet opening 11013 of the first valve body 11 through the injection port 183 of the ejector 18, and then flows into the third water inlet 531 through the thirteenth channel 1013, the eighth channel 108, the eleventh channel 1011 and the fourth opening 1104. After downstream regeneration of the water treatment material or mechanism of the third water treatment device 53, such as softening resin, the wastewater generated after regeneration flows out from the third water outlet 532, and then is discharged in sequence through the fifth opening 1105, the fifteenth channel 1015, the ninth channel 109, the tenth channel 1010 and the sewage opening 11010 of the first valve body 11. Accordingly, the water treatment machine is now in the regeneration working state.
[0254] As shown in the attached figure 7A to 9D 、 Figure 10Q 、 Figure 10R and Figure 20I As shown, when the movable valve disc 122 of the plane valve 1 is rotated to the point where the first equal part (the first lower end area 2001) of the second fluid control surface 1220 of the movable valve disc 122 is aligned with the ninth equal part (the ninth part 1209) of the first fluid control surface 1210 of the first fixed valve disc 121, the third equal part and the fourth equal part (the third lower end area 2003 and the fourth lower end area 2004) of the second fluid control surface 1220 of the movable valve disc 122 of the plane valve 1 are aligned with the first fixed valve disc 121 respectively. The eleventh equal part and the twelfth equal part (the eleventh part 12011 and the twelfth part 12012) of the first fluid control surface 1210, the seventh equal part (the seventh lower end area 2007) of the second fluid control surface 1220 of the movable valve plate 122 of the plane valve 1 and the seventh equal part (the seventh upper end area 3007) of the third fluid control surface 1223 are respectively opposite to the third equal part (the third part 1203) of the first fluid control surface 1210 of the first fixed valve plate 121 and the second fixed valve plate 1 23 of the fourth fluid control surface 1230 of the third equal division (the third partition 4003), so that the seventh channel 107 of the plane valve 1 is connected to the thirteenth channel 1013, the eighth channel 108 is connected to the first channel 101 and the fifteenth channel 1015, the ninth channel 109 is connected to the tenth channel 1010 and the fourth channel 104, the second channel 102, the third channel 103, the fifth channel 105, the eleventh channel 1011, the twelfth channel 101 2 and the fourteenth channel 1014 are respectively blocked by the second fluid control surface 1220 of the movable valve disc 122, and the sixth channel 106 is blocked by the third fluid control surface 1223 of the movable valve disc 122, allowing raw water to flow from the second fluid opening 1107 of the valve body 10, through the seventh channel 107 and the thirteenth channel 1013 into the second jet opening 11013, and then sequentially through the injection port 183 of the ejector 18, the salt intake port 181, and the salt intake pipe 184 into the regeneration solution tank 31 for water replenishment. Accordingly, the water treatment machine is now in the water replenishment working state.
[0255] It can be understood that when the second fluid control surface 1220 and the third fluid control surface 1223 of the movable valve disc 122 are respectively arranged on the first fluid control surface 1210 of the first fixed valve disc 121 and the fourth fluid control surface 1230 of the second fixed valve disc 123, the lower end center area 12201 of the second fluid control surface 1220 of the movable valve disc 122 is aligned with the center part 12101 of the first fluid control surface 1210 of the first fixed valve disc 121, and the lower end center area 12201 of the second fluid control surface 1220 of the movable valve disc 122 is aligned with the center part 12101 of the first fluid control surface 1210 of the first fixed valve disc 121. The end edge area 12202 is facing the edge portion 12102 of the first fluid control surface 1210 of the first fixed valve plate 121, the upper center area 12231 of the third fluid control surface 1223 of the movable valve plate 122 is facing the center partition 12301 of the fourth fluid control surface 1230 of the second fixed valve plate 123, and the upper edge area 12232 of the third fluid control surface 1223 of the movable valve plate 122 is facing the edge partition 12302 of the fourth fluid control surface 1230 of the second fixed valve plate 123.
[0256] Optionally, the first fluid control surface 1210 of the first fixed valve disc 121 of the plane valve 1, the fourth fluid control surface 1230 of the second fixed valve disc 123, the second fluid control surface 1220 and the third fluid control surface 1223 of the movable valve disc 122 are all circular, and the first connecting portion 10101 of the first channel 101 of the plane valve 1, the fourteenth channel 1014, the fourth channel 104, the third channel 103, the second conducting portion 10202 of the second channel 102, the twelfth channel 1012, the fifth channel 105, the eleventh channel 1011, the thirteenth channel 1013, the first The conducting portion 10201, the second connecting portion 10102 of the first channel 101 and the fifteenth channel 1015 are all radially arranged on the first fluid control surface 1210 of the first fixed valve plate 121, the seventh channel 107 and the eighth channel 108 of the plane valve 1 are both radially arranged on the second fluid control surface 1220 of the movable valve plate 122, the ninth channel 109 of the plane valve 1 is radially arranged on the second fluid control surface 1220 and the third fluid control surface 1223 of the movable valve plate 122, and the sixth channel 106 and the tenth channel 1010 of the plane valve 1 are both radially arranged on the fourth fluid control surface 1230 of the second fixed valve plate 123.
[0257] Preferably, the first channel 101 of the plane valve 1 extends downward and outward from the first fluid control surface 1210 of the first fixed valve disc 121, the fifth channel 105, the fourteenth channel 1014 and the fifteenth channel 1015 extend downward from the first fluid control surface 1210 of the first fixed valve disc 121, the fourth channel 104 and the eleventh channel 1011 extend downward from the first fluid control surface 1210 of the first fixed valve disc 121, the third channel 103 extends downward and outward from the first fluid control surface 1210 of the first fixed valve disc 121, and the second channel 105 extends downward from the first fluid control surface 1210 of the first fixed valve disc 121. 02 extends downward and outward from the first fluid control surface 1210 of the first fixed valve plate 121, the twelfth channel 1012 extends downward and outward from the first fluid control surface 1210 of the first fixed valve plate 121, the thirteenth channel 1013 extends downward and outward from the first fluid control surface 1210 of the first fixed valve plate 121, the sixth channel 106 of the planar valve 1 extends upward and outward from the fourth fluid control surface 1230 of the second fixed valve plate 123, and the tenth channel 1010 extends upward and outward from the fourth fluid control surface 1230 of the second fixed valve plate 123.
[0258] As shown in the attached figure Figures 6A to 6U As shown, the first valve body portion 11 of the planar valve 1 has a first inner wall 111, and the second valve body portion 13 has a second inner wall 131, wherein the first fixed valve plate 121 is suitable for being arranged in the valve cavity 110 with the first fluid control surface 1210 facing upward, the movable valve plate 122 is suitable for being arranged in the valve cavity 110 with the second fluid control surface 1220 facing downward (the third fluid control surface 1223 facing upward), and the second fixed valve plate 123 is suitable for being arranged in the valve cavity 110 with the fourth fluid control surface 1230 facing downward, wherein the valve cavity 110 is always connected to the seventh channel 107. It is worth noting that the first fixed valve plate 121 of the planar valve 1 can be detachably set on the first inner wall 111 of the first valve body portion 11, or can be integrally formed with the first inner wall 111 of the first valve body portion 11 of the planar valve 1; the second fixed valve plate 123 of the planar valve 1 can be detachably set on the second inner wall 131 of the second valve body portion 13, or can be integrally formed with the second inner wall 131 of the second valve body portion 13 of the planar valve 1. Those skilled in the art will appreciate that when the first fixed valve disc 121 is detachably disposed in the first valve body 11, a fixing mechanism is used between the first fixed valve disc 121 and the first valve body 11 to maintain synchronization between the first fixed valve disc 121 and the first valve body 11; when the second fixed valve disc 123 is detachably disposed in the second valve body 13, another fixing mechanism is used between the second fixed valve disc 123 and the second valve body 13 to maintain synchronization between the second fixed valve disc 123 and the second valve body 13. For example, as shown in the accompanying drawings Figures 6A to 6UAs shown, the first fixed valve disc 121 has a first brake member 1213 protruding outward from the edge of the first fixed valve disc 121, and the first inner wall 111 of the first valve body 11 has a first brake portion 1110, wherein the first brake member 1213 of the first fixed valve disc 121 is configured to engage with the first brake portion 1110 of the first inner wall 111 of the first valve body 11 to ensure that the first fixed valve disc 121 and the first valve body 11 are synchronized (or do not rotate relative to each other) and that the various channels provided on the first fixed valve disc 121 are connected to the corresponding openings provided on the first valve body 11 The second fixed valve disc 123 has a second stopper 1233 protruding outward from the edge of the second fixed valve disc 123, and the second inner wall 131 of the second valve body 13 has a second stopper 1310, wherein the second stopper 1233 of the second fixed valve disc 123 is configured to engage with the second stopper 1310 of the second inner wall 131 of the second valve body 13 to ensure that the second fixed valve disc 123 and the second valve body 13 are synchronized (or do not rotate relative to each other) and that the various channels provided in the second fixed valve disc 123 are connected to the corresponding openings provided in the second valve body 13. It can be understood that when the first fixed valve disc 121 is detachably provided in the first valve body 11, the first fixed valve disc 121 can be manufactured separately, and when the second fixed valve disc 123 is detachably provided in the second valve body 13, the second fixed valve disc 123 can be manufactured separately. In other words, in this case, the first fixed valve disc 121 and the second fixed valve disc 123 can be made of wear-resistant materials, thereby increasing the service life of the first fixed valve disc 121 and the second fixed valve disc 123 (or the entire flat valve). Preferably, the first fluid control surface 1210 of the first fixed valve disc 121 and the fourth fluid control surface 1230 of the second fixed valve disc 123 are smoothed to reduce their roughness.
[0259] As shown in the attached figure Figure 5 and Figure 6R As shown, the planar valve 1 further includes a driving element 17 extending upward from the movable valve disc 122 through the second fixed valve disc 123, wherein the driving element 17 is configured to drive the movable valve disc 122 of the planar valve 1 to rotate relative to the first fixed valve disc 121 and the second fixed valve disc 123. It will be understood that the driving element 17 can be any element or component that can drive the movable valve disc 122 to rotate relative to the first fixed valve disc 121 and the second fixed valve disc 123. For example, the driving element 17 can be a valve stem, a driving gear, or a driving gear set.
[0260] As shown in the attached figure Figures 6C to 6U and Figures 11A to 19As shown, the diameter of the movable valve plate 122 of the planar valve 1 is set to be slightly smaller than the diameter of the valve cavity 110 of the valve body 10, so that the seventh channel 107 of the planar valve 1 can remain connected to the valve cavity 110 of the valve body 10.
[0261] Reference to the accompanying drawings Figures 3A to 3F and Figures 22 to 24 , a water treatment machine according to a second embodiment of the present invention is illustrated, wherein the water treatment machine of the present invention includes a control valve 1B, a first water treatment device 51, a second water treatment device 52 and a third water treatment device 53, wherein the first water treatment device 51 has a first water inlet 511 and a first water outlet 512, so that water can flow into the first water inlet 511 of the first water treatment device 51 and flow out through the first water outlet 512 or can flow into the first water outlet 512 of the first water treatment device 51 and flow out through the first water inlet 511; the second water treatment device 52 has a second water inlet 521 and a second water outlet 522, so that water can flow into the second water inlet 521 of the second water treatment device 52 and flow out through the second water outlet 522 Or it can flow into the second water outlet 522 of the second water treatment device 52 and flow out through the second water inlet 521; the third water treatment device 53 has a third water inlet 531 and a third water outlet 532, so that water can flow into the third water inlet 531 of the third water treatment device 53 and flow out through the third water outlet 532, or can flow into the third water outlet 532 of the third water treatment device 53 and flow out through the third water inlet 531, and the control valve 1B is configured to control the flow of water, such as controlling the water flow provided to the first water treatment device 51, the second water treatment device 52 and / or the third water treatment device 53, controlling the flow of water in the first water treatment device 51, the second water treatment device 52 and the third water treatment device 53, and controlling the supply of treated water. It can be understood that the control valve 1B of the water treatment machine of the present invention is suitable for being connected to a water source. For example, the control valve 1B of the water treatment machine of the present invention can be connected to a tap water pipe. In other words, the control valve 1B controls raw water (e.g., tap water) to be provided to the first water treatment device 51, the second water treatment device 52 and / or the third water treatment device 53.
[0262] As shown in the attached figure Figure 3A and Figure 3BAs shown, exemplarily, the first water treatment device 51 of the water treatment machine according to the second embodiment of the present utility model includes a first outer shell 513, a first central tube 514 and a first water treatment material 515, the first outer shell 513 has a first end 5131 and a first shell body 5132 extending from the first end 5131, the first central tube 514 has a first tube upper end 5141 and a first tube lower end 5142, the first water inlet 511 is formed between the first end 5131 and the first tube upper end 5141, the first tube upper end 5141 forms the first water outlet 512, the first water treatment material 515 is arranged between the first outer shell 513 and the first central tube 514, wherein the first central tube 514 is arranged so that the primary treated water generated after the raw water is treated by the first water treatment material 515 can be collected by the first central tube 514. It is understood that the first water treatment material 515 of the first water treatment device 51 of the water treatment machine of the second embodiment of the present invention can be a filter material, such as activated carbon, PP cotton, or quartz sand. It is understood that the first water treatment material 515 of the first water treatment device 51 of the water treatment machine of the second embodiment of the present invention can be a dispersed filter material or a shaped filter material obtained through various molding techniques. The first water treatment material 515 of the first water treatment device 51 of the water treatment machine of the second embodiment of the present invention can also be a softening material, such as a softening resin.
[0263] As shown in the attached figure Figure 3C and Figure 3DAs shown, for example, the second water treatment device 52 of the water treatment machine according to the second embodiment of the present invention includes a second shell 523, a second central tube 524 and a second water treatment material 525, the second shell 523 has a second end 5231 and a second shell body 5232 extending from the second end 5231, the second central tube 524 has a second tube upper end 5241 and a second tube lower end 5242 extending downward from the second tube upper end 5241, the second inlet The water inlet 521 is formed between the second end 5231 of the second housing 523 and the upper end 5241 of the second tube. The upper end 5241 of the second tube forms the second water outlet 522. The second water treatment material 525 is disposed between the second housing 523 and the second central tube 524. The second central tube 524 is configured so that the secondary treated water generated by the primary treated water flowing in from the second water inlet 521 and treated by the second water treatment material 525 can be collected by the second central tube 524. It is understood that the second water treatment material 525 of the second water treatment device 52 of the water treatment machine of the second embodiment of the present invention can be a filter material, such as activated carbon, PP cotton, or quartz sand. It is understood that the second water treatment material 525 of the second water treatment device 52 of the water treatment machine of the second embodiment of the present invention can be a dispersed filter material or a shaped filter material obtained through various molding techniques. The second water treatment material 525 of the second water treatment device 52 of the water treatment machine according to the second embodiment of the present invention may also be a softening material, such as a softening resin.
[0264] As shown in the attached figure Figure 3E and Figure 3FAs shown, exemplarily, the third water treatment device 53 of the water treatment machine according to the second embodiment of the present utility model includes a third outer shell 533, a third central tube 534 and a third water treatment material 535, the third outer shell 533 has a third end 5331 and a third shell body 5332 extending from the third end 5331, the third central tube 534 has a third tube upper end 5341 and a third tube lower end 5342 extending downward from the third tube upper end 5341, the third water inlet 531 is formed between the third end 5331 and the third tube upper end 5341, the third tube upper end 5341 forms the third water outlet 532, the third water treatment material 535 is arranged between the third outer shell 533 and the third central tube 534, wherein the third central tube 534 is arranged so that the secondary treated water flowing in from the third water inlet 531 is treated by the third water treatment material 535 and the tertiary treated water generated can be collected by the third central tube 534. It is understood that the third water treatment material 535 of the third water treatment device 53 of the water treatment machine of the second embodiment of the present invention can be a filter material, such as activated carbon, PP cotton, or quartz sand. It is understood that the third water treatment material 535 of the third water treatment device 53 of the water treatment machine of the second embodiment of the present invention can be a dispersed filter material or a molded filter material obtained through various molding techniques. Preferably, the third water treatment material 535 of the third water treatment device 53 of the water treatment machine of the second embodiment of the present invention is a softening material, such as a softening resin.
[0265] As shown in the attached figure Figure 3A As shown, when the first water treatment device 51 of the water treatment machine according to the second embodiment of the present invention is used for water treatment or the first water treatment device 51 is forward flushed (positive flushing), water flows into the first water treatment device 51 from the first water inlet 511, and then flows through the first end 5131, the first water treatment material 515, the first tube lower end 5142, the first central tube 514 and the first tube upper end 5141 in sequence and flows out from the first water outlet 512; as shown in the accompanying drawings Figure 3B As shown, when the first water treatment device 51 of the water treatment machine according to the second embodiment of the present invention is backwashed (backwashed), water flows into the first water treatment device 51 from the first water outlet 512, and then flows through the first tube upper end 5141, the first central tube 514, the first tube lower end 5142, the first water treatment material 515 and the first end 5131 in sequence and flows out from the first water inlet 511.
[0266] As shown in the attached figure Figure 3CAs shown, when the second water treatment device 52 of the water treatment machine according to the second embodiment of the present invention is used for water treatment or the second water treatment device 52 is forward flushed (positive flushing), water flows into the second water treatment device 52 from the second water inlet 521, and then flows through the second end 5231, the second water treatment material 525, the second tube lower end 5242, the second center tube 524 and the second tube upper end 5241 in sequence and flows out from the second water outlet 522; as shown in the accompanying drawings Figure 3D As shown, when the second water treatment device 52 of the water treatment machine according to the second embodiment of the present invention is backwashed (backwashed), water flows into the second water treatment device 52 from the second water outlet 522, and then flows through the second tube upper end 5241, the second center tube 524, the second tube lower end 5242, the second water treatment material 525 and the second end 5231 in sequence and flows out from the second water inlet 521.
[0267] As shown in the attached figure Figure 3E As shown, when the third water treatment device 53 of the water treatment machine according to the second embodiment of the present invention is used as a purification filter element (or softening filter element) to purify water (or soften water) or the third water treatment device 53 is forward flushed (positive flushed), water flows into the third water treatment device 53 from the third water inlet 531, and then flows through the third end 5331, the third water treatment material 535, the third tube lower end 5342, the third center tube 534 and the third tube upper end 5341 and flows out from the third water outlet 532; as shown in the accompanying drawings Figure 3F As shown, when the third water treatment device 53 of the water treatment machine according to the second embodiment of the present invention is backwashed (backwashed) as a purification filter, water flows into the third water treatment device 53 from the third water outlet 532, and then flows through the third pipe upper end 5341, the third central pipe 534, the third pipe lower end 5342, the third water treatment material 535 and the third end 5331 in sequence and flows out from the third water inlet 531. Figure 3F As shown, when the third water treatment device 53 of the water treatment machine according to the second embodiment of the present utility model is backwashed (backwashed) as a softening filter element or the third water treatment device 53 is regenerated by countercurrent salt absorption, water or regeneration solution flows into the third water treatment device 53 from the third water outlet 532, and then flows through the third tube upper end 5341, the third central tube 534, the third tube lower end 5342, the third water treatment material 535 and the third end 5331 in sequence and flows out from the third water inlet 531.
[0268] As shown in the attached figure Figures 22 to 27UAs shown, the control valve 1B of the water treatment machine according to the second embodiment of the present utility model includes a valve body 10B and a valve core 12B, wherein the valve body 10B forms a valve cavity 110B, a first opening 1101B, a second opening 1102B, a third opening 1103B, a fourth opening 1104B, a fifth opening 1105B, a first fluid opening 1106B, a second fluid opening 1107B and a sewage discharge opening 11010B, wherein the valve core 12B is arranged in the valve cavity 110B, wherein the first opening 1101B of the valve body 10B is suitable for connecting with the second opening 1101B of the first water treatment device 51. The valve body 10B is connected to a water inlet 511, the second opening 1102B is suitable for being connected to the first water outlet 512 of the first water treatment device 51 and the second water inlet 521 of the second water treatment device 52 respectively, the third opening 1103B is suitable for being connected to the second water outlet 522 of the second water treatment device 52, the fourth opening 1104B is suitable for being connected to the third water inlet 531 of the third water treatment device 53, the fifth opening 1105B is suitable for being connected to the third water outlet 532 of the third water treatment device 53, and the second fluid opening 1107B of the valve body 10B is suitable for being connected to a raw water source (for example, tap water). Preferably, the second opening 1102B of the valve body 10B of the control valve 1B of the water treatment machine of the present invention, the first water outlet 512 of the first water treatment device 51, and the second water inlet 521 of the second water treatment device 52 form a three-way structure 61B. Optionally, the second opening 1102B of the valve body 10B of the control valve 1B of the water treatment machine of the present invention is respectively connected to the first water outlet 512 of the first water treatment device 51 and the second water inlet 521 of the second water treatment device 52 through the three-way structure 61B.
[0269] As shown in the attached figure Figures 25 to 29CAs shown, more specifically, the control valve 1B of the water treatment machine according to the second embodiment of the present utility model is a plane valve, wherein the valve core 12B of the plane valve 1B further includes a first fixed valve plate 121B, a movable valve plate 122B and a second fixed valve plate 123B, wherein the first fixed valve plate 121B has a first fluid control surface 1210B, the movable valve plate 122B has a second fluid control surface 1220B and a third fluid control surface 1223B, and the second fixed valve plate 123B has a fourth fluid control surface 1230B, wherein the first fixed valve plate 121B, the movable valve plate 122B and the second fixed valve plate 123B are all arranged in the valve cavity 110B, wherein the second fluid control surface 1220B and the third fluid control surface 1223B of the movable valve plate 122B are respectively formed on the opposite sides of the movable valve plate 122B, wherein the second fluid control surface 1220B of the movable valve plate 122B is arranged on the first fluid control surface 1210B of the first fixed valve plate 121B, and the fourth fluid control surface 1230B of the second fixed valve plate 123B is arranged on the third fluid control surface 1223B of the movable valve plate 122B, and the movable valve plate 122B is arranged to be able to rotate relative to the first fixed valve plate 121B and the second fixed valve plate 123B. Accordingly, the first fixed valve disc 121B is disposed between the valve body 10B and the movable valve disc 122B, and the second fixed valve disc 123B is disposed between the valve body 10B and the movable valve disc 122B. The first fixed valve disc 121B is configured to remain stationary relative to the valve body 10B, and the second fixed valve disc 123B is configured to remain stationary relative to the valve body 10B. Preferably, the second fluid opening 1107B is in communication with the valve cavity 110B of the valve body 10B.
[0270] As shown in the attached figure Figures 25 to 27U 、 Figure 42A and Figure 42B As shown, the valve body 10B of the control valve 1B of the water treatment machine according to the second embodiment of the present invention includes a first valve body portion 11B and a second valve body portion 13B, wherein a valve chamber 110B is formed between the first valve body portion 11B and the second valve body portion 13B, the first opening 1101B, the second opening 1102B, the third opening 1103B, the fourth opening 1104B, and the fifth opening 1105B are formed in the first valve body portion 11B, the first fluid opening 1106B and the sewage opening 11010B are formed in the second valve body portion 13B, and the second fluid opening 1107B is selectively provided in the first valve body portion 11B or the second valve body portion 13B of the valve body 10B. In other words, the second fluid opening 1107B can be provided in either the first valve body portion 11B or the second valve body portion 13B of the valve body 10B.
[0271] As shown in the attached figure Figure 32A 、 Figure 32B and Figure 41AAs shown, the control valve 1B of the water treatment machine according to the second embodiment of the present invention has a water treatment working position, wherein when the control valve 1B of the water treatment machine of the present invention is in the water treatment working position, the valve core 12B of the control valve 1B forms a first water treatment flow channel 7001B, a second water treatment flow channel 7002B and a third water treatment flow channel 7003B, wherein the first water treatment flow channel 7001B is respectively connected to the second fluid opening 1107B and the first opening 1101B, the second water treatment flow channel 7002B is respectively connected to the third opening 1103B and the fourth opening 1104B, and the third water treatment flow channel 7003B is respectively connected to the fifth opening 1105B and the first fluid opening 1106B. Accordingly, when the control valve 1B of the water treatment machine of the present invention is in the water treatment working position, raw water flows in from the second fluid opening 1107B of the valve body 10B of the control valve 1B under the action of water pressure, flows through the first water treatment flow channel 7001B to the first opening 1101B of the first valve body 11B, and further flows into the first water treatment device 51 from the first water inlet 511 under the action of water pressure. The primary treated water obtained after being treated by the first water treatment device 51 flows out from the first water outlet 512 and further flows into the second water treatment device 52 from the second water inlet 521. The secondary treated water after being treated by the second water treatment device 52 flows out from the second water outlet 522, and under the action of water pressure, further flows into the third opening 1103B, and then flows into the fourth opening 1104B through the second water treatment channel 7002B, and then flows into the third water treatment device 53 from the third water inlet 531. The tertiary treated water obtained after water treatment (purification or softening treatment) by the third water treatment device 53 flows out from the third water outlet 532 and flows into the fifth opening 1105B, and then flows to the first fluid opening 1106B through the third water treatment channel 7003B and is provided.Accordingly, when the control valve 1B of the water treatment machine according to the second embodiment of the present invention is controlled to be in the water treatment working position, the water flows in sequence through the second fluid opening 1107B of the valve body 10B, the first water treatment flow channel 7001B, the first opening 1101B of the first valve body portion 11B, the first water inlet 511 of the first water treatment device 51, the first water outlet 512 of the first water treatment device 51, the second water inlet 521 of the second water treatment device 52, the second water outlet 522 of the second water treatment device 52, the The third opening 1103B of the first valve body 11B, the second water treatment flow channel 7002B, the fourth opening 1104B of the first valve body 11B, the third water inlet 531 of the third water treatment device 53, the third water outlet 532 of the third water treatment device 53, the fifth opening 1105B of the first valve body 11B, the third water treatment flow channel 7003B, and the first fluid opening 1106B enable the control valve 1B of the water treatment machine of the present invention to control the three water treatment devices of the water treatment machine of the present invention in series. Preferably, the control valve 1B of the water treatment machine of the second embodiment of the present invention is configured to prevent the flow of water in the second opening 1102B when the control valve 1B is controlled to the water treatment working position. Furthermore, when the control valve 1B of the water treatment machine according to the second embodiment of the present invention is controlled to be in the water treatment working position, water cannot flow from the first water outlet 512 of the first water treatment device 51 to the second opening 1102B, nor can water flow from the second water inlet 521 of the second water treatment device 52 to the second opening 1102B, thereby ensuring that raw water can flow through the first water treatment device 51, the second water treatment device 52, and the third water treatment device 53 in sequence and be treated in sequence by the first water treatment device 51, the second water treatment device 52, and the third water treatment device 53. It can be understood that when the control valve 1B of the water treatment machine according to the second embodiment of the present invention is controlled to be in the water treatment working position, the water treatment machine of the present invention is controlled to be in its water treatment working state.
[0272] As shown in the attached figure Figure 33 and Figure 41BAs shown, the control valve 1B of the water treatment machine according to the second embodiment of the present invention has a first backwash working position, wherein when the control valve 1B of the water treatment machine of the present invention is in the first backwash working position, the valve core 12B of the control valve 1B forms a first backwash flow channel 7101B and a second backwash flow channel 7102B, wherein the first backwash flow channel 7101B is respectively connected to the second fluid opening 1107B and the second opening 1102B, and the second backwash flow channel 7102B is respectively connected to the sewage opening 11010B and the first opening 1101B. Correspondingly, when the control valve 1B of the water treatment machine of the present invention is in the first backwash working position, the raw water flows in from the second fluid opening 1107B of the valve body 10B of the control valve 1B under the action of water pressure, flows to the second opening 1102B through the first backwash channel 7101B, and further flows into the first water treatment device 51 from the first water outlet 512. The sewage generated after backwashing the first water treatment device 51 flows out from the first water inlet 511, and is then discharged through the first opening 1101B, the second backwash channel 7102B and the sewage opening 11010B. Preferably, the control valve 1B of the water treatment machine according to the second embodiment of the present invention is configured to prevent raw water from flowing from the second fluid opening 1107B of the valve body 10B of the control valve 1B to the third opening 1103B, the fourth opening 1104B, and the fifth opening 1105B when the control valve 1B is controlled to the first backwash operating position. More preferably, when the control valve 1B of the water treatment machine according to the present invention is controlled to the first backwash operating position, the flow of water in the third opening 1103B, the fourth opening 1104B, and the fifth opening 1105B is prevented, thereby preventing the flow of water in the second water treatment device 52 and the third water treatment device 53. More specifically, when the control valve 1B of the water treatment machine according to the second embodiment of the present invention is controlled to be in the first backwash working position, water cannot flow from the second opening 1102B or the third opening 1103B of the first valve body 11B to the second water treatment device 52, water cannot flow from the fourth opening 1104B or the fifth opening 1105B of the first valve body 11B to the third water treatment device 53, and water cannot flow from the first water outlet 512 of the first water treatment device 51 to the second water inlet 521 of the second water treatment device 52, thereby ensuring that raw water can and only can backwash the first water treatment device 51. It can be understood that when the control valve 1B of the water treatment machine according to the second embodiment of the present invention is controlled to be in the first backwash working position, the water treatment machine of the present invention is controlled to be in its first backwash working state to backwash the first water treatment device 51 of the water treatment machine of the present invention.
[0273] As shown in the attached figure Figure 34 and Figure 41C As shown, the control valve 1B of the water treatment machine according to the second embodiment of the present invention has a second backwash working position, wherein when the control valve 1B of the water treatment machine of the present invention is in the second backwash working position, the valve core 12B of the control valve 1B forms a third backwash flow channel 7103B and a fourth backwash flow channel 7104B, wherein the third backwash flow channel 7103B is respectively connected to the second fluid opening 1107B and the third opening 1103B, and the fourth backwash flow channel 7104B is respectively connected to the sewage opening 11010B and the second opening 1102B. Correspondingly, when the control valve 1B of the water treatment mach...
Claims
1. A control valve for a water treatment machine, characterized in that: include: a drive element; an ejector; a valve body; and A valve core, wherein the valve body forms a valve cavity, a first opening, a second opening, a third opening, a fourth opening, a fifth opening, a first fluid opening, a second fluid opening, a sewage opening and a first jet opening, wherein the valve core is arranged in the valve cavity, wherein the second fluid opening of the valve body is suitable for being connected to a raw water source, wherein the ejector has an ejection port suitable for being connected to the first jet opening and a salt absorption port connected to the ejection port, wherein the control valve for the water treatment machine is a plane valve, the valve core further comprises a first fixed valve plate, a movable valve plate and a second fixed valve plate, the driving element is arranged to be able to drive the movable valve plate of the plane valve to rotate relative to the first fixed valve plate and the second fixed valve plate, wherein the first fixed valve plate has a first fluid control surface, the movable valve plate has a second fluid control surface and a third fluid control surface, the second fixed valve plate has a fourth fluid control surface. The invention relates to a body control surface, wherein the first fixed valve plate, the movable valve plate and the second fixed valve plate of the valve core are all arranged in the valve cavity, wherein the second fluid control surface and the third fluid control surface of the movable valve plate are respectively formed on the opposite sides of the movable valve plate, wherein the second fluid control surface of the movable valve plate is arranged on the first fluid control surface of the first fixed valve plate, and the fourth fluid control surface of the second fixed valve plate is arranged on the third fluid control surface of the movable valve plate, and the movable valve plate is arranged to be able to rotate relative to the first fixed valve plate and the second fixed valve plate, wherein when the movable valve plate rotates relative to the first fixed valve plate and the second fixed valve plate, so that the plane valve is in a water treatment working position, the valve core of the plane valve forms a first water treatment flow channel respectively connected to the second fluid opening and the first opening, a second water treatment flow channel respectively connected to the third opening and the fourth opening, and a third water treatment flow channel respectively connected to the fifth opening and the first fluid opening.
2. The control valve for a water treatment machine according to claim 1, characterized in that: The valve body further forms a second jet opening, and the ejector further has an ejection port adapted to communicate with the second jet opening of the valve body, wherein the salt absorption port is respectively communicated with the ejection port and the ejection port.
3. The control valve for a water treatment machine according to claim 1, characterized in that: When the movable valve plate rotates relative to the first fixed valve plate and the second fixed valve plate, so that the planar valve is in the first backwash working position, the valve core forms a first backwash flow channel respectively connected to the second fluid opening and the second opening, and a second backwash flow channel respectively connected to the sewage opening and the first opening.
4. The control valve for a water treatment machine according to claim 3, characterized in that: When the movable valve plate rotates relative to the first fixed valve plate and the second fixed valve plate, so that the planar valve is in the second backwash working position, the valve core forms a third backwash flow channel respectively connected to the second fluid opening and the third opening, and a fourth backwash flow channel respectively connected to the sewage opening and the second opening.
5. The control valve for a water treatment machine according to claim 4, characterized in that: When the movable valve plate rotates relative to the first fixed valve plate and the second fixed valve plate, so that the planar valve is in the third backwash working position, the valve core forms a fifth backwash channel respectively connected to the second fluid opening and the fifth opening and a sixth backwash channel respectively connected to the sewage opening and the fourth opening.
6. The control valve for a water treatment machine according to claim 5, characterized in that: When the movable valve plate rotates relative to the first fixed valve plate and the second fixed valve plate, so that the planar valve is in the first positive flushing working position, the valve core forms a first positive flushing channel respectively connected to the second fluid opening and the first opening and a second positive flushing channel respectively connected to the sewage opening and the second opening.
7. The control valve for a water treatment machine according to claim 6, characterized in that: When the movable valve plate rotates relative to the first fixed valve plate and the second fixed valve plate, so that the planar valve is in the second positive flushing working position, the valve core forms a third positive flushing channel respectively connected to the second fluid opening and the second opening, and a fourth positive flushing channel respectively connected to the sewage opening and the third opening.
8. The control valve for a water treatment machine according to claim 7, characterized in that: When the movable valve plate rotates relative to the first fixed valve plate and the second fixed valve plate, so that the planar valve is in the third positive flushing working position, the valve core forms a fifth positive flushing channel respectively connected to the second fluid opening and the fourth opening and a sixth positive flushing channel respectively connected to the sewage opening and the fifth opening.
9. The control valve for a water treatment machine according to claim 2, characterized in that: When the movable valve plate rotates relative to the first fixed valve plate and the second fixed valve plate, so that the planar valve is in the regeneration working position, the valve core forms a first regeneration flow channel respectively connected to the second fluid opening and the first jet opening of the valve body, a second regeneration flow channel respectively connected to the second jet opening and the fourth opening, and a third regeneration flow channel respectively connected to the fifth opening and the sewage opening.
10. The control valve for a water treatment machine according to claim 2, characterized in that: When the movable valve plate rotates relative to the first fixed valve plate and the second fixed valve plate, so that the planar valve is in the regeneration working position, the valve core forms a first regeneration flow channel respectively connected to the second fluid opening and the first jet opening of the valve body, a second regeneration flow channel respectively connected to the second jet opening and the fifth opening, and a third regeneration flow channel respectively connected to the fourth opening and the sewage opening.
11. The control valve for a water treatment machine according to claim 9 or 10, characterized in that: When the movable valve disc rotates relative to the first fixed valve disc and the second fixed valve disc so that the plane valve is in the water replenishment working position, the valve core forms a water replenishment flow channel respectively connected to the second fluid opening and the second jet opening.
12. The control valve for a water treatment machine according to claim 2, characterized in that: The planar valve comprises a first channel, a second channel, a third channel, a fourth channel, a fifth channel, a sixth channel, a seventh channel, an eighth channel, a ninth channel, a tenth channel, an eleventh channel, a twelfth channel, a thirteenth channel, a fourteenth channel and a fifteenth channel, wherein the first channel, the second channel, the third channel, the fourth channel, the fifth channel, the eleventh channel, the twelfth channel, the thirteenth channel, the fourteenth channel and the fifteenth channel are respectively arranged on the first fixed valve plate and respectively extend from the first fluid control surface of the first fixed valve plate; The seventh channel, the eighth channel and the ninth channel are respectively arranged on the movable valve plate, wherein the seventh channel and the eighth channel extend respectively from the second fluid control surface of the movable valve plate, and the ninth channel extends from the second fluid control surface of the movable valve plate to the third fluid control surface; the sixth channel and the tenth channel are respectively arranged on the second fixed valve plate and extend respectively from the fourth fluid control surface of the second fixed valve plate, wherein the first channel is connected to the first opening, the second channel is connected to the second opening, the third channel is connected to the third opening, the fourth channel and the eleventh channel are respectively connected to the fourth opening, the fifth channel, the fourteenth channel and the fifteenth channel are respectively connected to the fifth opening, and the sixth channel is connected to the first fluid opening , the seventh channel is connected to the second fluid opening, the tenth channel is connected to the sewage opening, the twelfth channel is connected to the first jet opening, and the thirteenth channel is connected to the second jet opening, wherein when the planar valve is in the water treatment working position, the seventh channel of the planar valve is connected to the first channel, thereby forming the first water treatment flow channel respectively connected to the second fluid opening and the first opening, the eighth channel is respectively connected to the third channel and the fourth channel, thereby forming the second water treatment flow channel respectively connected to the third opening and the fourth opening, and the ninth channel is respectively connected to the fifth channel and the sixth channel, thereby forming the third water treatment flow channel respectively connected to the fifth opening and the first fluid opening.
13. The control valve for a water treatment machine according to claim 12, characterized in that: When the planar valve is in the first backwash working position, the seventh channel of the planar valve is connected with the second channel to form a first backwash flow channel respectively connected with the second fluid opening and the second opening, and the ninth channel is respectively connected with the tenth channel and the first channel to form a second backwash flow channel respectively connected with the sewage opening and the first opening.
14. The control valve for a water treatment machine according to claim 13, characterized in that: When the planar valve is in the second backwash working position, the seventh channel of the planar valve is connected with the third channel to form a third backwash flow channel respectively connected with the second fluid opening and the third opening, and the ninth channel is respectively connected with the tenth channel and the second channel to form a fourth backwash flow channel respectively connected with the sewage opening and the second opening.
15. The control valve for a water treatment machine according to claim 14, characterized in that: When the planar valve is in the third backwash working position, the seventh channel of the planar valve is connected with the fourteenth channel to form a fifth backwash channel respectively connected with the second fluid opening and the fifth opening, and the ninth channel is connected with the tenth channel and the eleventh channel to form a sixth backwash channel respectively connected with the sewage opening and the fourth opening.
16. The control valve for a water treatment machine according to claim 15, characterized in that: When the planar valve is in the first positive flushing working position, the seventh channel of the planar valve is connected with the first channel to form a first positive flushing channel respectively connected with the second fluid opening and the first opening, and the ninth channel is respectively connected with the tenth channel and the second channel to form a second positive flushing channel respectively connected with the sewage opening and the second opening.
17. The control valve for a water treatment machine according to claim 16, characterized in that: When the planar valve is in the second positive flushing working position, the seventh channel of the planar valve is connected with the second channel to form a third positive flushing channel respectively connected with the second fluid opening and the second opening, and the ninth channel is respectively connected with the tenth channel and the third channel to form a fourth positive flushing channel respectively connected with the sewage opening and the third opening.
18. The control valve for a water treatment machine according to claim 17, characterized in that: When the planar valve is in the third positive flushing working position, the seventh channel of the planar valve is connected with the eleventh channel to form a fifth positive flushing channel respectively connected with the second fluid opening and the fourth opening, and the ninth channel is connected with the tenth channel and the fourteenth channel to form a sixth positive flushing channel respectively connected with the sewage opening and the fifth opening.
19. The control valve for a water treatment machine according to claim 12, characterized in that: When the planar valve is in the regeneration working position, the seventh channel of the planar valve is connected with the twelfth channel to form a first regeneration channel respectively connected with the second fluid opening and the first jet opening of the valve body, the eighth channel is respectively connected with the thirteenth channel and the eleventh channel to form a second regeneration channel respectively connected with the second jet opening and the fourth opening, the ninth channel is respectively connected with the tenth channel and the fifteenth channel to form a third regeneration channel respectively connected with the fifth opening and the sewage opening.
20. The control valve for a water treatment machine according to claim 19, characterized in that: When the plane valve is in the water replenishment working position, the seventh channel of the plane valve is connected to the thirteenth channel, thereby forming a water replenishment channel respectively connected to the second fluid opening and the second jet opening.
21. The control valve for a water treatment machine according to claim 12, characterized in that: When the planar valve is in the water treatment working position, the second channel, the eleventh channel, the twelfth channel, the thirteenth channel, the fourteenth channel and the fifteenth channel are respectively blocked by the second fluid control surface of the movable valve plate, and the tenth channel is blocked by the third fluid control surface of the movable valve plate.
22. The control valve for a water treatment machine according to claim 15, characterized in that: When the plane valve is in the first backwash working position, the third channel, the fourth channel, the twelfth channel, the thirteenth channel, the fourteenth channel and the fifteenth channel of the plane valve are respectively blocked by the second fluid control surface of the movable valve plate; when the plane valve is in the second backwash working position, the first channel, the fourth channel, the eleventh channel, the thirteenth channel, the fourteenth channel and the fifteenth channel are respectively blocked by the second fluid control surface of the movable valve plate; when the plane valve is in the third backwash working position, the first channel, the fourth channel, the fifth channel, the twelfth channel, the thirteenth channel and the fifteenth channel of the plane valve are respectively blocked by the second fluid control surface of the movable valve plate.
23. The control valve for a water treatment machine according to claim 18, characterized in that: When the planar valve is in the first positive flushing working position, the third channel, the fourth channel, the fifth channel, the eleventh channel, the twelfth channel, the thirteenth channel and the fifteenth channel are respectively blocked by the second fluid control surface of the movable valve plate; when the planar valve is in the second positive flushing working position, the fourth channel, the fifth channel, the eleventh channel, the twelfth channel, the thirteenth channel and the fourteenth channel are respectively blocked by the second fluid control surface of the movable valve plate; when the planar valve is in the third positive flushing working position, the third channel, the fourth channel, the fifth channel, the twelfth channel, the thirteenth channel and the fifteenth channel are respectively blocked by the second fluid control surface of the movable valve plate.
24. The control valve for a water treatment machine according to claim 20, characterized in that: When the planar valve is in the regeneration working position, the first channel, the second channel, the third channel, the fourth channel, the fifth channel and the fourteenth channel are respectively blocked by the second fluid control surface of the movable valve plate; when the planar valve is in the water replenishment working position, the second channel, the third channel, the fifth channel, the eleventh channel, the twelfth channel and the fourteenth channel are respectively blocked by the second fluid control surface of the movable valve plate.
25. The control valve for a water treatment machine according to any one of claims 1-10 or 12-24, characterized in that: The valve body includes a first valve body portion and a second valve body portion, wherein the valve cavity is formed between the first valve body portion and the second valve body portion, the first opening, the second opening, the third opening, the fourth opening and the fifth opening are formed in the first valve body portion, the first fluid opening and the sewage opening are formed in the second valve body portion, and the second fluid opening is selectively arranged in the first valve body portion or the second valve body portion of the valve body.
26. The control valve for a water treatment machine according to any one of claims 12 to 24, characterized in that: The first channel of the planar valve has a first connecting portion and a second connecting portion, wherein the first connecting portion of the first channel is connected to the first opening, and the second connecting portion of the first channel is connected to the first opening; the second channel of the planar valve has a first conducting portion and a second conducting portion, wherein the first conducting portion of the second channel is connected to the second opening, and the second conducting portion of the second channel is connected to the second opening.
27. The control valve for a water treatment machine according to claim 26, characterized in that: The first fluid control surface of the first fixed valve plate of the planar valve forms a central portion and an edge portion extending outward from the central portion, and the first connecting portion of the first channel, the fourteenth channel, the fourth channel, the third channel, the second conducting portion of the second channel, the twelfth channel, the fifth channel, the eleventh channel, the thirteenth channel, the first conducting portion of the second channel, the second connecting portion of the first channel and the fifteenth channel are arranged clockwise in this order on the edge of the first fluid control surface of the first fixed valve plate. the seventh channel, the eighth channel and the ninth channel of the plane valve are arranged clockwise in this order on the second fluid control surface of the movable valve plate, the sixth channel and the tenth channel of the plane valve are arranged on the fourth fluid control surface of the second fixed valve plate, and the first channel, the fourteenth channel, the fourth channel, the third channel, the second channel, the twelfth channel, the fifth channel, the eleventh channel, the thirteenth channel and the fifteenth channel of the plane valve are arranged separately on the first fluid control surface of the first fixed valve plate; The seventh channel, the eighth channel and the ninth channel are arranged separately on the second fluid control surface of the movable valve plate; The sixth channel and the tenth channel are arranged separately on the fourth fluid control surface of the second fixed valve plate.
28. The control valve for a water treatment machine according to claim 26, characterized in that: The first fluid control surface of the first fixed valve plate of the planar valve forms a central portion and an edge portion extending outward from the central portion, and the first connecting portion of the first channel, the fourteenth channel, the fourth channel, the third channel, the second conducting portion of the second channel, the twelfth channel, the fifth channel, the eleventh channel, the thirteenth channel, the first conducting portion of the second channel, the second connecting portion of the first channel and the fifteenth channel are arranged counterclockwise in this order on the edge of the first fluid control surface of the first fixed valve plate. the seventh channel, the eighth channel and the ninth channel of the plane valve are arranged counterclockwise in this order on the second fluid control surface of the movable valve plate, the sixth channel and the tenth channel of the plane valve are arranged on the fourth fluid control surface of the second fixed valve plate, and the first channel, the fourteenth channel, the fourth channel, the third channel, the second channel, the twelfth channel, the fifth channel, the eleventh channel, the thirteenth channel and the fifteenth channel of the plane valve are arranged separately on the first fluid control surface of the first fixed valve plate; The seventh channel, the eighth channel and the ninth channel are arranged separately on the second fluid control surface of the movable valve plate; The sixth channel and the tenth channel are arranged separately on the fourth fluid control surface of the second fixed valve plate.
29. The control valve for a water treatment machine according to claim 2, characterized in that: The planar valve comprises a first channel, a second channel, a third channel, a fourth channel, a fifth channel, a sixth channel, a seventh channel, an eighth channel, a ninth channel, a tenth channel, an eleventh channel, a twelfth channel and a thirteenth channel, wherein the first channel, the second channel, the third channel, the fourth channel, the fifth channel, the eleventh channel, the twelfth channel and the thirteenth channel are respectively arranged on the first fixed valve plate and respectively extend from the first fluid control surface of the first fixed valve plate; The seventh channel, the eighth channel and the ninth channel are respectively arranged on the movable valve plate, wherein the seventh channel and the eighth channel extend from the second fluid control surface of the movable valve plate respectively, and the ninth channel extends from the second fluid control surface of the movable valve plate to the third fluid control surface; the sixth channel and the tenth channel are respectively arranged on the second fixed valve plate and extend from the fourth fluid control surface of the second fixed valve plate respectively, wherein the first channel is connected to the first opening, the second channel is connected to the second opening, the third channel is connected to the third opening, the fourth channel and the eleventh channel are respectively connected to the fourth opening, the fifth channel is connected to the fifth opening, the sixth channel is connected to the first fluid opening, and the seventh channel is connected to the The second fluid opening is connected, the tenth channel is connected to the sewage opening, the twelfth channel is connected to the first jet opening, and the thirteenth channel is connected to the second jet opening, wherein when the planar valve is in the water treatment working position, the seventh channel of the planar valve is connected to the first channel, thereby forming the first water treatment flow channel respectively connected to the second fluid opening and the first opening, the eighth channel is respectively connected to the third channel and the fourth channel, thereby forming the second water treatment flow channel respectively connected to the third opening and the fourth opening, and the ninth channel is respectively connected to the fifth channel and the sixth channel, thereby forming the third water treatment flow channel respectively connected to the fifth opening and the first fluid opening.
30. The control valve for a water treatment machine according to claim 29, characterized in that: When the planar valve is in the first backwash working position, the seventh channel of the planar valve is connected with the second channel to form a first backwash flow channel respectively connected with the second fluid opening and the second opening, and the ninth channel is respectively connected with the tenth channel and the first channel to form a second backwash flow channel respectively connected with the sewage opening and the first opening.
31. The control valve for a water treatment machine according to claim 30, characterized in that: When the planar valve is in the second backwash working position, the seventh channel of the planar valve is connected with the third channel to form a third backwash flow channel respectively connected with the second fluid opening and the third opening, and the ninth channel is respectively connected with the tenth channel and the second channel to form a fourth backwash flow channel respectively connected with the sewage opening and the second opening.
32. The control valve for a water treatment machine according to claim 31, characterized in that: When the planar valve is in the third backwash working position, the seventh channel of the planar valve is connected with the fifth channel to form a fifth backwash channel respectively connected with the second fluid opening and the fifth opening, and the ninth channel is connected with the tenth channel and the fourth channel to form a sixth backwash channel respectively connected with the sewage opening and the fourth opening.
33. The control valve for a water treatment machine according to claim 32, characterized in that: When the planar valve is in the first positive flushing working position, the seventh channel of the planar valve is connected with the first channel to form a first positive flushing channel respectively connected with the second fluid opening and the first opening, and the ninth channel is respectively connected with the tenth channel and the second channel to form a second positive flushing channel respectively connected with the sewage opening and the second opening.
34. The control valve for a water treatment machine according to claim 33, characterized in that: When the planar valve is in the second positive flushing working position, the seventh channel of the planar valve is connected with the second channel to form a third positive flushing channel respectively connected with the second fluid opening and the second opening, and the ninth channel is respectively connected with the tenth channel and the third channel to form a fourth positive flushing channel respectively connected with the sewage opening and the third opening.
35. The control valve for a water treatment machine according to claim 34, characterized in that: When the planar valve is in the third positive flushing working position, the seventh channel of the planar valve is connected with the fourth channel to form a fifth positive flushing channel respectively connected with the second fluid opening and the fourth opening, and the ninth channel is respectively connected with the tenth channel and the fifth channel to form a sixth positive flushing channel respectively connected with the sewage opening and the fifth opening.
36. The control valve for a water treatment machine according to claim 29, characterized in that: When the planar valve is in the regeneration working position, the seventh channel of the planar valve is connected with the twelfth channel to form a first regeneration channel respectively connected with the second fluid opening and the first jet opening, the eighth channel is connected with the thirteenth channel and the fifth channel to form a second regeneration channel respectively connected with the second jet opening and the fifth opening, the ninth channel is connected with the tenth channel and the eleventh channel to form a third regeneration channel respectively connected with the sewage opening and the fourth opening.
37. The control valve for a water treatment machine according to claim 36, characterized in that: When the plane valve is in the water replenishment working position, the seventh channel of the plane valve is connected to the thirteenth channel, thereby forming a water replenishment channel respectively connected to the second fluid opening and the second jet opening.
38. The control valve for a water treatment machine according to claim 29, characterized in that: When the planar valve is in the water treatment working position, the second channel, the eleventh channel, the twelfth channel and the thirteenth channel are respectively blocked by the second fluid control surface of the movable valve plate, and the tenth channel is blocked by the third fluid control surface of the movable valve plate.
39. The control valve for a water treatment machine according to claim 32, characterized in that: When the plane valve is in the first backwash working position, the third channel, the fifth channel, the eleventh channel, the twelfth channel and the thirteenth channel of the plane valve are respectively blocked by the second fluid control surface of the movable valve plate; when the plane valve is in the second backwash working position, the first channel, the fourth channel, the eleventh channel and the thirteenth channel of the plane valve are respectively blocked by the second fluid control surface of the movable valve plate; when the plane valve is in the third backwash working position, the first channel, the third channel, the eleventh channel, the twelfth channel and the thirteenth channel of the plane valve are respectively blocked by the second fluid control surface of the movable valve plate.
40. The control valve for a water treatment machine according to claim 35, characterized in that: When the planar valve is in the first positive flushing working position, the third channel, the fourth channel, the eleventh channel, the twelfth channel and the thirteenth channel of the planar valve are respectively blocked by the second fluid control surface of the movable valve plate; when the planar valve is in the second positive flushing working position, the fourth channel, the fifth channel, the twelfth channel and the thirteenth channel of the planar valve are respectively blocked by the second fluid control surface of the movable valve plate; when the planar valve is in the third positive flushing working position, the second channel, the eleventh channel, the twelfth channel and the thirteenth channel of the planar valve are respectively blocked by the second fluid control surface of the movable valve plate.
41. The control valve for a water treatment machine according to claim 37, characterized in that: When the planar valve is in the regeneration working position, the first channel, the second channel, the third channel and the fourth channel of the planar valve are respectively blocked by the second fluid control surface of the movable valve plate; when the planar valve is in the water replenishment working position, the first channel, the third channel, the fifth channel and the twelfth channel are respectively blocked by the second fluid control surface of the movable valve plate.
42. The control valve for a water treatment machine according to any one of claims 29 to 41, characterized in that: The valve body includes a first valve body portion and a second valve body portion, wherein the valve cavity is formed between the first valve body portion and the second valve body portion, the first opening, the second opening, the third opening, the fourth opening and the fifth opening are formed in the first valve body portion, the first fluid opening and the sewage opening are formed in the second valve body portion, and the second fluid opening is selectively arranged in the first valve body portion or the second valve body portion of the valve body.
43. The control valve for a water treatment machine according to any one of claims 29 to 41, characterized in that: The first channel of the planar valve has a first communicating portion and a second communicating portion, wherein the first communicating portion of the first channel is communicated with the first opening, and the second communicating portion of the first channel is communicated with the first opening.
44. The control valve for a water treatment machine according to claim 43, characterized in that: The first fluid control surface of the first fixed valve plate of the plane valve forms a central portion and an edge portion extending outward from the central portion. The first connecting portion of the first channel of the plane valve, the fourth channel, the third channel, the second connecting portion of the first channel, the twelfth channel, the fifth channel, the thirteenth channel, the second channel and the eleventh channel are arranged clockwise in this order on the edge portion of the first fluid control surface of the first fixed valve plate. The seventh channel, the eighth channel and the ninth channel of the plane valve are arranged clockwise in this order on the second fluid control surface of the movable valve plate. The sixth channel and the tenth channel of the planar valve are arranged on the fourth fluid control surface of the second fixed valve plate, and the first channel, the fourth channel, the third channel, the twelfth channel, the fifth channel, the thirteenth channel, the second channel and the eleventh channel are separated and arranged on the first fluid control surface of the first fixed valve plate; the seventh channel, the eighth channel and the ninth channel of the planar valve are separated and arranged on the second fluid control surface of the movable valve plate; the sixth channel and the tenth channel of the planar valve are separated and arranged on the fourth fluid control surface of the second fixed valve plate.
45. The control valve for a water treatment machine according to claim 43, characterized in that: The first fluid control surface of the first fixed valve plate of the plane valve forms a central portion and an edge portion extending outward from the central portion. The first connecting portion of the first channel of the plane valve, the fourth channel, the third channel, the second connecting portion of the first channel, the twelfth channel, the fifth channel, the thirteenth channel, the second channel and the eleventh channel are arranged counterclockwise in this order on the edge portion of the first fluid control surface of the first fixed valve plate. The seventh channel, the eighth channel and the ninth channel of the plane valve are arranged counterclockwise in this order on the second fluid control surface of the movable valve plate. The sixth channel and the tenth channel of the planar valve are arranged on the fourth fluid control surface of the second fixed valve plate, and the first channel, the fourth channel, the third channel, the twelfth channel, the fifth channel, the thirteenth channel, the second channel and the eleventh channel are separated and arranged on the first fluid control surface of the first fixed valve plate; the seventh channel, the eighth channel and the ninth channel of the planar valve are separated and arranged on the second fluid control surface of the movable valve plate; the sixth channel and the tenth channel of the planar valve are separated and arranged on the fourth fluid control surface of the second fixed valve plate.
46. A water treatment machine, characterized in that: include: A control valve according to any one of claims 1 to 45; a first water treatment unit; a second water treatment unit; and A third water treatment device, the first water treatment device has a first water inlet and a first water outlet, the second water treatment device has a second water inlet and a second water outlet, and the third water treatment device has a third water inlet and a third water outlet, wherein the first opening of the valve body is suitable for being connected to the first water inlet of the first water treatment device, the second opening is suitable for being connected to the first water outlet of the first water treatment device and the second water inlet of the second water treatment device respectively, the third opening is suitable for being connected to the second water outlet of the second water treatment device, the fourth opening is suitable for being connected to the third water inlet of the third water treatment device, and the fifth opening is suitable for being connected to the third water outlet of the third water treatment device.
47. The water treatment machine according to claim 46, characterized in that The second opening of the valve body, the first water outlet of the first water treatment device and the second water inlet of the second water treatment device form a three-way structure.
48. The water treatment machine according to claim 46, characterized in that The first water treatment device comprises a first shell, a first central tube and a first water treatment material, the first shell having a first end and a first shell body extending from the first end, the first central tube having a first tube upper end and a first tube lower end, the first water inlet is formed between the first end and the first tube upper end, the first tube upper end forms the first water outlet, and the first water treatment material is arranged between the first shell and the first central tube; the second water treatment device comprises a second shell, a second central tube and a second water treatment material, the second shell having a second end and a second shell body extending from the second end, the second central tube having a second tube upper end and a first tube lower end extending downward from the second tube upper end The lower end of the second tube extending from the third end portion of the second shell, the second water inlet is formed between the second end portion of the second shell and the upper end of the second tube, the upper end of the second tube forms the second water outlet, and the second water treatment material is arranged between the second shell and the second center tube; the third water treatment device includes a third shell, a third center tube and a third water treatment material, the third shell has a third end portion and a third shell body extending from the third end portion, the third center tube has a third tube upper end and a third tube lower end extending downward from the third tube upper end, the third water inlet is formed between the third end portion and the upper end of the third tube, the upper end of the third tube forms the third water outlet, and the third water treatment material is arranged between the third shell and the third center tube.
Citation Information