Automatic punching equipment for metal pipe fitting
By designing an automatic punching equipment for metal pipe fittings, the safety hazards and low efficiency problems caused by manual operation in the prior art are solved, and the automatic punching and forming of metal pipe fittings is realized, and the production efficiency is improved.
Patent Information
- Application Number
- CN202421308133.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-11
- Publication Date
- 2025-03-11
- Estimated Expiration
- 2034-06-11
AI Technical Summary
The existing metal pipe fitting stamping technology has safety hazards and low processing efficiency.
An automatic punching equipment for metal pipe fittings is designed, including a frame, feeding vibration disc, conveying track, punching mold, pushing mechanism and telescopic device, to realize automatic feeding, conveying and punching molding of metal pipe fittings.
Through automated processes, safety hazards caused by manual operations are avoided, production and processing efficiency is improved, and the disassembly and replacement of the upper module is simplified.
Smart Images

Figure CN222587836U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of metal part stamping, in particular to automatic punching equipment for metal pipe parts. Background Art
[0002] The metal pipe is punched to form a hole so that the hole on the metal pipe can be plugged with other accessories. In the prior art, the metal pipe is generally placed in a mold manually to be positioned and fixed, and then the punching machine is manually operated to punch the local hole structure of the metal pipe. However, when the metal pipe is placed in the mold manually, the punching machine is easily misoperated, causing the punching punch on the punching machine to punch down, resulting in serious injuries to the worker's hands. Therefore, there is a great safety hazard, and the processing efficiency is low. Therefore, there is an urgent need for an automatic punching device for metal pipes that can solve the above technical problems. Utility Model Content
[0003] The utility model aims to solve the deficiencies of the above-mentioned technology and is designed to provide an automatic punching device for metal pipe fittings, and the specific method is as follows.
[0004] The utility model is designed to provide an automatic punching device for metal pipe fittings, comprising a frame, a feeding vibration plate, a first conveying track, a second conveying track, a punching and forming die, a third conveying track, a telescopic device, a first pushing mechanism and a second pushing mechanism, and a punching die and a punching die for forming holes on the metal pipe fittings;
[0005] The discharge conveying track of the feeding vibration plate is connected to the first conveying track, and a push opening and a discharge opening which are arranged oppositely are arranged on the discharge end of the first conveying track. The second conveying track is located beside the discharge opening on the first conveying track, and the discharge opening is connected to the feed opening of the second conveying track correspondingly, and the first pushing mechanism is arranged beside the push opening.
[0006] The punching and forming die and the first pushing mechanism are respectively arranged at the two ends of the second conveying track. The punching and forming die is provided with a first through hole for the punching punch to pass through, a second through hole for the punched waste to fall, and a punching channel corresponding to the material transfer channel of the second conveying track. The first through hole and the second through hole are arranged opposite to each other and are respectively located on the upper and lower sides of the punching die. The third conveying track is installed at the discharge end of the punching channel. A material receiving box is arranged at the discharge end of the material transfer channel of the third conveying track. A telescopic device is installed on the side of the material receiving box opposite to the third conveying track. The punching die is installed on the telescopic rod of the telescopic device and corresponds to the punching channel and the material transfer channel of the third conveying track, so as to drive the punching die to enter the punching channel and then be located below the first through hole. The two ends of the waste channel on the punching die are coaxially arranged with the first through hole and the second through hole, or the punching die is driven to exit the punching channel through the material transfer channel of the third conveying track and be located above the material receiving box.
[0007] Further preferred solution: The blanking die includes an upper module and a lower module. The cross-section of the lower module is in a "U" shape to form a blanking channel on the lower module. The upper module is installed on the upper side of the lower module through an installation structure to block the upper opening of the blanking channel. The first through hole is arranged on the upper module, and the second through hole is arranged on the lower inner wall of the blanking channel.
[0008] Further preferred solution: The installation structure includes insertion holes located on two longitudinal parts of the lower module and insertion plates arranged at opposite ends of the upper module. Automatic telescopic pin columns are respectively arranged on opposite inner walls of the insertion holes, and pin holes are respectively arranged on opposite side surfaces of the insertion plates. The insertion plates are correspondingly inserted into the insertion holes, and the automatic telescopic pin columns are correspondingly inserted into the pin holes.
[0009] Further preferred solution: Each automatic telescopic pin column includes a locking cylinder, a locking block, and a pin column arranged on the locking block. Two installation grooves are arranged on each of the two longitudinal parts of the lower module. The two installation grooves are respectively opposite to two sides of the insertion hole. An installation block is fixed at the notch of the installation groove. Each locking cylinder is respectively fixed on the two installation blocks. There is an activity space between the installation block and the bottom of the installation groove. The locking block is movably arranged in the activity space. The piston rod of the locking cylinder penetrates through the installation block and is connected and fixed to the locking block to drive the locking block to be located at the bottom of the installation groove, so that the pin column penetrates through the bottom of the installation groove and is inserted into the pin hole.
[0010] Further preferred solution: The insertion plate and the lower module are integrally combined, or the insertion plate and the lower module are fixed by bolts.
[0011] Further preferred solution: The telescopic device includes a base and a telescopic cylinder. The telescopic cylinder is installed on the base, and the blanking die is fixed on the piston rod of the telescopic cylinder.
[0012] Further preferred solution: A contact switch is installed at the discharge end of the third conveying track.
[0013] The automatic punching equipment for metal pipe fittings designed by the present utility model has the following beneficial effects:
[0014] 1. The metal pipe fittings are automatically loaded in batches, and after loading, they are automatically conveyed to the lower part of the stamping station for blanking to form a hole structure. After blanking, they automatically enter the receiving box, thus avoiding production accidents caused by manual placement of metal pipe fittings and improving the production and processing efficiency at the same time.
[0015] 2. The through holes on the upper module often allow the blanking punch to pass through, thus causing wear and needing to be replaced. Therefore, the upper module is installed between the upper module and the lower module through an installation structure, making the disassembly and separation of the upper module more convenient, thus facilitating the replacement of the upper module. Description of the Drawings
[0016] Figure 1 is a schematic diagram of the overall structure (I);
[0017] Figure 2 is a schematic diagram of the overall structure (II);
[0018] Figure 3 is a schematic diagram of the overall structure (III);
[0019] Figure 4 Schematic diagram of the structure of the punching die (I);
[0020] Figure 5 Schematic diagram of the structure of the punching die (II);
[0021] Figure 6 Schematic diagram of the structure of the punching die (III);
[0022] Figure 7 It is a structural diagram of the upper module;
[0023] Figure 8 It is a structural diagram of the locking block.
[0024] In the figure: 1, feeding vibration plate; 11, discharging conveying track; 12, receiving box; 13, waste box; 14, first pushing mechanism; 141, pushing cylinder; 142, pushing block; 15, second pushing mechanism; 2, first conveying track; 20, material passing channel; 21, pushing opening; 22, discharging opening; 3, second conveying track; 4, punching die; 41, upper module; 411, first through hole; 42, lower module; 4 20. Punching channel; 421. Second through hole; 43. Insert plate; 431. Pin hole; 44. Insert hole; 45. Mounting groove; 46. Mounting block; 47. Locking cylinder; 48. Activity space; 49. Locking block; 491. Pin column; 5. Third conveying track; 6. Punching punch; 7. Punching die; 71. Waste channel; 8. Telescopic cylinder; 81. Telescopic cylinder; 82. Base; 9. Contact switch; 10. Frame. DETAILED DESCRIPTION
[0025] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of the utility model.
[0026] Example:
[0027] like Figure 1-Figure 8As shown, the automatic punching equipment for metal pipe fittings described in this embodiment includes a frame 10, a feeding vibration plate 1, a first conveying track 2, a second conveying track 3, a punching and forming mold, a third conveying track 5, a telescopic device 8, a first pushing mechanism 14 and a second pushing mechanism 15, a punching die 7 and a punching punch 6 for forming holes on the metal pipe fittings, wherein the punching punch 6 is installed on a stamping machine.
[0028] The discharge conveying track 11 of the feeding vibration plate 1 is connected to the first conveying track 2. The discharge end of the first conveying track 2 is provided with a push opening 21 and a discharge opening 22 which are arranged opposite to each other. The second conveying track 3 is located beside the discharge opening 22 on the first conveying track 2, and the discharge opening 22 is connected to the feed opening of the second conveying track 3 correspondingly. The first pushing mechanism 14 is arranged beside the push opening 21. The first conveying track 2 and the second conveying track 3 are both made of metal. The feeding vibration plate 1 is conventionally used in the prior art. It will not be described in detail here. During operation, the loading vibration plate 1 is used to load batches of metal pipes one by one and transport them to the first conveying track 2 via the discharge conveying track 11. Then, during the continuous loading process, the metal pipes are transported to the discharge opening 22 of the first conveying track 2. Then, the first pushing mechanism is started to push the metal pipes at this position and displace them and enter the transfer channel 20 of the second conveying track 3 through the discharge opening. The metal pipes in the transfer channel 20 of the second conveying track 3 wait to be pushed into the punching channel 420.
[0029] The punching and forming die and the first pushing mechanism 14 are respectively arranged at the two ends of the second conveying track 3. The punching and forming die is provided with a first through hole 411 for the punching punch 6 to pass through, a second through hole 421 for the punched waste to fall, and a punching channel 420 which is connected and arranged corresponding to the material passage 20 of the second conveying track 3. The first through hole 411 and the second through hole 421 are arranged opposite to each other and are respectively located at the upper and lower sides of the punching die 4. The third conveying track 5 is installed at the discharge end of the punching channel 420. The discharge end of the material passage 20 of the third conveying track 5 is provided with a receiving box 12. A telescopic device 8 is installed on the side opposite to the third conveying track 5, and a contact switch 9 is installed at the discharge end of the third conveying track 5. The shearing die 7 is installed on the telescopic rod of the telescopic device 8 and corresponds to the shearing channel 420 and the transfer channel 20 of the third conveying track 5, so as to drive the shearing die 7 to enter the shearing channel 420 and be located below the first through hole 411, and the two ends of the waste channel 71 on the shearing die 7 are coaxially arranged with the first through hole 411 and the second through hole 421, or the shearing die 7 is driven to exit the shearing channel 420 through the transfer channel 20 of the third conveying track 5 and be located above the receiving box 12.
[0030] When the metal pipe is located in the feeding channel 20 of the second conveying track 3, the second pushing mechanism 15 starts to push the metal pipe at this position into the punching channel 420. At this time, the punched metal pipe is pushed into the feeding channel 20 of the third conveying track 5 and contacts the contact switch 9. Therefore, the PLC controls the telescopic device 8 to work first according to the signal of the contact switch 9, and then drives the impact work. The telescopic device 8 starts to feed the punching die 7 into the metal pipe in the punching channel 420. At this time, the punching die 7 is pushed into the punching channel 420. The two ends of the waste channel 71 on the mold 7 are coaxially arranged with the first through hole 411 and the second through hole 421, and then the punching machine works to drive the punching punch 6 to pass through the first through hole 411 and then punch out the metal pipe in the punching channel 420 to form a hole structure. After the punching is completed, the waste enters the waste box 13 through the waste channel 71, the second through hole 421 and the perforation on the frame, and then the above punching steps are repeated to continuously process and produce batch metal pipes one by one. The whole process is automatically realized, so that the production and processing efficiency is high.
[0031] Preferably, the telescopic device 8 includes a base 82 and a telescopic cylinder 81, the telescopic cylinder 81 is installed on the base 82, and the punching die 7 is fixed on the piston rod of the telescopic cylinder 81, the first pushing mechanism 14 and the second pushing mechanism 15 both include a pushing cylinder 141 and a pushing block 142 installed on the piston rod of the pushing cylinder 141, the two pushing blocks 142 are respectively adapted to the corresponding sizes of the pushing opening 21 and a port of the material transfer channel 20 of the second conveying track 3, so the stamping machine is connected to and controlled by the PLC control, and the two pushing cylinders 141 and the telescopic cylinder 81 are connected to and controlled by the PLC controller through an air pump.
[0032] In this embodiment, the blanking die 4 includes an upper module 41 and a lower module 42. The cross-section of the lower module 42 is in a "U" shape to form a blanking channel 420 on the lower module 42. The upper module 41 is installed on the upper side of the lower module 42 through an installation structure to block the upper opening of the blanking channel 420. A first through hole 411 is provided on the upper module 41, and a second through hole 421 is provided on the lower inner wall of the blanking channel 420. The installation structure includes insertion holes 44 on two longitudinal portions of the lower module 42 and insertion plates 43 provided at opposite ends of the upper module 41. Automatic telescopic pin columns 491 are respectively provided on opposite inner walls of the insertion holes 44, and pin holes 431 are respectively provided on opposite side surfaces of the insertion plates 43. The insertion plates 43 are correspondingly inserted into the insertion holes 44, and the automatic telescopic pin columns 491 are correspondingly inserted into the pin holes 431. Each automatic telescopic pin column 491 includes a locking cylinder 47, a locking block 49, and a pin column 491 provided on the locking block 49. Two installation grooves 45 are provided on two longitudinal portions of the lower module 42. The two installation grooves 45 are respectively on opposite sides of the insertion holes 44. An installation block 46 is fixed by bolts at the notch of the installation groove 45. Each locking cylinder 47 is respectively fixed on the two installation blocks 46. There is a movable space 48 between the installation block 46 and the bottom of the installation groove 45. The locking block 49 is movably arranged in the movable space 48. The piston rod of the locking cylinder 47 penetrates through the installation block 46 and is connected and fixed to the locking block 49 to drive the locking block 49 to be located at the bottom of the installation groove 45, so that the pin column 491 penetrates through the bottom of the installation groove 45 and is inserted into the pin hole 431. Its structural setting makes the disassembly and installation of the upper module 41 convenient, improves the installation efficiency of the upper module 41. The insertion plates 43, the installation blocks 46, the upper module 41, and the lower module 42 are all made of metal materials.
[0033] Preferably, the insertion plate 43 and the lower module 42 are integrally combined, or the insertion plate 43 and the lower module 42 are fixed by bolts.
[0034] The present invention is not limited to the above best embodiment. Anyone can obtain other various forms of products under the inspiration of the present invention. However, no matter what changes are made in its shape or structure, as long as it has a technical solution identical or similar to the present application, it will fall within the protection scope of the present invention.
Claims
1. An automatic punching device for metal pipes, characterized in that: It includes a frame, a feeding vibrating bowl (1), a first conveying track (2), a second conveying track (3), a blanking and forming die, a third conveying track (5), a telescopic device (8), a first pushing mechanism (14) and a second pushing mechanism (15), a blanking female die (7) and a blanking male die (6) for forming holes on metal pipe fittings; The discharging conveying track (11) of the feeding vibrating bowl (1) is butted with the first conveying track (2). Oppositely arranged pushing openings (21) and discharging openings (22) are provided at the discharging end of the first conveying track (2). The second conveying track (3) is located beside the discharging opening (22) on the first conveying track (2), and the discharging opening (22) is correspondingly and communicatively arranged with the feeding opening of the second conveying track (3). The first pushing mechanism (14) is arranged beside the pushing opening (21); The blanking and forming die and the first pushing mechanism (14) are respectively arranged at the two ports of the second conveying track (3). A first through hole (411) for the blanking male die (6) to pass through, a second through hole (421) for the scrap cut off to fall, and a blanking channel (420) correspondingly and communicatively arranged with the material passing channel (20) of the second conveying track (3) are provided on the blanking and forming die. The first through hole (411) and the second through hole (421) are oppositely arranged and are respectively located on the upper and lower sides of the blanking die (4). The third conveying track (5) is installed at the discharging end of the blanking channel (420). A receiving box (12) is provided at the discharging end of the material passing channel (20) of the third conveying track (5). A telescopic device (8) is installed on the side of the receiving box (12) opposite to the third conveying track (5). The blanking female die (7) is installed on the telescopic rod of the telescopic device (8) and corresponds to the blanking channel (420) and the material passing channel (20) of the third conveying track (5) to drive the blanking female die (7) to enter the position below the first through hole (411) after entering the blanking channel (420), and the two ends of the scrap channel (71) on the blanking female die (7) are coaxially arranged with the first through hole (411) and the second through hole (421), or drive the blanking female die (7) to exit the blanking channel (420) through the material passing channel (20) of the third conveying track (5) and be located above the receiving box (12).
2. The automatic punching equipment for metal pipes according to claim 1, characterized in that: The blanking die (4) includes an upper module (41) and a lower module (42). The cross section of the lower module (42) is in a "U" shape to form a blanking channel (420) on the lower module (42). The upper module (41) is installed on the upper side of the lower module (42) through an installation structure to block the upper opening of the blanking channel (420). The first through hole (411) is provided on the upper module (41), and the second through hole (421) is provided on the lower inner wall of the blanking channel (420).
3. The automatic punching equipment for metal pipes according to claim 2, characterized in that: The mounting structure comprises a plug hole (44) located on two longitudinal parts of the lower module (42) and a plug plate (43) arranged at opposite ends of the upper module (41), and automatic telescopic pins (491) are respectively arranged on two opposite inner walls of the plug hole (44), and pin holes (431) are respectively arranged on two opposite side surfaces of the plug plate (43), the plug plate (43) is correspondingly inserted into the plug hole (44), and the automatic telescopic pins (491) are correspondingly inserted into the pin holes (431).
4. The automatic punching equipment for metal pipes according to claim 3, characterized in that: Each automatic telescopic pin (491) comprises a locking cylinder (47), a locking block (49) and a pin (491) arranged on the locking block (49). Two mounting grooves (45) are arranged on the two longitudinal parts of the lower module (42). The two mounting grooves (45) are respectively located on opposite sides of the insertion hole (44). A mounting block (46) is fixed at the groove of the mounting groove (45). Each locking cylinder (47) is respectively fixed on the two mounting blocks (46). There is an active space (48) between the mounting block (46) and the groove bottom of the mounting groove (45). The locking block (49) is movably arranged in the active space (48). The piston rod of the locking cylinder (47) penetrates the mounting block (46) and is connected and fixed to the locking block (49) to drive the locking block (49) to be located at the groove bottom position of the mounting groove (45), so that the pin (491) penetrates the groove bottom of the mounting groove (45) and is inserted into the pin hole (431).
5. The automatic punching equipment for metal pipes according to claim 3, characterized in that: The plug plate (43) and the lower module (42) are combined with each other into an integral structure, or the plug plate (43) and the lower module (42) are fixed by bolts.
6. The automatic punching equipment for metal pipes according to claim 1, characterized in that: The telescopic device (8) comprises a base (82) and a telescopic cylinder (81), the telescopic cylinder (81) is mounted on the base (82), and the punching die (7) is fixed on the piston rod of the telescopic cylinder (81).
7. The automatic punching equipment for metal pipes according to claim 1, characterized in that: A contact switch (9) is installed at the discharge end of the third conveying track (5).