Heavy-load balance hoisting device for building machine and building machine

By designing a heavy-load balanced lifting device for movable walking platforms, walking trolleys and lifting components, the problems of insufficient lifting capacity, limited coverage and poor stability in the prior art are solved, and a wider coverage, higher stability and higher construction efficiency are achieved.

CN222593284UActive Publication Date: 2025-03-11CHINA STATE CONSTR HAILONG TECH CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420806392.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-18
Publication Date
2025-03-11
Estimated Expiration
2034-04-18

AI Technical Summary

Technical Problem

When facing large prefabricated MiC products, the existing building machine lifting equipment has insufficient lifting capacity, limited working coverage, and poor lifting stability, resulting in low construction safety and accuracy.

Method used

A heavy-load balanced lifting device is designed, including a walking platform that can be moved in the Y direction, a walking car that can be moved in the X direction, and a lifting assembly that can be lifted in the Z direction, combining a multi-point lifting point and a detachable second hook to achieve flexible lifting in three-dimensional space.

Benefits of technology

The coverage of lifting operations has been expanded, the balance and stability of lifting is improved, the problem of lifting tilt is avoided, the versatility and applicability of lifting devices have been enhanced, and the safety and efficiency of construction have been improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222593284U_ABST
    Figure CN222593284U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building machines, in particular to a heavy-load balance hoisting device for a building machine and the building machine, and the heavy-load balance hoisting device comprises a walking platform, a walking trolley, a lifting assembly and a hoisting frame for hoisting products, the two opposite ends of the walking platform are used for being movably connected to hanging frames on the two opposite sides of the building machine in the Y direction correspondingly. The walking trolley is borne on the walking platform, and the walking trolley is movably connected to the walking platform in the X direction; the lifting assembly is borne on the walking trolley and provided with a hoisting part capable of moving in the Z direction, and the hoisting part is connected with the hanging bracket. The heavy-load balance hoisting device can adapt to heavy load, and has large-range coverage capability and a multi-point balance adjusting function.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction machines, in particular to a heavy-load balancing hoisting device for a building construction machine and the building construction machine. Background Art

[0002] In the modern construction industry, with the acceleration of industrialization, especially the development of modular integrated construction (MiC) technology, the volume and weight of prefabricated components have increased significantly, which has brought great challenges to the traditional building material lifting system. For example, the unit weight of advanced prefabricated MiC products can be as high as 20 tons, far exceeding the lifting capacity of conventional tower cranes. Especially when these heavy components need to be accurately lifted from the top of the building, the existing lifting methods show obvious limitations.

[0003] At present, building construction machines generally use tower cranes (tower cranes) as the main material lifting equipment at construction sites. However, due to the design load limit of the tower crane and the working coverage of the boom, the overweight MiC products cannot effectively cover the entire construction area and there are safety risks caused by excessive load. At the same time, as part of the building construction machine, the structural characteristics of the Bailey platform truss determine that it has certain constraints on the spatial layout of the lifting operation, which further limits the working range and flexibility of the lifting device.

[0004] In addition, the existing connection method between tower cranes and hangers is mostly a single-point connection design. This method is easy to cause tilting during the lifting process when lifting MiC products whose center of gravity is inconsistent with the lifting point position, seriously affecting the safety and accuracy of the lifting, and is not conducive to the efficient and stable installation of MiC products on building construction machines.

[0005] In view of this, it is urgent to develop a lifting device that can adapt to heavy loads, has a wide coverage range and multi-point balance adjustment functions, so as to overcome the shortcomings of existing technologies in the lifting operations of large-scale prefabricated MiC products and ensure the safe and efficient progress of construction. Utility Model Content

[0006] 1. Technical issues to be resolved

[0007] In view of the above-mentioned shortcomings and deficiencies of the prior art, the utility model provides a heavy-load balanced lifting device for a building construction machine and a building construction machine, which solves the technical problems of insufficient lifting capacity, limited working coverage and poor lifting stability of the existing devices.

[0008] (II) Technical solution

[0009] In order to achieve the above-mentioned purpose, the main technical solutions adopted by the utility model include:

[0010] In the first aspect, the embodiment of the utility model provides a heavy-load balanced lifting device for a building construction machine, comprising a walking platform 11, a walking trolley 12, a lifting assembly 13 and a hanger 14 for lifting products;

[0011] The two opposite ends of the walking platform 11 are used to be movably connected to the two opposite side brackets 3 of the building construction machine 2 along the Y direction;

[0012] The traveling trolley 12 is carried on the traveling platform 11 and is movably connected to the traveling platform 11 along the X direction; the lifting assembly 13 is carried on the traveling trolley 12 and has a lifting part that can move along the Z direction, and the lifting part is connected to the hanger 14.

[0013] Optionally, the walking trolley 12 includes a trolley body 121, a trolley driving wheel 122 mounted on the trolley body 121, and a trolley driving motor 123;

[0014] The trolley body 121 is carried on the walking platform 11 through the trolley driving wheel 122, and the trolley driving motor 123 is drivingly connected to the trolley driving wheel 122. When the trolley driving motor 123 works, it drives the trolley driving wheel 122 to move along the X direction on the walking platform 11.

[0015] Optionally, the lifting assembly 13 includes a motor 131 and at least three sets of lifting members 132;

[0016] At least three groups of lifting components 132 are evenly distributed around the center of gravity of the hanger 14, and each group of lifting components 132 includes a lifting rope 1321, a roller 1322 and a first hook 1323;

[0017] The motor 131 is fixedly mounted on the walking trolley 12, the first end of the lifting rope 1321 is connected to the motor 131, the second end of the lifting rope 1321 is connected to the drum 1322, the first hook 1323 is fixedly mounted on the bottom of the drum 1322, and the first hook 1323 is connected to the hanger 14; when the motor 131 works, it drives at least three groups of lifting components 132 to rise or fall.

[0018] Optionally, the lifting assembly 13 includes four groups of lifting components 132 .

[0019] Optionally, the trolley body 121 is a rectangular basket structure with five faces opening upward; the motor 131 is fixedly installed inside the basket structure and fixedly connected to the bottom plate of the basket structure.

[0020] Optionally, the walking platform 11 includes a rectangular frame 111, a platform driving wheel 112 and a platform driving motor 113;

[0021] The rectangular frame 111 includes a first walking beam 1111, a first box-shaped main beam 1112, a second walking beam 1113, and a second box-shaped main beam 1114 which are sequentially connected and surround to form a rectangle;

[0022] The bottom end of the first walking beam 1111 and the bottom end of the second walking beam 1113 are respectively installed with platform driving wheels 112;

[0023] The rectangular frame 111 is supported on the opposite side brackets of the building construction machine 2 through the platform driving wheel 112. The platform driving motor 113 is connected to the platform driving wheel 112. When the platform driving motor 113 works, it drives the platform driving wheel 112 to move along the Y direction on the opposite side brackets 3 of the building construction machine 2.

[0024] Optionally, a plurality of suspension point installation positions are provided on the lower surface of the hanger 14, and a second suspension hook is detachably installed on at least some of the suspension point installation positions;

[0025] The position of the second hook corresponds to the position of the upper surface ring of the assembled building product.

[0026] Optionally, at least two guide posts 141 are disposed on the upper surface of the hanger 14 , and at least two conical sleeves corresponding to the guide posts 141 are disposed on the lower surface of the trolley body 121 .

[0027] Optionally, a mobile terminal is also included.

[0028] The mobile terminal is communicatively connected with the walking platform 11 , the walking trolley 12 , and the lifting assembly 13 , respectively.

[0029] In the second aspect, an embodiment of the utility model provides a building construction machine, comprising a heavy-load balanced lifting device 1 as described in any one of the first aspects above and a hanger 3 for surrounding a building body, wherein the opposite ends of a walking platform 11 of the heavy-load balanced lifting device 1 are movably connected to opposite sides of the hanger 3.

[0030] (III) Beneficial effects

[0031] The utility model discloses a heavy-load balancing lifting device for a building construction machine and a building construction machine. By designing a walking platform that can move along the Y direction, the walking platform can flexibly adjust its position on the brackets on both sides of the building construction machine according to construction requirements, thereby expanding the coverage of the lifting operation. The walking trolley moves on the walking platform along the X direction, and combined with the lifting function of the lifting component along the Z direction, flexible lifting in three-dimensional space is realized, effectively solving the problem of insufficient lifting capacity.

[0032] Furthermore, the lifting assembly adopts at least three groups of evenly distributed lifting components, which are synchronously driven by electric motors to ensure balance and stability when lifting heavy-loaded MiC products, avoid the problem of lifting tilt caused by the inconsistency between the lifting point and the center of gravity, and through the reasonable configuration of multiple lifting point installation positions on the lower surface of the hanger and the detachable second hook, it can adapt to the lifting requirements of different models of MiC products, thereby enhancing the versatility and applicability of the lifting device;

[0033] In addition, the main body of the trolley adopts a rectangular basket structure design with five openings facing upwards, which not only ensures the structural strength but also provides a stable installation space for the motor. The driving mode of the walking platform and the lifting components are all driven by motor-driven wheels, which not only ensures the reliability of the drive but also realizes accurate and efficient movement and lifting control.

[0034] Finally, by setting guide columns on the hanger and corresponding conical sleeves on the lower surface of the trolley body, the shaking of the hanger can be limited during the lifting process, thereby improving the lifting accuracy and safety. At the same time, the introduction of mobile terminals for remote monitoring and control further improves the intelligence level and construction efficiency of the lifting operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 A structural schematic diagram of a heavy-load balancing lifting device for a building construction machine provided in one embodiment of the utility model;

[0036] Figure 2 The present invention is a schematic structural diagram of a building construction machine provided in another embodiment of the present invention.

[0037] [Description of Reference Numerals]

[0038] 1: Heavy load balance lifting device;

[0039] 11: walking platform, 12: walking trolley, 13: lifting assembly, 14: hanger;

[0040] 111: rectangular frame, 112: platform driving wheel, 113: platform driving motor;

[0041] 121: trolley body, 122: trolley driving wheel, 123: trolley driving motor;

[0042] 131: motor, 132: lifting member; 141: guide column;

[0043] 1111: first walking beam, 1112: first box-type main beam, 1113: second walking beam, 1114: second box-type main beam;

[0044] 1321: lifting rope, 1322: drum, 1323: first hook;

[0045] 2: Building machine;

[0046] 3: Hanging bracket. DETAILED DESCRIPTION

[0047] In order to better explain the present invention and facilitate understanding, the present invention is described in detail below in conjunction with the accompanying drawings through specific implementation methods. Figure 2 The direction shown in the coordinate system shall prevail.

[0048] Embodiment 1

[0049] Figure 1 A heavy-load balanced lifting device for a building construction machine provided in this embodiment includes a walking platform 11, a walking trolley 12, a lifting assembly 13 and a hanger 14 for lifting products.

[0050] Specifically, the walking platform 11 includes a rectangular frame 111, a platform driving wheel 112 and a platform driving motor 113;

[0051] The rectangular frame 111 includes a first walking beam 1111, a first box-shaped main beam 1112, a second walking beam 1113, and a second box-shaped main beam 1114 which are sequentially connected and surround to form a rectangle;

[0052] The bottom end of the first walking beam 1111 and the bottom end of the second walking beam 1113 are respectively installed with platform driving wheels 112;

[0053] The rectangular frame 111 is carried on the opposite side brackets of the building construction machine 2 through the platform driving wheel 112, and the platform driving motor 113 is connected to the platform driving wheel 112. When the platform driving motor 113 works, it drives the platform driving wheel 112 to move along the Y direction on the opposite side brackets 3 of the building construction machine 2;

[0054] In this embodiment, the platform driving motor 113 is connected to the power supply of the bracket of the building construction machine 2 .

[0055] The walking trolley 12 includes a trolley body 121, a trolley driving wheel 122 mounted on the trolley body 121, and a trolley driving motor 123;

[0056] The trolley body 121 is carried on the first box-type main beam 1112 and the second box-type main beam 1114 of the walking platform 11 through the trolley driving wheel 122. The trolley driving motor 123 is connected to the trolley driving wheel 122. When the trolley driving motor 123 works, it drives the trolley driving wheel 122 to move along the X direction on the walking platform 11.

[0057] In this embodiment, the lifting assembly 13 includes a motor 131 and four sets of lifting components 132;

[0058] Four groups of lifting components 132 are evenly distributed around the center of gravity of the hanger 14, and each group of lifting components 132 includes a lifting rope 1321, a roller 1322 and a first hook 1323;

[0059] Preferably, the lifting rope 1321 is a steel wire rope;

[0060] In this embodiment, the vehicle body 121 is a rectangular frame structure with five faces with openings facing upward; the motor 131 is fixedly installed inside the frame structure and is fixedly connected to the bottom plate of the frame structure;

[0061] The first end of the lifting rope 1321 is connected to the motor 131, the second end of the lifting rope 1321 is connected to the drum 1322, the first hook 1323 is fixedly installed at the bottom of the drum 1322, and the first hook 1323 is connected to the hanger 14; the motor 131 works to drive the four groups of lifting components 132 to rise or fall.

[0062] Preferably, a plurality of hanging point installation positions are provided on the lower surface of the hanger 14, and a second hanging hook is detachably installed on at least some of the hanging point installation positions;

[0063] The position of the second hook corresponds to the position of the lifting ring on the upper surface of the prefabricated building product, and can be adapted to the position of the lifting ring of each model of MiC product. The second hook is connected to the hanger 14 with a safety shackle, which makes it convenient and quick to change the relative position of the second hook.

[0064] In this embodiment, four guide columns 141 are provided on the upper surface of the hanger 14, and four conical sleeves corresponding to the guide columns 141 are provided on the lower surface of the trolley body 121. When the hanger 14 is lifted to the upper limit position, the guide columns 141 on the hanger 14 and the conical sleeves on the lower surface of the trolley body 121 are nested together, which can limit the shaking of the hanger in the X or Y direction due to factors such as acceleration and wind force.

[0065] Optionally, the heavy-load balance lifting device also has a mobile terminal, and the walking platform 11, the walking trolley 12 and the lifting assembly 13 are all equipped with corresponding controllers.

[0066] The mobile terminal is respectively connected to the walking platform 11, the walking trolley 12, and the lifting assembly 13 for communication to control the lifting work of the heavy-load balancing lifting device.

[0067] Embodiment 2

[0068] like Figure 2 As shown, this embodiment provides a building construction machine, comprising the heavy-load balanced lifting device 1 described in the first embodiment and a hanging frame 3 for surrounding a building body, the opposite ends of the walking platform 11 of the heavy-load balanced lifting device 1 are movably connected to the opposite sides of the hanging frame 3,

[0069] In this embodiment, a track beam is fixedly mounted on the hanger 3, and opposite ends of the walking platform 11 of the heavy-load balancing lifting device 1 are connected to the track beam through platform driving wheels;

[0070] A plurality of hydraulic jacks are installed at the bottom of the hanging frame 3 of the building construction machine 2, so that the building construction machine 2 can be moved in the Z direction.

[0071] In the description of the present utility model, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0072] In the present invention, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0073] In the present utility model, unless otherwise clearly specified and limited, when a first feature is “on” or “below” a second feature, it may be that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, when a first feature is “above”, “above” or “above” a second feature, it may be that the first feature is directly above or obliquely above the second feature, or it may simply mean that the first feature is higher in level than the second feature. When a first feature is “below”, “below” or “below” a second feature, it may be that the first feature is directly below or obliquely below the second feature, or it may simply mean that the first feature is lower in level than the second feature.

[0074] In the description of this specification, the description of the terms "one embodiment", "some embodiments", "embodiment", "example", "specific example" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.

[0075] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are illustrative and cannot be understood as limitations of the present invention. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present invention.

Claims

1. A heavy-load balancing lifting device for a building construction machine, characterized in that: It comprises a walking platform (11), a walking trolley (12), a lifting assembly (13) and a hanger (14) for hanging products; The two opposite ends of the walking platform (11) are used to be movably connected to the two opposite side brackets (3) of the building construction machine (2) along the Y direction; The traveling trolley (12) is carried on the traveling platform (11), and the traveling trolley (12) is movably connected to the traveling platform (11) along the X direction; the lifting assembly (13) is carried on the traveling trolley (12), and the lifting assembly (13) has a lifting part that can move along the Z direction, and the lifting part is connected to the hanging frame (14).

2. The heavy-load balancing lifting device for a building construction machine according to claim 1, characterized in that: The walking trolley (12) comprises a trolley body (121), a trolley driving wheel (122) mounted on the trolley body (121), and a trolley driving motor (123); The trolley body (121) is carried on the walking platform (11) via the trolley driving wheel (122), the trolley driving motor (123) is drivingly connected to the trolley driving wheel (122), and the trolley driving motor (123) works to drive the trolley driving wheel (122) to move on the walking platform (11) along the X direction.

3. The heavy-load balancing lifting device for a building construction machine according to claim 1 or 2, characterized in that: The lifting assembly (13) comprises a motor (131) and at least three sets of lifting components (132); At least three groups of lifting components (132) are evenly distributed around the center of gravity of the hanger (14), and each group of lifting components (132) includes a lifting rope (1321), a roller (1322) and a first hook (1323); The motor (131) is fixedly mounted on the walking trolley (12); the first end of the lifting rope (1321) is connected to the motor (131); the second end of the lifting rope (1321) is connected to the roller (1322); the first hook (1323) is fixedly mounted on the bottom of the roller (1322); and the first hook (1323) is connected to the hanger (14); when the motor (131) is in operation, it drives at least three groups of lifting components (132) to rise or fall.

4. The heavy-load balancing lifting device for a building construction machine according to claim 3, characterized in that: The lifting assembly (13) includes four groups of lifting components (132).

5. The heavy-load balancing lifting device for a building construction machine according to claim 3, characterized in that: The trolley body (121) is a rectangular basket structure with five openings facing upwards; the motor (131) is fixedly installed inside the basket structure and fixedly connected to the bottom plate of the basket structure.

6. The heavy-load balancing lifting device for a building construction machine according to claim 1, characterized in that: The walking platform (11) comprises a rectangular frame (111), platform driving wheels (112) and a platform driving motor (113); The rectangular frame (111) comprises a first walking beam (1111), a first box-type main beam (1112), a second walking beam (1113), and a second box-type main beam (1114) which are sequentially connected and surrounded to form a rectangle; The bottom ends of the first walking beam (1111) and the second walking beam (1113) are respectively equipped with platform driving wheels (112); The rectangular frame (111) is supported on two opposite side brackets of the building construction machine (2) via the platform driving wheel (112); the platform driving motor (113) is drivingly connected to the platform driving wheel (112); when the platform driving motor (113) is in operation, it drives the platform driving wheel (112) to move along the Y direction on the two opposite side brackets (3) of the building construction machine (2).

7. The heavy-load balancing lifting device for a building construction machine according to claim 1, characterized in that: A plurality of hanging point installation positions are arranged on the lower surface of the hanger (14), and a second hanging hook is detachably installed on at least some of the hanging point installation positions; The position of the second hook corresponds to the position of the lifting ring on the upper surface of the assembled building product.

8. The heavy-load balancing lifting device for a building construction machine according to claim 1, characterized in that: At least two guide columns (141) are arranged on the upper surface of the hanger (14), and at least two conical sleeves corresponding to the guide columns (141) are arranged on the lower surface of the trolley body (121).

9. The heavy-load balancing lifting device for a building construction machine according to claim 1, characterized in that: Also includes a mobile terminal, The mobile terminal is respectively connected to the walking platform (11), the walking trolley (12) and the lifting component (13) for communication.

10. A building construction machine, characterized in that: It comprises a heavy-load balancing lifting device (1) as described in any one of claims 1 to 9 and a hanger (3) for surrounding a building, wherein the opposite ends of a walking platform (11) of the heavy-load balancing lifting device (1) are movably connected to opposite sides of the hanger (3).