Elevator foundation pit structure

By using a quick installation method of T-troughs and T-blocks in the construction of elevator foundation pits, combined with asphalt layer, fixing frame and limiting grooves, the traditional problems of low construction efficiency and long cycle are solved, and the rapid installation and efficient construction of elevator foundation pits are achieved.

CN222594864UActive Publication Date: 2025-03-11FACTORY MENTOR JOINT ENG (SHANGHAI) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420815016.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-18
Publication Date
2025-03-11
Estimated Expiration
2034-04-18

AI Technical Summary

Technical Problem

Traditional elevator foundation pit construction methods are inefficient and have long cycles, resulting in longer construction time.

Method used

An elevator foundation pit structure is adopted, including a base plate, a first side plate and a second side plate, which is quickly installed through the cooperation of the T-trough and the T-block, and the construction efficiency and firmness are improved through asphalt layer, fixing frame and limit groove components.

Benefits of technology

It realizes rapid installation of elevator foundation pits, shortens construction cycles, improves construction efficiency, and enhances the waterproofness and stability of foundation pits through the use of asphalt layers and fixing frames.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222594864U_ABST
    Figure CN222594864U_ABST
Patent Text Reader

Abstract

The utility model discloses an elevator foundation pit structure, and relates to the technical field of elevators. The device comprises a bottom plate, the two ends of the top of the bottom plate are each provided with a first side plate, the two sides of the top of the bottom plate are each provided with a second side plate, the top of the bottom plate is provided with an assembling assembly, the bottom of the bottom plate is provided with a fixing assembly, and the two sides of the top of the bottom plate are each provided with a second T-shaped groove. According to the elevator foundation pit, the second T-shaped blocks and the second T-shaped grooves are matched to mount the second side plates, then the first T-shaped blocks and the first T-shaped grooves are matched to mount the first side plates, and the enclosed space is the elevator foundation pit, so that the beneficial effects of being simple in operation and fast in mounting are achieved, meanwhile, the construction efficiency is improved, and the construction period is shortened; and meanwhile, through cooperation of a limiting groove and a limiting plate, the second T-shaped block is limited, and the second T-shaped block is prevented from sliding in the second T-shaped groove.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of elevators, and in particular to an elevator foundation pit structure. Background Art

[0002] Elevators are common equipment in our lives. The elevator shaft is the shaft where the elevator is installed in the building. The elevator shaft must be constructed before the elevator is installed. The elevator foundation pit is an indispensable process in the construction of the elevator shaft. The elevator foundation pit refers to the place where the elevator installs some components such as buffers. The traditional construction method is: foundation excavation, pile head treatment, foundation cushion, casting frame, backfilling, protective structure, foundation pit monitoring, and equipment installation.

[0003] Casting the frame is an important process in construction. Before casting the frame, the formwork must be supported and erected first, then installed, reinforced and corrected, and finally cast.

[0004] However, the construction methods and processes used to install elevator foundation pits in existing buildings are relatively traditional. In this traditional construction method, the cast frame needs to be made on-site, which makes the construction efficiency of the elevator foundation pit low and the construction period long. Utility Model Content

[0005] The purpose of this application is to solve the problems of low construction efficiency and long construction period of elevator foundation pit, and this application provides an elevator foundation pit structure.

[0006] In order to achieve the above-mentioned purpose, this application specifically adopts the following technical solutions:

[0007] An elevator foundation pit structure comprises a base plate, first side plates are installed at both ends of the top of the base plate, second side plates are installed on both sides of the top of the base plate, an assembly component is arranged on the top of the base plate, a fixing component is arranged on the bottom of the base plate, second T-shaped slots are constructed on both sides of the top of the base plate, the assembly component comprises two second T-shaped blocks respectively fixed on the bottoms of the two second side plates, and the two second T-shaped blocks are respectively adapted to the two second T-shaped slots, first T-shaped slots are symmetrically constructed on the sides of the two second side plates close to each other, multiple first T-shaped blocks are fixed on both sides of the first side plate, and the multiple first T-shaped blocks are respectively adapted to the two first T-shaped slots.

[0008] By adopting the above technical solution, the second side panel is installed by cooperating with the second T-shaped block and the second T-shaped slot, and then the first side panel is installed by cooperating with the first T-shaped block and the first T-shaped slot. The bottom panel, the first side panel and the second side panel are all steel plates, and then the bottom panel is fixed by a fixing assembly.

[0009] Furthermore, the fixing assembly includes four steel plugs fixed at the four corners of the bottom of the base plate, and the surfaces of the steel plugs are fixed with abutment plates.

[0010] By adopting the above technical solution, the bottom plate is fixed by inserting the steel plug into the bottom of the foundation pit, and at the same time the abutment plate abuts against the earth pit, so that a certain distance is maintained between the bottom plate and the earth pit.

[0011] Furthermore, an asphalt layer is fixed on the top of the bottom plate, an asphalt layer is fixed on one end of the two first side plates close to each other, and an asphalt layer is fixed on one side of the two second side plates close to each other.

[0012] By adopting the above technical solution, the asphalt layer can achieve a waterproofing effect.

[0013] Furthermore, a fixing frame is fixed to each of the ends of the two first side panels that are away from each other.

[0014] By adopting the above technical solution, the contact area between the foundation pit and the concrete during pouring can be increased through the fixing frame.

[0015] Furthermore, a circular hole is symmetrically configured at the top of the second side plate, a plurality of inclined holes are configured in the circular hole, and the plurality of inclined holes are all interconnected with the first T-shaped groove.

[0016] By adopting the above technical solution, cement sand can be injected into the first T-shaped groove through the circular hole and the inclined hole, so as to fix the first side plate and the second side plate.

[0017] Furthermore, both ends of the first side plate are configured with L-shaped grooves, and the L-shaped grooves are connected to the first T-shaped grooves.

[0018] By adopting the above technical solution, the cement sand can be brought into contact with the inside of the second side plate through the L-shaped groove, thereby increasing the contact area between the second side plate and the cement sand.

[0019] Furthermore, both ends of the top of the bottom plate are constructed with limiting grooves, and limiting plates are fixed to the bottoms of the two first side plates, and the limiting plates are located in the limiting grooves.

[0020] By adopting the above technical solution, the second T-shaped block can be limited by the cooperation of the limiting groove and the limiting plate.

[0021] In summary, the present application includes at least one of the following beneficial effects:

[0022] 1. The second side panel is installed by cooperating with the second T-block and the second T-slot, and then the first side panel is installed by cooperating with the first T-block and the first T-slot. The enclosed space is the elevator foundation pit, thereby achieving the benefit of fast installation, while accelerating construction efficiency and reducing construction period. At the same time, the second T-block is limited by cooperating with the limit groove and the limit plate to prevent the second T-block from sliding in the second T-slot.

[0023] 2. Mud and sand can be injected through the circular hole. The injected mud and sand flows into the inclined hole through the circular hole, and then flows into the first T-shaped groove and the L-shaped groove to fix the first side plate and the second side plate, thereby increasing the firmness of the foundation pit. At the same time, the asphalt layer can play a waterproof role and protect the electrical components inside the elevator shaft. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a three-dimensional structural schematic diagram of the elevator foundation pit in this application;

[0025] Figure 2 is a cross-sectional view of the second side panel in the present application;

[0026] Figure 3 is a cross-sectional view of the first side panel in the present application;

[0027] Figure 4 This application Figure 2 The enlarged structural diagram at A in the middle;

[0028] Figure 5 This application Figure 3 Enlarged structural diagram at B in the middle.

[0029] Description of reference numerals:

[0030] 1. Bottom plate; 2. First side plate; 3. Second side plate; 4. Asphalt layer; 5. Fixing frame; 6. Steel plug; 7. Resistance plate; 8. First T-shaped block; 9. Second T-shaped block; 10. Round hole; 11. Oblique hole; 12. First T-shaped slot; 13. L-shaped slot; 15. Limiting slot; 16. Limiting plate. DETAILED DESCRIPTION

[0031] The following is combined with Figure 1-5 This application is described in further detail.

[0032] An embodiment of the present application discloses an elevator foundation pit structure.

[0033] Reference Figure 1 , Figure 2 and Figure 5, an elevator foundation pit structure, including a bottom plate 1, first side plates 2 are installed at both ends of the top of the bottom plate 1, second side plates 3 are installed on both sides of the top of the bottom plate 1, an assembly component is arranged on the top of the bottom plate 1, a fixing component is arranged on the bottom of the bottom plate 1, second T-shaped slots are constructed on both sides of the top of the bottom plate 1, the assembly component includes two second T-shaped blocks 9 respectively fixed at the bottoms of the two second side plates 3, and the two second T-shaped blocks 9 are respectively adapted to the two second T-shaped slots, the two second side plates 3 are symmetrically constructed with first T-shaped slots 12 on the sides close to each other, and multiple first T-shaped blocks 8 are fixed on both sides of the first side plate 2, and the multiple first T-shaped blocks 8 are respectively adapted to the two first T-shaped slots 12. During installation, first install the second T-block 9 in the second T-slot, install the second side panel 3, and then install the first T-block 8 in the first T-slot 12, and install the first side panel 2, thereby achieving the advantages of simple operation and fast installation. The enclosed space is the installation space of the elevator shaft, which speeds up the construction efficiency and reduces the construction period. The bottom plate 1, the first side panel 2 and the second side panel 3 are all steel plates, and then the bottom plate 1 is fixed in the pit through the fixing assembly.

[0034] Reference Figure 1-2 The fixing assembly includes four steel plugs 6 fixed at the four corners of the bottom of the bottom plate 1, and the surface of the steel plugs 6 is fixed with a contact plate 7. The steel plugs 6 are inserted into the bottom of the foundation pit, and then the contact plate 7 contacts the soil pit, so that a certain distance is maintained between the bottom plate 1 and the bottom of the foundation pit, and concrete can be poured on the bottom of the bottom plate 1.

[0035] Reference Figure 1-2 An asphalt layer 4 is fixed on the top of the bottom plate 1, an asphalt layer 4 is fixed on the ends of the two first side plates 2 close to each other, and an asphalt layer 4 is fixed on the sides of the two second side plates 3 close to each other. The asphalt layer 4 can play a waterproof role and protect the electrical components inside the elevator shaft.

[0036] Reference Figure 1-2 , the ends of the two first side plates 2 that are away from each other are both fixed with a fixing frame 5. The fixing frame 5 can interfere with the soil pit, and the contact area between the foundation pit and the concrete is increased during pouring, making the pouring more firm.

[0037] Reference Figure 2 and Figure 4 The second side plate 3 has a circular hole 10 symmetrically formed on the top, and a plurality of inclined holes 11 are formed inside the circular hole 10, and the plurality of inclined holes 11 are interconnected with the first T-shaped groove 12. Through the circular hole 10 and the inclined hole 11, cement sand can be injected into the first T-shaped groove 12 to fix the first side plate 2 and the second side plate 3, thereby improving the sealing performance between the first side plate 2 and the second side plate 3.

[0038] Reference Figure 4-5Both ends of the first side plate 2 are constructed with L-shaped grooves 13, and the L-shaped grooves 13 are connected to the first T-shaped grooves 12. Through the L-shaped grooves 13, cement sand can contact the inside of the second side plate 3, increasing the contact area between the second side plate 3 and the cement sand, and improving the stability of the elevator foundation pit.

[0039] Reference Figure 5 , both ends of the top of the bottom plate 1 are configured with limiting grooves 15, and limiting plates 16 are fixed to the bottoms of the two first side plates 2, and the limiting plates 16 are located in the limiting grooves 15. The limiting grooves 15 and the limiting plates 16 cooperate to limit the second T-shaped block 9, so as to prevent the second T-shaped block 9 from sliding in the second T-shaped groove after the foundation pit is installed.

[0040] The implementation principle of the elevator foundation pit structure of this embodiment is as follows: during construction, the second T-shaped block 9 is first installed in the second T-shaped groove, and the second side plate 3 is installed, and then the first T-shaped block 8 is installed in the first T-shaped groove 12, and the first side plate 2 is installed. At the same time, the second T-shaped block 9 is limited by the cooperation of the limiting groove 15 and the limiting plate 16 to prevent the second T-shaped block 9 from sliding in the second T-shaped groove. At this time, the enclosed space is the installation space of the elevator shaft, which achieves the advantage of fast installation, speeds up the construction efficiency, and reduces the construction period. Then, the entire assembled structure is lifted by a crane. It is hoisted into the foundation pit, and then the steel plug 6 is inserted into the bottom of the foundation pit to fix the bottom plate 1, and then the abutment plate 7 abuts against the soil pit, so that a certain distance is maintained between the bottom plate 1 and the bottom of the foundation pit, and concrete can be poured between the bottom plate 1 and the bottom of the foundation pit, and then the mud and sand are injected into the circular hole 10, so that it flows into the inclined hole 11, and then flows into the first T-shaped groove 12 and the L-shaped groove 13, to fix the first side plate 2 and the second side plate 3, thereby increasing the firmness between the first side plate 2 and the second side plate 3, and at the same time the asphalt layer 4 can play a waterproof role to protect the electrical components inside the elevator shaft.

Claims

1. An elevator foundation pit structure, comprising a bottom plate (1), characterized in that: Both ends of the top of the bottom plate (1) are mounted with first side plates (2), both sides of the top of the bottom plate (1) are mounted with second side plates (3), the top of the bottom plate (1) is provided with an assembly component, the bottom of the bottom plate (1) is provided with a fixing component, both sides of the top of the bottom plate (1) are constructed with second T-shaped grooves, the assembly component comprises two second T-shaped blocks (9) respectively fixed to the bottoms of the two second side plates (3), and the two second T-shaped blocks (9) are respectively adapted to the two second T-shaped grooves, the two second side plates (3) are symmetrically constructed with first T-shaped grooves (12) on the sides close to each other, and a plurality of first T-shaped blocks (8) are fixed to both sides of the first side plate (2), and the plurality of first T-shaped blocks (8) are respectively adapted to the two first T-shaped grooves (12).

2. An elevator foundation pit structure according to claim 1, characterized in that: The fixing assembly comprises four steel plugs (6) fixed at the four corners of the bottom of the base plate (1), and a contact plate (7) is fixed on the surface of the steel plugs (6).

3. An elevator foundation pit structure according to claim 1, characterized in that: An asphalt layer (4) is fixed on the top of the bottom plate (1), an asphalt layer (4) is fixed on one end of the two first side plates (2) close to each other, and an asphalt layer (4) is fixed on one side of the two second side plates (3) close to each other.

4. The elevator foundation pit structure according to claim 1, characterized in that: A fixing frame (5) is fixed to each of the two first side plates (2) at ends away from each other.

5. The elevator foundation pit structure according to claim 1, characterized in that: A circular hole (10) is symmetrically formed on the top of the second side plate (3), a plurality of inclined holes (11) are formed inside the circular hole (10), and the plurality of inclined holes (11) are all interconnected with the first T-shaped groove (12).

6. The elevator foundation pit structure according to claim 1, characterized in that: Both ends of the first side plate (2) are formed with L-shaped grooves (13), and the L-shaped groove (13) and the first T-shaped groove (12) are connected to each other.

7. The elevator foundation pit structure according to claim 1, characterized in that: Both ends of the top of the bottom plate (1) are formed with limiting grooves (15), and limiting plates (16) are fixed to the bottoms of the two first side plates (2), and the limiting plates (16) are located in the limiting grooves (15).