Water mist spraying device for floating dock

By installing a water mist spray device in the floating dock, and using nozzles to form water mist to spray the surface of the hull, the problem of dust pollution during ship maintenance is solved and the operating environment and product quality is improved.

CN222658196UActive Publication Date: 2025-03-25GUANGDONG COSCO SHIPPING HEAVY IND CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421235614.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-31
Publication Date
2025-03-25
Estimated Expiration
2034-05-31

AI Technical Summary

Technical Problem

When performing ship repairs in floating docks, dust pollution is easily generated, affecting the operating environment and product quality.

Method used

A floating dock water mist spray device is designed, including a floating dock main body, overpass, bracket, nozzle and nozzle. The hull surface is sprayed through the nozzle to reduce dust and prevent pollution.

Benefits of technology

It effectively reduces dust pollution during ship maintenance, improves the operating environment, improves product quality, and reduces the risk of occupational diseases.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222658196U_ABST
    Figure CN222658196U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of floating dock corollary equipment, and particularly relates to a floating dock water mist spraying device which comprises a floating dock body, and one side of the floating dock body is rotationally connected with two overbridges through hinges. The bracket is arranged at the top of the overbridge, and a spray pipe is arranged on one side of the floating dock main body and the bracket; and the nozzle is formed in the bottom of the spray pipe and used for forming water mist to spray the surface of the ship body. Water mist and a curtain can be formed on the overbridge through the support, the spraying pipe and the nozzles, a water curtain can be formed on the top of the ship body through the water mist and the curtain, flying dust and particulate matter generated in the floating dock ship building or repairing process are rapidly settled, the working environment is greatly improved, the product quality is improved, and meanwhile the product quality is improved. The problems of environmental pollution and occupational disease control are solved, and the practicability of the device is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of supporting equipment for floating docks, and in particular relates to a water mist spraying device for floating docks. Background Art

[0002] A floating dock is a highly flexible water engineering vessel that plays multiple roles in ship repair, construction and even salvage. Its operating principle is similar to that of a submarine, which can sink and float by adjusting the amount of water in the water tank. When a ship needs to be repaired, the floating dock sinks, and the ship enters and then drains and floats up, lifting the ship out of the water for dry dock operations. In addition, it can also help deep-draft ships pass through shallow waters and perform offshore platform support and shipwreck salvage tasks. As an important shipbuilding and repair facility, the floating dock is crucial to promoting the development of the global shipping and offshore engineering industries. It can handle large offshore structures including 10,000-ton tankers and container ships, demonstrating extremely high engineering value and strategic significance.

[0003] In the process of repairing ships on floating docks, the hull needs to be maintained, performance maintained, inspected and repaired. In this process, sandblasting dust, welding dust and grinding dust will be generated. The presence of these dusts will cause the surface of the hull to be contaminated and cause air pollution during the maintenance of the hull by the floating dock.

[0004] Therefore, it is necessary to design a new solution to solve the above problems. Utility Model Content

[0005] The utility model aims to provide a water mist spraying device for a floating dock, aiming to solve the dust pollution problem generated during the ship maintenance process in the floating dock in the prior art.

[0006] To achieve the above-mentioned purpose, an embodiment of the utility model provides a water mist spray device for a floating dock, comprising: a floating dock body, one side of the floating dock body is rotatably connected to two sky bridges through a hinge; a bracket, the bracket is arranged on the top of the sky bridge, and a nozzle is arranged on one side of the floating dock body and on the bracket; a nozzle, the nozzle is opened at the bottom of the nozzle, and is used to form water mist to spray the surface of the hull.

[0007] Furthermore, the spray pipe is divided into a right dock wall spray pipe and a skybridge spray pipe. The right dock wall spray pipe is arranged on one side of the floating dock body, and the skybridge spray pipe is suspended on the top of multiple brackets, and a lap pipe is provided between the right dock wall spray pipe and the skybridge spray pipe.

[0008] Furthermore, the spacing between the multiple nozzles is 500 mm.

[0009] Furthermore, a plurality of welding seats are provided at the bottom of the nozzle, the spacing between the plurality of welding seats is 250 mm, and the nozzle is arranged on the welding seats.

[0010] Furthermore, a plurality of support rods are provided at the upper end of the bracket, and the plurality of support rods are distributed in a triangular structure.

[0011] Furthermore, a connection port is provided at one end of the nozzle facing the floating dock body, and a pressure gauge is provided at the connection between the connection port and the nozzle.

[0012] Furthermore, a hanging position is provided on one side of the top of the bracket, and the nozzle passes through the hanging position and is connected to the bracket.

[0013] Furthermore, both sides of the bracket are provided with obliquely connected traction ropes, and the bottom of the traction ropes is connected to the overpass.

[0014] The above one or more technical solutions in the floating dock water mist spray device provided by the embodiment of the utility model have at least one of the following technical effects: water mist and curtain can be formed on the overpass by utilizing the bracket, nozzle and nozzle, and water curtain can be formed on the top of the hull by utilizing the water mist and curtain, so that the dust and particulate matter generated during the construction or repair of the floating dock ship can be quickly settled, which greatly improves the working environment, solves the problems of environmental pollution and occupational disease prevention and control while improving product quality, and improves the practicality of the device. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0016] Figure 1 A schematic diagram of the overall structure of a spray device for a floating dock provided in an embodiment of the utility model;

[0017] Figure 2 A schematic diagram of the distribution of the nozzle structure of the spray device for the floating dock provided in an embodiment of the utility model;

[0018] Figure 3 A schematic diagram of the nozzle structure distribution of a spray device for a floating dock provided in an embodiment of the utility model;

[0019] Figure 4 A schematic structural diagram of a floating dock body and a spray pipe of a floating dock spray device provided in an embodiment of the utility model;

[0020] Figure 5A schematic diagram of the support structure of a spray device for a floating dock provided in an embodiment of the utility model;

[0021] Among them, the figure marks in the figure are: 1-floating dock body; 101-bridge; 2-bracket; 201-suspension position; 202-support rod; 203-traction rope; 3-nozzle; 301-right dock wall spray pipe; 302-bridge spray pipe; 303-lap pipe; 304-welding seat; 305-nozzle; 306-pressure gauge; 307-connection port. DETAILED DESCRIPTION

[0022] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the embodiments of the present invention, and should not be construed as limiting the present invention.

[0023] In the description of the embodiments of the present invention, it should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the accompanying drawings, and are only for the convenience of describing the embodiments of the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0024] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the embodiments of the present utility model, the meaning of "multiple" is two or more, unless otherwise clearly and specifically defined.

[0025] In the embodiments of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the embodiments of the present invention can be understood according to specific circumstances.

[0026] In the present utility model, if Figure 1-Figure 5As shown, a floating dock water mist spraying device is provided, comprising: a floating dock body 1, one side of the floating dock body 1 is rotatably connected to two sky bridges 101 through a hinge; a bracket 2, the bracket 2 is arranged on the top of the sky bridge 101, and a nozzle 3 is arranged on one side of the floating dock body 1 and the bracket 2; a nozzle 305, the nozzle 305 is opened at the bottom of the nozzle 3, and is used to form water mist to spray the surface of the hull.

[0027] During use, the hull needs to pass under the overpass 101 and enter the floating dock body 1. The water flow can be guided to the position of the nozzle 305 through the nozzle 3. At this time, the passing water flow can be pressurized into water mist and sprayed downward through the nozzle 305. During the spraying process, the surface of the hull is wetted, dust is reduced and maintained.

[0028] Among them, the nozzle 3 is divided into a right dock wall spray pipe 301 and a bridge spray pipe 302. The right dock wall spray pipe 301 is arranged on one side of the floating dock body 1, and the bridge spray pipe 302 is suspended on the top of multiple brackets 2. A lap pipe 303 is provided between the right dock wall spray pipe 301 and the bridge spray pipe 302. During use, the distributed design enables the right dock wall spray pipe 301 to form water mist on one side of the floating dock body 1. During the grinding and maintenance of the hull, some lightweight parts need to be disassembled separately for comprehensive grinding and rust removal. When grinding some lightweight parts and parts, the lightweight components can be moved to the bottom of the right dock wall spray pipe 301 of the main body 1 for grinding, so as to use the water mist formed under the right dock wall spray pipe 301 to reduce and prevent dust generated during the grinding process and prevent dust from escaping.

[0029] Among them, the spacing between multiple nozzles 305 is 500 mm. Using multiple equidistantly arranged nozzles 305 can make the connection and formation of water mist more stable, so that the water mist can be evenly sprayed on the surface of the hull, thereby improving the integrity of spraying and dust reduction.

[0030] Among them, a plurality of welding seats 304 are provided at the bottom of the nozzle 3, and the spacing between the plurality of welding seats 304 is 250 mm, and the nozzle 3 is arranged on the welding seat 304. During use, the welding seat 304 is used as the base of the nozzle 3 to assist the use of the nozzle 3, and the use of the welding seat 304 with a shorter spacing can reserve a spare welding seat 304 between the two nozzles 305. When a nozzle 305 or a welding seat 304 is damaged, the reserved welding seat 304 can be directly used for coordinated spraying, thereby improving the maintenance convenience of the device.

[0031] Among them, a plurality of support rods 202 are provided at the upper end of the bracket 2, and the plurality of support rods 202 are distributed in a triangular structure. During use, the triangular structure formed by the plurality of support rods 202 can make the bracket 2 more stable and prevent the bracket 2 from becoming loose as a whole, thereby improving the stability of the device.

[0032] Among them, a connection port 307 is provided at one end of the nozzle 3 facing the floating dock body 1, and a pressure gauge 306 is provided at the connection between the connection port 307 and the nozzle 3. When water is supplied, the inside of the nozzle 3 is filled with water through the connection port 307. At this time, the water pressure is monitored by the pressure gauge 306, which can assist the user to better control the water pressure of the spray.

[0033] Among them, a hanging position 201 is provided on one side of the top of the bracket 2, and the nozzle 3 passes through the hanging position 201 and is connected to the bracket 2. The nozzle 3 is suspended by using the hanging position 201. When installing the nozzle 3, the staff only needs to insert the nozzle 3 into multiple hanging positions 201 to complete the installation, thereby improving the installation convenience of the nozzle 3.

[0034] Among them, inclined traction ropes 203 are provided on both sides of the bracket 2, and the bottom of the traction rope 203 is connected to the overpass 101. During use, the two traction ropes 203 are used to laterally fix the bracket 2. When facing strong winds and traction forces, the bracket 2 can be corrected to prevent the bracket 2 from deviating and collapsing.

[0035] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A floating dock water mist spraying device, characterized in that: include: A floating dock body (1), one side of the floating dock body (1) being rotatably connected to two sky bridges (101) via hinges; A bracket (2), the bracket (2) being arranged on the top of the overpass (101), and a nozzle (3) being arranged on one side of the floating dock body (1) and on the bracket (2); A nozzle (305) is provided at the bottom of the nozzle pipe (3) and is used to form water mist for spraying the surface of the hull.

2. The floating dock water mist spraying device according to claim 1, characterized in that: The spray pipe (3) is divided into a right dock wall spray pipe (301) and a bridge spray pipe (302); the right dock wall spray pipe (301) is arranged on one side of the floating dock body (1); the bridge spray pipe (302) is suspended on the top of a plurality of brackets (2); and a lap pipe (303) is arranged between the right dock wall spray pipe (301) and the bridge spray pipe (302).

3. The floating dock water mist spraying device according to claim 1, characterized in that: The distance between the multiple nozzles (305) is 500 mm.

4. The floating dock water mist spraying device according to claim 1, characterized in that: A plurality of welding seats (304) are provided at the bottom of the nozzle (3), the spacing between the plurality of welding seats (304) is 250 mm, and the nozzle (3) is arranged on the welding seats (304).

5. The floating dock water mist spraying device according to claim 1, characterized in that: A plurality of support rods (202) are provided at the upper end of the bracket (2), and the plurality of support rods (202) are distributed in a triangular structure.

6. The floating dock water mist spraying device according to claim 1, characterized in that: The nozzle (3) is provided with a connection port (307) at one end facing the floating dock body (1), and a pressure gauge (306) is provided at the connection between the connection port (307) and the nozzle (3).

7. The floating dock water mist spraying device according to claim 1, characterized in that: A hanging position (201) is provided on one side of the top of the support (2), and the nozzle (3) passes through the hanging position (201) and is connected to the support (2).

8. The floating dock water mist spraying device according to claim 1, characterized in that: Both sides of the support (2) are provided with obliquely connected traction ropes (203), and the bottom of the traction rope (203) is connected to the overpass (101).