Hoisting equipment for petroleum pipeline entering ditch
By designing the lower trench hoisting equipment of oil pipelines that support the rotating mechanism and the lifting mechanism, the problem that existing equipment is difficult to adjust the pipe position after lifting is solved, and efficient installation of the pipelines in the trench is achieved, and construction efficiency is improved.
Patent Information
- Application Number
- CN202421254085.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-04
- Publication Date
- 2025-03-25
- Estimated Expiration
- 2034-06-04
AI Technical Summary
It is difficult to adjust the position of the pipe after being lifted, which affects the efficiency of pipeline down-ditch construction.
A petroleum pipeline lower groove hoisting equipment is designed, using a supporting rotating mechanism and a hoisting mechanism. Through the cooperation of gear No. 1, gear No. 2 and rotating rod, the pipe position is adjusted and moved.
The equipment can stabilize the center of gravity of the device, avoid rollover, and adjust the position of the pipeline after being lifted, which facilitates the movement of the pipeline into the groove and improves the efficiency of the pipeline's down-trench construction.
Smart Images

Figure CN222665147U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of petroleum technology, and in particular to a petroleum pipeline trench hoisting device. Background Art
[0002] Petroleum is a dark brown viscous oily liquid with green fluorescence and a special smell. It is a mixture of various liquid hydrocarbons such as alkanes, cycloalkanes, aromatic hydrocarbons and olefins. After refining and processing, various fuel oils, solvent oils, lubricating oils, greases, paraffin, asphalt, liquefied gas, aromatic hydrocarbons and other products can be obtained, providing fuel, raw materials and chemical products for various sectors of the national economy. When laying oil transportation pipelines, if pipeline trenching construction is required, oil pipeline trenching lifting equipment is required to lay the pipeline.
[0003] For example, a Chinese utility model patent with publication number "CN217867751U" discloses a pipeline lifting device. The utility model has a winding frame fixedly installed on both sides of the top of the top plate, and the lifting chain is arranged along two support rods distributed in a Y shape with the top plate, so that the device uses two casing rings when lifting a pipeline, thereby making the pipeline force balanced, avoiding the phenomenon of pipeline tilting due to unbalanced center of gravity of the pipeline, and the driving gear is meshed with two driven gears. When the driving motor is working, the two winding frames release or reel in the wire at the same speed at the same time, so that the two ends of the pipeline between the two casing rings move upward or downward at the same time, avoiding the phenomenon of pipeline tilting due to inconsistent speed.
[0004] In the above patent, the pipeline can be lifted to facilitate the installation of the pipeline, but the device is difficult to adjust the position of the pipeline after lifting. If the pipeline is to be laid in the trench, it is difficult to lift the pipeline and move it into the trench, which can easily affect the pipeline laying work. Utility Model Content
[0005] 1. Technical issues to be resolved
[0006] In view of the deficiencies in the prior art, the present application provides a petroleum pipeline trench hoisting device, which solves the problems mentioned in the above background technology.
[0007] (II) Technical solution
[0008] To achieve the above objectives, the present application is implemented through the following technical solutions: a kind of oil pipeline trench hoisting equipment, including a base for installing a device, a supporting and rotating mechanism for supporting the device and adjusting the position of the pipeline is arranged above the base, a hoisting mechanism for hoisting the pipeline is arranged above the base, the supporting and rotating mechanism includes a No. 1 gear, a No. 2 gear and a rotating rod, the rotating rod is fixedly installed at one end of the No. 1 gear, and the No. 1 gear is meshed with the No. 2 gear.
[0009] By adopting the above technical scheme, the center of gravity of the device can be stabilized by supporting the rotating mechanism to prevent the device from tipping over due to excessive weight of the pipeline and affecting the construction progress. The position of the pipeline can also be adjusted after the pipeline is lifted, so that the pipeline can be moved to the trench to facilitate the installation of the pipeline. The lifting mechanism can adjust the position of the pipeline so that the device can move the pipeline to different adjacent trenches, which facilitates the use of the device and improves the efficiency of pipeline trench construction.
[0010] Preferably, a counterweight is slidably connected to the inner wall surface of the base, and a mounting box is fixedly mounted on the upper surface of the base.
[0011] By adopting the above technical solution, the center of gravity of the device can be stabilized by the counterweight block to prevent the device from tipping over due to excessive weight of the pipeline, which would affect the construction process.
[0012] Preferably, the first gear is rotatably connected to the bottom end of the inner wall of the installation box, the second gear is rotatably connected to the bottom end of the inner wall of the installation box, and the rotating rod passes through the upper surface of the installation box and is rotatably connected to the upper surface of the installation box.
[0013] By adopting the above technical solution, the position of the pipeline can be adjusted by meshing the No. 2 gear with the No. 1 gear to drive the No. 1 gear and the rotating rod to rotate.
[0014] Preferably, a support block is fixedly mounted on the bottom end of the inner wall of the installation box, a No. 1 motor is fixedly mounted on the upper surface of the support block, and an output shaft of the No. 1 motor is fixedly connected to the No. 2 gear.
[0015] By adopting the above technical solution, the pipeline position can be adjusted by driving the No. 2 gear to rotate through the No. 1 motor.
[0016] Preferably, an electric telescopic rod is fixedly mounted on the upper surface of the installation box, the electric telescopic rod passes through the upper surface of the installation box, and a limiting block is fixedly mounted on one end of the electric telescopic rod.
[0017] By adopting the above technical solution, the number one gear can be limited by the limit block to prevent the number one gear from rotating when the device is not in use.
[0018] Preferably, a mounting block is fixedly installed on the inner wall surface of the rotating rod, threaded rods are rotatably connected to both sides of the inner wall of the mounting block, a No. 2 motor is fixedly installed on one side of the mounting block, the output shaft of the No. 2 motor is fixedly connected to the threaded rod, a slider is threadedly connected to the surface of the threaded rod, and the slider passes through the lower surface of the mounting block and is slidably connected to the lower surface of the mounting block.
[0019] By adopting the above technical solution, the position of the pipeline can be adjusted by driving the threaded rod to rotate through the No. 2 motor, and then the slider drives the mounting plate and the pipeline to move.
[0020] Preferably, a mounting plate is fixedly mounted on the lower surface of the slider, and winding rollers are rotatably connected to both sides of the inner wall of the mounting plate. A connecting rope is wrapped around the inner wall surface of the winding roller, and a No. 3 motor is fixedly mounted on one side of the mounting plate, and the output shaft of the No. 3 motor is fixedly connected to the winding roller.
[0021] By adopting the above technical solution, the winding roller can be driven to rotate by the No. 3 motor to lift the pipeline.
[0022] Preferably, a connecting block is fixedly installed at one end of the connecting rope, and rings are fixedly installed on both sides of the connecting block.
[0023] By adopting the above technical solution, the connecting block can be used to prevent the pipeline from slipping out of the ring and thus affecting the construction of the pipeline trench.
[0024] (III) Beneficial effects
[0025] The present application provides a petroleum pipeline trench hoisting device. It has the following beneficial effects:
[0026] 1. The oil pipeline trench hoisting equipment is provided with a supporting rotation mechanism, which solves the problem that the previous pipeline hoisting equipment is difficult to adjust the position of the pipeline after hoisting. If the pipeline trench construction is carried out, it is difficult to move the pipeline into the trench after hoisting, which is easy to affect the pipeline trench construction work. The position of the pipeline can be adjusted after hoisting, which is convenient for moving the pipeline into the trench to facilitate the beneficial effect of pipeline installation.
[0027] 2. The oil pipeline trench hoisting equipment is provided with a hoisting mechanism, which can adjust the position of the pipeline so that the device can move the pipeline to different adjacent trenches, achieving the beneficial effects of facilitating the use of the device while improving the efficiency of pipeline trench construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] In order to more clearly illustrate the implementation scheme of the utility model or the technical scheme in the prior art, the drawings required for use in the implementation scheme or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some implementation schemes of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0029] Figure 1 This is a schematic diagram of the main appearance structure of this application;
[0030] Figure 2 This is a schematic diagram of the internal structure of the installation box of this application;
[0031] Figure 3 This is a schematic diagram of the internal structure of the mounting block of this application;
[0032] Figure 4 This is a schematic diagram of the connection block and its connection structure of the present application.
[0033] In the figure: 1. base; 2. supporting rotating mechanism; 201. counterweight block; 202. mounting box; 203. gear No. 1; 204. gear No. 2; 205. supporting block; 206. motor No. 1; 207. electric telescopic rod; 208. limiting block; 209. rotating rod; 3. lifting mechanism; 301. mounting block; 302. threaded rod; 303. motor No. 2; 304. slider; 305. mounting plate; 306. winding roller; 307. motor No. 3; 308. connecting block; 309. collar. DETAILED DESCRIPTION
[0034] It should be noted that in the description of the embodiments of the present application, the terms "front, rear", "left, right", "up, down", etc. indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present application. The terms "install", "connect", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to specific circumstances.
[0035] The present application is further described in detail below through drawings and examples.
[0036] Reference Figure 1 and Figure 2The embodiment of the present application provides a petroleum pipeline trench hoisting device, including a base 1 for installing a device, a supporting rotating mechanism 2 for supporting the device and being able to adjust the position of the pipeline is arranged above the base 1, a hoisting mechanism 3 for hoisting the pipeline is arranged above the base 1, the supporting rotating mechanism 2 includes a first gear 203, a second gear 204 and a rotating rod 209, the rotating rod 209 is fixedly installed at one end of the first gear 203, the first gear 203 is meshed with the second gear 204, and the supporting rotating mechanism 2 can drive the limit block 208 to move through the electric telescopic rod 207 to make the limit The positioning block 208 is disengaged from the No. 1 gear 203, and the No. 2 gear 204 is driven to rotate by the No. 1 motor 206 to engage with the No. 1 gear 203, driving the No. 1 gear 203 and the rotating rod 209 to rotate, thereby rotating the mounting block 301 to adjust the position of the pipeline. The No. 2 motor 303 can be used to drive the threaded rod 302 to rotate through the lifting mechanism 3, so that the slider 304 drives the mounting plate 305 to move to a suitable position, and the No. 3 motor 307 drives the winding roller 306 to rotate to lower the connecting rope and the connecting block 308, and then the ring 309 is put on the surface of the pipeline and the No. 3 motor 307 is started to lift the pipeline.
[0037] Reference Figure 1 and Figure 2 In one aspect of this embodiment, a counterweight block 201 is slidably connected to the inner wall surface of the base 1, and a mounting box 202 is fixedly installed on the upper surface of the base 1.
[0038] The first gear 203 is rotatably connected to the bottom end of the inner wall of the installation box 202 , the second gear 204 is rotatably connected to the bottom end of the inner wall of the installation box 202 , and the rotating rod 209 passes through the upper surface of the installation box 202 and is rotatably connected to the upper surface of the installation box 202 .
[0039] A support block 205 is fixedly mounted on the bottom end of the inner wall of the installation box 202 , and a No. 1 motor 206 is fixedly mounted on the upper surface of the support block 205 . The output shaft of the No. 1 motor 206 is fixedly connected to the No. 2 gear 204 .
[0040] An electric telescopic rod 207 is fixedly installed on the upper surface of the installation box 202. The electric telescopic rod 207 passes through the upper surface of the installation box 202. A limit block 208 is fixedly installed on one end of the electric telescopic rod 207. By starting the electric telescopic rod 207, the electric telescopic rod 207 drives the limit block 208 to move so that the limit block 208 is disengaged from the No. 1 gear 203, and then the No. 1 motor 206 is started. The No. 1 motor 206 drives the No. 2 gear 204 to rotate and engage with the No. 1 gear 203, driving the No. 1 gear 203 and the rotating rod 209 to rotate, thereby rotating the installation block 301 to adjust the position of the pipeline.
[0041] Reference Figure 3 and Figure 4In one aspect of the present embodiment, a mounting block 301 is fixedly mounted on the inner wall surface of the rotating rod 209, threaded rods 302 are rotatably connected to the inner walls of the mounting block 301 on both sides, a No. 2 motor 303 is fixedly mounted on one side of the mounting block 301, an output shaft of the No. 2 motor 303 is fixedly connected to the threaded rod 302, a slider 304 is threadedly connected to the surface of the threaded rod 302, the slider 304 passes through the lower surface of the mounting block 301 and is slidably connected to the lower surface of the mounting block 301.
[0042] A mounting plate 305 is fixedly installed on the lower surface of the slider 304, and winding rollers 306 are rotatably connected to both sides of the inner wall of the mounting plate 305. A connecting rope is wrapped around the inner wall surface of the winding roller 306. A No. 3 motor 307 is fixedly installed on one side of the mounting plate 305, and the output shaft of the No. 3 motor 307 is fixedly connected to the winding roller 306.
[0043] A connecting block 308 is fixedly installed at one end of the connecting rope, and rings 309 are fixedly installed on both sides of the connecting block 308. By starting the No. 2 motor 303, the No. 2 motor 303 drives the threaded rod 302 to rotate so that the slider 304 drives the mounting plate 305 to move to a suitable position, and then the No. 3 motor 307 is started, and the No. 3 motor 307 drives the winding roller 306 to rotate to make the connecting rope and the connecting block 308 descend, and then the ring 309 is put on the surface of the pipeline and the No. 3 motor 307 is started to lift the pipeline.
[0044] All electrical equipment in this solution are powered by an external power supply.
[0045] Working principle: When the device is used, the device should be placed at the designated position first, and the counterweight block 201 should be placed in the placement slot provided on the upper surface of the base 1. Then, the No. 2 motor 303 should be started, and the No. 2 motor 303 should drive the threaded rod 302 to rotate so that the slider 304 drives the mounting plate 305 to move to a suitable position. Then, the No. 3 motor 307 should be started, and the No. 3 motor 307 should drive the winding roller 306 to rotate so that the connecting rope and the connecting block 308 are lowered. Then, the ring 309 should be put on the surface of the pipe, and the No. 3 motor 307 should be started to lift the pipe, and the electric telescopic rod 2 should be started. 07, the electric telescopic rod 207 drives the limit block 208 to move so that the limit block 208 is disengaged from the No. 1 gear 203, and then the No. 1 motor 206 is started. The No. 1 motor 206 drives the No. 2 gear 204 to rotate and mesh with the No. 1 gear 203, drives the No. 1 gear 203 and the rotating rod 209 to rotate, and then rotates the installation block 301 to adjust the position of the pipeline. After rotating to the appropriate position, the No. 2 motor 303 is started to move the pipeline above the groove, and then the No. 3 motor 307 is started to lower the pipeline into the groove, and then the ring on the surface of the pipeline is removed to install the pipeline.
[0046] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0047] Although the embodiments of the present application have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present application, and that the scope of the present application is defined by the appended claims and their equivalents.
Claims
1. A petroleum pipeline trench hoisting device, comprising a base (1) for installing the device, characterized in that: A supporting rotating mechanism (2) for supporting the device and being able to adjust the position of the pipeline is arranged above the base (1); a hoisting mechanism (3) for hoisting the pipeline is arranged above the base (1); the supporting rotating mechanism (2) comprises a first gear (203), a second gear (204) and a rotating rod (209); the rotating rod (209) is fixedly mounted on one end of the first gear (203); the first gear (203) is meshed with the second gear (204).
2. The oil pipeline trench hoisting equipment according to claim 1 is characterized by: A counterweight block (201) is slidably connected to the inner wall surface of the base (1), and a mounting box (202) is fixedly mounted on the upper surface of the base (1).
3. The oil pipeline trench hoisting equipment according to claim 2 is characterized by: The first gear (203) is rotatably connected to the bottom end of the inner wall of the installation box (202), the second gear (204) is rotatably connected to the bottom end of the inner wall of the installation box (202), and the rotating rod (209) passes through the upper surface of the installation box (202) and is rotatably connected to the upper surface of the installation box (202).
4. The oil pipeline trench hoisting equipment according to claim 2 is characterized by: A support block (205) is fixedly mounted on the bottom end of the inner wall of the installation box (202), a No. 1 motor (206) is fixedly mounted on the upper surface of the support block (205), and an output shaft of the No. 1 motor (206) is fixedly connected to the No. 2 gear (204).
5. The oil pipeline trench hoisting equipment according to claim 2 is characterized by: An electric telescopic rod (207) is fixedly mounted on the upper surface of the installation box (202); the electric telescopic rod (207) passes through the upper surface of the installation box (202); and a limiting block (208) is fixedly mounted on one end of the electric telescopic rod (207).
6. The oil pipeline trench hoisting equipment according to claim 1 is characterized by: A mounting block (301) is fixedly mounted on the inner wall surface of the rotating rod (209), threaded rods (302) are rotatably connected to both sides of the inner wall of the mounting block (301), a second motor (303) is fixedly mounted on one side of the mounting block (301), an output shaft of the second motor (303) is fixedly connected to the threaded rod (302), a slider (304) is threadedly connected to the surface of the threaded rod (302), and the slider (304) passes through the lower surface of the mounting block (301) and is slidably connected to the lower surface of the mounting block (301).
7. The oil pipeline trench hoisting equipment according to claim 6 is characterized by: A mounting plate (305) is fixedly mounted on the lower surface of the slider (304), and winding rollers (306) are rotatably connected to both sides of the inner wall of the mounting plate (305), and a connecting rope is wound around the inner wall surface of the winding roller (306). A third motor (307) is fixedly mounted on one side of the mounting plate (305), and an output shaft of the third motor (307) is fixedly connected to the winding roller (306).
8. The oil pipeline trench hoisting equipment according to claim 7 is characterized by: A connection block (308) is fixedly mounted on one end of the connection rope, and sleeve rings (309) are fixedly mounted on both sides of the connection block (308).
Citation Information
Patent Citations
Pipeline hoisting equipment
CN217867751U