Combined type adjustable wire hanging frame
By designing a combined adjustable hanger, the problem of time-consuming and low accuracy in traditional masonry technology is solved, and the masonry effect is achieved with convenient operation and high accuracy, shortening the masonry time and improving quality.
Patent Information
- Application Number
- CN202420573057.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-22
- Publication Date
- 2025-03-28
- Estimated Expiration
- 2034-03-22
AI Technical Summary
In the existing masonry technology, the traditional vertical leather number rod and angle line hanging modes are time-consuming and have low accuracy, especially when building multi-faceted fancy walls, the masonry efficiency is insignificant.
A combined adjustable hanging frame is designed, including base, leveling assembly, vertical pole, leather pole, upper hanging line component, lower hanging line component, vertical hanging line, adjustment marking and pulling line. The horizontality of the hanging frame is adjusted by leveling bolts, and the adjustment marking and pulling line are used to ensure that the upright pole is parallel to the wall. The vertical hanging line and leather pole on the upper hanging line iron sheet are used to calibrate the wall height.
It achieves masonry effect with convenient operation, one-time correction throughout the whole process, and high accuracy, shortens the masonry time, improves the quality of sample wall masonry, and has good economic and social benefits.
Smart Images

Figure CN222686193U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction tools, in particular to a combined adjustable wire hanging rack. Background Art
[0002] Masonry engineering, also known as block masonry engineering, refers to the use of ordinary clay bricks, load-bearing clay hollow bricks, autoclaved fly ash bricks, fly ash bricks, various small and medium-sized blocks and other materials for masonry engineering in construction projects.
[0003] Masonry requires a "skin counting pole", and some walls during masonry will be more complicated. The traditional masonry mode of using erected skin counting poles, corner hanging lines, three skins and one hanging and five skins and one leaning is time-consuming and has low precision. It is relatively simple to control one wall, and when controlling multiple fancy walls, the structure of the entire wall is more complicated. The traditional skin counting poles with corner hanging lines not only require a large number, but the masonry is easy to be messy due to the many lines, and the tools are inconvenient to carry. The actual masonry efficiency is low and cannot meet actual usage needs. Utility Model Content
[0004] The utility model aims to overcome the deficiencies of the prior art and to provide a combined adjustable wire hanging rack, which is easy to operate, can be used in a single correction process with high accuracy, and has a low investment cost.
[0005] In order to achieve the above-mentioned purpose, the technical solution adopted by the utility model is: a combined adjustable wire hanging rack, comprising:
[0006] Base: The two bases are arranged opposite to each other on both sides of the wall;
[0007] A leveling component is arranged on the base and used to level the base in a horizontal position;
[0008] Vertical pole: vertically arranged on the base; Skin counting rod: the skin counting rod can be adjusted up and down and arranged in the length direction of the vertical pole;
[0009] An upper wire hanging component and a lower wire hanging component: the upper wire hanging component and the lower wire hanging component are respectively arranged at the upper and lower ends of the vertical pole; wherein the upper wire hanging component comprises a detachable upper wire hanging iron sheet arranged at the upper end of the vertical pole and an upper wire hanging member arranged on the upper wire hanging iron sheet and arranged parallel to the lower wire hanging component, and the upper wire hanging iron sheet is provided with a vertical hanging wire for keeping perpendicular to the wall when building a wall;
[0010] Adjustment marking line: arranged between the upper hanging wire member and the lower hanging wire member, and the adjustment marking line is arranged perpendicular to the horizontal plane of the base;
[0011] Pull wire: Both ends are buckled between the adjustment marking lines of the two side poles, and the pull wire is arranged perpendicular to the adjustment marking lines.
[0012] Furthermore, the base is a galvanized triangle plate.
[0013] Furthermore, a counterweight is provided on the upper surface of the base.
[0014] Furthermore, the leveling assembly includes three leveling bolts arranged in a triangle shape.
[0015] Furthermore, the leather counting rod is arranged in the length direction of the vertical rod so as to be adjustable up and down by at least two iron clips.
[0016] Furthermore, the upper wire hanging component is F-shaped.
[0017] Due to the application of the above technical solution, the utility model has the following advantages compared with the prior art:
[0018] The combined adjustable wire hanging rack of the utility model is easy to assemble and carry. At the same time, the horizontality of the wire hanging rack is adjusted by the leveling bolts, and the position of the vertical pole is set parallel to the wall to be built through the adjustment mark, which is easy to operate. The vertical hanging wire on the upper wire hanging iron sheet is used to be vertically downward and parallel to the plane of the wall, and then the masonry pull wire is pulled out, and finally the wall masonry height is calibrated through the skin number rod. The whole process is controlled at one time, the operation process of the players is reduced, the masonry time is shortened, the actual operation is greatly facilitated, the quality of sample wall masonry is improved, and the masonry time is shortened, which has good economic and social benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The technical solution of the utility model is further described below in conjunction with the accompanying drawings:
[0020] Figure 1 This is a schematic diagram of the structure of an embodiment of the utility model;
[0021] Figure 2 for Figure 1 A top view of
[0022] Figure 3 It is a schematic diagram of the structure when a single pole is provided with an upper wire hanging component and a lower wire hanging component;
[0023] Among them: 1. Base; 2. Wall; 3. Leveling assembly; 4. Vertical pole; 5. Skin counting rod; 6. Upper hanging wire component; 7. Lower hanging wire component; 8. Vertical hanging wire; 9. Pull wire; 10. Counterweight; 11. Iron clamp; 30. Leveling bolt; 60. Upper hanging wire iron sheet; 61. Upper hanging wire component. DETAILED DESCRIPTION
[0024] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.
[0025] The utility model provides a combined adjustable hanging wire rack to solve the problems in the prior art of using the traditional masonry mode of standing skin number poles, corner hanging wires, three skins and one hanging and five skins and one leaning, which is time-consuming, low in precision, and complicated to operate and has low masonry efficiency when building multi-sided fancy walls.
[0026] For ease of understanding, the specific process in the embodiments of the present application is described below. Figures 1 to 3 A combined adjustable wire hanging rack in the embodiment of the present application includes a base 1, a leveling component 3, a vertical pole 4, a skin number rod 5, an upper hanging wire component 6, a lower hanging wire component 7, a vertical hanging wire 8, an adjustment mark line and a pull wire 9; the two bases 1 are relatively arranged on both sides of the wall 2; the leveling component 3 is arranged on the base 1 to adjust the position of the base 1 to a horizontal position on the building ground; the vertical pole 4 is welded on the base 1 to ensure that the vertical pole 4 and the base 1 are vertically arranged at 90°, which is convenient for the subsequent masonry of the wall 2; the skin number rod 5 can be adjusted up and down in the length direction of the vertical pole 4.
[0027] The upper hanging wire component 6 and the lower hanging wire component 7 are respectively installed at the upper and lower ends of the vertical pole 4, and the lower hanging wire component 7 is directly welded to the bottom of the vertical pole 4; specifically, the upper hanging wire component 6 includes a detachable upper hanging wire iron sheet 60 arranged on the vertical pole 4 and an upper hanging wire member 61 arranged on one side of the upper hanging wire iron sheet 60 and arranged parallel to the lower hanging wire component 6, and the upper hanging wire iron sheet 60 is provided with a vertical hanging wire 8 for keeping parallel to the plane of the wall 2 when building the wall; the adjustment mark line is arranged between the upper hanging wire member 61 and the lower hanging wire component 7, and the adjustment mark line is arranged perpendicular to the horizontal plane of the base 1; the two ends of the pull wire 9 are buckled between the adjustment mark lines of the vertical poles 4 on both sides, and the pull wire 9 is arranged perpendicular to the adjustment mark line.
[0028] In this embodiment, the base 1 is made of a galvanized triangle plate, and the galvanizing prolongs the service life of the base 1.
[0029] based on Figure 2 In this embodiment, a counterweight block 10 is further provided on the upper surface of the base 1. The counterweight block is made of concrete. The counterweight block 10 can stabilize the wire hanging rack, and the operation is convenient and labor-saving.
[0030] based on Figure 2 In the present embodiment, the leveling assembly 3 includes three leveling bolts 30 arranged in a triangular shape. Of course, the number of the leveling bolts 30 may be more than three, as long as they can play a role in leveling the base 1.
[0031] In this embodiment, the skin counting rod 5 can be adjusted up and down in the length direction of the vertical rod 4 through three relatively parallel iron clamps 11, so that the position of the skin counting rod 5 can be adjusted according to actual conditions, which is convenient for actual wall construction operations.
[0032] In this embodiment, the upper hanging wire component 6 is formed by connecting the upper hanging wire sheet 60 and the upper hanging wire member 61 to form an F shape, and the upper hanging wire sheet 60 is U-shaped, so that multiple vertical hanging wires 8 can be pulled downward from the upper hanging wire sheet 60. The vertical hanging wires 8 are set parallel to the plane of the wall to ensure the verticality when building the wall.
[0033] The actual working process is as follows:
[0034] First, the vertical pole 4 is calculated according to the requirements of the masonry wall construction specifications, the cross-sectional dimensions of the masonry wall, the brick thickness, and the mortar joint thickness to calculate the average thickness of each brick layer, and the layer number rod 5 marked with the number of masonry wall layers is placed on the vertical pole 4 through the iron clamp 11 according to the calculated dimensions. Then, the vertical pole 4 is connected to the base 1 by welding at the masonry position, and the upper hanging wire component 6 is detachably fixed to the upper end of the vertical pole 4 with self-tapping screws, and the lower hanging wire component 7 is directly welded to the bottom of the vertical pole 4. An adjustment mark line (not shown in the figure) perpendicular to the bottom surface is hung between the upper hanging wire component 61 and the lower hanging wire component 7. The adjustment mark line is used to ensure the verticality of the entire hanging wire rack in the horizontal plane. After the assembly is completed, the two hanging wire racks are placed on both sides of the masonry wall 2 according to the axis position of the masonry wall.
[0035] Next, a counterweight block 10 is used to press and fix the two bases 1 respectively, and a red line level is used to cooperate. The horizontality of the entire wire hanging rack is leveled and corrected by three leveling bolts 30, and then a pull wire 9 for building the wall 2 is hung between the two vertical poles 4. The two ends of the pull wire 9 are tied to the adjustment mark line and adjusted up and down according to the height of the skin number rods 5 of the vertical poles 4 on both sides. Finally, a vertical hanging wire 8 that remains horizontal with the wall plane during wall building is placed on the upper hanging wire iron sheet 60. During operation, one end of the vertical hanging wire 8 is connected to the upper hanging wire iron sheet 60, and the other end is pressed into the position under the brick mortar joint of the first wall through an iron nail. It is also necessary to ensure that the wall and the vertical hanging wire 8 remain horizontal, and then the installation can be completed for wall building.
[0036] When the wall is built, it is disassembled in reverse order according to the assembly sequence, collected and cleaned, and then recycled. It is easy to operate and highly practical.
[0037] To sum up, the adjustable combined hanging wire rack is easy to assemble and carry. At the same time, the horizontality of the hanging wire rack is adjusted by the leveling bolts, and then the position of the vertical pole is set parallel to the wall to be built through the adjustment mark; the vertical hanging wire on the upper hanging wire iron sheet is used to hang down vertically and parallel to the wall surface, and then the masonry pull wire is pulled out, and finally the wall masonry height is calibrated through the skin number rod. The whole process is controlled at one time, the operation process of the players is reduced, the masonry time is shortened, the operation of the operators is greatly facilitated, the quality of the sample wall masonry is improved, and the masonry time can be shortened.
[0038] As described above, the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.
Claims
1. A combined adjustable wire hanger, characterized in that: include: A base, wherein two bases are arranged opposite to each other on two sides of the wall; A leveling assembly, disposed on the base, for leveling the base in a horizontal position; A vertical pole is vertically arranged on the base; A skin counting rod, which can be adjusted up and down and is arranged in the length direction of the vertical rod; An upper wire hanging component and a lower wire hanging component: the upper wire hanging component and the lower wire hanging component are respectively arranged at the upper and lower ends of the vertical pole; wherein the upper wire hanging component comprises a detachable upper wire hanging iron sheet arranged at the upper end of the vertical pole and an upper wire hanging member arranged on the upper wire hanging iron sheet and arranged parallel to the lower wire hanging component, and the upper wire hanging iron sheet is provided with a vertical hanging wire for keeping perpendicular to the wall when building a wall; An adjustment mark line is arranged between the upper hanging wire member and the lower hanging wire member, and the adjustment mark line is arranged perpendicular to the horizontal plane of the base; The two ends of the pull wire are buckled between the adjustment marking lines of the vertical poles on both sides, and the pull wire is arranged perpendicular to the adjustment marking lines.
2. The combined adjustable wire hanger according to claim 1, characterized in that: The base is a galvanized triangle plate.
3. The combined adjustable wire hanger according to claim 1, characterized in that: A counterweight is also provided on the upper surface of the base.
4. The combined adjustable wire hanger according to claim 1, characterized in that: The leveling assembly includes three leveling bolts arranged in a triangle shape.
5. The combined adjustable wire hanger according to claim 1, characterized in that: The leather counting rod is arranged in the length direction of the vertical rod in an adjustable manner up and down by at least two iron clips.
6. The combined adjustable wire hanger according to claim 1, characterized in that: The upper wire hanging component is F-shaped.