Construction structure of drainage pipe without pumping and discharge
By adopting a non-exhaust bump construction structure in the relocation of drainage pipes, including bump wells, diversion troughs, partition walls and plugging troughs, the problems of high construction difficulty, low efficiency and high safety hazards under complex working conditions are solved, and efficient and safe water flow redirection and sealing effects are achieved.
Patent Information
- Application Number
- CN202421404466.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-19
- Publication Date
- 2025-04-04
- Estimated Expiration
- 2034-06-19
AI Technical Summary
In the construction of drainage pipeline relocation, the existing technology is difficult to adapt to complex working conditions such as limited working face, large pipe burial depth and large pipeline water flow, resulting in high construction difficulty, low efficiency and high safety hazards.
A construction structure for drainage pipes without drainage and bumps is adopted, including the current drainage pipe, diversion drainage pipe and bumps are adopted. The bump structure includes applying a bump well on the current drainage pipe. The bump well is equipped with a flow channel, partition wall and plug groove. Through these structures, the water flow is diverted and sealed.
This structure does not require large-scale excavation of the site and is suitable for pipeline construction with large buried depths, improving construction efficiency and safety, and ensuring the normal operation of the drainage system.
Smart Images

Figure CN222716163U_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the technical field of water supply and drainage, and more specifically, to a construction structure for a drainage pipe without a pump-out or drainage connection. Background Art
[0002] In the process of drainage pipeline relocation, traditional construction methods such as earthbag cofferdam steel pipe diversion, pumping and drainage joint construction, and temporary pipeline blocking using airbags and brickwork are feasible in conventional construction environments. However, these traditional methods have gradually become limited in the face of complex and changing construction conditions. In particular, traditional methods are often difficult to adapt to complex working conditions such as limited working surface, deep pipeline burial, and large pipeline water flow.
[0003] First, when the construction work surface is limited, methods such as earthbag cofferdams and steel pipe diversions require a large space, which not only affects construction efficiency, but may also cause unnecessary interference to the surrounding environment. Secondly, for pipelines with greater burial depths, traditional plugging methods such as air bags and brickwork are difficult to deliver to the designated location, and it is difficult to ensure the plugging effect, which brings great inconvenience to the construction. Finally, when the water flow in the pipeline is large, traditional methods are difficult to effectively block the water flow, resulting in poor pumping and drainage effects, or even failure to complete the plugging. In addition, water-related operations also have safety hazards such as water scouring, release of toxic and harmful gases, and working in confined spaces, which pose a serious threat to construction personnel. Utility Model Content
[0004] The purpose of the embodiments of the present application is to provide a construction structure for drainage pipes without pumping out the collision, so as to solve the technical problems existing in the prior art that the drainage pipe relocation construction is difficult under complex working conditions such as limited working surface, deep buried pipe, and large water flow in the pipe.
[0005] To achieve the above purpose, the technical solution adopted in this application is:
[0006] Provided is a drainage pipe non-pumping and drainage joint construction structure, comprising:
[0007] Existing drainage pipes, including relocated sections;
[0008] A diverted drainage pipe, used to communicate with the existing drainage pipe to replace the diverted section;
[0009] A contact structure is arranged at the end of the relocation section, and the contact structure includes a contact well built on the existing drainage pipe, and the contact well is provided with a diversion groove, a partition wall and a plugging groove, one end of the diversion groove is arranged at the end of the relocation section, and the other end of the diversion groove is connected with the diverted drainage pipe; the partition wall is arranged on the outside of the diversion groove and on the side close to the relocation section, and the existing drainage pipe runs through the partition wall; the outer wall of the diversion groove, the partition wall and the inner wall of the contact well enclose the plugging groove; after the existing drainage pipe is broken, the plugging groove is used to fill with plugging materials to block the incoming and outgoing water of the relocation section.
[0010] As a further improvement of the above technical solution:
[0011] Optionally, the masonry top surface of the partition wall is higher than the top surface of the existing drainage pipe.
[0012] Optionally, the axial length of the plugging groove along the existing drainage pipe is greater than 0.5 m.
[0013] Optionally, the existing drainage pipe has a first breaking position and a second breaking position, and the first breaking position and the second breaking position are respectively arranged on both sides of the partition wall.
[0014] Optionally, the collision structure includes a first collision structure provided at a first end of the migration section, and a second collision structure provided at a second end of the migration section, and the first collision structure and the second collision structure are arranged in mirror symmetry with each other.
[0015] Optionally, the blocking material includes grilles, sandbags and concrete, the grilles are inserted into the broken existing drainage pipe, the sandbags are filled into the blocking groove and the broken existing drainage pipe, and the concrete is poured on the sandbags in the blocking groove.
[0016] A method for constructing a drainage pipe without pumping and drainage, comprising the following steps:
[0017] Laying diverted drainage pipes on the pre-set drainage pipe relocation routes;
[0018] Construct a well at the end of the relocated section of the existing drainage pipe;
[0019] A diversion groove is built in the collision well, one end of the diversion groove is set at the first breaking position of the existing drainage pipe, and the other end of the diversion groove is connected to the diverted drainage pipe; and a partition wall is built between the first breaking position and the second breaking position of the existing drainage pipe; the outer wall of the diversion groove, the partition wall and the inner wall of the collision well are enclosed to form a plugging groove;
[0020] Breaking the existing drainage pipe at a first breaking position and a second breaking position of the existing drainage pipe;
[0021] Fill the plugging groove with plugging material.
[0022] As a further improvement of the above technical solution:
[0023] Optionally, when filling the plugging material, first insert the grilles at the first breaking position and the second breaking position respectively, then fill the sandbags between the two grilles, and after filling the sandbags, pour concrete into the plugging groove.
[0024] Optionally, when a partition wall is built between the first breaking position and the second breaking position, the top surface of the partition wall is higher than the top surface of the existing drainage pipe.
[0025] Optionally, when constructing the diversion trough, the construction height of the diversion trough is greater than the height of the existing drainage pipe and the diverted drainage pipe.
[0026] The beneficial effects of the non-pumping and drainage joint construction structure of the drainage pipe provided by the present application are:
[0027] The present application provides a construction structure for a drainage pipe without pumping out the impact point, including an existing drainage pipe, a diverted drainage pipe and an impact point structure. The impact point structure includes an impact point well constructed on the existing drainage pipe, and a guide groove, a partition wall and a plugging groove are arranged in the impact point well. One end of the guide groove is arranged at the end of the diversion section, and the other end of the guide groove is connected to the diverted drainage pipe; the guide groove guides the water flow originally flowing to the diversion section to the diverted drainage pipe, ensuring smooth drainage. The partition wall is arranged on the outside of the guide groove and on the side close to the diversion section, and the existing drainage pipe runs through the partition wall; the outer wall of the guide groove, the partition wall and the inner wall of the impact point well enclose to form a plugging groove; the partition wall and the impact point well are key structures for realizing water flow diversion without pumping out the water. When the existing drainage pipe is broken, water flows into the diverted drainage pipe from one side of the partition wall, that is, the inner side of the diversion groove; on the other side of the partition wall, that is, the inner side of the plugging groove, plugging materials are filled to block the water flow from entering the diversion section, thereby realizing the diversion of water flow to the diverted drainage pipe.
[0028] When constructing the drainage pipe without pumping and drainage collision construction structure of this application, there is no need for a large area of excavation site, which is suitable for the construction of pipelines with a larger burial depth. Before breaking the existing drainage pipe, the masonry of the partition wall can be carried out in a dry working environment, which greatly improves the construction efficiency. After breaking the existing drainage pipe, the remaining operations can be completed on the ground with the help of construction equipment, ensuring the safety of the operation and the safety of personnel. In addition, during the construction process, the existing drainage pipe can flow water normally, ensuring the normal operation of the drainage system. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0030] Figure 1 A schematic cross-sectional view of the first stage of the construction structure of the drainage pipe without drainage and bumping provided in this application;
[0031] Figure 2 A schematic cross-sectional view of the second stage of the construction structure of the drainage pipe without drainage and bumping provided in this application;
[0032] Figure 3 for Figure 2 A schematic diagram of a local enlarged structure;
[0033] Figure 4 A schematic cross-sectional view of the third stage of the construction structure of the drainage pipe without drainage and bumping provided in this application;
[0034] Figure 5 for Figure 4 A local enlarged structural diagram Figure 1 ;
[0035] Figure 6 for Figure 4 A local enlarged structural diagram Figure 2 ;
[0036] Among them, the reference numerals in the figure are:
[0037] 1. Current drainage pipe; 11. Relocation section;
[0038] 2. Reroute the drainage pipe; 3. Bumping structure;
[0039] 31. Collision well; 32. Diversion trough;
[0040] 33. Partition wall; 34. Plug slot;
[0041] 35. Blocking materials; 351. Grille;
[0042] 352. Sandbags; 353. Concrete. DETAILED DESCRIPTION
[0043] In order to make the technical problems, technical solutions and beneficial effects to be solved by the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0044] It should be noted that when an element is referred to as being "fixed to" or "disposed on" another element, it can be directly on the other element or indirectly on the other element. When an element is referred to as being "connected to" another element, it can be directly connected to the other element or indirectly connected to the other element.
[0045] It should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0046] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0047] like Figure 1 , Figure 2 and Figure 4 As shown, the present application provides a drainage pipe non-pumping and drainage joint construction structure, including an existing drainage pipe 1, a diverted drainage pipe 2 and a joint structure 3.
[0048] The existing drainage pipe 1 refers to the existing drainage system, and the relocation section 11 is the part that needs to be relocated in this project. Due to the continuous updating of urban infrastructure, some old or non-conforming pipes need to be replaced or re-arranged.
[0049] The diverted drainage pipe 2 is a pipe laid according to the new drainage plan, and its function is to replace the relocation section 11 for drainage. When the diverted drainage pipe 2 is successfully connected to the existing drainage pipe 1, the drainage will no longer flow through the relocation section 11, thereby realizing the relocation of the drainage pipe.
[0050] The contact structure 3 is a structure located at the connection between the existing drainage pipe 1 and the diverted drainage pipe 2, and serves to connect the existing drainage pipe 1 and the diverted drainage pipe 2. The contact structure 3 is arranged at the end of the relocation section 11 and also at the end of the diverted drainage pipe 2. The contact structure 3 includes a contact well 31 constructed on the existing drainage pipe 1, and the contact well 31 is constructed by the reverse construction method, also known as a reverse well. This well construction method involves excavating and constructing the structure from top to bottom in sequence without erecting temporary supports, so that the structure itself acts as a retaining wall and support at the same time. In the construction of the working well, earth excavation and reinforced concrete construction are carried out in layers. The excavation depth of each layer needs to be controlled within the safe depth, and then the steel bar binding, formwork erection, concrete pouring and maintenance are carried out. After the concrete reaches a certain strength, the formwork is removed and the construction of the next layer section continues until the well bottom cushion and bottom plate required by the design are completed. The contact well 31 is provided with a diversion groove 32, a partition wall 33 and a plugging groove 34. One end of the guide groove 32 is arranged at the end of the relocation section 11, and the other end of the guide groove 32 is connected to the diverted drainage pipe 2; the guide groove 32 guides the water flow originally flowing to the relocation section 11 to the diverted drainage pipe 2, ensuring smooth drainage. The partition wall 33 is arranged on the outside of the guide groove 32 and on the side close to the relocation section 11, and the existing drainage pipe 1 runs through the partition wall 33; the outer wall of the guide groove 32, the partition wall 33 and the inner wall of the collision well 31 enclose to form a plugging groove 34; the partition wall 33 and the collision well 31 are key structures for realizing water flow diversion without pumping out water. When the existing drainage pipe 1 is broken, the water flows from one side of the partition wall 33, that is, the inner side of the guide groove 32, into the diverted drainage pipe 2; on the other side of the partition wall 33, that is, the inner side of the plugging groove 34, plugging materials 35 are filled to block the water flow from entering the relocation section 11, thereby realizing the diversion of the water flow to the diverted drainage pipe 2.
[0051] When constructing the drainage pipe without pumping and drainage collision construction structure of this application, there is no need for a large area of excavation site, which is suitable for the construction of pipelines with a large burial depth. Before breaking the existing drainage pipe 1, the masonry of the partition wall 33 can be carried out in a dry working environment, which greatly improves the construction efficiency. After breaking the existing drainage pipe 1, the remaining operations can be completed on the ground with the help of construction equipment, ensuring the safety of the operation and the safety of the personnel. In addition, during the construction process, the existing drainage pipe 1 can flow water normally, ensuring the normal operation of the drainage system.
[0052] To ensure the dryness of the indoor working environment of the collision well 31 and to prevent water from overflowing the plugging groove 34, Figure 3 ,and Figure 5As shown, in one embodiment of the present application, the top surface of the partition wall 33 needs to be higher than the top surface of the existing drainage pipe 1. After the existing drainage pipe 1 is broken, the water level overflowing from the existing drainage pipe 1 can never exceed the top surface of the partition wall 33. The top surface masonry height of the partition wall 33 is not fixed, but is flexibly adjusted according to the actual situation at the construction site. Specifically, its height needs to be calculated and adjusted based on key factors such as the pipe diameter, water flow size, and water pressure. The present application is also applicable to situations where the pipe is full of water or the downstream pipe has water pressure due to full water upstream. In this case, it is only necessary to further raise the height of the partition wall 33 to achieve a higher blocking water level. After breaking the existing drainage pipe 1, the water flow in the pipe will not overflow, and the dry working environment in the well chamber is always maintained, reducing the safety risks of construction workers.
[0053] In one embodiment of the present application, in order to ensure that the plugging groove 34 and the plugging material 35 can effectively stop the water flow and prevent leakage, the axial length L of the plugging groove 34 along the existing drainage pipe 1 needs to be greater than 0.5m, so as to ensure that the plugging groove 34 and the plugging material 35 have sufficient plugging thickness to ensure their ability to block the water flow. In other embodiments, the axial length L of the plugging groove 34 along the existing drainage pipe 1 can also be less than 0.5m. For example, if the plugging groove is technically feasible, the gate plate can be directly inserted into the plugging groove for plugging, so the size of the axial length L can be adjusted. The size of the axial length L depends on the actual plugging method used.
[0054] like Figure 6 As shown, in one embodiment of the present application, the existing drainage pipe 1 has a first breaking position and a second breaking position, and the first breaking position and the second breaking position are respectively arranged on both sides of the partition wall 33. Among them, the first breaking position is located on the side of the partition wall 33 facing the guide groove 32. At the first breaking position, it is only necessary to partially break the pipe wall of the existing drainage pipe 1 to create a suitable opening so that the water flow can smoothly flow into the guide groove 32 and then be guided to the diverted drainage pipe 2. The second breaking position is located on the side of the partition wall 33 facing the plugging groove 34. At the second breaking position, the existing drainage pipe 1 needs to be completely cut off. The purpose is to ensure that the existing drainage pipe 1 can be completely blocked from the broken position when the plugging material 35 is filled, so as to ensure that the plugging material 35 can be smoothly filled into the plugging groove 34, and the plugging effect of the plugging groove 34 and the plugging material 35 is ensured.
[0055] In one embodiment of the present application, the first end of the relocation section 11 is the water inlet end, and the second end of the relocation section 11 is the water outlet end. The first contact structure is provided at the water inlet end of the relocation section 11, and the second contact structure is provided at the water outlet end of the relocation section 11. The first contact structure and the second contact structure are relatively mirror-symmetrical in space, specifically, the guide groove of the first contact structure is connected to the existing drainage pipe 1 upstream, the guide groove of the second contact structure is connected to the existing drainage pipe 1 downstream, and the plugging groove of the first contact structure and the plugging groove of the second contact structure are clamped at both ends of the relocation section 11.
[0056] In one embodiment of the present application, the plugging material 35 includes a grille 351, a sandbag 352 and concrete 353. The grille 351 is inserted into the broken existing drainage pipe 1. The function of the grille 351 is to provide a support structure to ensure that the subsequent filled materials can be stably accumulated at the second broken position of the existing drainage pipe 1 and prevent the materials from being lost due to the impact of water flow. The sandbag 352 is filled into the plugging groove 34 and the broken existing drainage pipe 1. The sandbag 352 has good plasticity and density, and can effectively fill the gap and prevent water from passing through. In addition, the sandbag 352 can also withstand a certain water pressure to ensure the durability of the plugging effect. Finally, the concrete 353 is poured on the sandbag 352 in the plugging groove 34. The concrete 353 can not only further enhance the plugging effect, but also its hard and durable characteristics enable the plugging to withstand long-term water flow scouring and erosion.
[0057] The present application provides a method for constructing a drainage pipe without pumping and draining, comprising the following steps:
[0058] First, the diverted drainage pipe 2 is laid according to the preset drainage pipe relocation route to ensure that it can be smoothly connected with the existing drainage pipe 1.
[0059] Next, a collision well 31 is constructed at the end of the relocated section 11 of the existing drainage pipe 1. The construction of the collision well 31 must not only meet the engineering standards, but also consider its structural strength and stability to ensure the safety of subsequent construction. The construction method of the collision well 31 can specifically be caisson reverse construction or open excavation masonry, and the present application does not specifically limit the construction method of the collision well 31. Inside the collision well 31, a diversion groove 32 is further built. One end of the diversion groove 32 is set at the first breaking position of the existing drainage pipe 1, and the other end is connected to the diverted drainage pipe 2. In addition, a partition wall 33 is built between the first breaking position and the second breaking position of the existing drainage pipe 1 to separate the plugging groove 34. The plugging groove 34 is enclosed by the outer wall of the diversion groove 32, the partition wall 33 and the inner wall of the collision well 31, providing an operating space for subsequent plugging work.
[0060] Subsequently, a wire saw is used to perform pipe wall breaking operations at the first breaking position and the second breaking position of the existing drainage pipe 1. During the breaking process, the breaking size and position need to be strictly controlled to ensure that no unnecessary damage is caused to the drainage system.
[0061] Finally, the plugging material 35 is filled into the plugging groove 34 to block the incoming and outgoing water of the relocation section 11, ensuring that the water flow is completely diverted to the diverted drainage pipe 2. Then, the bumping well 31 is backfilled and compacted to complete the construction of the drainage pipe without pumping the bumping mouth.
[0062] In one embodiment of the present application, when filling the plugging material 35, in order to enhance the plugging effect and prevent material loss: a grid 351 is inserted at the first break position and the second break position respectively, and the grid 351 can play a role in blocking large particles in the pipeline, preventing the sandbags 352 and concrete 353 filled subsequently from being lost or shifted under the scouring of water flow. After inserting the two grids 351, the sandbags 352 are filled in the area between the two grids 351. As an intermediate filling layer, the sandbags 352 can not only effectively fill the gap, but also because of its compressibility, it can adapt to plugging grooves 34 of different shapes and sizes to ensure the tightness of the plugging. Finally, when the sandbags 352 are filled, concrete 353 is poured into the entire plugging groove 34. As the final solidification layer, the concrete 353 tightly combines the sandbags 352 and the grid 351 to form a solid and stable plugging structure. This structure can effectively block the incoming and outgoing water of the relocation section 11 for a long time, ensuring the safety and stability of the drainage system.
[0063] It should also be noted that when plugging, the grille 351 is against the pipe opening of the downstream diversion drainage pipe 2 in the plugging groove 34, and after the sandbag 352 is thrown in for simple plugging, the water flow in the plugging groove 34 becomes gentle, and at this time, concrete 353 is poured into the remaining space in the plugging groove 34 to form a better seal. If the entire plugging groove 34 is filled with sandbags 352 or other non-hydraulic materials, and finally the upper part of these filling materials is covered with concrete 353, although the plugging effect of this method is not good, the concrete mud 353 can be applied from the outside of the plugging groove 34 to the plugging end surface to ensure the plugging effect.
[0064] In one embodiment of the present application, when the partition wall 33 is built between the first breaking position and the second breaking position, the top surface of the partition wall 33 is higher than the top surface of the existing drainage pipe 1 to prevent water from overflowing.
[0065] In one embodiment of the present application, when constructing the guide groove 32 , in order to prevent water from overflowing the guide groove 32 , the construction height of the guide groove 32 needs to be greater than the height of the existing drainage pipe 1 and the diverted drainage pipe 2 .
[0066] The above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present application should be included in the protection scope of the present application.
Claims
1. A construction structure for drainage pipes without pumping and discharge, characterized in that: include: The existing drainage pipe (1), including the relocation section (11); A diverted drainage pipe (2) for communicating with the existing drainage pipe (1) to replace the diverted section (11); A contact structure (3) is arranged at the end of the diversion section (11), the contact structure (3) comprises a contact well (31) built on the existing drainage pipe (1), a guide groove (32), a partition wall (33) and a plugging groove (34) are arranged in the contact well (31), one end of the guide groove (32) is arranged at the end of the diversion section (11), and the other end of the guide groove (32) is connected to the diversion drainage pipe (2); the partition wall (33) is arranged at The existing drainage pipe (1) is located outside the diversion groove (32) and is arranged on a side close to the relocation section (11). The existing drainage pipe (1) passes through the partition wall (33); the outer wall of the diversion groove (32), the partition wall (33) and the inner wall of the collision well (31) are combined to form the plugging groove (34); after the existing drainage pipe (1) is broken, the plugging groove (34) is used to fill the plugging material (35) to block the incoming water and outgoing water of the relocation section (11).
2. The drainage pipe non-pumping and drainage construction structure according to claim 1 is characterized in that: The masonry top surface of the partition wall (33) is higher than the top surface of the existing drainage pipe (1).
3. The drainage pipe non-pumping and drainage construction structure according to claim 1 is characterized in that: The axial length of the plugging groove (34) along the existing drainage pipe (1) is greater than 0.5 m.
4. The construction structure of the drainage pipe without pumping and discharge according to claim 1, characterized in that: The existing drainage pipe (1) has a first breaking position and a second breaking position, and the first breaking position and the second breaking position are respectively arranged on both sides of the partition wall (33).
5. The drainage pipe non-pumping and drainage construction structure according to any one of claims 1 to 4, characterized in that: The contact structure (3) comprises a first contact structure arranged at the first end of the migration section (11), and a second contact structure arranged at the second end of the migration section (11), wherein the first contact structure and the second contact structure are arranged in a mirror-symmetrical manner.
6. The drainage pipe non-pumping and drainage construction structure according to any one of claims 1 to 4, characterized in that: The blocking material (35) comprises a grille (351), a sandbag (352) and concrete (353); the grille (351) is inserted into the broken existing drainage pipe (1); the sandbag (352) is filled into the blocking groove (34) and the broken existing drainage pipe (1); and the concrete (353) is poured on the sandbag (352) in the blocking groove (34).