Municipal road underground cable duct bank anti-floating construction structure

By designing a floating construction structure including power pipes, pipe clamps, lightning protection grounding and lightning protection grounding poles in the municipal power pipe construction, the problem of floating up the pipes during the pouring process is solved, and higher project quality and construction efficiency are achieved.

CN222775952UActive Publication Date: 2025-04-18CHINA MCC5 GROUP CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421428343.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-21
Publication Date
2025-04-18
Estimated Expiration
2034-06-21

AI Technical Summary

Technical Problem

In the construction of municipal power drainage pipes, the traditional cast-in-place concrete method causes the drainage pipes to easily float during the pouring process, resulting in unqualified finished product quality and increasing construction costs and construction period.

Method used

A municipal road underground cable pipe anti-floating construction structure is designed, including power pipes, pipe clamps, lightning protection grounding and lightning protection grounding poles in the cable pipe trench. Through the connection between the pipe clamps and the grounding poles, the friction between the grounding poles and the soil is used to fix the drain pipes to prevent floating.

Benefits of technology

It effectively prevents the drain pipe from floating during the pouring process, reduces construction defects, improves the quality of the project, improves the anti-floating performance of the drain pipe, saves costs and construction periods, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222775952U_ABST
    Figure CN222775952U_ABST
Patent Text Reader

Abstract

The utility model discloses a municipal road underground cable duct bank anti-floating construction structure, and relates to the technical field of municipal construction equipment tools. A municipal road underground cable duct bank anti-floating construction structure comprises a cable duct bank ditch, electric power duct banks, a pipe hoop, a lightning protection grounding plate and a lightning protection grounding electrode are arranged in the cable duct bank ditch, the electric power duct banks are longitudinally arranged, the pipe hoop hoops the electric power duct banks in a surrounding mode in the transverse direction, the lower portion of the pipe hoop is connected with the lightning protection grounding plate, and the lightning protection grounding electrode is connected with the lightning protection grounding plate. The lightning protection grounding plates are arranged in the longitudinal direction and connected between the lightning protection grounding electrodes, and the lower ends of the lightning protection grounding electrodes are inserted into the soil body. In combination with the characteristics of cast-in-place concrete and lightning protection grounding installation construction of the electric power calandria, when the electric power calandria is encapsulated and poured by concrete, the pipe hoop is additionally arranged to be connected with the grounding electrode, and the calandria is prevented from floating upwards in the pouring process by utilizing the friction force between the grounding electrode and soil. Construction defects are reduced, calandria installation is more standard, the engineering quality is improved, and the anti-floating performance of the underground cable calandria is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of municipal construction equipment and tooling, and in particular to an anti-floating construction structure for underground cable pipes on municipal roads. Background Art

[0002] In the construction of municipal power pipes, the traditional cast-in-place concrete method is to install the lightning protection and grounding embedded parts and formwork after the pipes are installed, and then pour the concrete. During the pouring process, the pipes are very easy to float up, resulting in unqualified quality of the finished product, causing rework, and increasing construction costs and construction period. Utility Model Content

[0003] The purpose of the present application is to provide an anti-floating construction structure for underground cable pipes in municipal roads, which solves the problem of floating of power pipes during the concrete pouring process.

[0004] The purpose of this application is achieved through the following technical solutions:

[0005] The utility model discloses an anti-floating construction structure of underground cable pipes in a municipal road, comprising a cable pipe trench, in which electric pipes, pipe clamps, lightning protection grounding plates and lightning protection grounding electrodes are arranged, a plurality of electric pipes are arranged in the longitudinal direction, pipe clamps are arranged around the electric pipes in the transverse direction, the lower part of the pipe clamps is connected to the lightning protection grounding plates, the lightning protection grounding plates are arranged in the longitudinal direction, the lightning protection grounding plates are connected between the lightning protection grounding electrodes, and the lower ends of the lightning protection grounding electrodes are inserted into the soil.

[0006] Furthermore, a pipe pillow is provided in the cable pipe trench, and the pipe pillow is laterally supported between the power pipes.

[0007] Furthermore, the power pipe is made of CPVC material.

[0008] Furthermore, the power pipes are arranged in a lattice shape in the horizontal direction.

[0009] Furthermore, the pipe clamp is galvanized flat iron.

[0010] Furthermore, one end of the pipe clamp is a straight head and the other end is a right-angle head, the straight head is connected to the lightning protection grounding plate, and the right-angle head is connected to the lightning protection grounding electrode.

[0011] Furthermore, the lightning protection grounding plate is galvanized flat iron, and the lightning protection grounding pole is angle steel.

[0012] Furthermore, the tube pillow is made of modified polypropylene.

[0013] Furthermore, half support heads are formed at both upper and lower ends of the tube pillow, and half ring grooves are provided on the half support heads.

[0014] Furthermore, a pipe clamp is arranged above the lightning protection grounding electrode, and the length of the lightning protection grounding plate is the distance between two adjacent lightning protection grounding electrodes.

[0015] Beneficial effects of this application:

[0016] 1. This application combines the construction characteristics of cast-in-place concrete and lightning protection grounding installation of power cable pipes. When the concrete is encapsulated and poured, a pipe clamp is added to connect with the grounding electrode, and the friction between the grounding electrode and the soil is used to prevent the cable pipe from floating during the pouring process. This reduces construction defects, makes the cable pipe installation more standardized, improves the project quality, and enhances the anti-floating performance of underground cable cable pipes.

[0017] 2. This application fixes the power pipes to prevent them from floating, improves construction efficiency, avoids rework, saves costs, speeds up construction progress, and achieves effective use of resources and maximization of economic benefits. It also improves the existing pipe construction technology level and promotes the innovation and development of corresponding technologies.

[0018] The aforementioned main scheme of the present application and its further options can be freely combined to form multiple schemes, all of which are schemes that can be adopted and claimed for protection in the present application; and in the present application, (non-conflicting options) can also be freely combined with each other and with other options. After understanding the present scheme, those skilled in the art can understand that there are many combinations based on the prior art and common knowledge, all of which are technical schemes to be protected by the present application, and they are not exhaustively listed here. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a three-dimensional diagram of the structure of this application.

[0020] Figure 2 It is a side view of the structure of this application.

[0021] In the figure: 1-power pipe, 2-pipe clamp, 3-lightning protection grounding plate, 4-lightning protection grounding electrode, 5-pipe pillow. DETAILED DESCRIPTION

[0022] The present application is further described below in conjunction with specific embodiments and drawings.

[0023] refer to Figure 1 and Figure 2 As shown, an anti-floating construction structure for underground cable pipes in municipal roads includes a cable pipe trench, in which are arranged power pipes 1, pipe clamps 2, lightning protection grounding plates 3 and lightning protection grounding electrodes 4. The power pipes 1 are made of chlorinated polyvinyl chloride (CPVC) with specifications of φ200mm (wall thickness 8.5mm) + φ110mm (wall thickness 5mm), the pipe clamps 2 and lightning protection grounding plates 3 are made of galvanized flat iron 50*5mm, and the lightning protection grounding electrodes 4 are made of angle steel L50*50*5mm.

[0024] A plurality of electric power pipes 1 are arranged in the longitudinal direction and in a lattice shape in the transverse direction. The pipe clamps 2 surround the electric power pipes 1 in the transverse direction, so that the plurality of electric power pipes 1 form a whole.

[0025] The lower part of the pipe clamp 2 is connected to the lightning protection grounding plate 3, which is arranged in the longitudinal direction. The lightning protection grounding plate 3 is set at the bottom of the pipe group of the power pipe 1 and is parallel to the power pipe 1. Specifically, one end of the pipe clamp 2 is a straight head and the other end is a right-angle head. The straight head is connected to the lightning protection grounding plate 3, and the right-angle head is connected to the lightning protection grounding electrode 4. The connection method is welding, and the three form a fixed structure.

[0026] The lightning protection grounding plate 3 is connected between the lightning protection grounding electrodes 4. The length of the lightning protection grounding plate 3 is the distance between two adjacent lightning protection grounding electrodes 4. In the present application, the spacing between two adjacent lightning protection grounding electrodes 4 is 5m, so the spacing between two adjacent pipe clamps 2 is also 5m, which can not only stabilize the connection and fix the structure, but also save costs, while meeting the effect of lightning protection grounding.

[0027] A pipe clamp 2 is arranged above each lightning protection grounding electrode 4 to ensure structural stability. The length of the lightning protection grounding electrode 4 is 2500mm, and its lower end is inserted into the soil to achieve grounding of the power pipe 1. At the same time, due to the connection between the lightning protection grounding electrode 4, the lightning protection grounding plate 3, and the pipe clamp 2, and the wrapping of the power pipe 1 by the pipe clamp 2, the power pipe 1 can be indirectly fixed in the cable pipe trench by the lightning protection grounding electrode 4, and will not float up during the later pouring process.

[0028] A pipe pillow 5 is also provided in the cable pipe trench, and the pipe pillow 5 is laterally supported between the power pipes 1. The specification of the pipe pillow 5 is DN200, and the material is modified polypropylene, which has extremely high strength, firmness, wear resistance, corrosion resistance and stability.

[0029] The pipe pillow 5 is arranged every 2.5m, and half supports are formed at both ends, and half ring grooves are arranged on the half supports to support the power pipes 1, so as to ensure that each power pipe 1 is stable and does not affect each other. At the same time, the upper and lower pipe pillows 5 form a complete wrapping support for the power pipe 1 in the middle.

[0030] The workflow of this application: The lightning protection grounding electrode 4 is injected into the soil after the cable drainage pipe trench foundation inspection groove is qualified, with a spacing of 5m. Then the lightning protection grounding plate 3 is installed along the longitudinal length of the trench, which is welded to the lightning protection grounding electrode 4, and a pipe clamp 2 is installed every 5m. The size of the pipe clamp 2 is the same as the outer size of the drainage pipe group. Overlap welding is used between the pipe clamp 2, the lightning protection grounding plate 3, and the lightning protection grounding electrode 4, and the overlap length is ≥2b (width). After the installation of the lightning protection grounding electrode 4 is completed, the foundation cushion layer is poured, and then the power drainage pipe 1 and the pipe pillow 5 are installed. The power drainage pipe 1 passes through the pipe clamp 2, and the pipe pillow 5 is installed every 2.5m to ensure that the drainage pipe gap is uniform and the positioning is secure.

[0031] The aforementioned basic examples and their further selected examples can be freely combined to form multiple embodiments, all of which are embodiments that can be adopted and claimed for protection in this application. In the scheme of this application, each selected example can be arbitrarily combined with any other basic examples and selected examples.

[0032] The above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present application should be included in the protection scope of the present application.

Claims

1. A municipal road underground cable pipe anti-floating construction structure, including a cable pipe trench, characterized in that: The cable pipe trench is provided with an electric power pipe (1), a pipe clamp (2), a lightning protection grounding plate (3) and a lightning protection grounding electrode (4). A plurality of electric power pipes (1) are arranged in the longitudinal direction. The pipe clamp (2) surrounds the electric power pipe (1) in the transverse direction. The lower part of the pipe clamp (2) is connected to the lightning protection grounding plate (3). The lightning protection grounding plate (3) is arranged in the longitudinal direction. The lightning protection grounding plate (3) is connected between the lightning protection grounding electrodes (4). The lower end of the lightning protection grounding electrode (4) is inserted into the soil.

2. The anti-floating construction structure for underground cable pipes in municipal roads according to claim 1 is characterized in that: A pipe pillow (5) is also provided in the cable pipe trench, and the pipe pillow (5) is supported between the power pipes (1) in the transverse direction.

3. The anti-floating construction structure for underground cable pipes in municipal roads according to claim 1 is characterized in that: The electric power pipe (1) is made of CPVC material.

4. The anti-floating construction structure for underground cable pipes in municipal roads according to claim 1 is characterized in that: The electric power pipes (1) are arranged in a lattice shape in the transverse direction.

5. The anti-floating construction structure for underground cable pipes in municipal roads according to claim 1 is characterized in that: The pipe clamp (2) is made of galvanized flat iron.

6. The anti-floating construction structure for underground cable pipes in municipal roads according to claim 1 is characterized in that: One end of the pipe clamp (2) is a straight head and the other end is a right-angle head. The straight head is connected to the lightning protection grounding plate (3), and the right-angle head is connected to the lightning protection grounding electrode (4).

7. The anti-floating construction structure for underground cable pipes in municipal roads according to claim 6 is characterized in that: The lightning protection grounding plate (3) is a galvanized flat iron, and the lightning protection grounding electrode (4) is an angle steel.

8. The anti-floating construction structure for underground cable pipes in municipal roads according to claim 2 is characterized in that: The tube pillow (5) is made of modified polypropylene.

9. The anti-floating construction structure for underground cable pipes in municipal roads according to claim 8 is characterized in that: The upper and lower ends of the tube pillow (5) are formed with half support heads, and the half support heads are provided with half annular grooves.

10. The anti-floating construction structure for underground cable pipes in municipal roads according to claim 1 is characterized in that: A pipe clamp (2) is arranged correspondingly above the lightning protection grounding electrode (4), and the length of the lightning protection grounding plate (3) is the distance between two adjacent lightning protection grounding electrodes (4).