Guiding device for SMW construction method pile construction

By designing a guide device for SMW working pile construction, the problem of "H" steel tilting during installation is solved, the foundation stability is ensured, and the installation accuracy is improved through a level detector and an alarm.

CN222782061UActive Publication Date: 2025-04-22SHANDONG ZHENGYUAN CONSTR ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421505807.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-28
Publication Date
2025-04-22
Estimated Expiration
2034-06-28

AI Technical Summary

Technical Problem

In the construction of SMW piles, the lack of guide devices causes the "H" steel to easily tilt during the descending process, which in turn affects the stability of the foundation.

Method used

A guide device for SMW pile construction is designed, including moving plates, threaded columns, threaded sleeves, guide plates, pulleys and horizontal detectors. By adjusting the position of threaded columns and threaded sleeves and rotating the guide plates and pulleys, the "H" steel remains perpendicular during installation.

Benefits of technology

It effectively avoids the inclination of the "H" steel during installation, ensures the stability of the foundation, and reduces the error of manual observation through a level detector and an alarm.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222782061U_ABST
    Figure CN222782061U_ABST
Patent Text Reader

Abstract

The utility model discloses a guide device for SMW construction method pile construction. The guide device comprises a moving plate, a guide plate and a guide plate, an adjusting mechanism is arranged on the lower side of the movable plate, the adjusting mechanism comprises threaded columns, threaded sleeves and connecting pieces, and the threaded columns are fixedly installed on the lower side of the movable plate and distributed in an array mode; a guide mechanism is arranged in the moving plate, the guide mechanism comprises a first guide plate, a first pulley and a first horizontal detector, the first horizontal detector is fixedly mounted on the upper side of the moving plate, and a first alarm is arranged on the upper side of the moving plate. According to the guide device for SMW construction method pile construction, the position relation between a threaded column and a threaded sleeve is adjusted, so that a first horizontal detector on the upper side of a movable plate is in a horizontal state, and then a first guide plate and a second guide plate are perpendicular to the ground; therefore, the H-shaped steel is prevented from inclining during installation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of SMW method piles, in particular to a guiding device used for SMW method pile construction. Background Art

[0002] SMW pile method, also known as steel-cement soil mixing (pile) wall, is an underground engineering construction technology. It combines the use of multi-axis drilling and mixing machines and cement-based reinforcers. It drills to a certain depth on site and sprays cement-based reinforcers at the drill bit to mix and stir repeatedly with the foundation soil to form an underground wall with certain strength and rigidity.

[0003] However, after drilling the common SMW piles, when inserting the "H" steel into the mixture of cement and soil, the workers hold the hoisted "H" steel, and the crane gradually lowers the "H" steel. During the descent of the "H" steel, if there is no guide device, it is easy to make the "H" steel tilt, resulting in the foundation made by the SMW piles not being strong enough;

[0004] Therefore, we propose a guiding device for SMW pile construction to solve the above problems. Utility Model Content

[0005] The utility model aims to provide a guiding device for SMW pile construction, so as to solve the problem raised in the above-mentioned background technology that after the drilling of the common SMW pile is completed, when the "H"-shaped steel is inserted into the mixture of cement and soil, the worker holds the hoisted "H"-shaped steel, and the crane gradually lowers the "H"-shaped steel. During the lowering process of the "H"-shaped steel, if there is no guiding device, the "H"-shaped steel is likely to tilt, thereby causing the foundation made by the SMW pile to be not strong enough.

[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solution: a guiding device for SMW method pile construction, comprising: a moving plate;

[0007] Also includes:

[0008] An adjustment mechanism is provided on the lower side of the movable plate, wherein the adjustment mechanism comprises a threaded column, a threaded sleeve and a connecting piece, wherein the threaded column is fixedly installed on the lower side of the movable plate and the threaded column is distributed in an array;

[0009] A guide mechanism is arranged inside the movable plate, wherein the guide mechanism comprises a first guide plate, a first pulley and a first level detector, the first level detector is fixedly mounted on the upper side of the movable plate, and a first alarm is arranged on the upper side of the movable plate.

[0010] Preferably, the threaded column is threadedly connected to the threaded sleeve, and the threaded sleeve is rotatably connected to the connecting piece, and a moving wheel is fixedly connected to the lower side of the connecting piece, and the threaded column, the threaded sleeve, the connecting piece and the moving wheel all correspond to each other one by one.

[0011] Preferably, a first support plate is fixedly connected to the upper side of the movable plate, the first support plate is threadedly connected to the first threaded rod, and the first threaded rod is rotatably connected to the first guide plate.

[0012] Preferably, a first pulley is rotatably connected to the inner side of the first guide plate, and the first pulleys are distributed in an array, and a first limiting rod is fixedly connected to the outer side of the first guide plate.

[0013] Preferably, the first limiting rod is slidably connected to the connecting plate at the lower side of the movable plate, and the first supporting plate, the first threaded rod, the first guide plate, the first pulley and the first limiting rod are all bilaterally symmetrical about the vertical center axis of the movable plate.

[0014] Preferably, the front side of the movable plate is threadedly connected to the second threaded rod, and the second threaded rod is rotatably connected to the second guide plate.

[0015] Preferably, a second pulley is rotatably connected to the inner side of the second guide plate, and the second pulley is vertically symmetrical about the horizontal center axis of the second guide plate, and a second limiting rod is fixedly connected to the outer side of the second guide plate.

[0016] Preferably, the second limit rod is slidably connected to the connecting plate on the lower side of the movable plate, and the second threaded rod, the second guide plate, the second pulley, and the second limit rod are all symmetrical front to back about the vertical center axis of the movable plate, and a second level detector and a second alarm are provided on the upper side of the movable plate.

[0017] Compared with the prior art, the utility model has the following beneficial effects: the guide device for SMW pile construction adjusts the positional relationship between the threaded column and the threaded sleeve, so that the first level detector on the upper side of the movable plate is in a horizontal state, thereby making the first guide plate and the second guide plate perpendicular to the ground, and by rotating the first threaded rod and the second threaded rod on both sides, the "H"-shaped steel is prevented from tilting during installation;

[0018] 1. A threaded column, a threaded sleeve and a connecting piece are provided. By rotating the threaded sleeve, the positional relationship between the threaded column and the threaded sleeve is adjusted, so that the first level detector on the upper side of the movable plate is in a horizontal state, and then the first guide plate and the second guide plate are perpendicular to the ground;

[0019] 2. A first guide plate, a first pulley and a first level detector are provided. By rotating the first threaded rods on both sides, the two first guide plates clamp the sides of the "H"-shaped steel to prevent one side of the "H"-shaped steel from tilting during installation;

[0020] 3. A second guide plate, a second pulley and a second level detector are provided. By rotating the second threaded rods on both sides, the two second guide plates are clamped in the middle of the "H"-shaped steel to prevent the other side of the "H"-shaped steel from tilting during installation. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 This is a schematic diagram of the front view structure of the utility model;

[0022] Figure 2 This is a schematic diagram of the front view cutaway structure of the utility model;

[0023] Figure 3 This is a side view of the structure of the utility model;

[0024] Figure 4 It is a schematic diagram of the side cutaway structure of the utility model.

[0025] In the figure: 1. moving plate; 2. threaded column; 3. threaded sleeve; 4. connecting piece; 5. moving wheel; 6. first supporting plate; 7. first threaded rod; 8. first guide plate; 9. first pulley; 10. first limiting rod; 11. first level detector; 12. first alarm; 13. second threaded rod; 14. second guide plate; 15. second pulley; 16. second limiting rod; 17. second level detector; 18. second alarm. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0027] See also Figure 1-4 The utility model provides a technical solution: a guide device for SMW pile construction, comprising: a moving plate 1, a threaded column 2, a threaded sleeve 3, a connecting piece 4, a moving wheel 5, a first supporting plate 6, a first threaded rod 7, a first guide plate 8, a first pulley 9, a first limiting rod 10, a first level detector 11, a first alarm 12, a second threaded rod 13, a second guide plate 14, a second pulley 15, a second limiting rod 16, a second level detector 17, and a second alarm 18;

[0028] When using the guide device for SMW pile construction, if Figure 1 As shown, when the SMW pile construction is adopted, the excavator will leave a groove on the ground. After pouring cement into the ground, the "H"-shaped steel is inserted into the mixture of cement and soil, and the movable plate 1 is moved to the top of the groove. The position relationship between the threaded column 2 and the threaded sleeve 3 on the lower side of the movable plate 1 is adjusted so that the movable plate 1 is in a horizontal state, thereby facilitating the positioning and installation of the "H"-shaped steel.

[0029] like Figure 1 As shown, the threaded columns 2 are distributed in an array on the lower side of the movable plate 1, and the threaded columns 2 are threadedly connected to the threaded sleeves 3, the threaded sleeves 3 are rotatably connected to the connecting pieces 4, and the lower side of the connecting pieces 4 is fixedly installed with movable wheels 5. After the movable plate 1 is placed on the ground, it moves along the direction of the groove, and all the movable wheels 5 move in one direction. Since the construction site is not necessarily flat, the movable plate 1 is not necessarily in a horizontal state. The upper side of the movable plate 1 is fixedly connected with a first level detector 11 and a second level detector 17. From the first level detector 11 and the second level detector 17, it can be observed which position the movable plate 1 is tilted. The threaded column 2 is rotated to extend or shorten the threaded column 2 in the threaded sleeve 3, so that the movable plate 1 is in a horizontal state. When the movable plate 1 is in a horizontal state, the first guide plate 8 and the second guide plate 14 in the movable plate 1 will be perpendicular to the ground, so as to ensure that the "H"-shaped steel can be vertically inserted into the cement pit, thereby ensuring that the foundation is relatively stable. In addition, the first alarm 12 and the second alarm 18 are arranged on the upper side of the movable plate 1. The first alarm 12 and the second alarm 18 monitor the first level detector 11 and the second level detector 17 respectively, so as to reduce the error caused by naked eye observation and affect the insertion angle of the "H"-shaped steel;

[0030] like Figure 1 As shown, after the movable plate 1 is placed on the ground, the threaded sleeve 3 is rotated. Since the threaded column 2 is fixedly connected to the movable plate 1 and the movable wheel 5 is in contact with the ground, when the threaded sleeve 3 is rotated, the threaded sleeve 3 rotates in the connecting member 4, and the threaded column 2 in the threaded sleeve 3 will be extended and retracted in a vertical state, and the movable wheel 5 will not be rotated, so that the movable plate 1 can be adjusted to a horizontal state conveniently;

[0031] like Figure 1 and Figure 2 As shown, since the specifications of the "H"-shaped steel inserted into the construction site are the same during one construction, it is only necessary to adjust the spacing between the first guide plates 8 and the spacing between the second guide plates 14 and the second guide plates 14 once during one construction. If the type of the "H"-shaped steel changes during the next construction, it is only necessary to adjust it again, which has a wide range of applications.

[0032] like Figure 1 and Figure 2 As shown, after the crane inserts the "H"-shaped steel from the inner side of the movable plate 1 into the cement soil, since the first support plate 6 is arranged on the upper side of the movable plate 1, the first support plate 6 is threadedly connected with the first threaded rod 7, and the first threaded rod 7 is rotatably connected with the first guide plate 8, the two first threaded rods 7 are rotated, and the first threaded rod 7 will move with the first guide plate 8, so that the first pulleys 9 inside the two first guide plates 8 are closely fitted with the side of the "H"-shaped steel, and in addition, the first limiting rod 10 is fixedly connected to the outer side of the first guide plate 8, and the first limiting rod 10 is slidably connected to the connecting plate on the lower side of the movable plate 1, and the first limiting rod 10 limits the first guide plate 8 to prevent the first guide plate 8 from tilting;

[0033] like Figure 3 and Figure 4 As shown, since the second threaded rod 13 is threadedly connected to the movable plate 1, and the second threaded rod 13 is rotatably connected to the second guide plate 14, the two second threaded rods 13 are rotated, and the second threaded rods 13 will move with the second guide plate 14, so that the second pulleys 15 inside the two second guide plates 14 are tightly fitted with the side of the "H"-shaped steel. In addition, the outer side of the second guide plate 14 is fixedly connected with a second limiting rod 16, and the second limiting rod 16 is slidably connected to the connecting plate on the lower side of the movable plate 1. The second limiting rod 16 limits the second guide plate 14 to prevent the first guide plate 8 from tilting. At this time, the "H"-shaped steel will be vertically inserted into the cement pit;

[0034] like Figure 1 As shown, when it is necessary to insert the "H"-shaped steel into other positions in the cement pit, it is only necessary to move the movable plate 1, and monitor the first level detector 11 and the second level detector 17 through the first alarm 12 and the second alarm 18 to observe in which direction the movable plate 1 is tilted, and adjust it to ensure that the "H"-shaped steel is vertically inserted into the cement pit to play a guiding role.

[0035] The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in the field. The standard parts used in the utility model can be purchased from the market, and special-shaped parts can be customized according to the records in the specification and the drawings. The specific connection methods of each part adopt the conventional means such as mature bolts, rivets, welding, etc. in the prior art. The machinery, parts and equipment all adopt the conventional models in the prior art, and the circuit connection adopts the conventional connection method in the prior art, which will not be described in detail here.

[0036] Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art may still modify the technical solutions described in the aforementioned embodiments, or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention shall be included in the protection scope of the present invention.

Claims

1. A guiding device for SMW pile construction, comprising: Moving plate (1); It is characterized by further comprising: An adjustment mechanism is provided on the lower side of the movable plate (1), wherein the adjustment mechanism comprises a threaded column (2), a threaded sleeve (3) and a connecting piece (4), wherein the threaded column (2) is fixedly mounted on the lower side of the movable plate (1), and the threaded columns (2) are distributed in an array; A guide mechanism is arranged inside the movable plate (1), wherein the guide mechanism comprises a first guide plate (8), a first pulley (9) and a first level detector (11), wherein the first level detector (11) is fixedly mounted on the upper side of the movable plate (1), and a first alarm (12) is arranged on the upper side of the movable plate (1).

2. A guide device for SMW pile construction according to claim 1, characterized in that: The threaded column (2) is threadedly connected to the threaded sleeve (3), and the threaded sleeve (3) is rotatably connected to the connecting piece (4), and a moving wheel (5) is fixedly connected to the lower side of the connecting piece (4), and the threaded column (2), the threaded sleeve (3), the connecting piece (4) and the moving wheel (5) all correspond to each other.

3. A guide device for SMW pile construction according to claim 1, characterized in that: A first support plate (6) is fixedly connected to the upper side of the movable plate (1), and the first support plate (6) is threadedly connected to a first threaded rod (7), and the first threaded rod (7) is rotatably connected to a first guide plate (8).

4. A guide device for SMW pile construction according to claim 3, characterized in that: The inner side of the first guide plate (8) is rotatably connected to a first pulley (9), and the first pulleys (9) are distributed in an array, and the outer side of the first guide plate (8) is fixedly connected to a first limiting rod (10).

5. A guide device for SMW pile construction according to claim 4, characterized in that: The first limiting rod (10) is slidably connected to the connecting plate at the lower side of the movable plate (1), and the first supporting plate (6), the first threaded rod (7), the first guide plate (8), the first pulley (9) and the first limiting rod (10) are all symmetrical about the vertical center axis of the movable plate (1).

6. The guide device for SMW pile construction according to claim 1, characterized in that: The front side of the movable plate (1) is threadedly connected to the second threaded rod (13), and the second threaded rod (13) is rotationally connected to the second guide plate (14).

7. A guide device for SMW pile construction according to claim 6, characterized in that: The inner side of the second guide plate (14) is rotatably connected to a second pulley (15), and the second pulley (15) is vertically symmetrical about the horizontal center axis of the second guide plate (14), and the outer side of the second guide plate (14) is fixedly connected to a second limiting rod (16).

8. The guide device for SMW pile construction according to claim 7, characterized in that: The second limiting rod (16) is slidably connected to the connecting plate at the lower side of the movable plate (1), and the second threaded rod (13), the second guide plate (14), the second pulley (15), and the second limiting rod (16) are all symmetrical front to back about the vertical center axis of the movable plate (1), and a second level detector (17) and a second alarm (18) are provided on the upper side of the movable plate (1).