Hole-drawing stacker crane for ALC (autoclaved lightweight concrete) building block production line

By setting up a limit device and multiple sets of parallel clamping devices between the walking cart and the beam frame of the ALC block palletizer, the problem of traditional palletizers being unable to accurately locate and require frequent use of pallets is solved, and efficient palletization and palletless operation of ALC blocks are achieved, which improves work efficiency and reduces production costs.

CN222808379UActive Publication Date: 2025-04-29SHANDONG TIANYI MACHINERY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420997133.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-10
Publication Date
2025-04-29
Estimated Expiration
2034-05-10

AI Technical Summary

Technical Problem

The traditional ALC block palletizer cannot accurately locate during the movement process, resulting in long clamping time of ALC blocks and low working efficiency. At the same time, it requires frequent use of pallets, which increases production costs.

Method used

A hole extraction palletizer for ALC block production line is designed. Accurate positioning is achieved by setting a limiting device between the walking cart and the beam frame, and the overall clamping and single-blocking holes of ALC blocks are realized through multiple sets of clamping devices arranged in parallel, avoiding the use of pallets.

Benefits of technology

The precise positioning and efficient clamping of ALC blocks are achieved, which reduces the clamping time of ALC blocks, improves work efficiency, and reduces production costs through pallet-free packaging and operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222808379U_ABST
    Figure CN222808379U_ABST
Patent Text Reader

Abstract

A hole drawing stacker crane for an ALC building block production line comprises a beam frame, a walking cart, a lifting device and a clamping device. The beam frame comprises longitudinal beams and stand columns, and the longitudinal beams and the stand columns are fixedly connected. Guide rails are arranged on the longitudinal beams, and limiting holes are further distributed in the outer sides of the longitudinal beams in an array mode. The walking cart comprises a walking beam, a guide column and a limiting device. The driving device controls the walking wheels of the walking cart to move along the beam frame. The lifting device comprises a supporting frame, a hydraulic oil cylinder, a lifting frame and a rotary drive. A rotary drive is arranged at the bottom of the lifting frame. The clamping device comprises a fixing frame, a first clamping assembly, a second clamping assembly, a third clamping assembly and a fourth clamping assembly. The first clamping assembly and the fourth clamping assembly are of a single-clamping-arm structure, and the second clamping assembly and the third clamping assembly are of a multi-clamping-arm structure. Compared with the prior art, the hole drawing stacker crane for the ALC building block production line not only can realize accurate positioning, but also can realize whole and single block hole drawing and crossed stacking of ALC bricks and non-tray packaging and operation, and the stacking efficiency is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of assembled building equipment, in particular to a hole-drawing stacker used for an ALC block production line. Background Art

[0002] With the continuous progress of modern science and technology, in the face of the demand for rapid construction and development, prefabricated housing construction has become a general trend. This construction method is more standardized, mechanized and automated. ALC board is the abbreviation of autoclaved lightweight concrete. It is a porous concrete forming board formed by high-pressure steam curing. According to actual needs, ALC board can be cut into blocks, packaged, and then transported. The traditional packaging process is that the stacker stacks the ALC blocks. When the ALC blocks accumulate to a certain number of layers, they are packaged. Then the stacker places the packaged ALC blocks on the pallet and inserts the pallet through the forklift for operation. The frequent use of pallets has led to increased production costs and low production efficiency; at the same time, the traditional palletizer cannot accurately position during the movement process, which further increases the clamping time of the ALC blocks and reduces the work efficiency. How to design an ALC block stacker that does not require a pallet, can accurately position, and has high work efficiency has become an engineering problem that needs to be solved in this industry. Summary of the invention

[0003] The utility model aims to provide a hole-drawing stacker for an ALC block production line. On the one hand, a limiting device is provided between a traveling trolley and a beam frame to realize accurate positioning of the stacker, so as to facilitate clamping of the ALC blocks; on the other hand, a plurality of groups of clamping devices arranged in parallel are provided to realize overall clamping of the ALC blocks and hole-drawing of a single block, so as to facilitate pallet-free stacking, packaging and operation of the ALC blocks in the later stage.

[0004] The utility model achieves the above-mentioned purpose through the following technical solutions:

[0005] A hole-drawing stacker for an ALC block production line comprises a beam frame, a traveling trolley, a lifting device and a clamping device.

[0006] The beam frame comprises a longitudinal beam and a column, wherein the longitudinal beam and the column are fixedly connected; a guide rail is arranged on the longitudinal beam, and limiting holes are distributed in an array on the outer side of the longitudinal beam.

[0007] The walking trolley comprises a walking beam, a guide column, and a limiting device. The walking beam moves along the guide rail on the longitudinal beam through the walking wheels. The walking beam is a frame structure, and the cross brace of the frame is fixedly connected to the guide column. The limiting device comprises a driving cylinder and a limiting wheel. The driving cylinder is fixedly mounted on the walking beam, and the limiting wheel is mounted at the end of the guide rod of the driving cylinder. The limiting device is used for precise positioning. Under the action of the driving cylinder, the guide rod is driven to move downward, and the limiting wheel is stuck in the limiting hole.

[0008] The lifting device comprises a support frame, a hydraulic oil cylinder, a lifting frame, and a rotary drive. The support frame is fixedly connected to the frame of the walking beam; the cylinder body of the hydraulic oil cylinder is fixedly connected to the support frame, and the piston rod head is hinged to the lifting frame; and a rotary drive is arranged at the bottom of the lifting frame.

[0009] The clamping device comprises a fixed frame, a first clamping assembly, a second clamping assembly, a third clamping assembly, and a fourth clamping assembly. The top of the fixed frame is fixedly connected to the rotary drive; the clamping assemblies are arranged in an array at the bottom of the fixed frame. The first clamping assembly and the fourth clamping assembly are single-clamping arm structures, and the second clamping assembly and the third clamping assembly are multi-clamping arm structures.

[0010] The first clamping assembly comprises a first clamping arm, a second clamping arm, a cylinder, an extension rod, a first sliding device, a second sliding device, and a linkage device.

[0011] The first sliding device comprises a slider and a slide rail. The slider and the slide rail are connected via a moving pair; the slider is fixedly connected to the top of the first clamp arm, and the slide rail is fixedly connected to the bottom of the fixed frame. The connection method between the second sliding device and the second clamp arm is the same as that between the first sliding device and the first clamp arm, and they are arranged symmetrically.

[0012] The cylinder body of the cylinder is fixedly connected to the inner side of the first clamp arm, the piston rod head of the cylinder is fixedly connected to one end of the extension rod, and the other end of the extension rod is fixedly connected to the inner side of the second clamp arm.

[0013] The linkage device comprises a first connecting rod, a second connecting rod and a linkage plate. The two ends of the first connecting rod are respectively hinged to the top of the first clamp arm and one end of the linkage plate through a rotating pair; the middle of the linkage plate is hinged to the bottom of the fixed frame through a rotating pair; the two ends of the second connecting rod are respectively hinged to the top of the second clamp arm and the other end of the linkage plate through a rotating pair. The linkage device cooperates with the cylinder to realize the synchronous opening and closing of the first clamp arm and the second clamp arm.

[0014] The second clamping assembly, the third clamping assembly, the fourth clamping assembly and the fixing frame are connected in the same manner and are all controlled individually by the cylinders.

[0015] The traveling trolley also includes a driving device. The driving device controls the traveling wheels of the traveling trolley to move along the beam frame. A sliding assembly is also arranged between the guide column of the traveling trolley and the vertical arm of the lifting frame to provide a guiding function for the lifting device.

[0016] Compared with the prior art, the outstanding advantages of the utility model are:

[0017] 1. The utility model is a kind of ALC block production line, the travel trolley of the hole-drawing stacker is provided with a limit device, and the cooperation of the limit device and the limit hole on the beam frame can realize accurate positioning, and avoid the longitudinal displacement and shaking of the clamped ALC blocks.

[0018] 2. The utility model is a kind of hole-drawing stacking machine for ALC block production line, which is provided with multiple groups of clamps, and each group of clamps can work independently. With the cooperation of rotary drive, it can realize the pallet-free packaging and operation of ALC bricks for the whole and single-block hole-drawing and cross-stacking, thus greatly improving the stacking efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 This is one of the structural schematic diagrams of a hole-drawing stacker used in an ALC block production line of the utility model.

[0020] Figure 2 This is the second structural schematic diagram of a hole-drawing stacker for an ALC block production line according to the utility model.

[0021] Figure 3 This is the third structural schematic diagram of a hole-drawing stacker for an ALC block production line of the utility model.

[0022] Figure 4 This is the fourth structural schematic diagram of a hole-drawing stacker for an ALC block production line of the utility model.

[0023] Figure 5 This is one of the partial structural schematic diagrams of a hole-drawing stacker used in an ALC block production line of the utility model. Implementation

[0024] The following is attached Figure 1-5 The technical solution of the utility model is further illustrated with embodiments.

[0025] Comparison Figure 1 , Figure 2 , Figure 3 The hole-drawing stacker used in the ALC block production line includes a beam frame 1, a traveling trolley 2, a lifting device 3, and a clamping device 4.

[0026] Comparison Figure 1 The beam frame 1 includes a longitudinal beam 5 and a column 6, wherein the longitudinal beam 5 and the column 6 are fixedly connected; a guide rail 7 is arranged on the longitudinal beam 5, and a limiting hole 8 is distributed in an array on the outer side of the longitudinal beam 5.

[0027] Comparison Figure 1 , Figure 3The walking trolley 2 comprises a walking beam 9, a guide column 10, and a limiting device 35. The walking beam 9 moves along the guide rail 7 on the longitudinal beam 5 through the walking wheel 11. The walking beam 9 is a frame structure, and the cross brace 12 of the walking beam 9 is fixedly connected to the guide column 10. The limiting device 35 comprises a driving cylinder 38 and a limiting wheel 40. The driving cylinder 38 is fixedly mounted on the walking beam 9, and the limiting wheel 40 is mounted at the end of the guide rod 39 of the driving cylinder 38. The limiting device 35 is used for precise positioning. Under the action of the driving cylinder 38, the guide rod 39 is driven to move downward, and the limiting wheel 40 is stuck in the limiting hole 8.

[0028] Comparison Figure 3 , Figure 4 The lifting device 3 comprises a support frame 13, a hydraulic cylinder 14, a lifting frame 15, and a slewing drive 16. The support frame 13 is fixedly connected to the frame of the walking beam 9; the cylinder body of the hydraulic cylinder 14 is fixedly connected to the support frame 13, and the piston rod head is hinged to the lifting frame 15; and a slewing drive 16 is provided at the bottom of the lifting frame 15.

[0029] Comparison Figure 2 , Figure 3 , Figure 4 The clamping device 4 comprises a fixed frame 17, a first clamping assembly 18, a second clamping assembly 19, a third clamping assembly 20, and a fourth clamping assembly 21. The top of the fixed frame 17 is fixedly connected to the rotary drive 16; the clamping assemblies are arranged in an array at the bottom of the fixed frame 17. The first clamping assembly 18 and the fourth clamping assembly 21 are single-clamping arm structures, and the second clamping assembly 19 and the third clamping assembly 20 are multi-clamping arm structures, which can realize the extraction of ALC blocks.

[0030] Comparison Figure 2 , Figure 4 , Figure 5 The first clamping assembly 18 includes a first clamping arm 22, a second clamping arm 23, a cylinder 24, an extension rod 25, a first sliding device 26, a second sliding device 27, and a linkage device 28.

[0031] Comparison Figure 4 , Figure 5 The first sliding device 26 includes a slider 29 and a slide rail 30. The slider 29 and the slide rail 30 are connected through a first moving pair 41; the slider 29 is fixedly connected to the top of the first clamping arm 22, and the slide rail 29 is fixedly connected to the bottom of the fixed frame 17. The connection method of the second sliding device 27 and the second clamping arm 23 is the same as the connection method of the first sliding device 23 and the first clamping arm 22, and they are arranged symmetrically.

[0032] Comparison Figure 2 , Figure 5The base of the cylinder 24 is fixedly connected to the inner side of the first clamping arm 22 , the piston rod head of the cylinder 24 is fixedly connected to one end of the extension rod 25 , and the other end of the extension rod 25 is fixedly connected to the inner side of the second clamping arm 23 .

[0033] Comparison Figure 2 , Figure 5 The linkage device 28 comprises a first connecting rod 31, a second connecting rod 32, and a linkage plate 33. One end of the first connecting rod 31 is hinged to the top of the first clamping arm 22 through a first rotating pair 42, and the other end is hinged to one end of the linkage plate 33 through a second rotating pair 43; the middle of the linkage plate 33 is hinged to the bottom of the fixed frame 17 through a third rotating pair 44; one end of the second connecting rod 32 is hinged to the top of the second clamping arm 23 through a fourth rotating pair 45, and the other end is hinged to the other end of the linkage plate 33 through a fifth rotating pair 46. The linkage device 28 cooperates with the cylinder 24 to realize the synchronous opening and closing of the first clamping arm 22 and the second clamping arm 23.

[0034] Comparison Figure 2 , Figure 4 The second clamping assembly 19 , the third clamping assembly 20 , and the fourth clamping assembly 21 are connected to the fixed frame 17 in the same manner and are all controlled individually by each cylinder 24 .

[0035] Comparison Figure 1 , Figure 2 The traveling trolley 2 further comprises a driving device 34. The driving device 34 controls the traveling wheels 11 of the traveling trolley 2 to move along the beam frame 1. A sliding assembly 37 is also provided between the guide column 10 of the traveling trolley 2 and the vertical arm 36 of the lifting frame 15 to provide a guiding function for the lifting device 3.

[0036] Comparison Figure 1 The actual working conditions of this type of hole-drawing stacker used in the ALC block production line are as follows:

[0037] During the working process, the hole-drawing stacker for the ALC block production line is displaced longitudinally along the beam frame 1 to the ALC block stacking position by the traveling trolley 2; the lifting device 3 drives the clamping device 4 to descend, the clamp is controlled to clamp a group of ALC blocks, and the lifting device 3 raises the clamping device 4; the traveling trolley 2 drives the hole-drawing stacker to move to the top of the packaging conveyor, and the limit device 35 is controlled to lock the traveling trolley 2; the lifting device 3 drops the clamping device 4, and the clamp releases the ALC block group to complete the stacking of the first layer of ALC blocks.

[0038] Furthermore, the hole-drawing stacker used in the ALC block production line clamps a group of ALC blocks again and transfers them to the upper end of the first layer of ALC blocks. The rotary drive 16 drives the clamping device 4 to rotate 90°, the lifting device 3 drops the clamping device 4, and the clamp releases the ALC block group; at this time, the second clamping component 19 and the third clamping component 20 clamp two separated blocks in the ALC block group, and cooperate with the movement of the walking cart 2 to place the two ALC blocks at other workstations to complete the stacking of the second layer of ALC blocks; the rotary drive 16 drives the clamp to rotate 90° again to stack the next layer of ALC blocks. After the stacking of the ALC blocks is completed, the packaging conveyor transports the ALC stacking pile to the packaging position for packaging.

[0039] Except for the technical features described in the specification, all other technical features are known technologies to the professionals in this field.

Claims

1. A hole-drawing stacker for an ALC block production line, comprising a beam frame, a traveling trolley, a lifting device, and a clamping device, characterized in that: The beam frame comprises a longitudinal beam and a column, wherein the longitudinal beam and the column are fixedly connected; a guide rail is arranged on the longitudinal beam, and a limiting hole is arranged in an array on the outer side of the longitudinal beam; The walking trolley comprises a walking beam, a guide column, and a limiting device; the walking beam moves along the guide rail on the longitudinal beam through the walking wheels; the walking beam is a frame structure, and the cross brace of the frame is fixedly connected to the guide column; the limiting device comprises a driving cylinder and a limiting wheel, the driving cylinder is fixedly installed on the walking beam, and the limiting wheel is installed at the end of the guide rod of the driving cylinder.

2. The hole-drawing stacker for an ALC block production line according to claim 1, characterized in that: The lifting device comprises a support frame, a hydraulic cylinder, a lifting frame, and a rotary drive; the support frame is fixedly connected to the frame of the walking beam; the cylinder body of the hydraulic cylinder is fixedly connected to the support frame, and the piston rod head is hinged to the lifting frame; a rotary drive is arranged at the bottom of the lifting frame.

3. The hole-drawing stacker for an ALC block production line according to claim 1, characterized in that: The clamping device comprises a fixed frame, a first clamping component, a second clamping component, a third clamping component, and a fourth clamping component; the top of the fixed frame is fixedly connected to the rotary drive; the clamping components are distributed in an array at the bottom of the fixed frame; the first clamping component and the fourth clamping component are single-clamping arm structures, and the second clamping component and the third clamping component are multi-clamping arm structures.

4. The hole-drawing stacker for an ALC block production line according to claim 3, characterized in that: The first clamping assembly comprises a first clamping arm, a second clamping arm, a cylinder, an extension rod, a first sliding device, a second sliding device, and a linkage device; The first sliding device comprises a slider and a slide rail; the slider and the slide rail are connected via a moving pair; the slider is fixedly connected to the top of the first clamp arm, and the slide rail is fixedly connected to the bottom of the fixed frame; the connection method between the second sliding device and the second clamp arm is the same as the connection method between the first sliding device and the first clamp arm, and they are symmetrically arranged; The cylinder body of the cylinder is fixedly connected to the inner side of the first clamp arm, the piston rod head of the cylinder is fixedly connected to one end of the extension rod, and the other end of the extension rod is fixedly connected to the inner side of the second clamp arm; The linkage device comprises a first connecting rod, a second connecting rod and a linkage plate; the two ends of the first connecting rod are respectively hinged to the top of the first clamping arm and one end of the linkage plate through a rotating pair; the middle of the linkage plate is hinged to the bottom of the fixed frame through a rotating pair; the two ends of the second connecting rod are respectively hinged to the top of the second clamping arm and the other end of the linkage plate through a rotating pair.

5. The hole-drawing stacker for an ALC block production line according to claim 3, characterized in that: The second clamping assembly, the third clamping assembly, the fourth clamping assembly and the fixing frame are connected in the same manner and are all controlled individually by the cylinders.

6. The hole-drawing stacker for an ALC block production line according to claim 1, characterized in that: The traveling trolley also includes a driving device; the driving device controls the traveling wheels of the traveling trolley to move along the beam frame; a sliding component is also provided between the guide column of the traveling trolley and the vertical arm of the lifting frame to provide a guiding function for the lifting device.