By using grouting pipes and liquid level sensors in the side grouting device for road construction, and tensioning hoses are tensioned using the rotary shaft and telescopic tensioning rod structures, the problems of hoses dragging and manual feeding in existing grouting equipment are solved, and construction efficiency and stability of grouting flow rate are improved.
Patent Information
- Application Number
- CN202421409218.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-20
- Publication Date
- 2025-04-29
- Estimated Expiration
- 2034-06-20
AI Technical Summary
During use, existing grouting equipment has problems such as hoses being dragged to the road surface and the slurry needs to be manually refilled after use, resulting in inefficient construction.
A side grouting device for road building of cement-stabilized gravel gravel was designed, and the grouting pipeline structure was used to achieve automatic feeding with a liquid level sensor, and the grouting hose was tensioned through the rotating shaft and telescopic tensioning rod structure to avoid hose dragging.
The continuous work of the grouting device is realized, which saves construction time, ensures the stability of the grouting flow rate, and avoids hose damage.
Smart Images

Figure CN222809827U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of cement-stabilized crushed stone base grouting equipment, and more specifically to an edge grouting device for cement-stabilized crushed stone base road construction. Background Art
[0002] During the road construction process, the road surface must be paved after the roadbed is completed. However, since the roadbed is easily softened and deformed by water and is prone to dust, a roadbed stabilization layer must be laid on the roadbed to stabilize the roadbed and protect it from water erosion. Generally, high-grade pavements basically use cement-stabilized graded crushed gravel as the stabilization layer.
[0003] In the actual construction process, in order to facilitate the effective control of the road width to save the loss of raw materials, and provide a certain lateral pressure to facilitate the compaction and forming of the edge of the road surface, a lateral formwork construction process is generally adopted, and it is usually rolled by a large-tonnage roller after being paved by a paver. Since the base layer is squeezed and extended to the edge during the rolling process of the roller, the paver often lacks fillers at the edge position near the formwork. In order to improve the forming effect of the edge position of the road surface, the prior art generally adopts manual or mechanical methods to fill and grout the edge of the base layer. The above-mentioned manual or mechanical methods have the following problems: first, the existing grouting equipment is directly placed on the edge of the paver. During use, it is necessary to adjust the lateral distance of the grouting slot according to the grouting position. When the distance is small, the grouting hose is easily dragged onto the road surface, which has the risk of damage and affects the grouting flow rate. The stability is not good enough; second, after the slurry in the grouting equipment is used up, it is still necessary to manually add materials, which increases the construction time and is not convenient enough. Utility Model Content
[0004] The purpose of the utility model is to provide an edge grouting device for road construction with a cement-stabilized crushed stone base. On the one hand, the device can tighten the grouting hose to prevent the grouting hose from being dragged onto the road surface and ensure the grouting flow rate. On the other hand, the slurry barrel can be automatically detected and fed to ensure the continuous working time of the edge grouting device and save work time.
[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is as follows:
[0006] A grouting device for edge grouting of cement-stabilized crushed stone base road construction, comprising a paver, a screed plate is arranged at the rear of the paver, bracket plates are arranged on the upper surfaces of both sides of the screed plate, and a grouting bucket is arranged on each bracket plate, a stirring assembly is arranged inside the grouting bucket, a plurality of mounting sleeves are arranged in front of the bracket plate, and a transverse adjustment rod passes through the mounting sleeve, a longitudinal adjustment rod is arranged on the outer end of the transverse adjustment rod through the mounting sleeve, the transverse adjustment rod and the longitudinal adjustment rod are both limited by bolts on the outer side of the mounting sleeve, and the lower end of the longitudinal adjustment rod is connected with A grouting slot, wherein the grouting slot is connected to the front lower end of the grouting bucket through a hose, a liquid level sensor is fixed at the middle and lower position of the inner side wall of the grouting bucket, a grouting pipe extends into the opening area above the grouting bucket, one end of the grouting pipe extends into the grouting bucket and the other end is connected to the inside of the barrel of the paver trolley, the grouting pipe is fixed near the paver through a plurality of L-shaped connecting rods, the upper end of the L-shaped connecting rod is mounted on the pipeline of the grouting pipe and the lower end is fixed to the surface of the ironing plate, and an electric control valve is installed on the pipeline of the grouting pipe near the trolley.
[0007] As a further optimization of the present solution, the front end surfaces on both sides of the ironing plate are provided with clamps, a rotating shaft is installed between the clamps, a telescopic tensioning rod is provided outwardly on the shaft body of the rotating shaft, a non-telescopic section of the telescopic tensioning rod is fixed to the shaft body of the rotating shaft and a ring is connected to the telescopic section, a hose passes through the inside of the ring and lifts the hose upward for tensioning, and the rotating shaft and the telescopic tensioning rod are both limited by side locking nuts.
[0008] As a further optimization of this solution, the liquid level sensor does not contact the stirring rod of the stirring assembly.
[0009] As a further optimization of this solution, an electric-controlled valve is also provided at the front outlet end of the grouting barrel, and the stirring assembly, the electric-controlled valve and the liquid level sensor are all connected to the control panel through lines.
[0010] Compared with the prior art, the beneficial effects of the utility model are as follows:
[0011] The utility model can detect the remaining amount of slurry in the grouting bucket by setting a grouting pipeline structure and combining it with a liquid level sensor. When the amount is lower than the threshold, the electric control valve on the grouting pipeline can be opened to automatically inject new slurry into the grouting bucket, replacing the traditional frequent manual feeding, ensuring the continuous working time of the edge grouting device and saving working hours.
[0012] The utility model provides a rotating shaft and a telescopic tensioning rod structure, which facilitates the adjustment of the support angle and the support length of the telescopic tensioning rod, provides tension support for the hose throughout the entire process, and caters to the grouting slot position adjusted by the lateral adjustment rod and the longitudinal adjustment rod, thereby preventing the grouting hose from being dragged onto the road surface and causing damage, and ensuring the grouting flow rate. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 This is a schematic diagram of the structure of the automatic screening device of the utility model (when performing overall vibration);
[0014] Figure 2 This is a schematic diagram of the disassembled structure of the automatic screening device of the utility model (when performing step-by-step vibration);
[0015] Figure 3 This is a schematic diagram of the vertical bracket plate connection structure of the utility model;
[0016] In the figure: 1. paver; 2. ironing plate; 3. bracket plate; 4. grouting bucket; 5. lateral adjustment rod; 6. longitudinal adjustment rod; 7. bolt; 8. grouting groove; 9. L-shaped connecting rod; 10. grouting pipeline; 11. electric control valve; 12. liquid level sensor; 13. hose; 14. splint; 15. rotating shaft; 16. telescopic tensioning rod; 17. locking nut; 18. ring. DETAILED DESCRIPTION
[0017] In order to make the technical means, creative features, objectives and effects achieved by the utility model easy to understand, the utility model is further explained below with reference to specific diagrams.
[0018] In order to solve the problem that after the slurry in the existing grouting equipment is used up, manual feeding operation is required, which increases the construction time and is not convenient enough, such as Figure 1 and Figure 2 As shown, the present application includes a paver 1, a screed plate 2 is arranged at the rear of the paver 1, bracket plates 3 are arranged on the upper surfaces of both sides of the screed plate 2, and a grouting bucket 4 is arranged on each bracket plate 3, a stirring assembly is arranged inside the grouting bucket 4, a plurality of mounting sleeves are arranged in front of the bracket plate 3, and a transverse adjustment rod 5 passes through the mounting sleeve, and a longitudinal adjustment rod 6 is arranged on the outer end of the transverse adjustment rod 5 through the mounting sleeve, and the transverse adjustment rod 5 and the longitudinal adjustment rod 6 are both limited by bolts 7 on the outer side of the mounting sleeve, and a grouting slot 8 is connected to the lower end of the longitudinal adjustment rod 6, and the grouting slot 8 is opened by a soft The pipe 13 is connected to the lower front end of the grouting bucket 4, a liquid level sensor 12 is fixed at the middle and lower position of the inner side wall of the grouting bucket 4, a grouting pipe 10 is extended into the upper opening area of the grouting bucket 4, one end of the grouting pipe 10 is extended into the grouting bucket 4 and the other end is connected to the barrel of the paver 1 cart, the grouting pipe 10 is fixed near the paver 1 by a plurality of L-shaped connecting rods 9, the upper end of the L-shaped connecting rod 9 is sleeved on the pipeline of the grouting pipe 10 and the lower end is fixed to the surface of the ironing plate 2, and an electric control valve 11 is installed on the pipeline of the grouting pipe 10 near the cart;
[0019] Specifically, when the liquid level sensor 12 detects that the slurry inside the grouting bucket 4 is lower than the threshold value, the electric control valve 11 on the grouting pipeline 10 is opened to add the slurry prepared inside the cart barrel into the grouting bucket 4 to achieve automatic feeding.
[0020] In order to solve the problem that the existing grouting hose is easily dragged onto the road surface, which may cause damage, affect the grouting flow rate, and have poor stability, such as Figure 3 As shown, the front end surfaces of both sides of the ironing plate 2 of the present application are provided with clamping plates 14, a rotating shaft 15 is installed between the clamping plates 14, a telescopic tensioning rod 16 is provided outwardly on the shaft body of the rotating shaft 15, the non-telescopic section of the telescopic tensioning rod 16 is fixed to the shaft body of the rotating shaft 15, and the telescopic section is connected to a collar 18, the inside of the collar 18 passes through the hose 13 and lifts the hose 13 upward for tensioning, and the rotating shaft 15 and the telescopic tensioning rod 16 are both limited by the locking nut 17 on the side;
[0021] Specifically, according to the needs of grouting on different edges, the position of the grouting slot 8 is adjusted by the lateral adjustment rod 5 and the longitudinal adjustment rod 6 and the grouting position is fixed by the bolt 17. Then, the inclination angle and the telescopic length of the telescopic tensioning rod 16 are adjusted and the position is fixed by the locking nut 17, so that the ring 18 lifts the hose 13 upward and tightens it to prevent the hose 13 from falling onto the road surface, while improving the stability of the hose 13 during operation.
[0022] The standard parts used in the utility model can all be purchased from the market, and special-shaped parts can be customized according to the instructions and the drawings. The specific connection methods of each part adopt the conventional means such as mature bolts, rivets, welding, etc. in the existing technology. The machinery, parts and equipment all adopt the conventional models in the existing technology, and the circuit connection adopts the conventional connection method in the existing technology, which will not be described in detail here.
[0023] The above shows and describes the basic principle and main features of the utility model and the advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.
Claims
1. A grouting device for edge grouting of cement-stabilized gravel base road, comprising a paver, a screed plate is arranged at the rear of the paver, bracket plates are arranged on the upper surfaces of both sides of the screed plate, and a grouting bucket is arranged on each bracket plate, a stirring assembly is arranged inside the grouting bucket, a plurality of mounting sleeves are arranged in front of the bracket plate, and a transverse adjustment rod passes through the mounting sleeve, a longitudinal adjustment rod is arranged on the outer end of the transverse adjustment rod through the mounting sleeve, the transverse adjustment rod and the longitudinal adjustment rod are both limited by bolts on the outer side of the mounting sleeve, a grouting notch is connected to the lower end of the longitudinal adjustment rod, and the grouting notch is connected to the lower end of the front of the grouting bucket through a hose, characterized in that: A liquid level sensor is fixed at the middle and lower position of the inner side wall of the grouting barrel, a grouting pipe extends into the opening area above the grouting barrel, one end of the grouting pipe extends into the grouting barrel and the other end is connected to the inside of the barrel of the paver cart, the grouting pipe near the paver is fixed by a plurality of L-shaped connecting rods, the upper end of the L-shaped connecting rod is sleeved on the pipeline of the grouting pipe and the lower end is fixed to the surface of the ironing plate, and an electric control valve is installed on the pipeline of the grouting pipe near the cart.
2. The edge grouting device for road construction with cement-stabilized crushed stone base according to claim 1 is characterized in that: The front end surfaces of both sides of the ironing plate are provided with clamps, a rotating shaft is installed between the clamps, a telescopic tensioning rod is provided outwardly on the shaft body of the rotating shaft, the non-telescopic section of the telescopic tensioning rod is fixed to the shaft body of the rotating shaft and a ring is connected to the telescopic section, a hose passes through the inside of the ring and lifts the hose upward for tensioning, and the rotating shaft and the telescopic tensioning rod are limited by side locking nuts.
3. The edge grouting device for road construction with cement-stabilized crushed stone base according to claim 2, characterized in that: The liquid level sensor does not contact the stirring rod of the stirring assembly.
4. The edge grouting device for road construction with cement-stabilized crushed stone base according to claim 3 is characterized by: An electric control valve is also provided at the front outlet end of the grouting bucket, and the stirring assembly, the electric control valve and the liquid level sensor are all connected to the control panel through lines.