Cement stabilizing layer template fixing device

By designing an inner pull rod structure for cement stabilizing layer formwork fixing device and connecting it with the formwork using an annular joint, the problem of increased workload and poor formwork stability in the prior art is solved, and more efficient formwork fixing and better construction quality are achieved.

CN222809830UActive Publication Date: 2025-04-29XUZHOU XINYUAN CONSTR ROAD SURFACE MASCH CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421389725.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-17
Publication Date
2025-04-29
Estimated Expiration
2034-06-17

AI Technical Summary

Technical Problem

During use, the existing cement stabilization layer formwork fixing system requires the internal pull rod to be flipped 90 degrees, which increases the workload of workers and the crossbar is easy to open and weld, resulting in poor formwork stability and affecting construction quality.

Method used

A cement stabilizing layer formwork fixing device is designed, including an inner pull rod, a formwork and a fixing nail. The inner pull rod is connected to the projection of the formwork through an annular joint, reducing the flip operation and enhancing stability through the support rod and U-shaped structure.

Benefits of technology

The device can firmly fix the formwork at one time, reduce the workload of workers, improve the stability of the formwork, and ensure the quality of the construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222809830U_ABST
    Figure CN222809830U_ABST
Patent Text Reader

Abstract

The utility model discloses a cement stabilizing layer formwork fixing device which comprises an inner pull rod, a formwork and a fixing nail. The inner pull rod comprises a first rod body and a second rod body, an annular connector is welded to one end of the first rod body, the other end of the first rod body is bent to be connected with one end of the second rod body, a supporting rod perpendicular to the second rod body is welded to the lower portion of the other end of the second rod body, and the tail end of the second rod body is bent into a U-shaped structure or punched into a hole-shaped structure. And a plurality of concave holes with bulges are formed in the side wall of the template. The fixing device for the cement stabilizing layer template reduces the workload of workers, improves the stability of the template, and ensures the construction quality.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of road construction, in particular to a cement stabilization layer template fixing device. Background Art

[0002] When constructing the stabilization layer of a cement road, it is necessary to support the formwork on both sides of the road to shape the concrete; after the formwork is laid, additional devices are needed to reinforce the formwork.

[0003] Chinese patent publication number CN215482153U discloses an inner-pull type cement stabilization layer formwork fixing system, including an inner pull rod, a formwork and fixing nails. One end of the inner pull rod is provided with two parallel cross bars for connecting and fixing with the rectangular holes on the formwork, and the other end of the inner pull rod is bent into a hook-shaped structure for inserting the fixing nails. During use, the inner pull rod needs to be turned 90 degrees, which increases the workload of workers; in addition, during the compaction process, the cross bar connected to the formwork is prone to welding, causing one of the cross bars to fall off, and the stability of the formwork is poor, which is not conducive to the fixation of the cement stabilization layer and affects the construction quality. Utility Model Content

[0004] The utility model aims to provide a cement stabilization layer formwork fixing device with high stability, which can reduce the workload of workers and ensure the construction quality.

[0005] To achieve the above-mentioned purpose, the utility model provides a cement stabilization layer formwork fixing device, comprising an inner pull rod, a formwork and a fixing nail; the inner pull rod comprises a first rod body and a second rod body, one end of the first rod body is welded with a ring joint, the other end of the first rod body is bent and connected to one end of the second rod body, a support rod perpendicular to the other end of the second rod body is welded below, and the tail end of the second rod body is bent into a U-shaped structure or punched into a hole-shaped structure; the side wall of the formwork is provided with a plurality of concave holes with protrusions.

[0006] As a further solution of the present invention: the first rod body and the second rod body are integrally formed, and the length of the first rod body is smaller than the length of the second rod body.

[0007] As a further solution of the utility model: the concave holes are arranged in a row in a direction parallel to the template, in which case the protrusions protrude upward from the bottom of the template and the concave holes are inverted concave; or the concave holes are arranged in two rows in a direction parallel to the template, in which case the concave holes are symmetrically arranged.

[0008] As a further solution of the utility model: the distance from the top of the protrusion to the top of the concave hole matches the height of the annular joint.

[0009] As a further solution of the utility model: the size of the annular joint matches the protrusion and the concave hole.

[0010] As a further solution of the utility model: the end of the annular joint is welded to the first rod body by winding or parallel welding.

[0011] As a further solution of the utility model: the support rod is welded through the first and second ends of the U-shaped structure, so that the U-shaped structure forms a closed space.

[0012] As a further solution of the utility model: the inner pull rod has eight different forms.

[0013] Compared with the prior art, the beneficial effects of the utility model are as follows:

[0014] The hole-shaped joint on the inner tie rod can be sleeved on the protrusion of the template, which can firmly fix the template at one time. There is no need to flip the inner tie rod, which reduces the workload of workers and prevents the joint from falling off, thereby improving the stability of the template; the angle between the first rod body and the second rod body can make the inner tie rod more stably sleeved on the protrusion of the template; the support rod is welded at the tail end of the inner tie rod to prevent the inner tie rod from flipping over, thereby increasing the contact area with cement; the end of the inner tie rod is set to a U-shaped structure or punched into a hole, both of which are for more convenient insertion of fixing nails; the cement stabilization layer template fixing device of the utility model reduces the workload of workers, improves the stability of the template, and ensures the construction quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a structural schematic diagram of the inner pull rod of the utility model.

[0016] Figure 2 The utility model is a structural schematic diagram of an inner pull rod adopting a first annular joint and a U-shaped structure at the tail end.

[0017] Figure 3 The utility model is a structural schematic diagram of an inner pull rod adopting a first annular joint and a hole-shaped structure at the tail end.

[0018] Figure 4 It is a top view of the inner pull rod of the utility model adopting a first annular joint and a hole-shaped structure at the tail end.

[0019] Figure 5 It is a top view of the utility model in which the inner pull rod adopts a second annular joint and the tail end is a U-shaped structure.

[0020] Figure 6 It is a top view of the utility model in which the inner pull rod adopts a second annular joint and the tail end is a hole-shaped structure.

[0021] Figure 7 It is a top view of the inner pull rod of the utility model adopting a third annular joint and having a U-shaped structure at the tail end.

[0022] Figure 8It is a top view of the utility model in which the inner pull rod adopts a third annular joint and the tail end is a hole-shaped structure.

[0023] Fig. 9 It is a top view of the utility model in which the inner pull rod adopts a fourth annular joint and the tail end is a U-shaped structure.

[0024] Fig.10 It is a top view of the utility model in which the inner pull rod adopts a fourth annular joint and the tail end is a hole-shaped structure.

[0025] Fig.11 The utility model is a schematic diagram of the structure of a cement stabilization layer template fixing device.

[0026] Fig.12 It is a structural schematic diagram of the symmetrically arranged concave holes of the utility model.

[0027] Fig.13 It is a structural schematic diagram of the concave hole of the utility model.

[0028] Fig.14 The utility model is a structural schematic diagram of the cement stabilization layer template fixing device during use.

[0029] In the figure: 1. annular joint, 11. first annular joint, 12. second annular joint, 13. third annular joint, 14. fourth annular joint, 2. first rod body, 3. second rod body, 4. support rod, 5. U-shaped structure, 6. hole structure, 7. template, 8. concave hole, 81. first concave hole, 82. second concave hole, 83. third concave hole, 84. fourth concave hole, 9. fixing nail, 10. cement, 15. base layer. DETAILED DESCRIPTION

[0030] The utility model will be further described below in conjunction with the accompanying drawings.

[0031] like Figures 1 to 11 As shown, a cement stabilization layer formwork fixing device comprises an inner pull rod, a formwork 7 and a fixing nail 9; the inner pull rod comprises a first rod body 2 and a second rod body 3, one end of the first rod body 2 is welded with a ring joint 1, the other end of the first rod body 2 is bent and connected to one end of the second rod body 3, a support rod 4 perpendicular to the other end of the second rod body 3 is welded below, the tail end of the second rod body 3 is bent into a U-shaped structure 5 or punched into a hole-shaped structure 6; the side wall of the formwork 7 is provided with a plurality of concave holes 8 with protrusions.

[0032] The first rod body 2 and the second rod body 3 are integrally formed, and the length of the first rod body 2 is smaller than that of the second rod body 3 .

[0033] The size of the annular joint 1 matches the protrusion and the concave hole 8; the ring of the annular joint is circular. Figure 2 , Figure 4The first annular joint 11, the second annular joint 12, or the arc-shaped triangle as shown in FIG. Figure 5 , Figure 6 The third and fourth annular joints are shown.

[0034] like Fig.11 As shown, when the concave holes 8 are arranged in a row in the direction parallel to the template, in order to facilitate the annular joint 1 to be sleeved on the protrusion of the template, the protrusion is protruding upward from the bottom of the template 7, so the concave holes 8 on the template are inverted concave. Considering that the direction of the concave holes 8 needs to be confirmed when placing the template, in order to facilitate the placement of the template, as shown in FIG. Fig.12 As shown, the concave holes 8 are arranged in two rows in the parallel direction of the template 7. At this time, symmetrical concave holes 8 are arranged on the template, so there is no need to confirm the direction of the template, and the annular joint can be sleeved on the concave holes 8 whether it is placed upright or upside down.

[0035] In order to make the connection between the annular joint 1 and the first rod body 2 more firmly, the end of the annular joint 1 is wound and welded with the first rod body 2 or welded in parallel, as shown in FIG. Figures 1 to 10 As shown, this increases the welding area and enables the annular joint to be more firmly sleeved on the template, thereby avoiding the open welding or falling off of the inner tie rod during use.

[0036] In order to facilitate the annular joint 1 to pass through the concave hole 8, the distance from the top of the protrusion to the top of the concave hole 8 matches the height of the annular joint 1. Fig.13 As shown, there are at least four shapes of the concave holes 8.

[0037] The support rod 4 is welded through the first and second ends of the U-shaped structure 5, so that the U-shaped structure forms a closed space, which is convenient for fixing and inserting steel nails.

[0038] Since the inner tie rod annular joint 1 and the tail end of the inner tie rod have different styles, the inner tie rod has eight different combinations, as shown in FIG. Figures 3 to 10 As shown, the inner pull rod adopts a combination form of a first annular joint and a U-shaped structure at the tail end; the inner pull rod adopts a combination form of a first annular joint and a hole-shaped structure at the tail end; the inner pull rod adopts a combination form of a second annular joint and a U-shaped structure at the tail end; the inner pull rod adopts a combination form of a second annular joint and a hole-shaped structure at the tail end; the inner pull rod adopts a combination form of a third annular joint and a U-shaped structure at the tail end; the inner pull rod adopts a combination form of a third annular joint and a hole-shaped structure at the tail end; the inner pull rod adopts a combination form of a fourth annular joint and a U-shaped structure at the tail end; the inner pull rod adopts a combination form of a fourth annular joint and a hole-shaped structure at the tail end.

[0039] The working process of this utility model: Fig.11 , 14As shown, first place the template 7 outside the edge of the road base layer 15; hold the inner tie rod, pass the annular joint 1 through the concave hole 8, and directly sleeve it on the protrusion, and then fix the tail end of the inner tie rod to the base layer 15 with a steel nail 9. At this time, the support rod 4 is close to the upper surface of the base layer 15; after paving the cement 10, compacting and curing, remove the annular joint to separate the template 7 from the inner tie rod, and complete the removal of the template 7.

Claims

1. A cement stabilized layer formwork fixing device, comprising an inner tie rod, a formwork (7) and a fixing nail (9), characterized in that: The inner pull rod comprises a first rod body (2) and a second rod body (3); one end of the first rod body (2) is welded with a ring joint (1); the other end of the first rod body (2) is bent and connected to one end of the second rod body (3); a support rod (4) perpendicular to the second rod body (3) is welded below the other end of the second rod body (3); the tail end of the second rod body (3) is bent into a U-shaped structure (5) or punched into a hole-shaped structure (6); and a plurality of concave holes (8) with protrusions are provided on the side wall of the template (7).

2. The cement stabilization layer formwork fixing device according to claim 1 is characterized in that: The first rod body (2) and the second rod body (3) are integrally formed, and the length of the first rod body (2) is shorter than the length of the second rod body (3).

3. The cement stabilization layer formwork fixing device according to claim 1 is characterized in that: The concave holes (8) are arranged in a row in a direction parallel to the template (7), in which case the protrusions protrude upward from the bottom of the template (7), and the concave holes (8) are inverted concave; or the concave holes (8) are arranged in two rows in a direction parallel to the template (7), in which case the concave holes (8) are symmetrically arranged.

4. The cement stabilization layer formwork fixing device according to claim 1 or 3, characterized in that: The distance from the top of the protrusion to the top of the concave hole (8) matches the height of the annular joint (1).

5. The cement stabilization layer formwork fixing device according to claim 1 or 2, characterized in that: The size of the annular joint (1) matches the protrusion and the concave hole (8).

6. The cement stabilization layer formwork fixing device according to claim 1, characterized in that: The end of the annular joint (1) is welded to the first rod body (2) by winding or parallel welding.

7. The cement stabilization layer formwork fixing device according to claim 1, characterized in that: The support rod (4) is welded through the front and rear ends of the U-shaped structure (5).

8. The cement stabilization layer formwork fixing device according to claim 5, characterized in that: The inner tie rod has eight different forms.