Integral floating gate access gate chamber structure
By designing the overall floating gate maintenance door warehouse structure, using the cooperation of the door warehouse components and the limit boss to form a closed maintenance space, and dry ground construction is realized through the pump, the problem of inconvenience in the overall floating gate of the ship lock is solved, and the convenience and safety of maintenance are improved.
Patent Information
- Application Number
- CN202420945994.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-30
- Publication Date
- 2025-05-06
- Estimated Expiration
- 2034-04-30
AI Technical Summary
In the prior art, the overall floating gate of the ship lock is inconvenient to be maintained, and there are safety risks and high costs for maintenance on the water surface.
An integral floating gate maintenance door library structure is designed, including two door library components, each door library component has a storage groove and a connecting opening. The gate is placed in the storage groove, and the limit boss is arranged at both ends of the opening. By cooperating with the limit boss, a closed maintenance space is formed, and water conservancy is pumped through a water pump to achieve dry ground construction conditions.
It greatly improves the convenience of the overall floating gate, reduces the cost of maintenance, ensures the personal safety of maintenance personnel, and solves the problem of inconvenient maintenance of the overall floating gate of the ship lock.
Smart Images

Figure CN222834862U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of water conservancy projects, in particular to an integral floating gate maintenance door storehouse structure. Background Art
[0002] In the ship lock project, two integral floating gates are generally set up to block the water upstream and downstream during the ship lock overhaul, drain the water inside the ship lock, and carry out the ship lock overhaul. The integral floating gate is similar to a ship, floating in the water, and the gate is opened and closed by pumping water in the cabin. When not in use, it is stored in the gatehouse next to the navigation wall, and the gatehouse is normally open. The integral floating gate is large in size and heavy in weight. Once it is launched into the water, it is difficult to get ashore. Therefore, the maintenance of the integral floating gate needs to be carried out on the water surface. When the integral floating gate needs to be maintained and replaced, water needs to be poured into the cabin. With manual assistance, the integral floating gate is turned from a vertical state to a lying state and floats on the water surface. During the process of filling water and lying down, the gate posture control is difficult. After lying down, the staff needs to replace the water stop on the water, which also poses a safety risk. In addition, since it is on the water surface, considering pollution and other issues, anti-corrosion maintenance cannot be carried out, and the integral floating gate can only be dragged out of the ship lock for maintenance, which greatly increases the maintenance cost.
[0003] As can be seen from the above, the existing technology has the problem that the integral floating gate of the ship lock is inconvenient to inspect and maintain. Utility Model Content
[0004] The main purpose of the utility model is to provide an integral floating gate maintenance door garage structure to solve the problem of inconvenient maintenance of the integral floating gate of the ship lock in the prior art.
[0005] In order to achieve the above-mentioned purpose, the utility model provides an integral floating gate maintenance door garage structure, including two door garage components, the door garage components including: a door garage, the door garage has a receiving groove and an opening connected to the receiving groove; a gate, the gate is placed in the receiving groove; a limiting boss, there are two limiting bosses, the two limiting bosses are arranged at both ends of the opening, the gate of one door garage component is used to move to the opening of the other door garage component and stop with the limiting boss and block the receiving groove when the gate of the other door garage component needs to be inspected.
[0006] Furthermore, the gate garage assembly also includes an inspection pier, which is arranged at the bottom of the accommodating groove, and the gate is placed on the inspection pier.
[0007] Furthermore, there are a plurality of maintenance piers, which are arranged at intervals along the length direction of the accommodating groove.
[0008] Furthermore, a mounting recess is provided on the top of the maintenance pier, and the bottom end of the gate is accommodated in the mounting recess.
[0009] Furthermore, the gatehouse assembly also includes a mooring post, which is arranged on the gatehouse and is used to connect and fix the gate.
[0010] Furthermore, a groove is provided on the inner side wall of the door garage, and the mooring post is accommodated in the groove.
[0011] Furthermore, there are multiple mooring posts, which are arranged at intervals along the length direction of the accommodating groove.
[0012] Furthermore, the gate is provided with a mounting hole, and the limiting boss is correspondingly provided with a through hole, and the fastener passes through the mounting hole and the through hole in sequence to fasten the gate and the limiting boss.
[0013] Furthermore, the door garage assembly also includes a water pump for draining the water in the accommodating tank.
[0014] Furthermore, the door garage assembly also includes a ladder, which is arranged on the inner wall of the door garage.
[0015] By applying the technical solution of the utility model, the overall floating gate maintenance door library structure includes two door library components, the door library components include a door library, a gate and a limiting boss, the door library has a receiving groove and an opening connected to the receiving groove, the gate is placed in the receiving groove, there are two limiting bosses, and the two limiting bosses are arranged at both ends of the opening, the gate of one door library component is used to move to the opening of the other door library component when the gate of the other door library component needs to be repaired, and the limiting boss is used to block the receiving groove, so that the two door library components can cooperate with each other, and the limiting boss is arranged at the opening. A limiting boss is arranged, and when the gate of one gate library assembly needs to be repaired, the gate of the other gate library assembly is moved to the opening of the gate library assembly, thereby cooperating with the limiting boss to block the accommodating groove to form a closed maintenance space, and then the water in the accommodating groove is drained to meet the dry land construction conditions, which is convenient for the maintenance procedures such as water stop replacement, painting and anti-corrosion of the gate, greatly improving the maintenance convenience of the overall floating gate, while reducing the maintenance cost, ensuring the personal safety of the maintenance personnel, and solving the problem of inconvenient maintenance of the overall floating gate of the ship lock in the prior art. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The drawings constituting part of the present application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention. In the drawings:
[0017] Figure 1 A schematic diagram showing the structure of an integrated floating gate maintenance door garage structure in a storage state in a specific embodiment of the utility model; and
[0018] Figure 2The schematic diagram of the structure of the integrated floating gate maintenance door garage structure in a maintenance state in a specific embodiment of the utility model is shown.
[0019] The above drawings include the following reference numerals:
[0020] 10. Gatehouse; 11. Receiving groove; 12. Opening; 13. Recess; 20. Gate; 30. Limiting boss; 40. Maintenance pier; 50. Mooring post; 60. Ladder. DETAILED DESCRIPTION
[0021] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present utility model will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0022] It should be noted that, unless otherwise specified, all technical and scientific terms used in this application have the same meanings as commonly understood by ordinary technicians in the technical field to which this application belongs.
[0023] In the present invention, unless otherwise specified, the directional words used, such as "up, down, top, bottom", usually refer to the directions shown in the drawings, or to the components themselves in the vertical, perpendicular or gravity directions; similarly, for ease of understanding and description, "inside and outside" refer to the inside and outside relative to the outline of each component itself, but the above-mentioned directional words are not used to limit the present invention.
[0024] Obviously, the embodiments described above are only some embodiments of the utility model, not all embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the utility model.
[0025] In order to solve the problem of inconvenient maintenance of the integral floating gate of the ship lock in the prior art, the utility model provides an integral floating gate maintenance door garage structure.
[0026] like Figure 1 to Figure 2 As shown, the integral floating gate maintenance door garage structure includes two door garage components. The door garage component includes a door garage 10, a gate 20 and a limiting boss 30. The door garage 10 has a receiving groove 11 and an opening 12 connected to the receiving groove 11. The gate 20 is placed in the receiving groove 11. There are two limiting bosses 30, and the two limiting bosses 30 are arranged at both ends of the opening 12. The gate 20 of one door garage component is used to move to the opening 12 of the other door garage component to limit and stop with the limiting boss 30 and block the receiving groove 11 when the gate 20 of the other door garage component needs to be repaired.
[0027] The overall floating gate maintenance door structure includes two door storage components, the door storage component includes a door storage 10, a gate 20 and a limiting boss 30, the door storage 10 has a receiving groove 11 and an opening 12 connected to the receiving groove 11, the gate 20 is placed in the receiving groove 11, and there are two limiting bosses 30, which are arranged at both ends of the opening 12. The gate 20 of one door storage component is used to move to the opening 12 of the other door storage component when the gate 20 of the other door storage component needs to be repaired, and the limiting boss 30 is used to limit and block the receiving groove 11. In this way, the two The gate garage components can cooperate with each other by setting a limiting boss 30 at the opening 12. When the gate 20 of one of the gate garage components needs to be repaired, the gate 20 of the other gate garage component is moved to the opening 12 of the gate garage component, thereby cooperating with the limiting boss 30 to block the accommodating groove 11 to form a closed maintenance space. After the water in the accommodating groove 11 is drained, dry land construction conditions can be met, which facilitates maintenance procedures such as water-stop replacement, painting and anti-corrosion of the gate 20, greatly improving the convenience of gate maintenance, while reducing maintenance costs and ensuring the personal safety of maintenance personnel.
[0028] It can be understood that in this embodiment, the two gate warehouse assemblies are respectively located upstream and downstream of the ship lock, and are used to block the water upstream and downstream when the ship lock is overhauled. The water inside the ship lock is drained and the ship lock is overhauled. When not in use, it is stored in the gate warehouse next to the navigation wall. The gate 20 is an integral floating gate as described in the background technology, which floats in the water and is opened and closed by pumping water in the cabin. In other words, when the gate 20 is full of water, the gate 20 will sink to the bottom of the water. In the storage state, the gate 20 is in a state of being full of water, and is thus fixed in the accommodating tank 11. The two gate warehouse assemblies are respectively a first gate warehouse assembly and a second gate warehouse assembly. For example, when the gate 20 of the first gate warehouse assembly needs to be overhauled, the water in the gate 20 of the second gate warehouse assembly is first drained so that it floats on the water surface, making it easy to move to the opening 12 of the first gate warehouse assembly. Then the gate 20 of the second door and garage assembly is filled with water, so that the gate 20 of the second door and garage assembly sinks to the bottom of the water at the opening 12 to block the water. In other words, the gates 20 of the two door and garage assemblies serve as water blocking parts for each other.
[0029] In this embodiment, the internal space of the door storage 10 is in a convex shape as a whole, that is, the diameter of the opening 12 is smaller than the length of the receiving groove 11. Further, the length of the gate 20 is smaller than the diameter of the opening 12 but larger than the distance between the two limiting bosses 30, so as to be limited and stopped by the limiting bosses 30. The receiving groove 11 is a strip groove, and the length direction of the receiving groove 11 corresponds to the length direction of the gate 20.
[0030] like Figure 1 to Figure 2As shown, the gatehouse assembly further includes an inspection pier 40. The inspection pier 40 is arranged at the bottom of the accommodating groove 11, and the gate 20 is placed on the inspection pier 40. By providing the inspection pier 40, the gate 20 can be lifted to a certain height, so that the bottom of the gate 20 can be inspected.
[0031] In order to improve the support stability, there are multiple maintenance buttresses 40, and the multiple maintenance buttresses 40 are arranged at intervals along the length direction of the accommodating groove 11. In other words, the multiple maintenance buttresses 40 are arranged at intervals along the length direction of the gate 20. Specifically, in this embodiment, there are three maintenance buttresses 40, wherein two maintenance buttresses 40 are respectively located at both ends of the gate 20, and one maintenance buttress 40 is located in the middle of the gate 20. Of course, the number of maintenance buttresses 40 can be more, and can be selected according to actual needs.
[0032] Furthermore, a mounting recess is provided on the top of the maintenance buttress 40, and the bottom end of the gate 20 is accommodated in the mounting recess. It is understandable that the width of the mounting recess is adapted to the width of the gate 20. By providing the mounting recess, the stability of the gate 20 can be improved, the gate 20 can be prevented from falling, and the personal safety of the maintenance personnel can be ensured.
[0033] like Figure 1 to Figure 2 The gatehouse assembly further comprises a mooring post 50. The mooring post 50 is arranged on the gatehouse 10 and is used to connect and fix the gate 20.
[0034] In order to improve the connection firmness of the gate 20, there are multiple mooring posts 50, and the multiple mooring posts 50 are arranged at intervals along the length direction of the receiving groove 11. In other words, the multiple mooring posts 50 are arranged at intervals along the length direction of the gate 20. Specifically, in this embodiment, there are two mooring posts 50, and the two mooring posts 50 are arranged corresponding to the two ends of the gate 20, so as to better restrain the gate 20.
[0035] like Figure 1 to Figure 2 As shown, a groove 13 is provided on the inner wall of the gatehouse 10, and the mooring post 50 is accommodated in the groove 13. Through the above arrangement, the space occupied by the mooring post 50 can be reduced, thereby increasing the maintenance space of the gate 20.
[0036] In this embodiment, the gate assembly further includes a seal, which is disposed between the gate 20 and the limiting boss 30. By providing the seal, the water-tightness of the gate 20 can be improved to prevent water in the ship lock from entering the receiving groove 11. Specifically, the seal can be a rubber seal.
[0037] In this embodiment, the gate 20 is provided with a mounting hole, and the limiting boss 30 is provided with a through hole correspondingly, and the fastener passes through the mounting hole and the through hole in sequence to fasten the gate 20 and the limiting boss 30. Specifically, the fastener can be a bolt, and the mounting hole is located at the upper part of the gate 20 to be located above the water level to prevent corrosion of the fastener. Through the above arrangement, the connection firmness between the gate 20 and the limiting boss 30 can be improved, thereby improving the water-retaining sealing performance.
[0038] In this embodiment, the door garage assembly further includes a water pump for draining the water in the accommodating tank 11 .
[0039] like Figure 1 to Figure 2 As shown, the door garage assembly also includes a ladder 60, which is arranged on the inner wall of the door garage 10. By arranging the ladder, it is convenient for maintenance personnel to enter the bottom of the accommodating groove 11 and perform all-round maintenance on the gate 20.
[0040] In this embodiment, guardrails or walls are also provided around the accommodating groove 11 and the opening 12 to prevent maintenance personnel from falling and ensure personal safety. Of course, an avoidance gap needs to be opened at the ladder 60 to provide an entry and exit passage.
[0041] From the above description, it can be seen that the above-mentioned embodiment of the utility model achieves the following technical effects: by setting an integral floating gate maintenance door library structure including two door library components, the door library component includes a door library 10, a gate 20 and a limiting boss 30, the door library 10 has a receiving groove 11 and an opening 12 connected to the receiving groove 11, the gate 20 is placed in the receiving groove 11, there are two limiting bosses 30, and the two limiting bosses 30 are arranged at both ends of the opening 12, and the gate 20 of one door library component is used to move to the opening 12 of the other door library component when the gate 20 of the other door library component needs to be repaired and is limited by the limiting boss 30 The limiting boss 30 is set at the opening 12, and when the gate 20 of one of the gate storage components needs to be repaired, the gate 20 of the other gate storage component is moved to the opening 12 of the gate storage component, thereby cooperating with the limiting boss 30 to block the accommodating groove 11 to form a closed maintenance space. After the water in the accommodating groove 11 is drained, dry land construction conditions can be met, which is convenient for maintenance procedures such as water-stop replacement, painting and anti-corrosion of the gate 20, thereby greatly improving the maintenance convenience of the overall floating gate, while reducing the maintenance cost and ensuring the personal safety of the maintenance personnel.
[0042] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprise" and / or "include" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.
[0043] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the numbers used in this way can be interchanged where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than those illustrated or described herein.
[0044] The above description is only the preferred embodiment of the utility model, and is not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. An integral floating gate maintenance door garage structure, characterized in that: It includes two door library components, and the door library components include: A door storage (10), wherein the door storage (10) has a receiving groove (11) and an opening (12) communicating with the receiving groove (11); A gate (20), the gate (20) being placed in the containing groove (11); A limiting boss (30), wherein there are two limiting bosses (30), and the two limiting bosses (30) are arranged at two ends of the opening (12). When the gate (20) of one door library component needs to be repaired, the gate (20) of the other door library component is used to move to the opening (12) of the other door library component to limit and stop with the limiting boss (30) and block the accommodating groove (11).
2. The integral floating gate maintenance door garage structure according to claim 1 is characterized in that: The gate garage assembly also includes an inspection pier (40), the inspection pier (40) is arranged at the bottom of the accommodating groove (11), and the gate (20) is placed on the inspection pier (40).
3. The integral floating gate maintenance door garage structure according to claim 2 is characterized in that: There are a plurality of maintenance piers (40), and the plurality of maintenance piers (40) are arranged at intervals along the length direction of the accommodating groove (11).
4. The integral floating gate maintenance door garage structure according to claim 2 is characterized in that: The top of the maintenance pier (40) is provided with a mounting recess, and the bottom end of the gate (20) is accommodated in the mounting recess.
5. The integral floating gate maintenance door garage structure according to claim 1 is characterized in that: The gatehouse assembly further comprises a mooring post (50), which is arranged on the gatehouse (10) and is used to connect and fix the gate (20).
6. The integral floating gate maintenance door garage structure according to claim 5 is characterized in that: A groove (13) is provided on the inner side wall of the door garage (10), and the mooring post (50) is accommodated in the groove (13).
7. The integrated floating gate maintenance door garage structure according to claim 5 is characterized in that: There are a plurality of mooring posts (50), and the plurality of mooring posts (50) are arranged at intervals along the length direction of the accommodating groove (11).
8. The integrated floating gate maintenance door garage structure according to claim 1 is characterized in that: The gate (20) is provided with a mounting hole, and the limiting boss (30) is correspondingly provided with a through hole, and a fastener passes through the mounting hole and the through hole in sequence to fasten the gate (20) and the limiting boss (30).
9. The integrated floating gate maintenance door garage structure according to any one of claims 1 to 8, characterized in that: The door garage component also includes a water pump for draining the water in the accommodating tank (11).
10. The integrated floating gate maintenance door garage structure according to any one of claims 1 to 8, characterized in that: The door garage assembly further comprises a ladder (60), and the ladder (60) is arranged on the inner side wall of the door garage (10).