Concrete pouring pump pipe supporting construction structure

By designing a rotatable mounting bracket plate and support shaft pump pipe support structure, the overlapping lifting and placement of pump pipe support is achieved, solving the problem of the inability to carry the traditional support structure and improving the convenience and efficiency of transportation.

CN222864350UActive Publication Date: 2025-05-13CHINA POWER CONSTRUCTION BUREAU JIUJIU CHONGQING ENGINEERING CONSTRUCTION CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202422007260.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2025-05-13
Estimated Expiration
2034-08-19

AI Technical Summary

Technical Problem

The existing pump pipe support structure cannot be overlapped, put and transported, resulting in inconvenient transportation.

Method used

A concrete pouring pump pipe support construction structure is designed, including a rotatable mounting frame plate and a support shaft. Through the cooperation of the hinge and pin holes, the spacing and storage of the frame plates can be achieved. The support shaft can be hung on the frame plate to achieve overall overlap and retraction.

Benefits of technology

The overlapping lifting and placement of the pump pipe support structure is achieved, which solves the problem that traditional support structures cannot be transported, and improves the convenience and efficiency of transportation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222864350U_ABST
    Figure CN222864350U_ABST
Patent Text Reader

Abstract

The utility model discloses a concrete pouring pump pipe supporting construction structure which comprises a frame plate A and a frame plate B. The frame plate A and the frame plate B are each provided with a step through hole, and the step through holes are smaller towards the outer side and larger than the inner side. The two ends of the supporting shaft are rotatably mounted on the frame plate A and the frame plate B; the bayonet lock is pulled out, the supporting shaft is taken down, the frame plate B gets close to the frame plate A to be stored, the mounting shaft rotates around a hinge joint to be in a vertical state, hanging holes in the two ends of the supporting shaft penetrate through the bayonet lock, the bayonet lock penetrates through a pin hole of the mounting shaft and is inserted into the small end of the pin hole, and the supporting shaft and the mounting shaft are hung on the frame plate B; the frame plate B is close to the frame plate A, the mounting shaft rotates to be vertical through the hinge joint, the whole body can be folded and placed for carrying, and the problem that the whole body supported by the pump pipe is fixed and cannot be folded and placed for carrying is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a concrete pouring pump pipe support construction structure, which belongs to the technical field of construction pump pipe support. Background Art

[0002] When concrete is transported to the side road of the construction site by a pump truck, it needs to be transported to the pouring construction point through a pump pipe. In order to ensure the stability of the pump pipe over a long distance, support is required in the middle of the pump pipe.

[0003] The existing pump tube support technology is shown in Chinese Patent Publication No. CN208473311U. Although the pump tube can be stably supported by the pump tube support, the pump tube support is a fixed whole and cannot be overlapped, folded, placed and transported. Utility Model Content

[0004] In order to solve the above technical problems, the utility model provides a concrete pouring pump pipe support construction structure.

[0005] The utility model is realized through the following technical solutions.

[0006] The utility model provides a concrete pouring pump pipe support construction structure, comprising:

[0007] The frame plate A and the frame plate B are both provided with step through holes, and the step through holes are smaller toward the outside and larger toward the inside;

[0008] The two ends of the support shaft can be rotatably mounted on the frame plate A and the frame plate B.

[0009] A hinge is fixed at the bottom of the frame A, and a mounting shaft is rotatably hinged on the hinge. The mounting shaft is provided with a plurality of spaced-apart pin holes. The frame B is provided with an insertion hole for the mounting shaft to pass through. A locking pin is inserted into the pin hole of the frame B to lock the frame A and the frame B is spaced apart.

[0010] The support shaft is externally covered with an elastic sleeve layer which can be elastically deformed.

[0011] The two ends of the support shaft not covered by the elastic sleeve layer are provided with hanging holes. When the shelf A and the shelf B are stored close to each other, the support shaft is hung by the bayonet pins passing through the hanging holes at the two ends.

[0012] Supporting foot plates are fixed at the bottom of the frame plates A and B.

[0013] The beneficial effects of the utility model are: pull out the bayonet, remove the support shaft, and the frame plate B is stored close to the frame plate A. The installation shaft is rotated by the hinge joint to present a vertical state, and the hanging holes at both ends of the support shaft pass through the bayonet, and the bayonet passes through the pin hole of the installation shaft and is inserted into the small end of the pin hole, so that the support shaft and the installation shaft are hung on the frame plate B; the frame plate B is close to the frame plate A, and the installation shaft is rotated vertically by the hinge joint, so that the whole can be overlapped, folded up and transported, which solves the problem that the pump tube support is a fixed whole that cannot be overlapped, folded up and transported. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a schematic diagram of the structure of the utility model when in use;

[0015] Figure 2 It is a schematic diagram of the structure of the utility model when it is folded;

[0016] In the figure: 1-frame A; 11-step through hole; 2-frame B; 3-support shaft; 31-elastic sleeve layer; 32-hanging hole; 4-pump pipe; 12-support foot plate; 13-hinge head; 5-installation shaft; 51-pin hole; 53-pin. DETAILED DESCRIPTION

[0017] The technical solution of the utility model is further described below, but the scope of protection required is not limited to the description.

[0018] like Figure 1 to Figure 2 shown.

[0019] A concrete pouring pump pipe support construction structure of the present application includes:

[0020] The frame plate A1 and the frame plate B2 are both provided with a stepped through hole 11, and the stepped through holes 11 are vertically spaced and distributed in a plurality on the frame plate A1 and the frame plate B2. A support shaft 3 is rotatably installed between the frame plate A1 and the frame plate B2, and the two rotatable ends of the support shaft 3 are in the stepped through hole 11 of the frame plate A1 and the stepped through hole 11 of the frame plate B2. The stepped through hole 11 is smaller toward the outside and larger toward the inside.

[0021] The support shaft 3 is covered with an elastic sleeve layer 31 that can be elastically deformed. The elastic sleeve layer 31 can generate elastic damping when it contacts and supports the pump pipe 4. When the pump pipe 4 vibrates when conveying concrete, the elastic sleeve layer 31 can have a buffering effect. The two ends of the support shaft 3 that are not covered by the elastic sleeve layer 31 have hanging holes 32. When the frame A1 and the frame B2 are close to each other for storage, the support shaft 3 is hung by the bayonet 53 through the hanging holes 32 at both ends.

[0022] Supporting foot plates 12 are fixed to the bottom of the frame plates A1 and B2. The supporting foot plates 12 increase the supporting area between the bottom of the frame plates A1 and B2 and the ground to improve stability.

[0023] A hinge head 13 is fixed at the bottom of the frame A1, and a mounting shaft 5 is rotatably hinged on the hinge head 13. The mounting shaft 5 is provided with a plurality of spaced-apart pin holes 51. The frame B2 is provided with an insertion hole for the mounting shaft 5 to pass through. A locking pin 53 is inserted into the pin hole 51 of the frame B2 to lock the frame A1 and the frame B2 so that the frame A1 and the frame B2 are spaced apart.

[0024] When the pump tube 4 needs to be supported, the frame A1 and the frame B2 are spaced apart, the mounting shaft 5 is rotated by the hinge joint 13 to present a horizontal state, the pin hole 51 is inserted into the bayonet 53 to be locked between the frame B2, and the two ends of the support shaft 3 can be rotatably installed in the step through hole 11 of the frame A1 and the large end of the step through hole 11 of the frame B2, such as Figure 1 shown.

[0025] When the overlapping and folding is required, the latch 53 is pulled out, the support shaft 3 is removed, the frame B2 is stored close to the frame A1, the installation shaft 5 is rotated by the hinge head 13 to present a vertical state, the hanging holes 32 at both ends of the support shaft 3 pass through the latch 53, the latch 53 passes through the pin hole 51 of the installation shaft 5 and is inserted into the small end of the pin hole 51, so that the support shaft 3 and the installation shaft 5 are hung on the frame B2, as shown in FIG. Figure 2 As shown; the shelf B2 is close to the shelf A1, and the mounting shaft 5 is rotated vertically with the hinge joint 13, so that the whole can be stacked and placed for transportation, which solves the problem that the pump tube support is a fixed whole that cannot be stacked and placed for transportation.

Claims

1. A concrete pouring pump pipe support construction structure, characterized in that: include: The frame plate A (1) and the frame plate B (2) are both provided with a stepped through hole (11), and the stepped through hole (11) is smaller toward the outside and larger toward the inside; The supporting shaft (3) is rotatably mounted on the frame plate A (1) and the frame plate B (2) at both ends.

2. The concrete pouring pump pipe support construction structure according to claim 1, characterized in that: The bottom of the frame plate A (1) is fixed with a hinge joint (13), and a mounting shaft (5) is rotatably hinged on the hinge joint (13). The mounting shaft (5) is provided with a plurality of spaced pin holes (51). The frame plate B (2) is provided with an insertion hole for the mounting shaft (5) to pass through. A locking pin (53) is inserted into the pin hole (51) of the frame plate B (2) to lock the frame plate A (1) and the frame plate B (2) to be spaced apart.

3. The concrete pouring pump pipe support construction structure according to claim 1, characterized in that: The support shaft (3) is externally covered with an elastic sleeve layer (31) that can be elastically deformed.

4. The concrete pouring pump pipe support construction structure as claimed in claim 3, characterized in that: Both ends of the support shaft (3) not covered by the elastic sleeve layer (31) are provided with hanging holes (32) for the bayonet pin (53) to pass through.

5. The concrete pouring pump pipe support construction structure according to claim 1, characterized in that: Supporting foot plates (12) are fixed at the bottom of the frame plates A (1) and B (2).

Citation Information

Patent Citations

  • Concrete placement pump line bearing structure

    CN208473311U