Water meter support of spring water direct drinking engineering water pipeline

By designing a water meter bracket in the spring water direct drinking project, the locking structure of the installation bracket and U-shaped rod, locking seat and push plate is used to solve the installation difficulties caused by limited operating space, and the stable fixation of the water meter and pipeline and the service life are extended.

CN222866005UActive Publication Date: 2025-05-13JINAN PURUN WATER CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421717724.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-07-19
Publication Date
2025-05-13
Estimated Expiration
2034-07-19

AI Technical Summary

Technical Problem

In the direct drinking project of spring water, it is difficult for the prior art to install cantilever brackets in an environment with limited operating space, resulting in difficulty in fixing and supporting water meters and pipelines, affecting service life.

Method used

A water meter bracket for a spring water direct drinking project water pipeline is designed. The water meter is fixed and supported by setting up a mounting bracket on the outside of the water meter and the pipeline, and a U-shaped rod, locking seat and push plate are used to form a locking structure.

Benefits of technology

It increases the operating space during installation, improves installation efficiency, and extends the service life of the water meter and pipes through a stable structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222866005U_ABST
    Figure CN222866005U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of water meter installation, in particular to a water meter support of a spring water direct drinking project water pipeline, which comprises pipelines arranged close to a wall body, a water meter arranged on the pipelines, snap rings arranged at two ends of the water meter, a mounting plate connected to one side of each snap ring far away from the wall body, and the snap rings fixed on a mounting support through the mounting plate. The mounting bracket is arranged on the outer sides of the water meter and the pipeline, so that the operation space is greatly increased during mounting by a worker; the clamping ring comprises a U-shaped rod and a clamping base, the end of the U-shaped rod penetrates through the clamping base and is fastened through a nut, the pipeline is arranged between the U-shaped rod and the clamping base, a circular groove is formed in the center of the clamping base, a spring screw is installed in the circular groove, the spring screw is connected with a push plate, and the push plate makes contact with the pipeline. The U-shaped rod, the clamping base and the push plate are matched to form a locking structure, the two ends of the water meter are fixed and supported, the structure is stable, and meanwhile the installation efficiency of workers is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of water meter installation, in particular to a water meter bracket for a water pipeline of a spring water direct drinking project. Background Art

[0002] In the construction of the spring water direct drinking project, pipelines are used to transport spring water and divert it to thousands of households. The flow of spring water is calculated through water meters to make rational use of water resources.

[0003] Since the pipeline is subjected to the load of water flow impact and strong internal pressure, a cantilever bracket is usually installed at the water meter installation location to fix and support the water meter and the pipeline, and prevent the connection position from being misaligned and deformed, which would affect the service life.

[0004] However, in the prior art, in order to facilitate recording of water meters, water meters of different users are usually installed in the same position. Since the adjacent water meters and pipelines are close to each other and close to the wall, the operating space is extremely limited, and it is very difficult to install the cantilever bracket. Utility Model Content

[0005] In order to improve the problems in the above-mentioned background technology, the utility model provides a water meter bracket for a water pipeline of a spring water direct drinking project.

[0006] The utility model provides a water meter bracket for a water pipeline of a spring water direct drinking project, which adopts the following technical solution:

[0007] A water meter bracket for a water pipeline of a spring water direct drinking project comprises a pipeline arranged close to a wall, a water meter is arranged on the pipeline, clamps are arranged at both ends of the water meter, a mounting plate is connected to the side of the clamp away from the wall, and the clamp is fixed to the mounting bracket through the mounting plate.

[0008] Preferably, the clamping ring includes a U-shaped rod and a socket, the end of the U-shaped rod passes through the socket and is fastened by a nut, the pipe is arranged between the U-shaped rod and the socket, a circular groove is opened at the center position of the socket and a spring screw is installed, the spring screw is connected to a push plate, and the push plate is in contact with the pipe.

[0009] Preferably, shock-absorbing rubber pads are provided on the outer side of the U-shaped rod and on the side of the push plate in contact with the pipeline.

[0010] Preferably, both ends of the mounting bracket are bent and in contact with the wall, and a fixing hole is provided at the end of the mounting bracket, and a wall nail is installed in the fixing hole.

[0011] Preferably, a plurality of mounting holes are evenly formed on the mounting bracket, bolts are installed in the mounting holes, and the mounting plate is fixed to the mounting bracket by bolts.

[0012] To sum up, the utility model has the following beneficial technical effects: the utility model designs a water meter bracket for the water pipe of the spring water direct drinking project, and sets the installation bracket on the outside of the water meter and the pipe, which greatly increases the operating space for workers during installation; a locking structure is formed by the cooperation of a U-shaped rod, a socket and a push plate to fix and support both ends of the water meter, which not only stabilizes the structure but also increases the installation efficiency of the workers. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 This is a partial installation diagram of a water meter bracket for a water pipeline of a spring water direct drinking project in Example 1 of the utility model;

[0014] Figure 2 is a side view of the clamping ring of Example 1 of the utility model;

[0015] Figure 3 It is a rear view of the clamping ring of Embodiment 1 of the present utility model;

[0016] Figure 4 It is a partial structural schematic diagram of the mounting bracket of Example 1 of the utility model;

[0017] Figure 5 It is a structural schematic diagram of a water meter bracket for a water pipeline in a spring water direct drinking project in Example 2 of the utility model.

[0018] Explanation of the reference numerals in the accompanying drawings: 1. wall; 2. pipe; 3. water meter; 4. clamping ring; 5. mounting plate; 6. mounting bracket; 7. U-shaped rod; 8. holder; 9. nut; 10. round groove; 11. spring screw; 12. push plate; 13. shock-absorbing rubber pad; 14. fixing hole; 15. wall nail; 16. mounting hole; 17. bolt; 18. water meter box; 19. shock-absorbing ring; 20. support. DETAILED DESCRIPTION

[0019] The following combination Figure 1-Figure 5 The utility model is described in further detail.

[0020] Embodiment 1 of the present utility model discloses a water meter support for a water pipeline of a spring water direct drinking project.

[0021] Reference Figure 1 , Figure 2 , Figure 4 A water meter bracket for a water pipeline of a spring water direct drinking project includes a pipeline 2 arranged close to a wall 1, a water meter 3 is arranged on the pipeline 2, clamp rings 4 are arranged at both ends of the water meter 3, a mounting plate 5 is connected to the clamp ring 4 on the side away from the wall 1, the clamp ring 4 is fixed to the mounting bracket 6 through the mounting plate 5, that is, two mounting brackets 6 are provided, and multiple clamp rings 4 are fixed on the two mounting brackets 6 and are respectively sleeved on both ends of the water meter 3.

[0022] Reference Figure 1 , Figure 2 , Figure 3 The clamping ring 4 includes a U-shaped rod 7 and a socket 8. The end of the U-shaped rod 7 passes through the socket 8 and is fastened by a nut 9. The pipeline 2 is arranged between the U-shaped rod 7 and the socket 8. A circular groove 10 is opened at the center of the socket 8 and a spring screw 11 is installed. The spring screw 11 is connected to a push plate 12. The push plate 12 contacts the pipeline 2 to press the pipeline 2.

[0023] Reference Figure 1 , Figure 2 Shock-absorbing rubber pads 13 are provided on the outside of the U-shaped rod 7 and on the side where the push plate contacts the pipe 2 to reduce damage caused by the shock of water flow and the vibration caused by the internal pressure.

[0024] Reference Figure 1 , Figure 4 The two ends of the mounting bracket 6 are bent and in contact with the wall 1 , and a fixing hole 14 is opened at the end of the mounting bracket 6 , and a wall nail 15 is installed in the fixing hole 14 , and the end of the mounting bracket 6 is fixed to the wall 1 using the wall nail 15 .

[0025] Reference Figure 2 , Figure 4 A plurality of mounting holes 16 are evenly formed on the mounting bracket 6 , and bolts 17 are installed in the mounting holes 16 . The mounting plate 5 is fixed to the mounting bracket 6 by the bolts 17 , so as to fix the retaining ring 4 .

[0026] The implementation principle of the water meter bracket of a spring water direct drinking project water pipeline in Example 1 of the utility model is: when installing the water meter bracket, a clamping ring 4 is set at both ends of the water meter 3, and a locking structure is formed by the cooperation of a U-shaped rod 7, a clamping seat 8 and a push plate 12 to fix and support both ends of the water meter 3, and the clamping ring 4 is fixed to the mounting bracket 6 through the mounting plate 5, and the mounting bracket 6 is fixed.

[0027] Embodiment 2 of the present utility model discloses a water meter support for a water pipeline of a spring water direct drinking project.

[0028] Reference Figure 2 , Figure 5 A water meter bracket for a water pipeline of a spring water direct drinking project includes a water meter box 18, a pipeline 2 passes through the side of the water meter box 18, a water meter 3 is arranged inside the water meter box 18, a shock-absorbing ring 19 is arranged at the contact position between the water meter box 18 and the pipeline 2, and clamping rings 4 are arranged at both ends of the water meter 3. The clamping ring 4 is connected to a mounting plate 5 on the side away from the water meter box 18, and the clamping ring 4 is fixed to the mounting bracket 6 through the mounting plate 5. The two ends of the mounting bracket 6 are respectively fixed to the top and bottom of the water meter box 18 through supports 20. The support 20 adopts a structure in which a screw penetrates the end of the mounting bracket 6 and is connected to a rubber plunger, and the screw is tightened to achieve top connection and fixation.

[0029] Reference Figure 2 , Figure 3 , Figure 5 The clamping ring 4 includes a U-shaped rod 7 and a socket 8. The end of the U-shaped rod 7 passes through the socket 8 and is fastened by a nut 9. The pipeline 2 is arranged between the U-shaped rod 7 and the socket 8. A circular groove 10 is opened at the center of the socket 8 and a spring screw 11 is installed. The spring screw 11 is connected to a push plate 12, and the push plate 12 is in contact with the pipeline 2.

[0030] Reference Figure 2 , Figure 5 Shock-absorbing rubber pads 13 are provided on the outer side of the U-shaped rod 7 and on the side where the push plate contacts the pipe 2 .

[0031] Reference Figure 2 , Figure 5 A plurality of mounting holes 16 are evenly formed on the mounting bracket 6 , bolts 17 are installed in the mounting holes 16 , and the mounting plate 5 is fixed to the mounting bracket 6 by the bolts 17 .

[0032] The implementation principle of the water meter bracket of a spring water direct drinking project water pipeline in Example 2 of the utility model is as follows: Example 2 of the utility model is applicable to when the water meter 3 is concentrated in the water meter box 18, the mounting bracket 6 is installed, a shock-absorbing ring 19 is provided at the contact position between the water meter box 18 and the pipeline 2, and the two ends of the mounting bracket 6 are fixed by the support 20 to achieve the fixation and support of the water meter.

[0033] The above are all preferred embodiments of the present utility model, and are not intended to limit the protection scope of the present utility model. Therefore, any equivalent changes made based on the structure, shape, and principle of the present utility model should be included in the protection scope of the present utility model.

Claims

1. A water meter support for a water pipeline in a spring water direct drinking project, characterized in that: The invention comprises a pipe (2) arranged close to a wall (1), a water meter (3) being arranged on the pipe (2), clamping rings (4) being arranged at both ends of the water meter (3), a mounting plate (5) being connected to the side of the clamping ring (4) away from the wall (1), and the clamping ring (4) being fixed to a mounting bracket (6) via the mounting plate (5).

2. A water meter support for a water pipeline for a spring water direct drinking project according to claim 1, characterized in that: The clamping ring (4) comprises a U-shaped rod (7) and a clamping seat (8); the end of the U-shaped rod (7) passes through the clamping seat (8) and is fastened by a nut (9); the pipeline (2) is arranged between the U-shaped rod (7) and the clamping seat (8); a circular groove (10) is opened at the center of the clamping seat (8) and a spring screw (11) is installed; the spring screw (11) is connected to a push plate (12); and the push plate (12) is in contact with the pipeline (2).

3. A water meter support for a water pipeline for a spring water direct drinking project according to claim 2, characterized in that: Shock-absorbing rubber pads (13) are provided on the outside of the U-shaped rod (7) and on the side of the push plate in contact with the pipe (2).

4. The water meter support for a water pipeline for a spring water direct drinking project according to claim 1, characterized in that: The two ends of the mounting bracket (6) are bent and in contact with the wall (1); a fixing hole (14) is provided at the end of the mounting bracket (6); a wall nail (15) is installed in the fixing hole (14).

5. The water meter support for a water pipeline for a spring water direct drinking project according to claim 1, characterized in that: A plurality of mounting holes (16) are evenly formed on the mounting bracket (6), bolts (17) are installed in the mounting holes (16), and the mounting plate (5) is fixed to the mounting bracket (6) by means of the bolts (17).