Waterproof structure of basement bearing platform

By solving the problems of poor waterproofing effect and short service life in the prior art in the waterproof construction layer of the basement bearing, the waterproofing parts at the end of the pile and the casting layer, the problems of poor waterproofing effect and short service life in the prior art are solved, and more efficient waterproofing performance and longer service life are achieved.

CN222990794UActive Publication Date: 2025-06-17华煜建设集团有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422020252.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2025-06-17
Estimated Expiration
2034-08-20

AI Technical Summary

Technical Problem

The existing basement platform has poor waterproofing effect and short service life, making it difficult to meet the waterproofing needs of buildings.

Method used

A waterproof structure including a waterproof construction layer, a waterproof part at the end of the pile foundation and a cast layer are adopted. The waterproofing layer is used to carry out waterproofing treatment on the periphery of the pile foundation. The waterproofing parts at the end of the pile foundation are waterproofed, and the bearing is constructed on the waterproof structure to improve waterproof performance.

Benefits of technology

It significantly improves the waterproof performance at the connection between the basement base and the pile foundation, extends the waterproof service life, and ensures the waterproof effect of the basement.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222990794U_ABST
    Figure CN222990794U_ABST
Patent Text Reader

Abstract

According to the waterproof structure of the basement bearing platform, the basement bearing platform comprises a pile foundation and a bearing platform body located above the pile foundation, and the waterproof structure is arranged between the pile foundation and the bearing platform body and used for preventing water leakage at the position of the bearing platform body of a basement. The waterproof structure comprises a waterproof construction layer, a pile foundation end waterproof piece and a pouring layer, the waterproof construction layer is arranged on the periphery of the pile foundation and used for conducting waterproof treatment on the connecting face between the foundation pit and the pile foundation, the pouring layer is arranged above the waterproof construction layer, the waterproof construction layer is protected through the pouring layer, the service life of the waterproof construction layer is prolonged, and the waterproof construction cost is reduced. And the pile foundation end waterproof piece is fixed to the end of the pile foundation and abuts against the waterproof construction layer, and water prevention is conducted on the connecting face of the pile foundation and the pouring layer through the pile foundation end waterproof piece.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the field of construction, and particularly relates to a waterproof structure for a basement bearing platform. Background Art

[0002] Due to geological reasons, when a building is designed with a basement part, the foundation more often adopts the form of pile cap + raft, and the waterproof project of the basement pile cap is an essential part of the basement project. The existing waterproof treatment process often uses a polyurethane waterproof coating to seal the connection between the base layer of the bearing platform and the pile head of the pipe pile to achieve the waterproof effect. However, the waterproof effect of this process is poor and the waterproof service life is short. Summary of the Invention

[0003] Aiming at the above deficiencies, the technical problem to be solved by the utility model is to provide a waterproof structure for a basement bearing platform, which is used to improve the waterproof performance of the bearing platform and extend the waterproof service life at the bearing platform.

[0004] To solve the above technical problems, the technical solution adopted by the utility model is

[0005] A waterproof structure for a basement bearing platform, the basement bearing platform includes a pile foundation and a bearing platform located above the pile foundation, the waterproof structure includes a waterproof construction layer, a pile foundation end waterproof member and a pouring layer. The waterproof construction layer is arranged around the pile foundation, the pouring layer is arranged above the waterproof construction layer, the pile foundation end waterproof member is fixed at the end of the pile foundation and abuts against the waterproof construction layer, and the bearing platform is arranged above the pile foundation end waterproof member.

[0006] As a preferred solution of the utility model, the pouring layer wraps the outside of the pile foundation end waterproof member.

[0007] As a preferred solution of the utility model, the pile foundation end waterproof member includes a side water stop belt and an end water stop belt. The side water stop belt is sleeved outside the pile foundation, and the end water stop belt covers the outside of the side water stop belt and the pile foundation.

[0008] As a preferred solution of the utility model, the bottom of the side water stop belt is provided with a bending part.

[0009] As a preferred solution of the utility model, the top of the side water stop belt is higher than the upper end surface of the pile foundation.

[0010] As a preferred solution of the utility model, a sealing gasket is arranged inside the end water stop belt, and the sealing gasket abuts against the side water stop belt.

[0011] As a preferred solution of the utility model, a connecting ring is arranged at the edge of the end water stop belt.

[0012] As a preferred embodiment of the present utility model, the pile foundation is provided with pile foundation steel bars, the outer side of the pile foundation steel bars is provided with external threads, and the end water stop is fixed on the end face of the pile foundation through nuts.

[0013] As a preferred embodiment of the present utility model, the waterproof construction layer sequentially includes a concrete cushion layer, a waterproof layer, and a polyethylene self-adhesive board layer from bottom to top, and the pile foundation end waterproof member abuts against the polyethylene self-adhesive board layer.

[0014] As a preferred embodiment of the present utility model, a filling gap is provided between the concrete cushion layer and the pile foundation, and the waterproof layer extends into the filling gap.

[0015] The beneficial effects of the present utility model are that the side and top of the pile foundation are waterproofed through the waterproof construction layer and the pile foundation end waterproof member, improving the waterproof performance around the pile foundation. Then, constructing the bearing platform on the waterproof mechanism can effectively improve the waterproof performance at the connection between the bearing platform and the pile foundation, and extend the service life of the basement bearing platform. Description of the Drawings

[0016] Figure 1 is a cross-sectional schematic diagram of this waterproof structure.

[0017] Figure 2 is Figure 1 a partial enlarged view of part A in

[0018] Reference numerals: bearing platform 1, pile foundation 2, pile foundation steel bars 2-1, nuts 2-2, waterproof construction layer 3, concrete cushion layer 3-1, waterproof layer 3-2, polyethylene self-adhesive board layer 3-3, filling gap 3-4, pile foundation end waterproof member 4, side water stop 4-1, end water stop 4-2, connecting ring 4-3, cylindrical part 4-4, bending part 4-5, gasket 4-6, pouring layer 5, foundation pit 6. Detailed Embodiments

[0019] The present utility model will be further described below with reference to the drawings.

[0020] A waterproof structure for a basement bearing platform. The basement bearing platform includes a pile foundation 2 constructed and formed in a foundation pit 6 and a bearing platform 1 located above the pile foundation 2. The waterproof structure is arranged between the pile foundation 2 and the bearing platform 1 to prevent water leakage at the bearing platform 1 of the basement. The waterproof structure includes a waterproof construction layer 3, a pile-end waterproof member 4, and a pouring layer 5. The waterproof construction layer 3 is arranged around the pile foundation 2 to waterproof the connection surface between the foundation pit 6 and the pile foundation 2. The pouring layer 5 is arranged above the waterproof construction layer 3 to protect the waterproof construction layer 3 through the pouring layer 5 and improve the service life of the waterproof construction layer 3. The pile-end waterproof member 4 is fixed at the end of the pile foundation 2 and abuts against the waterproof construction layer 3 to waterproof the connection surface between the pile foundation 2 and the pouring layer 5. The bearing platform 1 is cast and formed above the pile foundation 2, so that the pile-end waterproof member 4 is located between the bearing platform 1 and the pile foundation 2. When the bottom width of the bearing platform 1 is relatively large, the bearing platform 1 is connected to the waterproof construction layer 3.

[0021] To further improve the waterproof performance of the pile-end waterproof member 4 for the pile foundation 2, the pouring layer 5 wraps around the outside of the pile-end waterproof member 4 to fix the pile-end waterproof member 4 through the pouring layer 5 and prevent the pile-end waterproof member 4 from deforming and affecting its waterproof performance. When the pile-end waterproof member 4 is wrapped in the pouring layer 5, the bearing platform 1 is cast and formed above the pouring layer 5, and it is ensured that the bearing platform 1 and the pile foundation 2 are connected through a steel reinforcement cage.

[0022] The pile-end waterproof member 4 includes a side water stop belt 4-1 and an end water stop belt 4-2. The side water stop belt 4-1 is sleeved outside the pile foundation 2 to further waterproof the connection between the waterproof construction layer 3 and the pile foundation 2. The end water stop belt 4-2 covers the outside of the side water stop belt 4-1 and the pile foundation 2 to waterproof the top of the pile foundation 2 and ensure the overall waterproof performance of the top of the pile foundation 2.

[0023] Among them, the side water stop belt 4-1 is square or cylindrical, and different side water stop belts 4-1 can be selected according to the cross-sectional shape and size of the pile foundation 2. The side water stop belt 4-1 includes a vertical cylindrical part 4-4 and a bent part 4-5. The cylindrical part 4-4 is sleeved outside the pile foundation 2, and the bent part 4-5 abuts against the waterproof construction layer 3 to waterproof the connection between the waterproof construction layer 3 and the pile foundation 2. Preferably, the top of the side water stop belt 4-1 is higher than the upper end surface of the pile foundation 2 to ensure that the end water stop belt 4-2 abuts against the side water stop belt 4-1.

[0024] A connection ring 4-3 is provided at the edge of the end water stop belt 4-2, and a sealing gasket 4-6 is provided inside the end water stop belt 4-2. The sealing gasket 4-6 abuts against the side water stop belt 4-1. Preferably, the edge of the sealing gasket 4-6 extends to the inside of the connection ring 4-3, so that the sealing gasket 4-6 abuts against the side wall of the side water stop belt 4-1 to further improve the waterproof performance of the top of the pile foundation.

[0025] The pile foundation 2 is provided with pile foundation steel bars 2-1. The top of the pile foundation steel bars 2-1 extends out of the upper end face of the pile foundation 2. External threads are provided on the outer side of the pile foundation steel bars 2-1. The end water stop 4-2 is fixed on the end face of the pile foundation 2 through nuts 2-2, ensuring that the gasket 4-6 is in a compressed state, and realizing the tight connection between the end water stop 4-2 and the side water stop 4-1. After the installation of the end water stop 4-2 is completed, waterproof paint is coated at the connection between the nut and the end water stop 4-2, thereby preventing water leakage at the pile foundation steel bars 2-1. As a preferred implementation manner, the pile foundation steel bars 2-1 extending out of the top of the pile foundation 2 can be connected to the steel cage in the bearing platform 1 to improve the stability of the bearing platform 1.

[0026] The waterproof construction layer 3 sequentially includes a concrete cushion layer 3-1, a waterproof layer 3-2, and a polyethylene self-adhesive board layer 3-3 from bottom to top. The pile foundation end waterproof part 4 abuts against the polyethylene self-adhesive board layer 3-3. Preferably, the waterproof layer 3-2 can be a waterproof paint coating layer, and the waterproof layer is formed by waterproof paint construction.

[0027] A filling gap 3-4 is provided between the concrete cushion layer 3-1 and the pile foundation 2. The waterproof layer 3-2 extends into the filling gap 3-4, increasing the contact area between the waterproof layer 3-2 and the pile foundation 2, thereby further improving the waterproof performance at the waterproof layer 3-2.

[0028] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present utility model. Various modifications to these embodiments will be obvious to those skilled in the art. The general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present utility model. Therefore, the present utility model will not be limited to the embodiments shown herein, but rather will conform to the widest scope consistent with the principles and novel features disclosed herein.

[0029] Although more terms corresponding to the reference numerals in the drawings are used herein, the possibility of using other terms is not excluded; these terms are only used to more conveniently describe and explain the essence of the present utility model; interpreting them as any additional limitation is contrary to the spirit of the present utility model.

Claims

1. A waterproof structure of a basement cap, the basement cap comprising a pile foundation (2) and a cap (1) located above the pile foundation (2), characterized in that: The waterproof structure comprises a waterproof construction layer (3), a pile foundation end waterproof member (4) and a casting layer (5); the waterproof construction layer (3) is arranged on the periphery of the pile foundation (2); the casting layer (5) is arranged above the waterproof construction layer (3); the pile foundation end waterproof member (4) is fixed to the end of the pile foundation (2) and abuts against the waterproof construction layer (3); and the cap (1) is arranged above the pile foundation end waterproof member (4).

2. The waterproof structure of a basement cap according to claim 1, characterized in that: The casting layer (5) is wrapped around the outside of the waterproof member (4) at the end of the pile foundation.

3. The waterproof structure of a basement cap according to claim 1, characterized in that: The pile foundation end waterproofing member (4) comprises a side waterstop (4-1) and an end waterstop (4-2); the side waterstop (4-1) is sleeved on the outside of the pile foundation (2), and the end waterstop (4-2) is covered on the outside of the side waterstop (4-1) and the pile foundation (2).

4. The waterproof structure of a basement cap according to claim 3, characterized in that: A bending portion (4-5) is provided at the bottom of the side water stop strip (4-1).

5. The waterproof structure of a basement cap according to claim 3, characterized in that: The top of the side water stop strip (4-1) is higher than the upper end surface of the pile foundation (2).

6. The waterproof structure of a basement cap according to claim 3, characterized in that: A sealing gasket (4-6) is provided on the inner side of the end water stop strip (4-2), and the sealing gasket (4-6) abuts against the side water stop strip (4-1).

7. The waterproof structure of a basement cap according to claim 3, characterized in that: A connecting ring (4-3) is provided on the edge of the end water stop strip (4-2).

8. The waterproof structure of a basement cap according to claim 2, characterized in that: A pile foundation steel bar (2-1) is provided inside the pile foundation (2), an external thread is provided on the outside of the pile foundation steel bar (2-1), and an end water stop strip (4-2) is fixed to the end face of the pile foundation (2) via a nut (2-2).

9. The waterproof structure of a basement cap according to claim 1, characterized in that: The waterproof construction layer (3) comprises, from bottom to top, a concrete cushion layer (3-1), a waterproof layer (3-2) and a polyethylene self-adhesive board layer (3-3), and the waterproof member (4) at the end of the pile foundation is in contact with the polyethylene self-adhesive board layer (3-3).

10. The waterproof structure of a basement cap according to claim 9, characterized in that: A filling gap (3-4) is provided between the concrete cushion layer (3-1) and the pile foundation (2), and the waterproof layer (3-2) extends into the filling gap (3-4).