Cable erecting device

By designing a cable mount device including main body bracket, support frame, fixture and locking components, the problem of irregular and messy cable layout is solved, the cable is neat and beautiful and safely fixed, the risk of electric shock accidents is reduced, and the reliability and safety of the construction process is improved.

CN223093455UActive Publication Date: 2025-07-11MCC COMM CONSTR GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421905895.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-08-07
Publication Date
2025-07-11
Estimated Expiration
2034-08-07

AI Technical Summary

Technical Problem

The existing cable mount method can easily lead to irregular, messy and unstable cable layout during temporary construction, increasing the risk of electric shock accidents.

Method used

A temporary construction cable mount device is designed, including a main body bracket, a support frame, a fixing member and a locking assembly. The cable is fixed to the outside of the main body bracket through the support frame and the fixing member. The locking assembly is used to fix the cable on the support frame to ensure that the cable is neat and beautiful and is isolated from the main body bracket and the operator.

Benefits of technology

It improves the firmness and safety of cable layout, reduces the risk of cable damage and electric shock accidents, and ensures the reliability and safety of the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223093455U_ABST
    Figure CN223093455U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of cable construction, and discloses a cable erecting device for temporary construction, which comprises a main body bracket, a plurality of support frames arranged on the main body bracket, fixing pieces arranged on one sides of the support frames, and locking assemblies arranged on the support frames, wherein the main body bracket is used for being connected with the supporting frame; the support frame is used for supporting the cable; the fixing piece is used for fixing the support frame on the main body bracket; the locking assembly is used for fixing a cable to be erected on the supporting frame. According to the utility model, the problems of easy electric leakage and disordered cable arrangement due to the fact that cables are close to the rack body in a traditional cable rack can be solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of cable construction, and specifically, to a cable erection device for temporary construction. Background Art

[0002] Among the production safety accidents that occur in the housing and municipal engineering every year, electric shock accidents rank among the top, causing huge economic losses. Among electric shock accidents, accidents caused by temporary electricity use are the most. Temporary electricity use requires numerous electrical equipment and numerous cables, and the cable layout is complex. Among them, it is often necessary to lay cables through scaffolding or along guardrails. Therefore, the temporary electricity use in the face of complex situations requires standardized layout. If the layout is not standardized, it is easy to cause cable damage and leakage, resulting in electric shock accidents, posing a serious threat to the life and property safety of construction workers.

[0003] The existing layout methods mainly have two types: (1) directly binding the cable to the frame and routing along the frame, (2) directly hanging the cable on the inner side of the railing with an S-shaped plastic hook. The above two layout methods can fix a limited number of cables, and the layout is messy and not firm, easy to fall. If it is close to the railing, the distance from the railing will be insufficient; if it is hung on the inner side, although the operator is easy to touch, once the cable is damaged and leaks electricity, an electric shock accident will occur, and even cause casualties. Summary of the Utility Model

[0004] The utility model is made to solve the above technical problems, and its purpose is to provide a cable erection device for temporary construction, which fixes and erects the cable on the outside of the main bracket, isolates it from the main bracket and the operator, reduces the possibility of cable damage, thereby reducing the risk of electric shock accidents, and can also solve the problem of messy cable layout.

[0005] To achieve the above purpose, the utility model provides a cable erection device for temporary construction, including: a main bracket, a plurality of support brackets arranged on the main bracket, a fixing member arranged on one side of the support bracket, and a locking assembly arranged on the support bracket; wherein,

[0006] The main bracket is used to connect the support brackets;

[0007] The support bracket is used to support the cable;

[0008] The fixing member is used to fix the support bracket on the main bracket;

[0009] The locking assembly is used to fix the cable to be erected on the support bracket.

[0010] Preferably, the locking assembly includes: a locking surface disposed on the upper surface of the support frame, a hinge joint disposed at one end of the locking surface, and a fastener disposed at the other end of the locking surface; wherein,

[0011] The locking surface is rotatably disposed on the support frame, and the cable is disposed between the locking surface and the support frame;

[0012] The hinge joint is used to drive the locking surface to rotate;

[0013] The fastener is used to limit the rotation of the locking surface.

[0014] Preferably, the fastener is a bolt.

[0015] Preferably, the fixing member is connected to the support frame by welding.

[0016] Preferably, a plurality of cross bars and a plurality of vertical bars are provided on the main body bracket; wherein,

[0017] A plurality of the vertical bars are horizontally arranged, and a plurality of the cross bars are evenly distributed on the plurality of vertical bars;

[0018] The fixing member is fixedly sleeved on the vertical bar.

[0019] Preferably, an insulating layer is provided outside the locking surface.

[0020] Preferably, the support frame is a right-angled triangular support frame, wherein,

[0021] The fixing member is disposed on the short right-angled side of the support frame.

[0022] Preferably, an insulating layer is provided on the upper surface of the long right-angled side of the support frame.

[0023] Preferably, the number of the fixing members is at least two.

[0024] Preferably, the fixing member is a fastener.

[0025] According to the above description and practice, for the cable erection device for temporary construction described in the present invention, the main body bracket and the support frame are fixedly connected by the fixing member, the support frames are arranged horizontally in a row, the cables are placed on the support frames, and the cables are evenly arranged according to a certain rule according to the number and type of the cables. The cables are disposed on one side away from the main body bracket, separated from the main body bracket and the operators, which can reduce the risk of the cables being damaged by external forces, thereby reducing the risk of electric shock accidents. Finally, the movement of the cables is restricted by the locking assembly, and the cables are fixed to realize the cable layout. The wire layout is neat, beautiful and firm, improving the reliability and safety during the temporary power use in construction. Description of the Drawings

[0026] Figure 1 This is a schematic structural diagram of a cable erection device for temporary construction involved in an embodiment of the present utility model.

[0027] Figure 2 This is a side view of a support frame and a locking assembly involved in an embodiment of the present utility model.

[0028] The reference numerals in the figure are as follows:

[0029] 1. Main body support; 2. Support frame; 3. Fixing member; 4. Locking assembly; 41. Locking surface; 42. Hinge joint; 43. Fastening member; 5. Cable. Detailed implementation manners

[0030] Exemplary embodiments will now be described more fully with reference to the accompanying drawings. However, the exemplary embodiments can be implemented in various forms and should not be construed as limited to the examples set forth herein; rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the concept of the exemplary embodiments to those skilled in the art. The features, structures, or characteristics described may be combined in any suitable manner in one or more embodiments.

[0031] In addition, the accompanying drawings are only schematic illustrations of the present disclosure and are not necessarily drawn to scale. The same reference numerals in the figures denote the same or similar parts, and thus repeated descriptions thereof will be omitted. It should be noted that in the present disclosure, the terms "including", "configured with", and "provided with" are used to mean an open inclusion, and mean that there may be additional elements / components / etc. in addition to the listed elements / components / etc.; the terms "first", "second", etc. are only used as labels and are not limitations on the quantity or order of their objects; the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus cannot be construed as a limitation on the present utility model.

[0032] Unless otherwise clearly defined and limited, the terms "installed", "connected", and "coupled" shall be understood in a broad sense. For example, it may be a fixed connection, a detachable connection, or an integral connection; it may be a mechanical connection or an electrical connection; it may be directly connected or indirectly connected through an intermediate medium, and it may be the internal communication of two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present utility model can be understood according to specific circumstances.

[0033] In view of the problems in the prior art that in the traditional cable erection device, the cable layout is relatively close to the main bracket and the cable layout is messy, the present utility model proposes a cable erection device for temporary construction.

[0034] The following will describe in detail the specific embodiments of the present utility model with reference to the accompanying drawings.

[0035] The structure of a cable erection device for temporary construction is disclosed in this embodiment. Figure 1 and Figure 2 The specific structure of the cable erection device for temporary construction is shown from different angles. Specifically, Figure 1 shows the entire three-dimensional structure of the cable erection device for temporary construction. Figure 2 shows the side structure of the support frame and the locking member involved in the cable erection device for temporary construction.

[0036] Please refer to Figure 1 and Figure 2 , the cable erection device for temporary construction in the present utility model includes: a main bracket 1, a plurality of support frames 2 provided on the main bracket 1, and a fixing member 3 provided on one side of the support frame 2; wherein, the main bracket 1 is used to connect the support frame 2; the support frame 2 is used to support the cable 5; the fixing member 3 is used to fix the support frame 2 on the main bracket 1. The fixing member 3 is provided on one side of the support frame 2, and the support frame 2 is provided on the main bracket 1 through a fixing frame. Among them, a plurality of support frames 2 are arranged horizontally in a row and evenly provided on the main bracket 1. The cable 5 is placed on the support frame 2, and the cable 5 is evenly arranged according to a certain rule according to the quantity and model of the cable 5 to ensure the neatness of the cable layout. A locking assembly 4 is provided at the upper end of the support frame 2, and the locking assembly 4 is used to fix the cable 5. The locking assembly 4 can keep the cable 5 fixed during the erection process and prevent safety accidents caused by the movement or sliding of the cable 5. In this embodiment, the main bracket 1 is generally a scaffolding and a formwork support frame 2. In another embodiment, the main bracket 1 can be a edge protection railing.

[0037] Among them, the locking assembly 4 includes: a locking surface 41 provided on the upper surface of the support frame 2, a hinge joint 42 provided at one end of the locking surface 41, and a fastener 43 provided at the other end of the locking surface 41. Among them, the locking surface 41 is rotatably provided on the support frame 2, and the cable 5 is provided between the locking surface 41 and the upper surface of the support frame 2. The hinge joint 42 is used to drive the locking surface 41 to rotate, and the fastener 43 is used to limit the rotation of the locking surface 41. This makes the fixing operation of the cable 5 convenient and fast, greatly improving the work efficiency. During construction operations, first unlock the fastener 43, then rotate the locking surface 41 through the hinge joint 42, arrange the cable 5 on the support frame 2 according to a certain rule. When the cable 5 is placed, rotate the locking surface 41 to press the cable 5, and then lock the fastener 43 to fix the cable 5. In this embodiment, the hinge joint 42 is a rotatable fixing bolt. One end of the hinge joint 42 is fixedly provided at one end of the locking surface 41, and the other end is rotatably provided on the support frame 2. Through the hinge joint 42, the locking surface 41 can be flexibly driven to rotate around the hinge joint 42.

[0038] Among them, the fastener 43 is a bolt. This kind of fastener 43 has a simple structure, convenient operation, and reliable fixing effect. It is convenient for construction workers to flexibly unlock and lock the locking surface 41 when fixing the cable 5.

[0039] Among them, the fixing member 3 and the support frame 2 are connected by welding. The welding is firm and reliable, which can effectively resist vibration and impact during the construction process, ensuring the stability and safety of the cable 5 erection.

[0040] Among them, on the main body support 1, there are provided several cross bars and several vertical bars. Among them, several vertical bars are arranged horizontally, and several cross bars are evenly distributed on several vertical bars. The fixing member 3 is fixedly sleeved on the vertical bar. The several cross bars make the structure of the main body support 1 more stable, capable of bearing a greater load, and at the same time, it is also convenient to set more support frames 2 on the main body support 1 to meet the requirements of different construction environments.

[0041] Among them, an insulating layer is provided outside the locking surface 41. In this embodiment, the locking surface 41 is made of a metal material, and insulating rubber is covered on the outer surface of the locking surface 41 as the insulating layer. This further enhances the safety of the cable 5 erection. Even when the locking surface 41 is in contact with the cable 5, it can effectively prevent the occurrence of electrical contact and avoid possible safety accidents.

[0042] Among them, the support frame 2 is a right-angled triangular support frame. This design not only ensures the stability of the support frame 2, but also makes the structure of the entire device more compact and stable. Among them, the triangular support frame is a right triangle, the fixing member 3 is arranged at the short right-angled side of the right triangle, and the cable 5 is arranged on the long right-angled side. In this embodiment, the triangular support frame is assembled by welding angle steel. The angle steel has good mechanical properties and a more solid structure.

[0043] Among them, an insulating layer is provided on the upper surface of the long right-angled side of the support frame 2. The insulating layer is arranged on the upper surface of the support frame 2. The insulating layer can effectively prevent electrical contact between the cable 5 and the support frame 2, which is beneficial to the safety of the cable 5 erection device, thereby avoiding possible electric shock accidents.

[0044] Among them, the number of the fixing members 3 is at least two, and the fixing members 3 are fasteners. Using fasteners saves maintenance costs, reduces the manpower and material resources for maintenance, and increases the construction efficiency and quality. In a specific embodiment, the appropriate number of the fixing members 3 is selected according to the specific construction needs to ensure the stable and reliable connection between the support frame 2 and the main support frame 1, and maintain a stable support effect even in a harsh construction environment.

[0045] In summary, for the cable 5 erection device for temporary construction of the present utility model, the main support frame 1 and the support frame 2 are fixedly connected by the fixing member 3. The support frames 2 are arranged horizontally in a row, and the cable 5 is placed on the support frames 2. The cables 5 are evenly arranged according to a certain rule according to the quantity and model of the cables 5. The cable 5 is arranged on the side far from the main support frame 1, separated from the main support frame 1 and the operators, which can reduce the risk of the cable 5 being damaged by external forces, thereby reducing the risk of electric shock accidents. Finally, the movement of the cable 5 is restricted by the locking assembly 4 to fix the cable 5, realizing the cable 5 layout. The wire layout is neat, beautiful and firm, improving the reliability and safety during the temporary power use in construction.

[0046] For those skilled in the art, it is obvious that the present utility model is not limited to the details of the above exemplary embodiments, and can be implemented in other specific forms without departing from the spirit or basic characteristics of the present utility model. Therefore, in any aspect, the embodiments should be regarded as exemplary and non-limiting. The scope of the present utility model is defined by the appended claims rather than the above description. Therefore, all changes falling within the meaning and scope of the equivalent elements of the claims are intended to be included in the present utility model. Any reference signs in the claims should not be regarded as limiting the claimed rights.

Claims

1. A cable erection device, characterized in that, Comprising: A main body bracket, a plurality of support brackets arranged on the main body bracket, a fixing member arranged on one side of the support bracket, and a locking assembly arranged on the support bracket; wherein, The main body bracket is used to connect the support brackets; The support brackets are used to support the cables; The fixing member is used to fix the support bracket on the main body bracket; The locking assembly is used to fix the cable to be erected on the support bracket.

2. The cable erection device according to claim 1, wherein, The locking assembly comprises: a locking surface arranged on the upper surface of the support bracket, a hinge joint arranged at one end of the locking surface, and a fastening member arranged at the other end of the locking surface; wherein, The locking surface is rotatably arranged on the support bracket, and the cable is arranged between the locking surface and the support bracket; The hinge joint is used to drive the locking surface to rotate; The fastening member is used to limit the rotation of the locking surface.

3. The cable erection device according to claim 2, wherein, The fastening member is a bolt.

4. The cable erection device according to claim 2, wherein, The fixing member and the support bracket are connected by welding.

5. The cable erection device according to claim 2, wherein, A plurality of cross bars and a plurality of vertical bars are arranged on the main body bracket; wherein, The plurality of vertical bars are arranged horizontally, and the plurality of cross bars are evenly distributed on the plurality of vertical bars; The fixing member is fixedly sleeved on the vertical bar.

6. The cable erection device according to claim 2, characterized in that, An insulating layer is arranged outside the locking surface.

7. The cable erection device according to claim 1, characterized in that, The support bracket is a right-angled triangular support bracket, wherein, The fixing member is arranged on the short right-angled side of the support bracket.

8. The cable erection device according to claim 7, characterized in that, An insulating layer is arranged on the upper surface of the long right-angled side of the support bracket.

9. The cable erection device according to claim 1, wherein, The number of the fixing members is at least two.

10. The cable erection device according to claim 1, wherein, The fixing member is a fastener.