Pipeline on-site fixing and mounting structure

Through the combined structure of structural beams, reserved ribs, fixture components and support hoops, the problem of confusion in the distribution of wire and pipelines is solved, orderly distribution and stable fixed position are achieved, the construction process is simplified, and the project quality and aesthetics are improved.

CN223124545UActive Publication Date: 2025-07-18THE THIRD CONSTR ENG CO LTD OF CHINA CONSTR SECOND ENG BUREAU +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422326569.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-09-24
Publication Date
2025-07-18
Estimated Expiration
2034-09-24

AI Technical Summary

Technical Problem

In the prior art, the pipe arrangement of wires and pipes during the construction of the main building body is chaotic, resulting in inconsistent sorting of wires and pipes entering the box and inconsistent spacing, which affects the aesthetics and project quality, and is difficult to adjust.

Method used

The combined structure of structural beams, reserved ribs, fixture components and support hoops is adopted. The pipeline distribution is straightened out through the vertical setting of the clamps, and the base and adhesive layer are used to facilitate construction. The connecting rod installation ensures construction accuracy, and the reserved ribs provide stress support.

Benefits of technology

The orderly distribution and stable fixed position of the pipeline are achieved, the construction process is simplified, and the construction accuracy and aesthetics are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223124545U_ABST
    Figure CN223124545U_ABST
Patent Text Reader

Abstract

The utility model discloses a pipeline on-site fixing and installing structure which comprises a structural beam, a reserved rib connected into the structural beam and extending out of the structural beam, a group of clamp assemblies vertically connected to a pipeline on the reserved rib and a supporting hoop arranged between the upper clamp assembly and the lower clamp assembly. According to the utility model, through the arrangement of the hoop, the distribution of pipelines can be straightened out, and the positioning and design are ensured to be the same; the positioning stability is ensured due to the vertical arrangement of multiple groups of hoops; the installation foundation of the hoop is guaranteed through the arrangement of the base, the bonding layer is easy and convenient to construct, the connecting rod type installation is convenient to adjust on site, construction precision is guaranteed, and operation is easy; and through the arrangement of the reserved ribs, the overall stress of the base and the clamp assembly is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pipeline positioning and installation, and particularly relates to a pipeline on-site fixing and installation structure. Background Art

[0002] During the construction of the main building body, a lot of pre-buried wire pipes are involved. However, in many cases, the pipe laying is rather chaotic, resulting in inconsistent sorting and non-uniform spacing of the wire pipes entering the box, which affects the aesthetics and the project quality. To solve the above problems, the prior art is to tie all the wire pipes together with iron wires, transparent tapes, etc. However, if the sorting and spacing of the wire pipes need to be adjusted, it will be very troublesome. The existing public technologies are not easy to use. Therefore, for the problems of inconsistent sorting and non-uniform spacing of the wire pipes entering the box, targeted settings are required. Content of the Utility Model

[0003] The utility model provides a pipeline on-site fixing and installation structure to solve technical problems such as the distribution and sorting, fixing, and convenient installation of pipelines.

[0004] To achieve the above object, the utility model adopts the following technical solutions:

[0005] A pipeline on-site fixing and installation structure includes a structural beam, reserved bars connected in the structural beam and extending out of the structural beam, a set of fixture assemblies vertically connected to the reserved bars, and a support hoop arranged between the upper and lower fixture assemblies;

[0006] The fixture assemblies are arranged at intervals in the vertical direction of the reserved bars and at least two are provided. Each fixture assembly includes a base connected to the reserved bar and a clamp spacedly connected to the base. The clamp is an arc-shaped member and is provided one by one corresponding to the pipelines.

[0007] Further, the structural beam includes a beam body, beam longitudinal bars arranged in the beam body, and beam stirrups arranged outside the beam longitudinal bars; the beam longitudinal bars are respectively arranged at the top and bottom of the beam body and two rows are arranged at the corners.

[0008] Further, the top of the stirrup is arranged in the structural floor slab.

[0009] Further, the reserved bars are respectively fixedly connected to the longitudinal bars at the top and bottom in the beam body, and the height of the extending end of the reserved bar is adapted to the height required for pipeline fixing.

[0010] Further, the base is a square steel pipe, which is welded to the reserved bar or fixedly connected by binding wires.

[0011] Further, the clamp is fixedly connected to the base through an adhesive layer, and the adhesive layer is filled with glue or structural adhesive; the position of the clamp is the pipeline installation and positioning position.

[0012] Furthermore, a clamp link rod is integrally connected to the back of the clamp, and the clamp link rod passes through the base and is fixed by a nut.

[0013] Furthermore, the base includes a base main seat and a base connection hole provided on the base main seat. The base main seat is made of steel plate or steel pipe, and the base connection hole is an oval hole and is provided one by one corresponding to the clamp link rod.

[0014] Furthermore, a support sleeve is detachably installed on the reserved rib between the upper and lower fixture assemblies. The support sleeve is made of steel pipe or plastic pipe, and its height corresponds to the layout height of the fixed pipeline point.

[0015] The beneficial effects of the present utility model are reflected in:

[0016] 1) Through the setting of the clamp in the present utility model, it is beneficial to straighten out the distribution of the pipeline and ensure its positioning is the same as the design; and the multiple sets of vertical settings of the clamp ensure the positioning stability;

[0017] 2) Through the setting of the base in the present utility model, the installation foundation of the clamp is ensured. Among them, the bonding layer is easy for convenient construction, and the link type installation is convenient for on-site adjustment to ensure the construction accuracy and is easy to operate;

[0018] 3) Through the setting of the reserved rib in the present utility model, the overall force of the base and the fixture assembly is ensured.

[0019] Other features and advantages of the present utility model will be described in the subsequent description, and will be partially obvious from the description, or understood by implementing the present utility model; the main purpose and other advantages of the present utility model can be realized and obtained through the solutions specifically pointed out in the description. Description of the Drawings

[0020] Figure 1 It is a schematic diagram of the on-site fixed installation structure of the pipeline;

[0021] Figure 2 It is a partial schematic diagram of the on-site fixed installation structure of the pipeline;

[0022] Figure 3 It is a schematic diagram of the connection structure of the base, the clamp and the bonding layer;

[0023] Figure 4 It is a partial schematic diagram of the connection structure of the base, the clamp and the bonding layer;

[0024] Figure 5 It is a schematic diagram of the clamp, the link rod and their connection structure;

[0025] Figure 6 It is a schematic diagram of the base structure.

[0026] Reference numerals: 1 - Structural beam, 11 - Beam body, 12 - Longitudinal beam reinforcement, 13 - Beam stirrup, 2 - Structural floor slab, 3 - Reserved reinforcement, 4 - Clamping assembly, 41 - Base, 411 - Main base, 412 - Base connection hole, 42 - Clamp, 43 - Adhesive layer, 44 - Link rod, 45 - Nut, 5 - Support hoop, 6 - Pipeline. Detailed implementation mode

[0027] Taking the pipeline installation of a certain distribution box as an example, in order to ensure the orderly installation of the pipeline, construction is carried out through the on-site fixed installation structure of the pipeline. As Figures 1 to 6 shown, the on-site fixed installation structure of the pipeline includes a structural beam 1, a reserved reinforcement 3 connected to and extending out of the structural beam 1, a pipeline 6 vertically connected to the reserved reinforcement 3, a set of clamping assemblies 4, and a support hoop 5 arranged between the upper and lower clamping assemblies 4.

[0028] In this embodiment, two clamping assemblies 4 are arranged at intervals in the vertical direction of the reserved reinforcement 3. The clamping assembly 4 includes a base 41 connected to the reserved reinforcement 3 and a clamp 42 connected to the base 41 at intervals. The clamp 42 is an arc-shaped part and is arranged one by one corresponding to the pipeline 6.

[0029] In this embodiment, a support sleeve is detachably installed on the reserved reinforcement 3 between the upper and lower pipeline 6 clamping assemblies 44. The support sleeve is a steel pipe or a plastic pipe, and its height corresponds to the layout height of the fixed pipeline 6 points.

[0030] In this embodiment, the structural beam 1 includes a beam body 11, longitudinal beam reinforcements 12 arranged in the beam body 11, and beam stirrups 13 arranged outside the longitudinal beam reinforcements 12; the longitudinal beam reinforcements 12 are respectively arranged at the top and bottom of the beam body 11 and there are two rows at the corners. The beam body 11 is made of cast-in-place concrete. The top of the stirrup is arranged in the structural floor slab 2.

[0031] In this embodiment, the reserved reinforcements 3 are fixedly connected to the longitudinal reinforcements at the top and bottom in the beam body 11 respectively, and the height of the protruding end of the reserved reinforcement 3 is adapted to the height required for pipeline fixation. The base 41 is a square steel pipe, which is welded to the reserved reinforcement 3 or fixedly connected by binding wires.

[0032] As Figure 4 described, the clamp 42 is fixedly connected to the base 41 through an adhesive layer 43, and the adhesive layer 43 is filled with glue or structural glue; the position of the clamp 42 is the installation and positioning position of the pipeline 6.

[0033] As Figure 5 and Figure 6As shown, a clamp 42 connecting rod 44 is integrally connected to the back of the clamp 42. The clamp 42 connecting rod 44 passes through the base 41 and is fixed by a nut 45. The base 41 includes a base main seat 411 and a base connecting hole 412 provided on the base main seat 411. The base main seat 411 is made of a steel plate or a steel pipe, and the base connecting hole 412 is an oval hole and is provided corresponding to the clamp 42 connecting rod 44 one by one.

[0034] The above is only the preferred specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be thought of by those skilled in the art within the technical scope disclosed by the present invention should be covered within the protection scope of the present invention.

Claims

1. A pipeline on-site fixed installation structure, characterized in that, It includes a structural beam (1), a reserved reinforcement bar (3) connected inside the structural beam (1) and extending out of the structural beam (1), a pipeline (6) vertically connected to the reserved reinforcement bar (3), a set of fixture components (4), and a support hoop (5) arranged between the upper and lower fixture components (4); The fixture components (4) are arranged at intervals in the vertical direction of the reserved reinforcement bar (3) and at least two are provided. The fixture components (4) include a base (41) connected to the reserved reinforcement bar (3) and a clamp (42) connected to the base (41) at intervals. The clamp (42) is an arc-shaped member and is arranged one by one corresponding to the pipeline (6).

2. The on-site fixed installation structure of a pipeline according to claim 1, characterized in that, The structural beam (1) includes a beam body (11), beam longitudinal reinforcement bars (12) arranged inside the beam body (11), and beam stirrups (13) arranged outside the beam longitudinal reinforcement bars (12); the beam longitudinal reinforcement bars (12) are respectively arranged at the top and bottom of the beam body (11) and two rows are arranged at the corners.

3. The on-site fixed installation structure of a pipeline according to claim 2, characterized in that, The top of the stirrup is arranged in the structural floor slab (2).

4. The on-site fixed installation structure of a pipeline according to claim 3, characterized in that The reserved reinforcement bars (3) are respectively fixedly connected to the longitudinal reinforcement bars at the top and bottom inside the beam body (11), and the height of the extended end of the reserved reinforcement bar (3) is adapted to the height required for pipeline fixation.

5. The on-site fixed installation structure of a pipeline according to claim 4, characterized in that, The base (41) is a square steel pipe, which is welded to the reserved reinforcement bar (3) or fixedly connected by binding wire.

6. The on-site fixed installation structure of a pipeline according to claim 5, characterized in that, The clamp (42) is fixedly connected to the base (41) through an adhesive layer (43), and the adhesive layer (43) is filled with glue or structural adhesive; the position of the clamp (42) is the installation and positioning position of the pipeline (6).

7. The on-site fixed installation structure of a pipeline according to claim 4, characterized in that, A clamp (42) connecting rod (44) is integrally connected to the back of the clamp (42), and the clamp (42) connecting rod (44) passes through the base (41) and is fixed by a nut (45).

8. The on-site fixed installation structure of a pipeline according to claim 7, wherein The base (41) includes a base main seat (411) and a base connecting hole (412) arranged on the base main seat (411). The base main seat (411) is a steel plate or a steel pipe, and the base connecting hole (412) is an oval hole and is arranged one by one corresponding to the clamp (42) connecting rod (44).

9. The on-site fixed installation structure of a pipeline according to claim 1, characterized in that, A support sleeve is detachably installed on the reserved reinforcement bar (3) between the upper and lower pipeline (6) fixture components (4). The support sleeve is a steel pipe or a plastic pipe, and its height corresponds to the layout height of the fixed pipeline (6) points.