High slope hanging basket construction platform
Through the lifting adjustment device of the suspension platform and the slope moving frame, a stable construction platform is provided for high-slope construction, which solves the safety and stability problems caused by the establishment of scaffolding in the prior art, and achieves efficient drilling construction.
Patent Information
- Application Number
- CN202420924071.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-29
- Publication Date
- 2025-07-22
- Estimated Expiration
- 2034-04-29
AI Technical Summary
When drilling on high slopes, the existing technology requires the erecting of full-house scaffolding, which causes great damage to the mountain structure and reduces construction safety and stability.
The suspension platform and slope moving frame are adopted, combined with the lifting device and the lifting adjustment device, to provide a stable construction platform, and the lifting and horizontal adjustment of the platform is achieved through electric hoists to reduce damage to the mountain.
It improves construction safety, reduces the occurrence of construction accidents, enhances the stability and service life of the platform, and improves construction efficiency.
Smart Images

Figure CN223135608U_ABST
Abstract
Description
Technical Field
[0001] This application relates to the technical field of high slope construction, and in particular to a hanging basket construction platform for high slopes. Background Art
[0002] A high slope generally refers to a soil slope with a height greater than 20 meters or a rock slope with a height greater than 30 meters. Due to geological and geographical factors, high slopes are prone to disasters such as weathering and spalling, flowing stones and mud, falling stones, collapse, and landslides. Therefore, it is necessary to reinforce and protect high slopes. Generally, drilling treatment is first carried out on the slope of the high slope, and then the high slope is combinedly supported by means of anchor rods, anchor cables, and active nets.
[0003] Currently, before drilling construction on a high slope, it is necessary to first set up a full hall scaffold on the slope surface of the high slope as a construction platform to facilitate the movement of construction workers on the slope for construction. However, when setting up the scaffold on the slope surface, it is also necessary to install connecting wall members on the slope surface to stabilize the scaffold; usually, holes are first drilled on the slope surface, and then the steel bars are inserted into the rock for more than 100 centimeters to complete the installation of the connecting wall members, and it is required to set up a connecting wall member every horizontal meter, which causes great damage to the mountain slope surface, greatly reduces the structural stability of the high slope, makes the originally unstable slope have great potential safety hazards, and reduces the construction safety. Summary of the Invention
[0004] In order to improve construction safety, this application provides a hanging basket construction platform for high slopes.
[0005] The hanging basket construction platform for high slopes provided by this application adopts the following technical solutions:
[0006] The hanging basket construction platform for high slopes includes: a suspension platform, a slope surface moving frame is arranged on one side side wall of the suspension platform, a moving member is arranged on the side of the slope surface moving frame facing the slope surface, a lifting device is arranged on the slope surface moving frame, the lifting device is used to drive the slope surface moving frame to lift and move, a lifting and adjusting device is arranged on the suspension platform, and the lifting and adjusting device is used to adjust the horizontal inclination angle of the suspension platform during the lifting and moving process.
[0007] By adopting the above technical solutions, a stable installation structure is provided for the down-the-hole drill through the suspension platform, enabling the down-the-hole drill to be stably installed on the hanging basket construction platform. Moreover, through the suspension platform, a stable construction platform is provided for the constructors, so that the constructors can more conveniently carry out stable drilling construction on the slope surface of the high slope. When carrying out reinforcement and protection treatment on the high slope, under the driving action of the lifting device, through the moving member, the slope surface moving frame is lifted and moved on the slope surface, and at the same time, the lifting and moving of the suspension platform are driven. And under the cooperative action of the lifting adjustment device, the adjustment of the horizontal inclination angle of the suspension platform during the lifting process is realized, so that the suspension platform can be stably maintained in a horizontal lifting state, providing a stable supporting effect for the constructors and the down-the-hole drill, thereby realizing the mobile construction of the constructors on the high slope, presenting the effect of the hanging basket construction platform stably, and thus eliminating the need to provide a construction platform for the constructors by erecting a scaffolding, reducing the occurrence of construction accidents caused by damaging the slope surface structure during the construction process, effectively improving the construction safety, and making the construction of the constructors on the high slope more convenient, so as to improve the construction efficiency.
[0008] Preferably, both the lifting device and the lifting adjustment device are electric hoists, and one end of the towing rope of the electric hoist is fixedly connected to the top of the slope of the high slope.
[0009] By adopting the above technical solutions, during construction, one end of the towing rope of the electric hoist is fixedly connected to the top of the slope of the high slope, and then the electric hoist is started. By retracting and releasing the towing rope, the lifting and moving of the hanging basket construction platform on the slope surface are realized, thus facilitating the mobile construction of the constructors on the high slope.
[0010] Preferably, two lifting devices are provided, and the two lifting devices are symmetrically arranged at one end of the slope surface moving frame close to the suspension platform.
[0011] By adopting the above technical solutions, through the cooperation of the two lifting devices, the driving force of the lifting device on the slope surface moving frame can be made more uniform, so as to reduce the shaking of the slope surface moving frame during the moving process, and further realize the more stable lifting and moving of the hanging basket platform on the slope surface.
[0012] Preferably, the lifting adjustment device is arranged on the supporting surface of the suspension platform along the central axis direction of the two lifting devices.
[0013] By adopting the above technical solutions, the lifting adjustment device and the two lifting devices form an isosceles triangle structure, so as to facilitate the cooperative action of the lifting adjustment device and the lifting device, and further evenly and balance the driving forces of the lifting device and the lifting adjustment device on the hanging basket construction platform, thereby further realizing the stable lifting and moving of the hanging basket construction platform, and at the same time being beneficial to maintaining the horizontal state of the suspension platform, and further effectively improving the construction safety.
[0014] Preferably, a reinforcement member is provided between the suspension platform and the slope moving frame, and the reinforcement member is used to strengthen the connection between the suspension platform and the slope moving frame.
[0015] By adopting the above technical solution, the setting of the reinforcement member strengthens the connection between the suspension platform and the slope moving frame, thereby enhancing the overall structural stability of the hanging basket construction platform, facilitating further improvement of construction safety, and prolonging the service life of the hanging basket construction platform.
[0016] Preferably, the reinforcement member is provided as a reinforcement rod, and both ends of the reinforcement rod are respectively connected to the suspension platform and the slope moving frame.
[0017] By adopting the above technical solution, through the reinforcement rod, the connectivity between the suspension platform and the slope moving frame is strengthened, thereby effectively consolidating and enhancing the overall structure of the hanging basket construction platform, effectively improving the overall structural stability of the hanging basket construction platform, and further providing a stable movable construction platform for constructors, effectively realizing a further improvement in construction safety, and being beneficial to prolonging the service life of the hanging basket construction platform, facilitating the improvement of the recycling rate of the hanging basket construction platform, and reducing resource waste.
[0018] Preferably, a protective fence is provided on the periphery of the suspension platform.
[0019] By adopting the above technical solution, the protective fence provides a protective effect for constructors to reduce the occurrence of the situation where constructors fall on the suspension platform, thereby providing a safe and stable construction platform for constructors on the high slope and effectively realizing a further improvement in construction safety.
[0020] Preferably, the moving member is a wheel, and the wheel is rotatably installed on the side of the slope moving frame facing the slope.
[0021] By adopting the above technical solution, through the rotation of the wheel, the slope moving frame is moved on the slope, and at the same time, the lifting and moving of the suspension platform is driven, thereby realizing the stable movement of the hanging basket construction platform on the slope.
[0022] In summary, the present application includes at least one of the following beneficial technical effects:
[0023] 1. By means of a suspension platform, a stable installation structure is provided for the down-the-hole drill, enabling the down-the-hole drill to be stably installed on the hanging basket construction platform. And through the suspension platform, a stable construction platform is provided for the constructors, so that the constructors can more conveniently carry out stable drilling construction on the slope surface of the high slope. When carrying out reinforcement and protection treatment on the high slope, under the driving action of the lifting device, through the moving member, the slope surface moving frame is lifted and moved on the slope surface, and at the same time, the lifting and moving of the suspension platform are driven. And under the cooperative action of the lifting adjustment device, the adjustment of the horizontal inclination angle of the suspension platform during the lifting process is realized, so that the suspension platform can be stably maintained in a horizontal lifting state, providing a stable supporting effect for the constructors and the down-the-hole drill, thereby realizing the mobile construction of the constructors on the high slope, presenting the effect of the hanging basket construction platform stably, and then there is no need to provide a construction platform for the constructors by erecting a scaffolding, reducing the occurrence of construction accidents caused by damaging the slope surface structure during the construction process, effectively improving the construction safety, and making the construction of the constructors on the high slope more convenient, so as to improve the construction efficiency;
[0024] 2. Both the lifting device and the lifting adjustment device are electric hoists. During construction, one end of the towing rope of the electric hoist is fixedly connected to the top of the high slope. Then, the electric hoist is started, and through the winding and unwinding of the towing rope, the lifting and moving of the hanging basket construction platform on the slope surface are realized, thus facilitating the mobile construction of the constructors on the high slope;
[0025] 3. Through the cooperation of two lifting devices, the driving force of the lifting device on the slope surface moving frame can be made more uniform, so as to reduce the situation of the slope surface moving frame shaking during the movement, and then realize the more stable lifting and moving of the hanging basket platform on the slope surface. Description of the Drawings
[0026] Figure 1 is the overall structural schematic diagram of the high slope hanging basket construction platform in the embodiment of the present application;
[0027] Figure 2 is the structural schematic diagram of the slope surface moving frame in the embodiment of the present application;
[0028] Figure 3 is the top view of the suspension platform in the embodiment of the present application.
[0029] Description of the Reference Numerals: 1, suspension platform; 11, lifting adjustment device; 12, supporting plate; 13, protective fence; 2, slope surface moving frame; 21, lifting device; 3, wheel; 4, towing rope; 5, reinforcing rod; 6, strengthening rod; 7, high slope. Detailed Embodiment
[0030] The following is a further detailed description of the present application in conjunction with the attached Figures 1-3 drawings.
[0031] The embodiment of the present application discloses a construction platform for a high-slope hanging basket.
[0032] Refer to Figure 1 , the construction platform for a high-slope hanging basket includes a suspension platform 1. A slope moving frame 2 is arranged on one side wall of the suspension platform 1 facing the slope surface of the high slope 7. A moving member is arranged on the side of the slope moving frame 2 facing the slope surface. A lifting device 21 is arranged on the slope moving frame 2. The lifting device 21 is used to drive the slope moving frame 2 to lift and move. A lifting adjustment device 11 is arranged on the suspension platform 1. The lifting adjustment device 11 is used to adjust the horizontal inclination angle of the suspension platform 1 during the lifting and moving process to cooperate with the lifting device 21 to realize the stable lifting and moving of the suspension platform 1.
[0033] Through the suspension platform 1, a stable installation structure is provided for the down-the-hole drill, so that the down-the-hole drill can be stably installed on the hanging basket construction platform. And through the suspension platform 1, a stable construction platform is provided for the constructors, so that the constructors can more conveniently carry out stable drilling construction on the slope surface of the high slope 7; when carrying out reinforcement and protection treatment on the high slope 7, under the driving action of the lifting device 21, through the moving member, the slope moving frame 2 is lifted and moved on the slope surface, and at the same time, the lifting and moving of the suspension platform 1 is driven. And under the cooperation of the lifting adjustment device 11, the adjustment of the horizontal inclination angle of the suspension platform 1 during the lifting process is realized, so that the suspension platform 1 can be stably maintained in a horizontal lifting state, providing a stable supporting effect for the constructors and the down-the-hole drill, which is conducive to improving the construction safety, and thus realizing the mobile construction of the constructors on the high slope 7.
[0034] Therefore, under the cooperation of the lifting device 21 and the lifting adjustment device 11, through the slope moving frame 2, the stable lifting and moving of the suspension platform 1 on the slope surface is realized. And through the suspension platform 1, a stable installation structure is provided for the down-the-hole drill, and a stable construction platform is provided for the constructors, so as to realize the mobile construction of the constructors on the high slope 7, stably presenting the effect of the hanging basket construction platform. Furthermore, there is no need to provide a construction platform for the constructors by erecting a scaffolding, reducing the occurrence of construction accidents caused by damaging the slope surface structure of the mountain body during the construction process, effectively improving the construction safety, and making the construction of the constructors on the high slope 7 more convenient, so as to improve the construction efficiency.
[0035] Refer to Figure 1 and Figure 2, specifically, both the suspension platform 1 and the slope moving frame 2 are constructed by splicing steel pipes. Moreover, a support plate 12 is laid on the support surface of the suspension platform 1 to provide a more stable support for the constructor and a more stable construction platform for the constructor. Also, the outer contour of the slope moving frame 2 is arranged in a square structure, and the moving parts are wheels 3. There are four wheels 3, and the four wheels 3 are respectively rotatably installed at the four end points on the side of the slope moving frame 2 facing the slope. Thus, through the cooperation of the four wheels 3, the stable movement of the slope moving frame 2 is realized. The lifting device 21 and the lifting adjustment device 11 are both electric hoists; during construction, one end of the towing rope 4 of the electric hoist is fixedly connected to the top of the high slope 7, and then the electric hoist is started. By retracting and releasing the towing rope 4, the lifting and moving of the hanging basket construction platform on the slope are realized, so as to facilitate the moving construction of the constructor on the high slope 7 and improve the construction efficiency.
[0036] Refer to Figures 1 to 3 , more specifically, there are two lifting devices 21, and the two lifting devices 21 are symmetrically arranged at one end of the slope moving frame 2 close to the suspension platform 1. Thus, through the cooperation of the two lifting devices 21, the driving force of the lifting device 21 on the slope moving frame 2 can be made more uniform, so as to reduce the shaking of the slope moving frame 2 during movement, and further realize the more stable lifting and moving of the hanging basket platform on the slope. Further, the lifting adjustment device 11 is arranged on the support plate 12 of the suspension platform 1 along the central axis direction of the two lifting devices 21, and the lifting adjustment device 11 is arranged on the top surface of the support plate 12 on the side far from the slope moving frame 2, so that the lifting adjustment device 11 and the two lifting devices 21 form an isosceles triangle structure, which is convenient to realize the cooperation between the lifting adjustment device 11 and the lifting device 21, and further evenly and balance the driving forces of the lifting device 21 and the lifting adjustment device 11 on the hanging basket construction platform, so as to further realize the stable lifting and moving of the hanging basket construction platform, and at the same time is beneficial to maintaining the horizontal state of the suspension platform 1, and further effectively improves the construction safety.
[0037] Refer to Figure 1, a reinforcing member is provided between the suspension platform 1 and the slope moving frame 2. The reinforcing member is used to strengthen the connection between the suspension platform 1 and the slope moving frame 2, thereby enhancing the overall structural stability of the hanging basket construction platform, so as to further improve the construction safety and extend the service life of the hanging basket construction platform. Specifically, the reinforcing member is provided as a reinforcing rod 5. One end of the reinforcing rod 5 is connected to the side wall of the suspension platform 1 away from the slope moving frame 2, and the other end of the reinforcing rod 5 is connected to the end of the slope moving frame 2 away from the suspension platform 1. Thus, both ends of the reinforcing rod 5 are respectively connected to the suspension platform 1 and the slope moving frame 2, and the reinforcing rod 5, the suspension platform 1 and the slope moving frame 2 are arranged to form a triangular stable structure around them, thereby effectively strengthening and enhancing the overall structure of the hanging basket construction platform, effectively improving the overall structural stability of the hanging basket construction platform, and further providing a stable movable construction platform for the constructors, effectively further improving the construction safety, and being beneficial to extending the service life of the hanging basket construction platform, so as to improve the recycling rate of the hanging basket construction platform and reduce the waste of resources.
[0038] Refer to Figure 1 , in order to further strengthen the overall structure of the hanging basket construction platform, a strengthening rod 6 is provided between the reinforcing rod 5 and the slope moving frame 2. Both ends of the strengthening rod 6 are respectively connected to the reinforcing rod 5 and the slope moving frame 2, thereby further strengthening and consolidating the triangular stable structure formed by the suspension platform 1, the reinforcing rod 5 and the slope moving frame 2 around them, and further realizing the further improvement of the overall structural stability of the hanging basket construction platform.
[0039] Refer to Figure 1 , a protective fence 13 is provided on the periphery of the suspension platform 1. The protective fence 13 provides a protective effect for the constructors to reduce the occurrence of the situation that the constructors fall on the suspension platform 1, thereby providing a safe and stable construction platform for the constructors on the high slope 7 and effectively realizing the further improvement of the construction safety.
[0040] The above are all the preferred embodiments of the present application. This embodiment is only an explanation of the present application and does not limit the protection scope of the present application accordingly. Therefore: Any equivalent changes made according to the structure, shape and principle of the present application shall be covered within the protection scope of the present application.
Claims
1. High-slope hanging basket construction platform, characterized in that, Including: A suspension platform (1), on one side wall of the suspension platform (1), there is a slope moving frame (2). On the side of the slope moving frame (2) facing the slope, there is a moving member. On the slope moving frame (2), there is a lifting device (21), and the lifting device (21) is used to drive the slope moving frame (2) to lift and move. On the suspension platform (1), there is a lifting adjustment device (11), and the lifting adjustment device (11) is used to adjust the horizontal inclination angle of the suspension platform (1) during the lifting and moving process. The reinforcement member is provided as a reinforcement rod (5), and both ends of the reinforcement rod (5) are respectively connected to the suspension platform (1) and the slope moving frame (2). The reinforcement rod (5), the suspension platform (1), and the slope moving frame (2) are arranged to form a triangular stable structure around them. The moving member is a wheel (3), and there are four wheels (3). The four wheels (3) are respectively rotatably installed at the four end points on the side of the slope moving frame (2) facing the slope.
2. The high-slope hanging basket construction platform according to claim 1, characterized in that, Both the lifting device (21) and the lifting adjustment device (11) are electric hoists, and one end of the traction rope (4) of the electric hoist is fixedly connected to the top of the high slope (7).
3. The high-slope hanging basket construction platform according to claim 2, characterized in that, There are two lifting devices (21), and the two lifting devices (21) are symmetrically arranged at one end of the slope moving frame (2) close to the suspension platform (1).
4. The high-slope hanging basket construction platform according to claim 3, characterized in that The lifting adjustment device (11) is arranged on the bearing surface of the suspension platform (1) along the central axis direction of the two lifting devices (21).
5. The high-slope hanging basket construction platform according to claim 1, wherein A reinforcement member is provided between the suspension platform (1) and the slope moving frame (2), and the reinforcement member is used to strengthen the connection between the suspension platform (1) and the slope moving frame (2).
6. The high-slope hanging basket construction platform according to claim 1, wherein A protective fence (13) is provided on the periphery of the suspension platform (1).