Gas pipeline anti-settling device

By setting limit holes and limit columns at both ends of the metal hose, the pre-alignment design of the connecting rod and the clamp is solved, the installation inconvenience at the connection of the gas pipeline is achieved, convenient installation and stable connection are achieved, and the risk of leakage is reduced.

CN223137277UActive Publication Date: 2025-07-22ANYANG KUNLUN GAS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422419965.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-10-08
Publication Date
2025-07-22
Estimated Expiration
2034-10-08

AI Technical Summary

Technical Problem

It is difficult to achieve pre-alignment and limiting at the connection between existing underground gas pipes and building gas pipes and metal hoses, resulting in inconvenient installation and prone to misalignment and leakage.

Method used

The fixing discs at both ends of the metal hose are connected to the mounting discs by bolts. The mounting disc is provided with a limit hole and a limiting column. The connecting rod and the clamp are connected by a spring to achieve pre-alignment and fixing with bolts to avoid manual position adjustment.

Benefits of technology

It realizes convenient installation of underground gas pipes, building gas pipes and metal hoses, reduces the risk of misalignment, and improves the stability and sealing of the connection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223137277U_ABST
    Figure CN223137277U_ABST
Patent Text Reader

Abstract

The utility model relates to a gas pipeline anti-sedimentation device which comprises a metal hose installed between an underground gas pipe and a building gas pipe, the connecting end of the underground gas pipe and the metal hose and the connecting end of the building gas pipe and the metal hose are fixedly connected with installation discs respectively, and fixing discs are fixed to the two ends of the metal hose respectively. The two fixing discs are connected with the corresponding mounting discs through a plurality of bolts, a plurality of limiting holes arranged in an annular array are formed in the mounting discs, and a plurality of limiting columns corresponding to the limiting holes in a one-to-one mode are fixed to one sides of the fixing discs. A building gas pipe and an external building are fixedly installed, an underground gas pipe is buried underground, and a plurality of limiting columns are inserted into corresponding limiting holes respectively, so that the effect of limiting an installation disc and a fixed disc when the installation disc and the fixed disc are installed is achieved; and the clamping block abuts against one side of the mounting disc under the action of the tension spring, so that the pre-alignment effect is achieved between the fixing disc and the mounting disc.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technology of preventing settlement of gas pipelines, in particular to a gas pipeline settlement prevention device. Background Art

[0002] When transporting natural gas, generally, an underground gas pipeline buried underground is connected to a building gas pipeline in a building for transportation. When laying the underground gas pipeline buried underground, the laying of the gas pipeline will be affected by the foundation. If the foundation settles, the pipeline is prone to longitudinal uneven settlement risks together with the soil layer or by itself. Eventually, it is easy to cause misalignment, cracking, etc. at the weld position of the pipeline, thus easily causing gas leakage and affecting the normal operation of the urban gas supply system.

[0003] At present, the existing underground gas pipeline and the building gas pipeline are connected by a metal hose to compensate for their offset and offset the misalignment between the underground gas pipeline and the building gas pipeline. However, at present, the installation of the underground gas pipeline, the building gas pipeline and the metal hose is relatively inconvenient, and it is not easy to pre-align and limit the connection between the underground gas pipeline, the building gas pipeline and the metal hose, so the installation is relatively troublesome. Summary of the Utility Model

[0004] The purpose of the utility model is to provide a gas pipeline settlement prevention device, which is used to solve the problem that it is not easy to pre-align and limit the connection between the underground gas pipeline, the building gas pipeline and the metal hose in the prior art, making the installation of the underground gas pipeline, the building gas pipeline and the metal hose relatively inconvenient.

[0005] To solve the above problems, the utility model provides a gas pipeline settlement prevention device, which includes a metal hose installed between the underground gas pipeline and the building gas pipeline. Installation discs are respectively fixedly connected to the connection ends of the underground gas pipeline and the building gas pipeline with the metal hose. Fixing discs are respectively fixed at both ends of the metal hose. The two fixing discs are respectively connected to the corresponding installation discs through a plurality of bolts. A plurality of limiting holes arranged in a circular array are formed in the installation discs. A plurality of limiting columns corresponding to the limiting holes one by one are fixed on one side of the fixing disc. The plurality of limiting columns can be slidably connected to the corresponding limiting holes. Two relatively arranged supports are fixed inside the fixing disc. A connecting rod is rotatably connected to the inside of the support through a rotating shaft. One end of the connecting rod is slidably connected to a sliding frame. One end of the connecting rod is fixedly connected to the sliding frame through a tension spring. A clamping block is fixed on one side of the sliding frame. The clamping block can be abutted against one side of the corresponding installation disc.

[0006] The gas pipeline settlement prevention device provided by the utility model further has the following technical features:

[0007] Further, both ends of the rotating shaft are respectively fixedly connected to the support through torsion springs.

[0008] Further, one end of the clamping block is an inclined surface, and the inclined surface of the clamping block can contact the corresponding mounting disc.

[0009] Further, a sealing ring is provided between the corresponding mounting disc and the fixing disc.

[0010] Further, an L-shaped rod is fixed on one of the fixing discs, a benchmark is fixed on the other fixing disc, a jack is provided on the L-shaped rod, the bottom of the benchmark can pass through the jack, and a positioning seat is sleeved on the benchmark.

[0011] Further, a fastening bolt is threadedly connected to one side of the positioning seat, and one end of the fastening bolt abuts against the surface of the benchmark.

[0012] The utility model has the following beneficial effects: By fixedly installing the building gas pipe with the external building and burying the underground gas pipe underground, when installing the metal hose, by inserting a plurality of limiting posts into the corresponding limiting holes respectively, the function of limiting the two when installing the mounting disc and the fixing disc is achieved. By passing one end of the connecting rod through the corresponding mounting disc and making the clamping block abut against one side of the mounting disc under the action of the tension spring, a pre-alignment function is achieved between the fixing disc and the mounting disc, and then the fixing disc and the mounting disc are connected by bolts, avoiding manually fixing the position between the fixing disc and the mounting disc when tightening the bolts. Description of the Drawings

[0013] Figure 1 is a three-dimensional view of an embodiment of the utility model;

[0014] Figure 2 is a main view sectional view of an embodiment of the utility model with a break;

[0015] Figure 3 is an embodiment of the utility model Figure 2 is an enlarged structural schematic diagram of part A in the embodiment;

[0016] Figure 4 is a right view sectional view of an embodiment of the utility model with a break. Detailed Embodiment

[0017] The present utility model will be described in detail below with reference to the drawings and in conjunction with embodiments. It should be noted that, without conflict, the embodiments in the present utility model and the features in the embodiments can be combined with each other.

[0018] As Figures 1 to 4In the embodiment of the gas pipeline anti-settlement device of the present utility model shown, the gas pipeline anti-settlement device includes a metal hose 3 installed between an underground gas pipeline 1 and a building gas pipeline 2. Installation discs 4 are respectively fixedly connected to the connection ends of the underground gas pipeline 1 and the building gas pipeline 2 with the metal hose 3. Fixing discs 5 are respectively fixed at both ends of the metal hose 3. The two fixing discs 5 are respectively connected to the corresponding installation discs 4 through a plurality of bolts. A plurality of limiting holes arranged in an annular array are formed in the installation disc 4. A plurality of limiting columns 6 corresponding to the limiting holes one by one are fixed on one side of the fixing disc 5. The plurality of limiting columns 6 can be slidably connected to the corresponding limiting holes. Two relatively arranged supports 7 are fixed inside the fixing disc 5. A connecting rod 8 is rotatably connected to the inside of the support 7 through a rotating shaft. One end of the connecting rod 8 is slidably connected with a sliding frame 9. One end of the connecting rod 8 is fixedly connected to the sliding frame 9 through a tension spring. A clamping block 10 is fixed on one side of the sliding frame 9. The clamping block 10 can be in contact with one side of the corresponding installation disc 4. By fixedly installing the building gas pipeline 2 to an external building and burying the underground gas pipeline 1 underground, when installing the metal hose 3, by inserting the plurality of limiting columns 6 into the corresponding limiting holes respectively, the function of limiting the two when installing the installation disc 4 and the fixing disc 5 is achieved. By passing one end of the connecting rod 8 through the corresponding installation disc 4 and making the clamping block 10 contact one side of the installation disc 4 under the action of the tension spring, the function of pre-aligning between the fixing disc 5 and the installation disc 4 is further achieved. Then, the fixing disc 5 and the installation disc 4 are connected through bolts, avoiding manually fixing the position between the fixing disc 5 and the installation disc 4 when tightening the bolts.

[0019] In an embodiment of the present application, preferably, both ends of the rotating shaft are respectively fixedly connected to the support 7 through torsion springs 11, so that the connecting rod 8 is in a horizontal state under the action of the torsion springs 11 under normal conditions. Since the metal hose 3 can be deformed, when it is necessary to separate the clamping block 10 from the installation disc 4, by pressing one end of the connecting rod 8 in the metal hose 3 away from the clamping block 10, the clamping block 10 can be made to tilt, thus facilitating the separation of the clamping block 10 from the installation disc 4.

[0020] In an embodiment of the present application, preferably, one end of the clamping block 10 is an inclined surface, and the inclined surface of the clamping block 10 can be in contact with the corresponding installation disc 4. Through the setting of the inclined surface of the clamping block 10, it is convenient to pass one end of the connecting rod 8 through the corresponding installation disc 4.

[0021] In an embodiment of the present application, preferably, a sealing ring 12 is provided between the corresponding installation disc 4 and the fixing disc 5. Through the setting of the sealing ring 12, the sealing performance between the installation disc 4 and the fixing disc 5 can be enhanced.

[0022] In an embodiment of the present application, preferably, an L-shaped rod 13 is fixed on one of the fixed disks 5, and a benchmark 14 is fixed on the other fixed disk 5. A jack is formed on the L-shaped rod 13. The bottom of the benchmark 14 can pass through the jack. A positioning seat 15 is sleeved on the benchmark 14. By presetting the height positions of the fixed disks 5 at both ends of the metal hose 3, and by making the upper side of the positioning seat 15 contact with the lower side of the L-shaped rod 13, after the underground gas pipeline 1 settles, the settlement amount can be observed through the distance between the positioning seat 15 and the L-shaped rod 13.

[0023] In an embodiment of the present application, preferably, a fastening bolt 16 is threadedly connected to one side of the positioning seat 15, and one end of the fastening bolt 16 abuts against the surface of the benchmark 14. By tightening the fastening bolt 16, the position of the positioning seat 15 on the benchmark 14 is fixed.

[0024] When the utility model is in use, the building gas pipeline 2 is fixedly installed with an external building, and the underground gas pipeline 1 is buried underground. When installing the metal hose 3, by inserting a plurality of limiting posts 6 into the corresponding limiting holes respectively, the function of limiting the installation disk 4 and the fixed disk 5 when they are installed is achieved. A sealing ring 12 is arranged between the installation disk 4 and the fixed disk 5. By passing one end of the connecting rod 8 through the corresponding installation disk 4 and making the clamping block 10 abut against one side of the installation disk 4 under the action of the tension spring, a pre-alignment function is achieved between the fixed disk 5 and the installation disk 4. Then, the fixed disk 5 and the installation disk 4 are connected by bolts, avoiding manually fixing the position between the fixed disk 5 and the installation disk 4 when tightening the bolts. Tighten the fastening bolt 16 to fix the position of the positioning seat 15 on the benchmark 14. Preset the height positions of the fixed disks 5 at both ends of the metal hose 3, and make the upper side of the positioning seat 15 contact with the lower side of the L-shaped rod 13. After the underground gas pipeline 1 settles, the settlement amount can be observed through the distance between the positioning seat 15 and the L-shaped rod 13.

[0025] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present utility model and are not intended to limit them; although the present utility model has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: they can still modify the technical solutions described in the foregoing embodiments, or perform equivalent replacements for some of the technical features; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present utility model.

Claims

1. A gas pipeline anti-settlement device, comprising a metal hose (3) installed between an underground gas pipeline (1) and a building gas pipeline (2), characterized in that, The connecting ends of the underground gas pipe (1) and the building gas pipe (2) with the metal hose (3) are respectively fixedly connected with mounting plates (4). Fixing plates (5) are respectively fixed at both ends of the metal hose (3). The two fixing plates (5) are respectively connected to the corresponding mounting plates (4) by a plurality of bolts. A plurality of limiting holes arranged in an annular array are formed in the mounting plates (4). A plurality of limiting columns (6) corresponding to the limiting holes one by one are fixed on one side of the fixing plate (5). The plurality of limiting columns (6) can be slidably connected to the corresponding limiting holes. Two relatively arranged supports (7) are fixed inside the fixing plate (5). A connecting rod (8) is rotatably connected to the inside of the support (7) through a rotating shaft. One end of the connecting rod (8) is slidably connected with a sliding frame (9). One end of the connecting rod (8) is fixedly connected to the sliding frame (9) through a tension spring. A clamping block (10) is fixed on one side of the sliding frame (9). The clamping block (10) can be in contact with one side of the corresponding mounting plate (4).

2. The gas pipeline anti-settlement device according to claim 1, characterized in that: Both ends of the rotating shaft are respectively fixedly connected to the support (7) through torsion springs (11).

3. The gas pipeline anti-settlement device according to claim 1, characterized in that: One end of the clamping block (10) is an inclined surface. The inclined surface of the clamping block (10) can be in contact with the corresponding mounting plate (4).

4. The gas pipeline anti-settlement device according to claim 1, wherein: A sealing ring (12) is provided between the corresponding mounting plate (4) and the fixing plate (5).

5. The gas pipeline anti-settlement device according to claim 1, characterized in that: An L-shaped rod (13) is fixed on one of the fixing plates (5), and a benchmark (14) is fixed on the other fixing plate (5). A jack is formed in the L-shaped rod (13). The bottom of the benchmark (14) can pass through the jack. A positioning seat (15) is sleeved on the benchmark (14).

6. The gas pipeline anti-settlement device according to claim 5, characterized in that: A fastening bolt (16) is threadedly connected to one side of the positioning seat (15). One end of the fastening bolt (16) is in contact with the surface of the benchmark (14).