Desulfurization system pipeline purging device
By designing a pipeline purge device for the desulfurization system in the electrolytic aluminum desulfurization system, and using high-pressure air to purge the air inlet elbow of the dust collector, the problem of material blockage is solved, and the stable operation of the dust collector and the reduction of the risk of blockage is achieved.
Patent Information
- Application Number
- CN202422268408.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-14
- Publication Date
- 2025-07-25
- Estimated Expiration
- 2034-09-14
AI Technical Summary
In the existing electrolytic aluminum desulfurization system, due to the high friction force of the material inlet material during the flow of the dust collector, material blockage is prone to occur at the elbow, affecting the system operation.
A desulfurization system pipeline purging device is designed, including an air storage tank, an air pump, a rubber pipe and a purge pipe. The dust collector air inlet elbow is purged through high-pressure air, the flat tube is used to increase the purge pressure, and a sealing assembly is equipped to prevent materials from entering the pipe.
It effectively reduces the risk of blocking materials in the air inlet elbow of the dust collector, ensures the normal operation of the system, and prevents materials from entering the pipeline through sealing components, improving the reliability of the device.
Smart Images

Figure CN223145504U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of metallurgy, and particularly relates to a pipeline purging device for a desulfurization system. Background Art
[0002] Metallurgy is the process and technology of extracting metals or metal compounds from minerals and making metals into metal materials with certain properties by various processing methods. Metallurgy has a long development history, from the Stone Age to the subsequent Bronze Age, and then to the large-scale development of modern iron and steel smelting. The history of human development is integrated with the development history of metallurgy. The technologies of metallurgy mainly include pyrometallurgy, hydrometallurgy, and electrometallurgy. With the successful application of physical chemistry in metallurgy, metallurgy has evolved from a process to a science, and thus there is a metallurgical engineering major in universities.
[0003] The existing technologies have the following problems: In the existing electrolytic aluminum desulfurization system, during the flow of the incoming material of the dust collector, due to the large frictional force of the material, material blockage is likely to occur at the elbow, resulting in the obstruction of the incoming air of the dust collector and affecting the operation of the system. Summary of the Utility Model
[0004] To solve the problems raised in the above background art, the utility model provides a pipeline purging device for a desulfurization system, which has the characteristics of being able to purge the pipeline and not being easily blocked by materials.
[0005] To achieve the above object, the utility model provides the following technical solution: A pipeline purging device for a desulfurization system includes an air storage tank. One end of the air storage tank is provided with an air inflation pump, and the air inflation pump and the air storage tank are connected through an air charging pipe. A one-way valve is arranged on the air charging pipe. Several rubber pipes are arranged at the upper end of the air storage tank. One side of the rubber pipe is provided with a valve. One end of the valve close to the rubber pipe is provided with a connecting pipe, and the other end of the valve is provided with a purging pipe. A steel plate is arranged on the purging pipe. The other end of the purging pipe is provided with a connecting hopper. The other end of the connecting hopper is provided with a flat pipe, and one end of the flat pipe is provided with a sealing component.
[0006] Preferably, a pressure gauge is arranged on the front side of the upper end of the air storage tank. The pressure gauge is connected to the air storage tank through a thread, and a rubber sealing ring is arranged between the pressure gauge and the air storage tank.
[0007] Preferably, both between the steel plate and the purging pipe and between the connecting hopper and the purging pipe are welded by spot welding, and the flat pipe and the connecting hopper are of a welded integral structure.
[0008] Preferably, the sealing component includes a baffle plate, a folding plate, a rotating seat, a first magnetic block, a second magnetic block, and a limiting plate. Among them, two folding plates are arranged on one side of the upper end of the flat pipe. A rotating seat is arranged between the two folding plates. One end of the rotating seat is provided with a baffle plate. One end of the baffle plate is provided with a first magnetic block. A second magnetic block is arranged at a position corresponding to the first magnetic block at one end of the flat pipe. A limiting plate is arranged at the upper end of the folding plate.
[0009] Preferably, the swivel base is rotatably connected to the folding plate by a shaft pin, and the swivel base and the baffle are integrally welded.
[0010] Preferably, one side of the magnetic block is flush with the side of the baffle, and the other side of the magnetic block is flush with the side of the flat tube. The baffle is made of aluminum.
[0011] Compared with the prior art, the beneficial effects of the present utility model are as follows:
[0012] 1. By providing a purging pipe in the present utility model, a hole is opened at a suitable position of the inlet elbow of the dust collector, one end of the flat tube of the purging pipe is inserted, and the steel plate on the purging pipe is fixed to the inlet elbow of the dust collector by welding. The air inflation pump inflates the air storage tank through the air inflation pipe. When the valve is opened, the high-pressure air in the air storage tank enters the purging pipe through the rubber pipe. The flat tube at one end of the purging pipe blows air into the inlet elbow of the dust collector for purging. The setting of the flat tube can increase the purging pressure. By providing the purging pipe, the inside of the inlet elbow of the dust collector can be purged, reducing the risk of material blockage.
[0013] 2. By providing a sealing assembly in the present utility model, when the device is in use, the swivel base at one end of the baffle is blown by the blowing air of the flat tube and rotates on the folding plate. The baffle can be opened for purging. At the same time, the limiting plate at the upper end of the folding plate can limit the baffle. When the device is not in use, the baffle resets due to gravity. The first magnetic block on the baffle adsorbs the second magnetic block at one end of the flat tube, achieving the effect of adsorbing and fixing the baffle. The baffle can seal one end of the flat tube to prevent materials from entering the flat tube. Description of the Drawings
[0014] Figure 1 is a perspective view of the present utility model;
[0015] Figure 2 is a rear perspective view of the present utility model;
[0016] Figure 3 is a perspective view of the sealing assembly of the present utility model;
[0017] In the figure: 1. Air storage tank; 2. Sealing assembly; 21. Baffle; 22. Folding plate; 23. Swivel base; 24. First magnetic block; 25. Second magnetic block; 26. Limiting plate; 3. Air inflation pump; 4. Air inflation pipe; 5. Check valve; 6. Pressure gauge; 7. Purging pipe; 8. Steel plate; 9. Connecting hopper; 10. Flat tube; 11. Valve; 12. Connecting pipe; 13. Rubber pipe. Detailed Embodiment
[0018] Next, the technical solutions in the embodiments of the present invention will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. All other embodiments obtained by those of ordinary skill in the art based on the embodiments of the present invention without creative efforts shall fall within the protection scope of the present invention.
[0019] Embodiment 1
[0020] Please refer to Figures 1-3 , the present invention provides the following technical solutions: A pipeline purging device for a desulfurization system, including a gas storage tank 1, an air inflation pump 3 is arranged at one end of the gas storage tank 1, the air inflation pump 3 is connected to the gas storage tank 1 through an inflation pipe 4, a check valve 5 is arranged on the inflation pipe 4, a plurality of rubber pipes 13 are arranged at the upper end of the gas storage tank 1, a valve 11 is arranged on one side of the rubber pipe 13, a connecting pipe 12 is arranged at one end of the valve 11 close to the rubber pipe 13, a purging pipe 7 is arranged at the other end of the valve 11, a steel plate 8 is arranged on the purging pipe 7, a connecting hopper 9 is arranged at the other end of the purging pipe 7, a flat pipe 10 is arranged at the other end of the connecting hopper 9, and a sealing assembly 2 is arranged at one end of the flat pipe 10.
[0021] Specifically, a pressure gauge 6 is arranged at the front side of the upper end of the gas storage tank 1, the pressure gauge 6 is connected to the gas storage tank 1 through a thread, and a rubber sealing ring is arranged between the pressure gauge 6 and the gas storage tank 1.
[0022] By adopting the above technical solution, the pressure gauge 6 is provided to monitor the air pressure inside the gas storage tank 1. When the pressure inside the gas storage tank 1 is insufficient, the air inflation pump 3 can be turned on to inflate the gas storage tank 1.
[0023] Specifically, both between the steel plate 8 and the purging pipe 7 and between the connecting hopper 9 and the purging pipe 7 are welded by spot welding, and the flat pipe 10 and the connecting hopper 9 are of a welded integral structure.
[0024] By adopting the above technical solution, spot welding makes the connection between the steel plate 8 and the purging pipe 7 and between the connecting hopper 9 and the purging pipe 7 more firm, and the welded integral structure of the flat pipe 10 and the connecting hopper 9 is more durable.
[0025] When this embodiment is in use, when the desulfurization system pipeline purging device is in use, the device is installed at a suitable position. By setting the purging pipe 7, a hole is opened at a suitable position of the inlet elbow of the dust collector, one end of the flat pipe 10 of the purging pipe 7 is inserted, and then the steel plate 8 on the purging pipe 7 is fixed to the inlet elbow of the dust collector by welding. The air inflation pump 3 inflates the air storage tank 1 through the air inflation pipe 4. The valve 11 is opened, and the high-pressure air in the air storage tank 1 enters the purging pipe 7 through the rubber pipe 13. The flat pipe 10 at one end of the purging pipe 7 blows air into the inlet elbow of the dust collector for purging work. The setting of the flat pipe 10 can increase the purging pressure. By setting the purging pipe 7, the inside of the inlet elbow of the dust collector can be purged, reducing the risk of material blockage.
[0026] Embodiment 2
[0027] The difference between this embodiment and Embodiment 1 is that: the sealing assembly 2 includes a baffle 21, a folding plate 22, a rotating seat 23, a first magnetic block 24, a second magnetic block 25 and a limiting plate 26. Among them, two folding plates 22 are arranged on one side of the upper end of the flat pipe 10, a rotating seat 23 is arranged between the two folding plates 22, a baffle 21 is arranged at one end of the rotating seat 23, a first magnetic block 24 is arranged at one end of the baffle 21, and a second magnetic block 25 is arranged at a position corresponding to the first magnetic block 24 at one end of the flat pipe 10. A limiting plate 26 is arranged at the upper end of the folding plate 22.
[0028] By adopting the above technical solution, when the device is in use, the rotating seat 23 at one end of the baffle 21 is blown by the air blown by the flat pipe 10 and rotates on the folding plate 22. The baffle 21 is opened to carry out the purging work. At the same time, the limiting plate 26 at the upper end of the folding plate 22 can limit the baffle 21. When the device is not in use, the baffle 21 resets due to the action of gravity. The first magnetic block 24 on the baffle 21 adsorbs the second magnetic block 25 at one end of the flat pipe 10, achieving the effect of adsorbing and fixing the baffle 21. The baffle 21 can seal one end of the flat pipe 10 to prevent materials from entering the flat pipe 10.
[0029] Specifically, the rotating seat 23 is rotatably connected to the folding plate 22 through a shaft pin, and the rotating seat 23 and the baffle 21 are of an integrally welded structure.
[0030] By adopting the above technical solution, the rotating seat 23 can rotate on the folding plate 22, and the integrally welded structure of the rotating seat 23 and the baffle 21 is more solid.
[0031] Specifically, the side of the first magnetic block 24 and the side of the baffle 21 are flush, and the side of the second magnetic block 25 and the side of the flat pipe 10 are flush. The baffle 21 is made of an aluminum structure.
[0032] By adopting the above technical solution, the baffle 21 fits more closely to the flat pipe 10 after being closed. The baffle 21 made of an aluminum structure is lighter and more convenient to use.
[0033] When this embodiment is in use, by setting the sealing component 2, when the device is in use, the blowing air from the flat tube 10 blows the rotating seat 23 at one end of the baffle 21 to rotate on the folding plate 22, and the baffle 21 opens to carry out the purging work. At the same time, the limiting plate 26 at the upper end of the folding plate 22 can play a limiting role on the baffle 21. When the device is not in use, the baffle 21 resets due to gravity, and the magnet one 24 on the baffle 21 adsorbs with the magnet two 25 at one end of the flat tube 10, achieving the effect of adsorbing and fixing the baffle 21. The baffle 21 can seal one end of the flat tube 10 to prevent materials from entering the flat tube 10.
[0034] The air inflation pump 3 in the present utility model is a publicly known prior art, and the selected model is OTS-750x3-65L.
[0035] The working principle and usage process of the present utility model: When the desulfurization system pipeline purging device is in use, the device is installed at a suitable position. By setting the purging pipe 7, a hole is opened at a suitable position on the inlet elbow of the dust collector, one end of the flat tube 10 of the purging pipe 7 is inserted, and then the steel plate 8 on the purging pipe 7 is fixed to the inlet elbow of the dust collector by welding. The air inflation pump 3 inflates the air storage tank 1 through the air inflation pipe 4. The valve 11 is opened, and the high-pressure air in the air storage tank 1 enters the purging pipe 7 through the rubber pipe 13. The flat tube 10 at one end of the purging pipe 7 blows air into the inlet elbow of the dust collector to carry out the purging work. The setting of the flat tube 10 can increase the purging pressure. By setting the purging pipe 7, the inside of the inlet elbow of the dust collector can be purged, reducing the risk of material blockage. By setting the sealing component 2, when the device is in use, the blowing air from the flat tube 10 blows the rotating seat 23 at one end of the baffle 21 to rotate on the folding plate 22, and the baffle 21 opens to carry out the purging work. At the same time, the limiting plate 26 at the upper end of the folding plate 22 can play a limiting role on the baffle 21. When the device is not in use, the baffle 21 resets due to gravity, and the magnet one 24 on the baffle 21 adsorbs with the magnet two 25 at one end of the flat tube 10, achieving the effect of adsorbing and fixing the baffle 21. The baffle 21 can seal one end of the flat tube 10 to prevent materials from entering the flat tube 10.
[0036] Although the embodiments of the present utility model have been shown and described, for those of ordinary skill in the art, it can be understood that various changes, modifications, substitutions, and variations can be made to these embodiments without departing from the principles and spirit of the present utility model. The scope of the present utility model is defined by the appended claims and their equivalents.
Claims
1. A pipeline purging device for a desulfurization system, comprising a gas storage tank, characterized in that: One end of the gas storage tank is provided with an air inflation pump, which is connected to the gas storage tank through an air inflation pipe. A one-way valve is arranged on the air inflation pipe. Several rubber pipes are arranged at the upper end of the gas storage tank. A valve is arranged on one side of the rubber pipe. A connecting pipe is arranged at one end of the valve close to the rubber pipe, and a purging pipe is arranged at the other end of the valve. A steel plate is arranged on the purging pipe, and a connecting hopper is arranged at the other end of the purging pipe. A flat pipe is arranged at the other end of the connecting hopper, and a sealing component is arranged at one end of the flat pipe.
2. The pipe purging device for a desulfurization system according to claim 1, wherein: A pressure gauge is arranged on the front side of the upper end of the gas storage tank. The pressure gauge is connected to the gas storage tank through a thread, and a rubber sealing ring is arranged between the pressure gauge and the gas storage tank.
3. The pipeline purging device for a desulfurization system according to claim 1, characterized in that: Both the steel plate and the purging pipe and the connecting hopper and the purging pipe are welded by spot welding. The flat pipe and the connecting hopper are of a welded integral structure.
4. A pipeline purging device for a desulfurization system according to claim 1, characterized in that: The sealing component includes a baffle plate, a folding plate, a rotating seat, a first magnetic block, a second magnetic block and a limiting plate. Among them, two folding plates are arranged on one side of the upper end of the flat pipe. A rotating seat is arranged between the two folding plates. A baffle plate is arranged at one end of the rotating seat. A first magnetic block is arranged at one end of the baffle plate. A second magnetic block is arranged at a position corresponding to the first magnetic block at one end of the flat pipe. A limiting plate is arranged at the upper end of the folding plate.
5. A pipeline purging device for a desulfurization system according to claim 4, characterized in that: The rotating seat and the folding plate are rotatably connected through a pin. The rotating seat and the baffle plate are of a welded integral structure.
6. The pipe purging device for a desulfurization system according to claim 4, wherein: The side edges of the first magnetic block and the baffle plate and the side edges of the second magnetic block and the flat pipe are flush. The baffle plate is made of an aluminum structure.