Concrete pouring tumbling barrel tool
By designing the concrete casting string tool for adjusting flexible conduits and brackets, the problems of quality and safety hazards of exterior wall structural columns are solved, and the rapid and efficient concrete casting effect is achieved.
Patent Information
- Application Number
- CN202421994006.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2025-08-08
- Estimated Expiration
- 2034-08-16
AI Technical Summary
In specific environments, it is difficult to pump concrete pouring of exterior wall structural columns, resulting in difficult to ensure the pouring quality, slow progress and high safety risks.
A concrete casting string tool including a loading hopper and a flexible conduit is designed. The flexible conduit is used to transfer the concrete into the pouring hole in multiple directions, and the position of the loading hopper is adjusted in combination with the bracket to improve the transfer performance.
The pouring speed and quality of exterior walls and blind corner concrete has been improved, manpower demand has been reduced, construction efficiency has been improved, and safety risks have been reduced.
Smart Images

Figure CN223202738U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to a concrete pouring barrel tool. Background Art
[0002] The exterior wall is flush with the outside of the structural beam, so the concrete structural columns connected to the concrete structural beam need to be poured on the outside of the wall; however, in certain environments, concrete pouring cannot be achieved by pumping, and manual labor is required to stand on the external scaffolding and shovel the concrete into the pouring hole one shovel at a time. In this way, the quality of the concrete for pouring the exterior wall structural columns is difficult to guarantee, the progress will be extremely slow, and the safety risks are very large. Utility Model Content
[0003] In order to solve the above technical problems, the utility model provides a concrete pouring string barrel tool.
[0004] The technical solution of the present utility model is achieved as follows:
[0005] A concrete pouring string barrel tool comprises a charging hopper and a conduit. The charging hopper is in the shape of a funnel with an open top. One end of the conduit is connected to the bottom end of the charging hopper, and the conduit is a flexible tube.
[0006] Furthermore, a hopper connecting pipe is provided at the center of the bottom end of the charging hopper, and the hopper connecting pipe is provided with its bottom end tilted to one side, and one end of the conduit is connected to the hopper connecting pipe.
[0007] Furthermore, one end of the conduit is detachably mounted on the bottom end of the charging hopper via a pipe clamp.
[0008] Furthermore, the conduit is a PVC hose.
[0009] Furthermore, it also includes a bracket, and the upper and lower ends of the bracket are configured to be able to be covered with an annular structure on the outer surface of the charging hopper.
[0010] The utility model has the following beneficial effects:
[0011] 1. This application places a concrete pouring string on a reliable platform, and transfers concrete to the pouring hole in multiple directions through a loading hopper and a flexible conduit, thereby improving the pouring speed and quality of exterior wall concrete and dead corner concrete that are difficult to pour mechanically or manually, while ensuring construction safety.
[0012] 2. This application reduces manpower, improves construction efficiency, is simple to operate, and can quickly complete the pouring of secondary structures and dead corner concrete. At the same time, it ensures the workability of concrete, achieves the quality control goals of concrete pouring, and reduces the safety risks of manual coordination during the pouring process. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a structural diagram of the present utility model.
[0014] Figure 2 It is a working schematic diagram of the utility model.
[0015] Figure 3 It is a schematic cross-sectional view of the working of the utility model.
[0016] In the figure: 1- bracket, 2- charging hopper, 3- pipe clamp, 4- guide tube. DETAILED DESCRIPTION
[0017] The following is a clear and complete description of the technical solutions in the embodiments of the present invention. Obviously, the embodiments described are only a part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative efforts are within the scope of protection of the present invention.
[0018] like Figures 1 to 3 As shown, this embodiment provides a concrete pouring string barrel tool, comprising a charging hopper 2 and a conduit 4. The charging hopper 2 is funnel-shaped with an open top, and one end of the conduit 4 is connected to the bottom end of the charging hopper 2. The conduit 4 is a flexible tube. By providing the flexible tube as a concrete transfer component and utilizing its bendability, the flexible tube can better transfer concrete to the pouring hole, thereby improving the pouring speed and quality of exterior wall concrete and blind corner concrete, which are difficult to pour mechanically or manually, while also ensuring construction safety.
[0019] As another embodiment of the present application, a hopper pipe is provided at the bottom center of the charging hopper 2. The hopper pipe is arranged with its bottom end tilted to one side, and one end of the conduit 4 is connected to the hopper pipe.
[0020] Specifically, by setting up a hopper pipe, during the process of pouring concrete, by adjusting the position of the charging hopper 2, the bottom end of the hopper pipe is oriented in the same direction as the bending direction of the conduit 4, which can reduce the bending degree of the conduit 4. At the same time, the concrete in the charging hopper 2 can better enter the conduit 4, thereby improving the transfer performance of the concrete.
[0021] As another embodiment of the present application, one end of a conduit 4 is detachably mounted to the bottom end of the hopper 2 via a pipe clamp 3. The use of the pipe clamp 3 provides a detachable connection between the conduit 4 and the hopper pipe, further facilitating the installation and removal of the conduit 4. Specifically, at least three pipe clamps 3 are provided. The use of multiple pipe clamps 3 enhances the stability and strength of the conduit 4 mounted to the hopper pipe. The pipe clamps 3 are made of steel.
[0022] The conduit 4 is a PVC tube, specifically, the conduit 4 is a PVC steel hose, specifically a DN100 steel hose or a rubber hose of the same specification, with a tube wall thickness of ≥5 mm.
[0023] As another embodiment of the present application, it also includes a bracket 1, and the upper and lower ends of the bracket 1 are configured to be able to fit over the annular structure on the outer surface of the charging hopper 2. Specifically, when using the concrete pouring string barrel tool of the present application, the charging hopper 2 can be directly placed on the top annular structure of the bracket 1.
[0024] The upper and lower ring structures of the bracket 1 are connected by vertical members, which can be made of steel bars or steel pipes. By placing the charging hopper 2 directly on the bracket 1, the direction of the charging hopper 2 can be easily adjusted to achieve the adjustment of the direction of the hopper pipe.
[0025] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A concrete pouring string barrel tool, characterized in that: The invention comprises a charging hopper (2) and a conduit (4), wherein the charging hopper (2) is in the shape of a funnel with an open top, one end of the conduit (4) is connected to the bottom end of the charging hopper (2), and the conduit (4) is a flexible tube; a hopper pipe is provided at the center of the bottom end of the charging hopper (2), the hopper pipe is provided in a state in which the bottom end is inclined to one side, and one end of the conduit (4) is connected to the hopper pipe.
2. A concrete pouring string barrel tool as claimed in claim 1, characterized in that: One end of the conduit (4) is detachably mounted on the bottom end of the charging hopper (2) via a pipe clamp (3).
3. A concrete pouring string barrel tool as claimed in claim 2, characterized in that: The conduit (4) is a PVC hose.
4. A concrete pouring string barrel tool as claimed in claim 1 or 3, characterized in that: It also includes a bracket (1), wherein the upper and lower ends of the bracket (1) are configured to form an annular structure that can be sleeved onto the outer surface of the charging hopper (2).