Device for dragging bottom-passing steel cable in sunken ship salvage
By connecting multiple bottom-crossing steel cable traction units through the submarine trenching main unit, the problem of only being able to insert one steel cable at a time in the existing technology is solved, multiple steel cables can be quickly salvaged, and the efficiency and safety of shipwreck salvage operations are improved.
Patent Information
- Application Number
- CN202422665993.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-01
- Publication Date
- 2025-09-05
- Estimated Expiration
- 2034-11-01
AI Technical Summary
In the existing technology, only one steel cable can be inserted at a time during shipwreck salvage operations, resulting in repeated construction, low efficiency, increased costs and diver safety risks, and affecting the progress of operations in emergency situations.
A submarine trenching main unit is used to connect multiple bottom cable traction units, including a guide unit, an auxiliary trenching unit and a bottom cable traction unit, to achieve the traction operation of towing multiple bottom cables at one time.
It improves the efficiency of shipwreck salvage operations, reduces the number of repeated operations, shortens the construction period, reduces costs and risks, and improves the economic efficiency of salvage projects.
Smart Images

Figure CN223302860U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of underwater salvage equipment, in particular to a device for towing a bottom-crossing steel cable for salvaging a sunken ship. Background Art
[0002] In existing shipwreck salvage operations, the primary method for towing a bottom-crossing cable is to use a thin guide cable. This guide cable must pass through a pre-prepared jack hole on the seabed, a hole designed specifically for salvage operations. A thicker bottom-crossing cable is connected to the end of the guide cable. As the guide cable is pulled through the jack hole and reaches the other side of the shipwreck, the bottom-crossing cable is towed.
[0003] While this traditional over-the-bottom cable-dragging method is technically capable of laying cables, it has some significant limitations. The most prominent issue is that this method can only thread one cable at a time. This means that if multiple cables need to be laid to enhance salvage stability and efficiency, the entire cable-threading process must be repeated multiple times. This not only significantly increases construction costs but also significantly prolongs underwater operations. In this scenario, divers and salvage equipment must perform multiple underwater maneuvers, which is not only inefficient but also increases diver safety risks. Furthermore, since only one cable can be threaded at a time, this limits the progress of salvage operations. Especially in emergency or complex situations, this inefficient method can seriously impact the smooth progress of the salvage mission.
[0004] Therefore, the industry urgently needs a new technology or method that can achieve the towing of multiple bottom cables at one time, thereby significantly improving operational efficiency, reducing costs, and shortening underwater operation time to improve the safety and economic benefits of the overall salvage operation. Utility Model Content
[0005] The purpose of this application is to overcome the above technical deficiencies and propose a device for dragging bottom steel cables for shipwreck salvage, so as to solve the technical problem in the prior art that it is difficult to drag multiple bottom steel cables at one time for rapid salvage.
[0006] In order to achieve the above technical objectives, this application adopts the following technical solutions:
[0007] The present application provides a device for towing a bottom cable for shipwreck salvage, comprising a submarine trenching main unit, a guide unit, an auxiliary trenching unit, and at least two bottom cable towing units:
[0008] Subsea trenching main unit;
[0009] A guide unit, the guide unit being installed at the head of the seabed trenching main unit;
[0010] Auxiliary trenching units, the auxiliary trenching units are installed on the seabed trenching main unit and are located on both sides of the guide unit;
[0011] At least two bottom-crossing steel cable traction units are installed on both sides of the seabed trenching main unit.
[0012] In some embodiments of the present application, the submarine trenching main unit includes a main arm and at least two extension arms, the head end of each extension arm is connected to the side wall of the main arm, the extension arm extends laterally and rearwardly from the main arm, and the angle between the main arm and the extension arm is an acute angle.
[0013] In some embodiments of the present application, the guide unit includes a guide drill bit, which is installed on the head of the main arm and is used for expanding the hole and guiding the guide cable.
[0014] In some embodiments of the present application, the guide unit includes a guide cable eye, which is installed on the head of the main arm and is used to fix the guide cable.
[0015] In some embodiments of the present application, the auxiliary trenching unit includes a trenching tool, which is installed on the extension arm with the blade facing forward and is used for cutting seabed geology.
[0016] In some embodiments of the present application, the auxiliary trenching unit further includes a mud flushing nozzle, which is mounted on the extension arm and opens forward, and is used for impacting and removing seabed geology.
[0017] In some embodiments of the present application, the mud flushing nozzles on the two extension arms are symmetrically distributed, the trenching tools on the two extension arms are symmetrically distributed, and the mud flushing nozzles and the trenching tools on the same extension arm are staggered and spaced apart.
[0018] In some embodiments of the present application, the auxiliary ditching unit further includes a high-pressure pipe, which is installed at the tail of the main arm and is respectively connected to the plurality of mud flushing nozzles.
[0019] In some embodiments of the present application, the bottom cable opening traction unit includes a traction arm, and a side wall of the traction arm is connected to the end of the extension arm.
[0020] In some embodiments of the present application, the bottom cable opening traction unit further includes a bottom cable eye, and the bottom cable eye is installed at the tail of the traction arm.
[0021] Compared with the existing technology, the technical solution provided by this application brings the following beneficial technical effects:
[0022] This embodiment of the present application utilizes a submarine trenching main unit connected to multiple bottom-crossing cable traction units, enabling the simultaneous towing of multiple bottom-crossing cables. This significantly improves the efficiency of shipwreck salvage operations, reduces the number of repetitive operations, and shortens the overall construction period. This device reduces the manpower, material resources, and time required during the construction process. This effectively controls the high costs of underwater operations and improves the economic efficiency of salvage projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the technical solutions in this application, the following briefly introduces the drawings required for use in the embodiments:
[0024] Figure 1 This is a schematic structural diagram of a device for towing a bottom-crossing steel cable for salvaging a sunken ship, provided in an embodiment of the present application;
[0025] Figure 2 This is a structural schematic diagram of a submarine trenching main unit provided in an embodiment of the present application;
[0026] Figure 3 This is a schematic structural diagram of a mud flushing nozzle provided in an embodiment of the present application;
[0027] Figure 4 This is a structural schematic diagram of a bottom cable traction unit provided in an embodiment of the present application.
[0028] Reference numerals:
[0029] Subsea trenching main unit 1, main arm 11, extension arm 12, guide drill bit 2, guide cable lifting ring 3, trenching tool 4, mud flushing nozzle 5, high-pressure pipeline 6, traction arm 7, bottom cable lifting ring 8. DETAILED DESCRIPTION
[0030] In order to make the purpose, technical solutions and advantages of this application more clearly understood, the present application is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain this application and are not intended to limit this application.
[0031] Those skilled in the art will understand that in this specification, the wording "including" is an open-ended expression, which means that the described features exist but does not exclude other features. The directional words "up", "down", "left", "right", etc. are exemplary directions based on the drawings. Features defined as "first" and "second" implicitly include one or more of the features. Singular expressions can also be used in the plural. "Multiple" means two or more. The terms "installed", "connected", and "connected" can be fixed connections, detachable connections, or integrated connections; they can be directly connected, or indirectly connected through an intermediate medium, or they can be internal connections between two elements. In addition, "connected" can include wireless connections.
[0032] The purpose of this application is to overcome the above technical deficiencies and propose a device for dragging bottom steel cables for shipwreck salvage, so as to solve the technical problem in the prior art that it is difficult to drag multiple bottom steel cables at one time for rapid salvage.
[0033] In order to achieve the above technical objectives, this application adopts the following technical solutions:
[0034] The present application provides a device for dragging a bottom steel cable for salvaging a sunken ship, such as Figure 1 As shown, Figure 1 It is a structural schematic diagram of a device for dragging a bottom steel cable for salvaging a sunken ship provided in an embodiment of the present application.
[0035] A device for towing a bottom-crossing steel cable for shipwreck salvage comprises a main submarine trenching unit 1, a guide unit, an auxiliary trenching unit, and at least two bottom-crossing steel cable towing units:
[0036] Subsea trenching main unit 1;
[0037] A guide unit, the guide unit being installed at the head of the seabed trenching main unit 1;
[0038] Auxiliary trenching units, which are installed on the seabed trenching main unit 1 and located on both sides of the guide unit;
[0039] At least two bottom-crossing steel cable traction units are installed on both sides of the seabed trenching main unit 1.
[0040] The present embodiment utilizes a submarine trenching main unit 1 connected to multiple bottom-crossing cable traction units, enabling the simultaneous towing of multiple bottom-crossing cables. This significantly improves the efficiency of shipwreck salvage operations, reduces the number of repetitive operations, and shortens the overall construction period. This device reduces the manpower, material resources, and time required during the construction process. This effectively controls the high costs of underwater operations and improves the economic efficiency of salvage projects.
[0041] The present embodiment utilizes a submarine trenching main unit 1 connected to multiple bottom-crossing cable traction units, enabling the simultaneous towing of multiple bottom-crossing cables. This significantly improves the efficiency of shipwreck salvage operations, reduces the number of repetitive operations, and shortens the overall construction period. This device reduces the manpower, material resources, and time required during the construction process. This effectively controls the high costs of underwater operations and improves the economic efficiency of salvage projects.
[0042] It is worth mentioning that, in this embodiment, the number of bottom cable traction units is mainly introduced as two. In fact, the number of bottom cable traction units can be three or even more, which also falls within the protection scope of this application.
[0043] like Figure 2 As shown, Figure 2 It is a structural schematic diagram of a submarine trenching main unit 1 provided in an embodiment of the present application.
[0044] In some embodiments of the present application, the submarine trenching main unit includes a main arm 11 and at least two extension arms 12, the head end of each extension arm 12 is connected to the side wall of the main arm 11, the extension arm 12 extends from the main arm 11 to the side and rear, and the angle between the main arm 11 and the extension arm 12 is an acute angle.
[0045] In this embodiment, the combined design of the main boom 11 and extension boom 12 increases the contact area and digging force of the trenching machine, making submarine trenching operations more efficient and enabling the rapid creation of a trench suitable for the passage of a steel cable. The lateral and rearward placement of the extension boom 12 effectively reduces soil resistance encountered during trenching, making the trenching process smoother and reducing energy consumption. The presence of the extension boom 12 enables the trenching unit to achieve deeper excavation depths and wider trench widths, meeting the requirements of various shipwreck salvage operations.
[0046] In some embodiments of the present application, the guide unit includes a guide drill bit 2, which is installed on the head of the main arm 11 and is used for expanding the hole and guiding the guide cable.
[0047] In this embodiment, the pilot drill bit 2, mounted on the head of the main arm 11, precisely controls the direction of the guide cable's installation, ensuring it follows the intended path and minimizing operational difficulties caused by directional deviations. The pilot drill bit 2 has both drilling and reaming functions, further expanding the hole in the created trench to provide more space for subsequent cable installation and ensure smooth cable passage.
[0048] In some embodiments of the present application, the guide unit includes a guide cable eye 3 , which is installed at the head of the main arm 11 for fixing the guide cable.
[0049] In this embodiment, the guide cable lifting ring 3 can stably fix the guide cable to prevent it from moving or loosening during operation, thereby ensuring the accurate position of the guide cable on the seabed.
[0050] like Figure 3 As shown, Figure 3 It is a structural schematic diagram of a mud flushing nozzle 5 provided in an embodiment of the present application.
[0051] In some embodiments of the present application, the auxiliary trenching unit includes a trenching tool 4, which is installed on the extension arm 12 with the blade facing forward and is used for cutting seabed geology.
[0052] In this embodiment, the trenching cutter 4 has its blade facing forward, directly facing the seabed geology, enabling efficient cutting and accelerating the trenching process. By cutting the seabed geology, the trenching cutter 4 can reduce the resistance of the seabed soil to the seabed trenching main unit 1, making the trenching operation smoother.
[0053] In some embodiments of the present application, the auxiliary trenching unit further includes a mud flushing nozzle 5 , which is mounted on the extension arm 12 and opens forward, and is used for impacting and removing seabed geology.
[0054] In this embodiment, by providing a trenching tool 4 and a mud flushing nozzle 5, the hard soil on the seabed can be quickly loosened and removed, so that the device can smoothly pass through the shipwreck and sit on the seabed; the use of the mud flushing nozzle 5 can reduce the resistance of the seabed soil to the seabed trenching main unit 1, thereby improving the efficiency of the trenching operation.
[0055] In some embodiments of the present application, the mud flushing nozzles 5 on the two extension arms 12 are symmetrically distributed, the trenching tools 4 on the two extension arms 12 are symmetrically distributed, and the mud flushing nozzles 5 and the trenching tools 4 on the same extension arm 12 are staggered and spaced apart.
[0056] In this embodiment, the symmetrically distributed mud flushing nozzles 5 and trenching cutters 4 can simultaneously act on the seabed geology, reducing operation time and improving overall efficiency. The symmetrical distribution design ensures balanced and stable operation, reducing imbalance problems caused by excessive work intensity on one side. The staggered distribution design helps minimize disturbance to the seabed geology and avoids excessive damage caused by continuous scouring or cutting.
[0057] In some embodiments of the present application, the auxiliary ditching unit further includes a high-pressure pipe 6 , which is installed at the tail of the main arm 11 and is respectively connected to the multiple mud flushing nozzles 5 .
[0058] In this embodiment, the high-pressure pipe 6 is used to deliver high-pressure water to the mud flushing nozzle 5. The internal flow channel of the submarine trenching main unit 1 and the tail pipe form a water supply, which can realize the water supply to the mud flushing nozzle 5 and form a jet to remove the hard seabed.
[0059] like Figure 4 As shown, Figure 4 This is a structural schematic diagram of a bottom cable traction unit provided in an embodiment of the present application.
[0060] In some embodiments of the present application, the bottom cable opening traction unit includes a traction arm 7 , and a side wall of the traction arm 7 is connected to the end of the extension arm 12 .
[0061] In this embodiment, the integrated design allows the operator to control trenching and cable traction simultaneously, reducing the complexity and difficulty of the operation.
[0062] In some embodiments of the present application, the bottom cable opening traction unit further includes a bottom cable eye 8 , and the bottom cable eye 8 is installed at the tail of the traction arm 7 .
[0063] In this embodiment, the bottom cable eye 8 is located at the tail end of the traction arm 7, which can more effectively secure and pull the bottom cable, ensuring its stable laying on the seabed. By securing the bottom cable, it can reduce the risk of collision and friction with seabed obstacles or shipwrecks during seabed operations, reducing the risk of damage to the bottom cable.
[0064] Compared with the existing technology, the technical solution provided by this application brings the following beneficial technical effects:
[0065] The present embodiment utilizes a submarine trenching main unit 1 connected to multiple bottom-crossing cable traction units, enabling the simultaneous towing of multiple bottom-crossing cables. This significantly improves the efficiency of shipwreck salvage operations, reduces the number of repetitive operations, and shortens the overall construction period. This device reduces the manpower, material resources, and time required during the construction process. This effectively controls the high costs of underwater operations and improves the economic efficiency of salvage projects.
[0066] Those skilled in the art will understand that the various operations, methods, steps, measures, and schemes in the processes discussed in this application may be alternated, changed, rearranged, decomposed, combined, or deleted.
[0067] The specific implementation methods of the present application described above do not limit the scope of protection of the present application. Any other corresponding changes and modifications made based on the technical concept of the present application should be included in the scope of protection of the claims of the present application.
Claims
1. A device for dragging a bottom-crossing steel cable for salvaging a sunken ship, characterized in that: include: Subsea trenching main unit; A guide unit, the guide unit being installed at the head of the seabed trenching main unit; Auxiliary trenching units, the auxiliary trenching units are installed on the seabed trenching main unit and are located on both sides of the guide unit; At least two bottom-crossing steel cable traction units are installed on both sides of the seabed trenching main unit.
2. The device for dragging a bottom-crossing steel cable for salvaging a sunken ship according to claim 1, characterized in that: The submarine trenching main unit includes a main arm and at least two extension arms, the head end of each extension arm is connected to the side wall of the main arm, the extension arm extends laterally and rearwardly from the main arm, and the angle between the main arm and the extension arm is an acute angle.
3. The device for dragging a bottom-crossing steel cable for salvaging a sunken ship according to claim 2, characterized in that: The guide unit includes a guide drill bit, which is installed on the head of the main arm and is used for expanding the hole and guiding the guide cable.
4. The device for dragging a bottom-crossing steel cable for salvaging a sunken ship according to claim 2, characterized in that: The guide unit includes a guide cable lifting ring, which is installed on the head of the main arm and is used to fix the guide cable.
5. The device for dragging a bottom-crossing steel cable for salvaging a sunken ship according to claim 2, characterized in that: The auxiliary trenching unit includes a trenching tool, which is installed on the extension arm with the blade facing forward and is used for cutting seabed geology.
6. The device for dragging a bottom-crossing steel cable for salvaging a sunken ship according to claim 5, characterized in that: The auxiliary trenching unit further comprises a mud flushing nozzle, which is mounted on the extension arm and opens toward the front, and is used for impacting and removing seabed geology.
7. The device for dragging a bottom-crossing steel cable for salvaging a sunken ship according to claim 6, characterized in that: The mud flushing nozzles on the two extension arms are symmetrically distributed, the trenching cutters on the two extension arms are symmetrically distributed, and the mud flushing nozzles and the trenching cutters on the same extension arm are staggered and spaced apart.
8. The device for dragging a bottom-crossing steel cable for salvaging a sunken ship according to claim 6, characterized in that: The auxiliary ditching unit further includes a high-pressure pipeline, which is installed at the tail of the main arm and is respectively connected to the multiple mud flushing nozzles.
9. The device for dragging a bottom-crossing steel cable for salvaging a sunken ship according to claim 2, characterized in that: The bottom cable opening traction unit includes a traction arm, and a side wall of the traction arm is connected to the end of the extension arm.
10. The device for dragging a bottom-crossing steel cable for salvaging a sunken ship according to claim 9, characterized in that: The bottom cable opening traction unit further comprises a bottom cable lifting ring, and the bottom cable lifting ring is installed at the tail of the traction arm.