Maintenance device for construction of prefabricated T beam in summer and winter
By designing a combination device of supporting scaffolding and gantry, equipped with water supply pipes and constant temperature lamps, the problem of low maintenance efficiency of traditional prefabricated T-beams was solved, uniform moisture and temperature control was achieved, and construction quality and efficiency were improved.
Patent Information
- Application Number
- CN202422646080.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-31
- Publication Date
- 2025-10-14
- Estimated Expiration
- 2034-10-31
AI Technical Summary
Traditional precast T-beam curing methods are inefficient and difficult to ensure uniform moisture supply and temperature control, especially in low temperatures in winter, which affects the quality of concrete curing.
A maintenance device is designed, which includes multiple supporting scaffolds and gantry frames, and is equipped with water supply pipes and constant temperature lamps. The water supply pipes and constant temperature lamps are arranged in the same direction as the gantry frames and are staggered. Galvanized steel pipes are used as risers, and a collection tank is provided at the bottom. Universal wheels are used for easy movement.
It achieves automated and uniform moisture and temperature control, improves curing efficiency, ensures that prefabricated T-beams are cured under suitable conditions, reduces resource waste and safety hazards, and improves construction quality and efficiency.
Smart Images

Figure CN223431781U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to the technical field of precast beam maintenance, especially to a kind of maintenance device for prefabricated T beam summer and winter construction. BACKGROUND
[0002] In bridge engineering, the upper structure is usually pre-processed before the lower structure construction is completed, such as prefabricated T beam and prefabricated box beam. After the lower structure construction is completed, the upper structure can be assembled on the lower structure, thereby greatly shortening the construction period of the entire project. However, after the prefabricated T beam is poured, it needs to be cured for about 28 days to ensure that the concrete reaches the required strength of the design.
[0003] Traditionally, the curing of prefabricated T beam and box beam after pouring is achieved by covering insulation materials such as film or geotextile, supplemented by manual watering. This method has several obvious disadvantages:
[0004] Low efficiency: manual watering is not only time-consuming and labor-intensive, but also difficult to ensure that each prefabricated component receives uniform and sufficient water supply in large-scale construction sites, especially when there are many prefabricated components, some sides may be missed or insufficiently watered, which can cause the concrete surface to dry too quickly, resulting in cracks and affecting the overall quality of the structure.
[0005] Temperature control difficulty: especially in low temperature conditions in winter, the traditional covering method is difficult to effectively maintain the temperature of the prefabricated beam after demolding. The hydration heat inside the concrete will evaporate quickly, causing the surface temperature to fluctuate greatly and unable to maintain within a stable range. This temperature instability can affect the solidification process of the concrete, making it difficult to reach the required tensile strength and elastic modulus within the specified time.
[0006] Quality problem: if the concrete cannot harden normally in a suitable environment, it may lead to slow or even stop growth of late strength, thereby seriously affecting the construction quality and progress. SUMMARY
[0007] To solve the technical problems of low efficiency and temperature control difficulty of existing curing methods, the utility model provides a curing device for prefabricated T beam summer and winter construction, which improves curing efficiency and effectively controls temperature and humidity.
[0008] The technical solution adopted by the utility model to solve its technical problems is:
[0009] The cam is connected to the support frame of the lifting post by the spring, and the support frame is connected to the support frame by the spring.
[0010] Furthermore, the length directions of the water supply pipe and the constant temperature lamp are consistent with the arrangement direction of the multiple portal frames.
[0011] Furthermore, at least two water supply pipes and at least two constant temperature lamps are provided on the vertical pipe on one side of the gantry, and the water supply pipes and the constant temperature lamps are arranged at intervals in the vertical direction.
[0012] Furthermore, there are three water supply pipes and three thermostatic lamps, and the water supply pipes and the thermostatic lamps are arranged in a staggered manner.
[0013] Furthermore, the riser is a galvanized steel pipe.
[0014] Furthermore, a collection tank for recovering spray water is provided at the bottom of the gantry.
[0015] Furthermore, the lower ends of the two vertical pipes of each gantry are provided with universal wheels.
[0016] The beneficial effects of the utility model are:
[0017] 1. The design creates a movable and structurally stable curing environment through the combination of multiple supporting scaffolds and multiple portal frames. Connecting rods and cross-links ensure the stability of the overall frame, while the design of slides and pins allows the entire device to be freely extended and retracted according to actual needs, enhancing flexibility. This not only facilitates the transfer of equipment between different sites, but also facilitates the adjustment of coverage according to the actual size of the prefabricated T-beams. In addition, the provision of water supply pipes and constant temperature lamps ensures that the concrete can receive sufficient water supply and appropriate temperature control during the curing process. This type of automated spraying and heat preservation curing solves the problem of low efficiency of traditional manual curing. When the temperature is low in winter, the constant temperature lamps ensure that the prefabricated T-beams are cured at an appropriate temperature, which helps to improve the quality of the final product.
[0018] 2. Direction consistency of water supply pipes and constant temperature lamps: The water supply pipes and constant temperature lamps are arranged along the arrangement direction of the portal frames, which helps to evenly distribute water resources and heat energy, thereby creating a balanced humidity and temperature environment throughout the entire curing area, avoiding local over-wetting or over-drying.
[0019] 3. Vertical and spaced arrangement of multiple water supply pipes and constant temperature lamps: At least two water supply pipes and constant temperature lamps are provided and are spaced along the vertical direction, which can further optimize the water mist coverage range and heat transfer efficiency, ensuring that each precast T beam can receive sufficient moisture and suitable temperature.
[0020] 4. The design of three water supply pipes and constant temperature lamps staggered arrangement not only improves the uniformity of water mist and heat distribution throughout the entire curing area, ensuring that the precast T beam is uniformly hardened under ideal humidity and temperature conditions, avoiding quality problems caused by local over-wetting or over-drying; at the same time, this layout effectively reduces the possibility of direct impact of the spray flow on the constant temperature lamp, protecting the heating element and improving the reliability and efficiency of the system. In addition, staggered distribution helps to achieve balance of humidity and temperature throughout the entire curing area, optimizing resource utilization, saving water resources and improving energy efficiency.
[0021] 5. Using galvanized steel pipe as standpipe material: Galvanized steel pipe has good corrosion resistance and mechanical strength, can withstand long-term use in outdoor environment, and reduces maintenance cost and prolongs equipment service life.
[0022] 6. Collecting tank for recycling spray water: The bottom is provided with a collecting tank to effectively recycle the sprayed water, which not only saves water resources, but also prevents safety hazards caused by accumulated water on site, and also maintains the cleanliness of the construction site.
[0023] 7. Universal wheel design: The lower end of each standpipe is equipped with universal wheels, making the entire curing device easy to move, allowing easy adjustment of position according to actual needs, enhancing the flexibility and adaptability of the device, which is very helpful for improving construction efficiency. BRIEF DESCRIPTION OF DRAWINGS
[0024] Fig. 1 is a structural schematic view of the curing device for precast T beam construction in summer and winter of the utility model;
[0025] Fig. 2 is a structural schematic view of multiple portal frames arranged at intervals;
[0026] In the figure, 1 is a standpipe, 2 is a connecting rod, 3 is a connecting rod, 4 is a sliding groove, 5 is a pin, 6 is a support shed frame, 61 is a horizontal rod, 62 is an arc-shaped support rod, 63 is a vertical rod, 7 is a water supply pipe, 8 is a spray head, 9 is a constant temperature lamp, 10 is a collecting tank, 11 is a universal wheel, and 12 is a precast T beam. DETAILED DESCRIPTION
[0027] In order to make the purpose, technical scheme and advantages of the embodiments of the present application more clear, the present application is further described below with reference to the drawings.
[0028] First of all, it needs to be pointed out that the technical scheme of the embodiments of the present application is clearly and completely described, the described embodiments are part of the embodiments of the present application, not a limitation of the present application, based on the embodiments in the present application, all other embodiments obtained by the ordinary skilled in the art without doing creative work belong to the scope of protection of the present application.
[0029] In the description of the present application, it is understood that the terms "first", "second", "upper", "lower", "left", "right", "inner", "outer", "axial" or "radial" indicate the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present application, and are not intended to indicate or imply that the devices or elements referred to must have a particular orientation structure and operation, therefore it cannot be understood as a limitation of the present application.
[0030] It should be noted that in the present application, unless otherwise specified and limited, the terms "connection", "fixing" and the like should be broadly understood, for example, "fixing" can be fixed connection, can also be detachable connection, or integral: can be mechanical connection, can also be electrical connection; can be direct connection, can also be indirect connection through intermediate medium, can be the internal communication of two elements or the interaction relationship of two elements, unless otherwise explicitly limited. For the ordinary skilled in the art, the specific meaning of the above terms in the present application can be understood according to the specific circumstances.
[0031] Reference Figs. 1-2 The present application provides a kind of for prefabricated T beam summer and winter construction maintenance device.
[0032] In some embodiments, a maintenance device for prefabricated T-beams for summer and winter construction includes multiple support scaffolds 6 and multiple portal frames, wherein the multiple portal frames are arranged horizontally at intervals, and each portal frame includes two vertically arranged risers 1. A connecting rod 2 is provided on the upper part of the first portal frame and the last portal frame along the arrangement direction of the portal frames. The upper ends of the two risers 1 of the portal frames are connected and fixed by the connecting rod 2. The risers 1 of two adjacent portal frames on the same side are connected by two cross-arranged connecting rods 3. The outer side of each riser 1 is provided with a vertical slide groove. 4. The end of the connecting rod 3 is movably connected with a pin 5, which is movably mounted in the slide groove 4 and can slide back and forth along the slide groove 4. The single supporting scaffold 6 includes a cross bar 61, an arc-shaped supporting rod 62 and two vertical rods 63. The two vertical rods 63 are vertically arranged and connected by the cross bar 61. The upper ends of the two vertical rods 63 are connected by the arc-shaped supporting rod 62. The vertical rods 63 of the single supporting scaffold 6 are sleeved in the riser 1 of the single gantry frame. The riser 1 of the gantry frame is provided with a water supply pipe 7 and a constant temperature lamp 9. The water supply pipe 7 is provided with multiple sprinkler heads 8 in its own length direction.
[0033] The present application creates a movable and structurally stable maintenance environment by combining multiple supporting scaffolds 6 with multiple portal frames. To avoid rain intrusion, a tarpaulin can be laid outside the supporting scaffolds 6 and the portal frames and fixed with screws. Windows can also be opened on the tarpaulin to ensure that the entire device has a certain ventilation effect.
[0034] As for how to set the water supply pipe 7 and the constant temperature lamp 9 on the gantry, the length direction of the water supply pipe 7 and the constant temperature lamp 9 can be made consistent with the arrangement direction of multiple gantry frames. The setting of such long lamp tubes and long water pipes can simplify the setting on the one hand, and on the other hand, it can ensure that the spray water in each maintenance area can be sprayed evenly and the lighting can be balanced, creating a balanced humidity and temperature environment; circular lights and water supply pipes 7 can also be evenly set on the vertical pipe 1. Although it increases the difficulty of setting, the spraying and lighting are more balanced.
[0035] The design of the slide 4 and the pin 5 of the present application allows the entire device to be freely extended and retracted according to actual needs, thereby enhancing flexibility. This not only facilitates the transfer of equipment between different sites, but also, after storage, the entire device occupies a smaller usable area. The scalability of the device can match prefabricated T-beams 12 of different lengths.
[0036] In some embodiments, the length direction of the water supply pipe 7 and the constant temperature lamp 9 is consistent with the arrangement direction of the multiple portal frames.
[0037] In some embodiments, at least two water supply pipes 7 are arranged on the vertical pipe 1 of one side of the portal frame, and at least two constant temperature lamps 9 are arranged. The water supply pipes 7 and the constant temperature lamps 9 are arranged in a vertical direction and are spaced apart. The water supply pipes 7 and the constant temperature lamps 9 can be arranged at equal intervals or at unequal intervals according to the actual construction device to adapt to the light and spray water required by different parts of the prefabricated T-beam 12.
[0038] In some embodiments, the water supply pipes 7 and the constant temperature lamps 9 are three. The water supply pipes 7 and the constant temperature lamps 9 are arranged in an alternating manner.
[0039] In some embodiments, the vertical pipe 1 is a galvanized steel pipe. The galvanized steel pipe has good corrosion resistance and mechanical strength, can withstand long-term use in outdoor environments, reduces maintenance costs, and prolongs the service life of the equipment. In addition, stainless steel pipes, aluminum alloy pipes, etc. can also be used.
[0040] In some embodiments, the portal frame is provided with a collection tank 10 for recycling spray water at the bottom. The collection tank 10 provided at the bottom of the portal frame can effectively recycle the sprayed water, which not only saves water resources, but also prevents safety hazards caused by accumulated water on site, and also keeps the construction site clean. The collection tank 10 provided at the bottom of the portal frame can be designed with a proper slope or installed with a water pump to make the spray water flow to the collection point. The collected water is subjected to primary filtration to remove large particles, for example, a grid and a sedimentation tank, and then subjected to further purification through a sand filter. The water is redistributed to the water supply pipeline through a pumping system for use by the spray head 8 again.
[0041] In some embodiments, the lower end of each vertical pipe 1 of the portal frame is provided with a universal wheel 11.
Claims
1. A curing device for prefabricated T-beams during summer and winter construction, characterized by: The invention comprises a plurality of supporting scaffolds (6) and a plurality of gantry frames, wherein the plurality of gantry frames are arranged at intervals in a horizontal direction, each gantry frame comprises two vertically arranged risers (1), a connecting rod (2) is provided on the upper part of the first gantry frame and the last gantry frame along the gantry frame arrangement direction, the upper ends of the two risers (1) of the gantry frames are connected and fixed by the connecting rod (2), the risers (1) of two adjacent gantry frames located on the same side are connected by two cross-arranged connecting rods (3), a vertical slide groove (4) is provided on the outer side of each riser (1), and a pin (5) is movably connected to the end of the connecting rod (3), and the pin (5) is fixed to the upper end of the gantry frame. ) is movably mounted in the slide groove (4) and can slide back and forth along the slide groove (4). A single supporting scaffold (6) comprises a cross bar (61), an arc-shaped supporting bar (62) and two vertical bars (63). The two vertical bars (63) are vertically arranged and connected by the cross bar (61). The upper ends of the two vertical bars (63) are connected by the arc-shaped supporting bar (62). The vertical bars (63) of the single supporting scaffold (6) are sleeved in the vertical pipe (1) of the single gantry frame. The vertical pipe (1) of the gantry frame is provided with a water supply pipe (7) and a constant temperature lamp (9). The water supply pipe (7) is provided with a plurality of sprinkler heads (8) in its own length direction.
2. The maintenance device for prefabricated T-beam construction in summer and winter according to claim 1, characterized in that: The length direction of the water supply pipe (7) and the constant temperature lamp (9) is consistent with the arrangement direction of the multiple portal frames.
3. The maintenance device for prefabricated T-beam construction in summer and winter according to claim 2, characterized in that: At least two water supply pipes (7) and at least two constant temperature lamps (9) are provided on the vertical pipe (1) on one side of the gantry frame. The water supply pipes (7) and the constant temperature lamps (9) are arranged at intervals in the vertical direction.
4. The curing device for prefabricated T-beams in summer and winter construction according to claim 3, characterized in that: There are three water supply pipes (7) and three constant temperature lamps (9), and the water supply pipes (7) and the constant temperature lamps (9) are arranged in a staggered manner.
5. The maintenance device for prefabricated T-beam construction in summer and winter according to claim 1, characterized in that: The riser (1) is a galvanized steel pipe.
6. The maintenance device for prefabricated T-beam construction in summer and winter according to claim 1, characterized in that: A collecting tank (10) for recovering spray water is provided at the bottom of the gantry.
7. The curing device for prefabricated T-beams in summer and winter construction according to any one of claims 1 to 6, characterized in that: The lower ends of the two vertical pipes (1) of each gantry are provided with universal wheels (11).