Preset assembly type temporary road
By setting reserved grooves and embedded lifting rings on the concrete structure, the problems of high lifting cost and poor safety in the existing technology are solved, and low-cost and safe temporary road lifting operations are realized.
Patent Information
- Application Number
- CN202422688114.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-05
- Publication Date
- 2025-10-17
- Estimated Expiration
- 2034-11-05
AI Technical Summary
The existing prefabricated temporary roads have high hoisting costs and are not conducive to frequent relocation, posing safety hazards. In particular, small excavators are difficult to lift, while large excavators are expensive and not suitable for frequent use.
A pre-reserved groove is set on the concrete structure and a lifting ring is pre-embedded. The lifting ring is welded and fixed to the lower steel bars. During hoisting, the external hoisting device can be directly connected to the pre-embedded lifting ring. Hoisting can be completed using a small hook or a small crane, which simplifies the operation and improves safety.
It reduces hoisting costs, improves operational safety and convenience, and is suitable for temporary road hoisting needs with frequent location changes.
Smart Images

Figure CN223445922U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to the technical field of building construction, more specifically, relates to a pre-installed assembly type temporary road. BACKGROUND
[0002] In the building construction process, usually, the precast assembly type concrete is formed into a temporary road on site, and the position of the precast assembly type concrete temporary road needs to be frequently replaced according to the actual construction requirements. Currently, the position replacement of the precast road generally adopts the loading and unloading mode of a hook machine cooperating with a transport machine. The conventional method is as follows: the hook machine is used to pre-lift the precast road, then a sling is passed through the precast road for fixation, and then the loading and unloading operation is completed.
[0003] However, such a method has the problems of low loading and unloading efficiency, high risk of the precast road falling off the sling or the hook machine, and harm to the surrounding construction personnel. In addition, direct hoisting of the temporary road also has high requirements for the hook machine. Small hook machines are difficult to lift the temporary road, while large hook machines are expensive and not suitable for frequent position replacement.
[0004] Therefore, there is an urgent need for a pre-installed assembly type concrete temporary road that can reduce the hoisting cost and safely and reliably realize frequent hoisting operation of the temporary road. SUMMARY
[0005] In view of the above problems, the purpose of the utility model is to provide a pre-installed assembly type temporary road to solve the problems of high hoisting cost and inconvenience of repeated hoisting operation of the existing temporary road.
[0006] The pre-installed assembly type temporary road provided by the utility model comprises at least one temporary road section that can be assembled. The temporary road section comprises lower reinforcement, upper reinforcement, and a concrete main body formed by surrounding the upper reinforcement and the lower reinforcement. A reserved groove is arranged on the concrete main body, and a pre-buried lifting ring is arranged in the reserved groove. The pre-buried lifting ring is welded and fixed with the lower reinforcement and is accommodated in the reserved groove. When the temporary road section needs to be hoisted, an external hoisting device is buckled with the pre-buried lifting ring.
[0007] In addition, the optional structural feature is that the pre-buried lifting ring is arranged at the four corner positions of the concrete main body, and the arrangement position and the number of the reserved groove correspond to the pre-buried lifting ring.
[0008] In addition, the optional structural feature is that the pre-buried lifting ring is a "j" shaped structure comprising a fixed part arranged horizontally and a lifting ring part arched from the fixed part. The fixed part is welded and fixed with the lower reinforcement.
[0009] In addition, an optional structural feature is that a cover plate covering the reserved groove is provided on the concrete main body; one side of the cover plate is hinged to the concrete main body, and the cover plate is used to flip around the hinge to cover or open the reserved groove.
[0010] In addition, an optional structural feature is that the size of the cover plate is larger than the cross-sectional size of the reserved groove.
[0011] In addition, an optional structural feature is that a cover plate groove is provided on the reserved groove; when the cover plate covers the reserved groove, the cover plate is accommodated in the cover plate groove, and the upper surface of the cover plate is flush with the upper surface of the concrete body.
[0012] In addition, an optional structural feature is that angle steel guard plates are provided at the edge of the concrete body; the angle steel guard plates are attached to two mutually perpendicular outer surfaces of the slow-setting soil body.
[0013] In addition, an optional structural feature is that the angle steel guard plate is provided on the upper surface and / or lower surface of the concrete body.
[0014] In addition, an optional structural feature is that the cover plate is a steel plate.
[0015] In addition, an optional structural feature is that the lifting ring portion of the embedded lifting device is movably connected to the fixed portion, and the lifting ring portion rotates 360° around the fixed portion.
[0016] By utilizing the above-mentioned prefabricated temporary road, a plurality of temporary road sections that can be assembled and disassembled with each other are set up. Each temporary road section includes a concrete body and upper and lower steel bars embedded in the concrete body. To facilitate the lifting operation, the lifting of each temporary road section can be completed only by a small hook. A reserved groove is further provided on the concrete body, and a pre-embedded lifting ring is provided in the reserved groove. The part of the pre-embedded lifting ring is welded and fixed to the lower steel bar. When lifting the temporary road section, the hook of the external lifting device can be buckled on the embedded lifting ring. The lifting operation of the temporary road can be realized by using a small trolley. The operation is simple, the cost is low, and the safety is higher. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] By referring to the following description in conjunction with the accompanying drawings, and with a more comprehensive understanding of the present invention, other objects and results of the present invention will become more clear and easy to understand. In the accompanying drawings:
[0018] Figure 1 This is a cross-sectional view of a prefabricated temporary road according to an embodiment of the present invention;
[0019] Figure 2 It is a top view of a prefabricated temporary road according to an embodiment of the utility model.
[0020] The reference numerals include: 1. lower steel bars; 2. upper steel bars; 3. concrete body; 4. angle steel guard plate; 5. cover plate; 6. embedded lifting ring; 61. fixing part; 62. lifting ring part; 7. reserved groove.
[0021] The same reference numerals throughout the drawings indicate similar or corresponding features or functions. DETAILED DESCRIPTION
[0022] In the following description, for illustrative purposes, numerous specific details are set forth to provide a comprehensive understanding of one or more embodiments. However, it will be apparent that the embodiments may be practiced without these specific details. In other instances, well-known structures and devices are shown in block diagram form to facilitate description of one or more embodiments.
[0023] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential", "longitudinal" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation to the present invention.
[0024] In order to solve the problems of complex operation, high cost and inconvenience of frequent lifting operations in the existing temporary road lifting, the utility model provides a prefabricated assembled temporary road, which is provided with a plurality of temporary road sections that can be assembled and disassembled with each other. Each temporary road section further includes a concrete body and upper and lower steel bars embedded in the concrete body. To facilitate the lifting operation, the lifting of each temporary road section can be completed only by a small hook. At the same time, a reserved groove and a pre-buried lifting ring located in the reserved groove are provided on the concrete body. When the temporary road section is lifted, the hook of the external lifting device can be buckled on the pre-buried lifting ring. The lifting operation of the temporary road can be realized by using a small trolley, which is simple to operate, low in cost and safer.
[0025] In order to describe the prefabricated temporary road of the present invention in detail, the specific embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
[0026] Figure 1 and Figure 2 The cross-sectional structure and top view structure of the prefabricated temporary road according to the embodiment of the utility model are respectively shown.
[0027] like Figure 1 and Figure 2 As collectively stated, the prefabricated assembled temporary road implemented by the present invention includes at least one temporary road section that can be assembled and assembled, and each temporary road section further includes a lower steel bar, an upper steel bar 2, and a concrete body 3 cast around the upper steel bar 2 and the lower steel bar 1; wherein, a plurality of reserved grooves 7 are provided on the concrete body 3, and a pre-embedded lifting ring 6 is provided in the reserved groove 7. The pre-embedded lifting ring 6 is welded and fixed to the lower steel bar 1 and accommodated in the reserved groove 7. When the temporary road is not hoisted, the setting of the reserved groove 7 will not affect the normal use of the temporary road. When the temporary road section needs to be hoisted, the hook of the external hoisting device can be buckled with the pre-embedded lifting ring 6, thereby simplifying the hoisting operation. The hoisting operation of the temporary road section can be completed by only a small crane or a hook machine.
[0028] Among them, the embedded lifting rings 6 can be set at the four corners of the concrete body 3. When the length of the concrete body 3 is long, the embedded lifting ring 6 structure can also be added in the length direction of the concrete body 3. The embedded lifting rings 6 are evenly or regularly distributed on the temporary road section, so that the temporary road section is evenly stressed during the lifting operation. It can be seen that the setting position and number of the reserved grooves 7 correspond to the embedded lifting rings 6. The attached drawings of the utility model show that there are 4 cases where the embedded lifting rings 6 are set.
[0029] In a specific embodiment of the present invention, the structure of the embedded lifting ring 6 can be set to a "J"-shaped structure, including a horizontally arranged fixing portion 61 and a lifting ring portion 62 arched from the fixing portion 61. The fixing portion 61 is welded and fixed to the lower steel bar 1. Before pouring concrete, the embedded lifting ring 6 can be embedded in the reserved groove 7, and the template can be blocked with cotton felt to prevent concrete from falling into the reserved groove 7. After the concrete is poured and solidified, the cotton felt in the reserved groove 7 can be cleaned.
[0030] It should be noted that, since the external hook is directly connected to the embedded lifting ring 6 during the lifting process, in order to ensure that the force direction of the embedded lifting ring 6 can be adjusted along with the force direction of the hook, a movable limiting structure can be provided between the fixed portion 61 and the lifting ring portion 62. The lifting ring portion 62 is movably connected to the fixed portion 61 through the movable limiting structure, so that the lifting ring portion 62 can rotate 360° around the fixed portion 61, thereby improving the flexibility of the embedded lifting ring 6 when connected to the external hook.
[0031] Further, in order to prevent foreign matters from entering the reserved groove 7 during use of the temporary road section and affecting the normal use of the embedded lifting ring 6, a cover plate 5 covering the reserved groove 7 can be arranged on the concrete main body 3 in the utility model, the cover plate 5 can be made of steel plate, one side of the cover plate 5 is connected with the concrete main body 3 through a hinge or the like, the cover plate 5 can be turned around the hinge to cover or open the reserved groove 7, during use of the temporary road section, the cover plate 5 can be covered, the reserved groove 7 is covered by the cover plate 5, when the temporary road section needs to be hoisted, the cover plate 5 is turned to be opened, the hook or the rope of the external hoisting device is buckled with the lifting ring part 62, thereby the hoisting operation is assisted to be completed through the lifting ring part 62.
[0032] It can be known that, in order to realize the shielding function of the cover plate 5, the size of the cover plate 5 needs to be set to be greater than the cross-sectional dimension of the reserved groove 7, in addition, in order to ensure that the cover plate 5 can cooperate with the concrete main body 3 to form a temporary road in the closed state, and avoid that the cover plate 5 and the concrete main body 3 are uneven, a cover plate groove can be further arranged on the reserved groove 7; when the cover plate 5 covers the reserved groove 7, the free end of the cover plate 5 can be accommodated in the cover plate groove, so that the upper surface of the cover plate 5 is flush with the upper surface of the concrete main body 3, and the normal use of the temporary road is ensured.
[0033] In order to improve the overall structural strength of the temporary road section, improve the use frequency, and prolong the service life, an angle steel guard plate 4 can be arranged at the edge of the concrete main body 3, the angle steel guard plate 4 is attached to two mutually perpendicular outer surfaces of the concrete main body, that is, the angle steel guard plate 4 includes two mutually perpendicular edges, the angle steel guard plate 4 is arranged around the edge of the concrete main body 3, and an external frame protecting the concrete main body 3 is formed, thereby prolonging the service life; wherein the angle steel guard plate 4 can be arranged on the upper surface and / or the lower surface of the concrete main body 3, and the length and width of the angle steel guard plate 4 are consistent with the concrete main body 3.
[0034] According to the pre-assembled temporary road of the utility model, a plurality of temporary road sections which can be assembled and disassembled with each other are arranged, each temporary road section includes a concrete main body and upper and lower steel bars embedded in the concrete main body, in order to facilitate hoisting operation, the hoisting of each temporary road section can be completed through only a small hook, a reserved groove is further arranged on the concrete main body, and a pre-embedded lifting ring is arranged in the reserved groove, part of the pre-embedded lifting ring is welded and fixed with the lower steel bar, when the temporary road section is hoisted, the hook of the external hoisting device can be buckled on the pre-embedded lifting ring, the hoisting operation of the temporary road can be realized through a small trolley, the operation is simple, the cost is low, and the safety is higher.
[0035] The pre-assembled temporary road according to the present application is described above with reference to the drawings by way of example. However, those skilled in the art should understand that various improvements can be made to the pre-assembled temporary road of the present application described above without departing from the content of the present application. Therefore, the protection scope of the present application should be determined by the content of the appended claims.
Claims
1. A prefabricated temporary road, characterized in that: The temporary road section comprises at least one assembleable temporary road section, wherein the temporary road section comprises a lower steel bar, an upper steel bar, and a concrete body cast around the upper steel bar and the lower steel bar; wherein, A reserved groove is provided on the concrete main body, and a pre-buried lifting ring is provided in the reserved groove; The embedded lifting ring is welded and fixed to the lower steel bar and accommodated in the reserved groove. When the temporary road section needs to be hoisted, the external hoisting device is buckled with the embedded lifting ring.
2. The prefabricated temporary road according to claim 1, characterized in that: The embedded lifting rings are arranged at the four corners of the concrete body; and The arrangement position and number of the reserved grooves correspond to the embedded lifting rings.
3. The prefabricated temporary road according to claim 1, characterized in that: The embedded lifting ring is a "J"-shaped structure, including a horizontally arranged fixing portion and a lifting ring portion arched from the fixing portion; The fixing portion is fixed to the lower steel bar by welding.
4. The prefabricated temporary road according to claim 1, characterized in that: A cover plate covering the reserved groove is provided on the concrete main body; One side of the cover plate is hingedly connected to the concrete body, and the cover plate is used to flip around the hinge to cover or open the reserved groove.
5. The prefabricated temporary road according to claim 4, characterized in that: The size of the cover plate is larger than the cross-sectional size of the reserved groove.
6. The prefabricated temporary road according to claim 4, characterized in that: A cover plate groove is provided on the reserved groove; When the cover plate covers the reserved groove, the cover plate is accommodated in the cover plate groove, and the upper surface of the cover plate is flush with the upper surface of the concrete body.
7. The prefabricated temporary road according to claim 1, characterized in that: An angle steel guard plate is provided at the edge of the concrete body; The angle steel guard plate is attached to two mutually perpendicular outer surfaces of the concrete body.
8. The prefabricated temporary road according to claim 7, characterized in that: The angle steel guard plate is arranged on the upper surface and / or the lower surface of the concrete body.
9. The prefabricated temporary road according to claim 4, characterized in that: The cover plate is a steel plate.
10. The prefabricated temporary road according to claim 3, characterized in that: The lifting ring portion of the embedded lifting device is movably connected to the fixing portion, and the lifting ring portion rotates 360 degrees around the fixing portion.