Anti-abrasion chute and pipeline for conveying cullet, mineral powder and ore sand

By designing an anti-wear chute and piping system, the problems of chute damage and material loss during transportation are solved, achieving efficient material transportation and simplified maintenance processes.

CN223457526UActive Publication Date: 2025-10-21QINGDAO DAJIANG MACHINERY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422910560.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-11-28
Publication Date
2025-10-21
Estimated Expiration
2034-11-28

AI Technical Summary

Technical Problem

When transporting fine materials such as broken glass, mineral powder, and mineral sand, existing chutes are easily damaged by friction, resulting in low transportation efficiency and material loss. In particular, materials are prone to rushing out of the chute on routes with large height differences.

Method used

A wear-resistant chute and pipeline system is designed, which includes a conveying pipeline body, a bracket structure, a base structure, a chute structure and a fixed structure. Through the coordinated use of the chute and the pipeline, the chute is located inside the pipeline and can be easily replaced. The pipeline is used for secondary transportation of lost materials. The operator can judge whether the chute is damaged according to the outlet and replace it in time.

Benefits of technology

It effectively prevents materials from falling during transportation, improves transportation efficiency, ensures normal material delivery, reduces chute wear and loss, and simplifies maintenance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223457526U_ABST
    Figure CN223457526U_ABST
Patent Text Reader

Abstract

The utility model discloses a cullet, mineral powder and ore sand conveying anti-abrasion chute and pipeline, and relates to the technical field of chutes, the cullet, mineral powder and ore sand conveying anti-abrasion chute and pipeline comprise a conveying pipeline body, two support structures are installed in the conveying pipeline body, the lower wall surfaces of the two support structures are respectively provided with a base structure, and the upper wall surfaces of the two base structures are provided with chute structures. A fixing structure is mounted outside the conveying pipeline body; the chute and the pipeline are used in a matched mode, the chute is located in the pipeline, the chute is a main part of transportation, bears most material transportation and is the most serious in friction consumption, the chute can be replaced conveniently, the pipeline is a supplement of transportation, materials can be prevented from being left behind in the transportation process, and the transportation efficiency is improved. Even if the chute is damaged due to friction, the pipeline can carry out secondary transportation on materials left in the chute, and meanwhile, an operator can judge whether the chute breaks down or not according to material distribution at an outlet.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to a chute technical field especially relates to a kind of broken glass, ore powder, ore sand conveying anti-abrasion chute and pipeline. BACKGROUND

[0002] Chute refers to the groove from high to low on the ground, inner surface is smooth, things can automatically slide down. It is mainly applied to small open-pit mine, in large and medium-sized open-pit mine, chute is often connected with chute shaft, which can be arranged within the range of stope or outside.

[0003] When chute is used to transport broken glass, ore powder, ore sand and other fine materials, friction occurs between materials and chute. Therefore, if not timely maintenance, a large number of materials will be lost during transportation after long-term use of chute. Since the transportation power of chute mainly depends on the gravity of materials, materials will be out of chute and lost in some transportation routes with large height difference, which reduces the transportation efficiency of chute. UTILITY MODEL CONTENT

[0004] The utility model aims at solving the shortcomings in the prior art and provides a kind of broken glass, ore powder, ore sand conveying anti-abrasion chute and pipeline.

[0005] To achieve the above object, the utility model adopts the following technical scheme:

[0006] A kind of broken glass, ore powder, ore sand conveying anti-abrasion chute and pipeline, comprising: conveying pipeline body, two groups of support structures are installed in the inside of conveying pipeline body, bottom seat structure is respectively installed on the lower wall of two groups of support structures, chute structure is installed on the upper wall of two groups of bottom seat structure, fixed structure is installed on the outside of conveying pipeline body;Two groups of support structures include: two sleeve pipes, two screw rods and two support plates;Two sleeve pipes are respectively installed in the inside of conveying pipeline body, two screw rods are respectively inserted into the inside of sleeve pipe, and the screw rod is fixed by nut, two support plates are respectively installed on the lower wall of screw rod.

[0007] The utility model is further provided as follows: the bottom seat structure includes: bottom seat body and two connecting shafts;Two ends of the bottom seat body are movably connected with support plates through connecting shafts.

[0008] The utility model is further provided as follows: the chute structure includes: chute body and two chute bases;Two chute bases are respectively installed on the upper wall of bottom seat body, and the chute base and the bottom seat body are fixed by bolt, the chute body is fixedly installed on the upper wall of two chute bases.

[0009] The utility model further sets up as the fixed structure includes: fixed outer ring and fixed base, the fixed outer ring installs the outside of conveying pipeline body, the fixed base installs the lower wall surface of fixed outer ring.

[0010] The utility model further sets up as the tail end of chute body is installed with chute connecting plate.

[0011] The utility model further sets up as the inner wall of base body and conveying pipeline body is left twenty centimeter's gap.

[0012] The utility model discloses the beneficial effect is: the utility model discloses a chute and pipeline cooperation uses, and the chute is located in the inside of pipeline, and the chute is the main part of transportation, and bears most of the material transportation, and also is the most serious friction consumption, the utility model discloses can conveniently replace the chute, and the pipeline is the supplement of transportation, can prevent material from falling in the process of transportation, even if the chute breaks down due to friction, and the pipeline can carry out secondary transportation to the material that the chute falls, and simultaneously operating personnel can judge whether the chute breaks down according to the material distribution of export. BRIEF DESCRIPTION OF DRAWINGS

[0013] Fig. 1 The utility model discloses a kind of broken glass, mineral powder, mineral sand conveying anti-abrasion chute and the overall structure schematic diagram of pipeline proposed by the utility model;

[0014] Fig. 2 The first partial structure schematic diagram of a kind of broken glass, mineral powder, mineral sand conveying anti-abrasion chute and pipeline proposed by the utility model;

[0015] Fig. 3 The second partial structure schematic diagram of a kind of broken glass, mineral powder, mineral sand conveying anti-abrasion chute and pipeline proposed by the utility model.

[0016] In the drawing: 1, conveying pipeline body;2, sleeve;3, screw;4, support plate;5, base body;6, connecting shaft;7, chute body;8, chute base;9, fixed outer ring;10, fixed base;11, chute connecting plate. DETAILED DESCRIPTION

[0017] The technical scheme of the patent will be further described in detail in combination with specific implementation manners.

[0018] The embodiments of the patent are described in detail below, and the examples of the embodiments are shown in the drawings, wherein the same or similar reference signs represent the same or similar elements or elements with the same or similar functions throughout. The embodiments described below by referring to the drawings are exemplary, and are only used to explain the patent, and cannot be understood as the limitation of the patent.

[0019] In the description of the present patent, it needs to be understood that the terms "center", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer" and the like indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present patent and simplifying the description, and do not indicate or imply that the devices or elements referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore cannot be understood as a limitation of the present patent.

[0020] In the description of the present patent, it needs to be understood that unless otherwise explicitly specified and limited, the terms "mounting", "connecting", "connecting", "setting" should be understood broadly, for example, it can be fixedly connected, set, or it can be detachably connected, set, or integrally connected, set. For those skilled in the art, the specific meaning of the above terms in the present patent can be understood according to the specific circumstances.

[0021] Reference Figs. 1-3 A kind of glass, ore powder, ore sand conveying anti-abrasion chute and pipeline, comprising: conveying pipeline body 1, two groups of support structures are installed in the inside of conveying pipeline body 1, the lower wall of two groups of support structures is respectively installed with base structure, the upper wall of two groups of base structures is installed with chute structure, fixed structure is installed on the outside of conveying pipeline body 1;Two groups of support structures include: two sleeve pipes 2, two screw rods 3 and two support plates 4;Two sleeve pipes 2 are respectively installed in the inside of conveying pipeline body 1, two screw rods 3 are respectively inserted into the inside of sleeve pipe 2, and screw rod 3 is fixed by nut, two support plates 4 are respectively installed on the lower wall of screw rod 3.

[0022] Specifically, the base structure includes: base body 5 and two connecting shafts 6;Two ends of base body 5 are movably connected by connecting shafts 6 and support plates 4, respectively, and a twenty-centimeter gap is left between base body 5 and the inner wall of conveying pipeline body 1.

[0023] Specifically, the chute structure includes: chute body 7 and two chute bases 8;Two chute bases 8 are respectively installed on the upper wall of base body 5, and chute base 8 and base body 5 are fixed by bolts, chute body 7 is fixedly installed on the upper wall of two chute bases 8, and chute connecting plate 11 is installed at the tail end of chute body 7.

[0024] Specifically, the fixed structure includes: fixed outer ring 9 and fixed base 10;Fixed outer ring 9 is installed on the outside of conveying pipeline body 1, and fixed base 10 is installed on the lower wall of fixed outer ring 9.

[0025] Working principle: when using the utility model, first need to install the utility model, the operator according to the transmission route, splice assembly is carried out to the plurality of utility model, and the conveying pipeline body 1 is aligned according to the need splice, and the chute body 7 is spliced through the chute connecting plate 11, and the installation of the conveying pipeline body 1 is laid through the fixed outer ring 9 and the fixed base 10 outside it, the chute base 8 is installed on the lower wall surface of the chute body 7, and the chute base 8 and the base body 5 are connected and fixed through bolts, when the broken glass, the mineral powder, the mineral sand and other materials need to be conveyed, the materials are placed on the chute body 7 from the inlet, under the action of gravity, the materials can slide to the outlet by oneself, at this moment, the conveying is completed, when the materials fall off, can be directly caught by the conveying pipeline body 1, and continue to convey, can effectively prevent the materials from losing a lot in the process of transportation, and if the operator finds that most of the materials are sent out through the conveying pipeline body 1 at the outlet, it can be judged that the chute body 7 is damaged, and it can be directly replaced, ensuring the normal transportation of materials.

[0026] The above is only the preferred embodiment of the utility model, but the protection scope of the utility model is not limited to this, any skilled person in the art can replace or change according to the technical scheme and the utility model concept of the utility model within the technical range disclosed by the utility model, which should be covered in the protection scope of the utility model.

Claims

1. A wear resistant chute for conveying crushed glass, ore fines, and ore sand, comprising: The utility model provides a conveying pipeline body (1), its characterized in be installed with two groups of support structure in the inside of conveying pipeline body (1), the lower wall of two groups of support structure is installed with base structure respectively, the upper wall of two groups of base structure is installed with chute structure, the outside of conveying pipeline body (1) is installed with fixed structure, Two groups of support structure includes: two sleeve pipes (2), two screw rods (3) and two support plates (4); Two sleeve pipes (2) are installed in the inside of conveying pipeline body (1) respectively, two screw rods (3) are inserted into the inside of sleeve pipe (2) respectively, and the screw rod (3) is fixed by nut, two support plates (4) are installed in the lower wall of screw rod (3) respectively.

2. A wear resistant chute for conveying crushed glass, ore fines, and ore sand as claimed in claim 1, wherein, The base structure includes: base body (5) and two connecting shafts (6); Two ends of base body (5) are movably connected by connecting shaft (6) and support plate (4) respectively.

3. A wear resistant chute for conveying crushed glass, ore fines, and ore sand as claimed in claim 1, wherein, The chute structure includes: chute body (7) and two chute bases (8); Two chute bases (8) are installed on the upper wall of base body (5) respectively, and the chute base (8) and base body (5) are fixed by bolt, the chute body (7) is fixedly installed on the upper wall of two chute bases (8), and the tail end of chute body (7) is installed with chute connecting plate (11).

4. A wear resistant chute for conveying crushed glass, ore fines, and ore sand as claimed in claim 1, wherein, The fixed structure includes: fixed outer ring (9) and fixed base (10); The fixed outer ring (9) is installed on the outside of conveying pipeline body (1), and the fixed base (10) is installed on the lower wall of fixed outer ring (9).

5. A wear resistant chute for conveying crushed glass, ore fines, and ore sand as claimed in claim 2, wherein, The inner wall of base body (5) and conveying pipeline body (1) leaves a gap of twenty centimeters.