Assembled electric power iron tower
By using a segmented design with pre-embedded steel pipes and threaded connection components, the problems of long construction cycles and difficulty in soil restoration after dismantling existing assembled power towers have been solved, enabling rapid installation and efficient construction.
Patent Information
- Application Number
- CN202422297406.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-20
- Publication Date
- 2025-11-25
- Estimated Expiration
- 2034-09-20
AI Technical Summary
Existing prefabricated power transmission towers require a long time for concrete pouring during installation, and the foundation soil is difficult to restore after dismantling.
By using pre-embedded steel pipes and threaded connection components, and through a segmented design of fixed base plate, connection components, tower body components and tower head, assembly is carried out using threaded rods and limit nuts, avoiding concrete pouring and improving construction efficiency.
It enables rapid installation and dismantling, reduces the impact on the soil environment, and improves construction efficiency and convenience.
Smart Images

Figure CN223593890U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to power iron tower technical field especially relates to a kind of assembled power iron tower. BACKGROUND
[0002] Power iron tower generally refers to transmission line iron tower, and the transmission line iron tower is tower-like building for power transmission, and the structural characteristics thereof are that various tower types belong to space truss structure, and the rod member is mainly composed of single equilateral angle steel or combined angle steel.
[0003] In the prior art, the common assembled power iron tower is mostly poured by concrete during installation, and the tower body structure is fixed, on the one hand, the construction period required by the concrete pouring is long, and on the other hand, after the iron tower is removed, the foundation poured by the concrete changes the original soil environment, and it is difficult to restore.
[0004] Therefore, an assembled power iron tower is provided to solve the above problems. UTILITY MODEL CONTENTS
[0005] The utility model aims at solving the problems in the prior art.
[0006] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: an assembled power iron tower comprises a fixed bottom plate, four embedded steel pipes are mounted on the surface of the fixed bottom plate, a connecting assembly is arranged on the top of the fixed bottom plate, a tower body assembly is arranged on the top of the connecting assembly, a tower body two is mounted on the top of the tower body assembly, and a tower head is mounted on the top of the tower body two.
[0007] As a preferred embodiment, four threaded holes one are formed in the surface of the fixed bottom plate, and mounting holes one are formed in four ends of the fixed bottom plate.
[0008] As a preferred embodiment, the surface of the embedded steel pipe is movably embedded in the inside of the mounting hole one, a threaded groove is formed in the surface of the top end of the embedded steel pipe, and a threaded rod one is fixedly mounted on the top of the embedded steel pipe.
[0009] As a preferred embodiment, the connecting assembly comprises a mounting plate, a plurality of threaded rods two are fixedly mounted on the top of the mounting plate, four mounting holes two are formed in the surface of the mounting plate, four threaded rods one are movably embedded in the surface of the mounting holes two, four connecting threaded rods are movably embedded in the surface of the mounting plate, two limiting nuts are threadedly mounted on the surface of each connecting threaded rod, and the surface of each connecting threaded rod is threadedly mounted in the inside of each threaded hole one.
[0010] As a preferred implementation, the tower body assembly includes a connecting base, the surface of the connecting base is provided with a plurality of mounting holes three, a plurality of the mounting holes three are respectively sleeved on the surfaces of a plurality of threaded rods two, the bottom of the connecting base is provided with a movable slot, the movable slot is sleeved on the surfaces of the top of four connecting threaded rods, the top of the connecting base is fixedly installed with a tower body one, the top of the tower body one is fixedly installed with a connecting ring one, and the surface of the connecting ring one is fixedly and circumferentially installed with a plurality of threaded rods three.
[0011] As a preferred implementation, the bottom of the tower body two is fixedly installed with a connecting ring two, the surface of the connecting ring two is circumferentially provided with a plurality of mounting holes four, a plurality of the mounting holes four are correspondingly sleeved on the surfaces of a plurality of threaded rods three, the top of the tower body two is fixedly installed with a connecting ring three, and the surface of the connecting ring three is fixedly and circumferentially installed with a plurality of threaded rods four.
[0012] As a preferred implementation, the bottom of the tower head is fixedly installed with a connecting ring four, the surface of the connecting ring four is circumferentially provided with a plurality of mounting holes five, a plurality of the mounting holes five are correspondingly sleeved on the surfaces of a plurality of threaded rods four, and the surface of the connecting ring four is installed with two groups of cross arms.
[0013] Compared with the prior art, the utility model has the advantages and positive effects that:
[0014] 1. Before use, the utility model digs a foundation pit in the position to be installed, places a fixed bottom plate horizontally at the bottom of the foundation pit, inserts four embedded steel pipes into four mounting holes one correspondingly, inserts the bottom surface of the embedded steel pipe into the ground, places an installation plate on the top of the embedded steel pipe, sleeves mounting holes two on the surface of threaded rods one correspondingly, spirally installs connecting threaded rods into threaded holes one, fixes the installation plate by installing a nut on the top of the threaded rod one, adjusts two limiting nuts on the surface of the connecting threaded rod, rotates one to tightly attach to the bottom of the installation plate, rotates the other to tightly attach to the top of the fixed bottom plate, strengthens the connection between the installation plate and the fixed bottom plate, finally backfills the foundation pit, inserts a steel plate into the gap between the fixed bottom plate and the installation plate, strengthens the stability, and makes the backfilled ground flush with the bottom of the installation plate, so that the base fixing and installation of the power iron tower are completed, the influence of concrete pouring on the soil quality is avoided, and the construction efficiency is improved.
[0015] 2. After the base is fixed, the utility model installs a connecting base on the surface of the installation plate, sleeves mounting holes three on the surface of threaded rods two, fixes by using a nut, sleeves mounting holes four on the bottom of the tower body two on threaded rods three, fixes by installing a nut, finally sleeves mounting holes five on the bottom of the tower head on the surface of threaded rods four, and fixes by installing a nut, so that the assembly of the power iron tower is completed, the tower body part is divided into a tower body assembly, a tower body two and a tower head three sections, assembly is conducted, transportation and construction are facilitated. BRIEF DESCRIPTION OF DRAWINGS
[0016] Figure 1 A main body schematic view of the assembled power iron tower is provided in the utility model.
[0017] Figure 2 A connection assembly structure split view of the assembled power iron tower is provided in the utility model.
[0018] Figure 3 A connection assembly structure split view of the assembled power iron tower is provided in the utility model.
[0019] Figure 4 A tower body assembly structure view of the assembled power iron tower is provided in the utility model.
[0020] Figure 5 A tower body structure split view of the assembled power iron tower is provided in the utility model.
[0021] Legend:
[0022] 1, fixed bottom plate, 101, threaded hole one, 102, mounting hole one, 2, embedded steel pipe, 201, threaded groove, 202, threaded rod one, 3, connection assembly, 301, mounting plate, 302, threaded rod two, 303, mounting hole two, 304, connecting threaded rod, 305, limit nut, 4, tower body assembly, 401, connecting base, 402, mounting hole three, 403, movable groove, 404, tower body one, 405, connecting ring one, 406, threaded rod three, 5, tower body two, 501, connecting ring two, 502, mounting hole four, 503, connecting ring three, 504, threaded rod four, 6, tower head, 601, connecting ring four, 602, mounting hole five, 603, cross arm. DETAILED DESCRIPTION
[0023] The technical solutions in the embodiments of the utility model will be clearly and completely described below with reference to the drawings in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of protection of the utility model.
[0024] Please refer to Figures 1-5 The utility model provides a kind of technical scheme: a kind of assembled power iron tower, comprising: fixed bottom plate 1, the surface of fixed bottom plate 1 is equipped with four embedded steel pipes 2, the top of fixed bottom plate 1 is provided with connection assembly 3, the top of connection assembly 3 is provided with tower body assembly 4, the top of tower body assembly 4 is installed with tower body two 5, the top of tower body two 5 is installed with tower head 6.
[0025] Specifically, the embedded steel pipe 2 is inserted into the ground through the fixed base plate 1 to provide support, the fixed base plate 1 increases the support area, the connecting assembly 3 strengthens the connection between the fixed base plate 1 and the embedded steel pipe 2, and the embedded steel pipe 2 and the connecting assembly 3 are connected, the tower body assembly 4, the tower body two 5, and the tower head 6 are assembled into a tower body, facilitating transportation and installation construction.
[0026] In one embodiment, four threaded holes 101 are formed on the surface of the fixed base plate 1, and mounting holes 102 are formed at the four ends of the fixed base plate 1.
[0027] Specifically, the threaded holes 101 facilitate the installation of the limiting nuts 305, and the mounting holes 102 facilitate the installation of the embedded steel pipe 2.
[0028] In one embodiment, the embedded steel pipe 2 is movably embedded in the mounting hole 102, a threaded groove 201 is formed on the top end of the embedded steel pipe 2, and a threaded rod 202 is fixedly installed on the top of the embedded steel pipe 2.
[0029] Specifically, the threaded groove 201 facilitates the installation of the limiting nuts for limiting the fixed base plate 1, and the threaded rod 202 facilitates the installation and fixation of the mounting plate 301.
[0030] In one embodiment, the connecting assembly 3 includes a mounting plate 301, a plurality of threaded rods 302 are fixedly installed on the top of the mounting plate 301, four mounting holes 303 are formed on the surface of the mounting plate 301, the four mounting holes 303 are correspondingly sleeved on the surface of the four threaded rods 202, four connecting threaded rods 304 are movably embedded on the surface of the mounting plate 301, two limiting nuts 305 are threadedly installed on the surface of each of the four connecting threaded rods 304, and the four connecting threaded rods 304 are threadedly installed in the four threaded holes 101, respectively.
[0031] Specifically, the mounting holes 303 facilitate the embedding installation of the threaded rods 202, the connecting threaded rods 304 connect the mounting plate 301 and the fixed base plate 1, and the two limiting nuts 305 are respectively tightened to limit the mounting plate 301 and the fixed base plate 1.
[0032] In one embodiment, the tower body assembly 4 includes a connecting base 401, a plurality of mounting holes 402 are formed on the surface of the connecting base 401, the plurality of mounting holes 402 are respectively sleeved on the surface of the plurality of threaded rods 302, a movable groove 403 is formed on the bottom of the connecting base 401, the movable groove 403 is sleeved on the surface of the top of the four connecting threaded rods 304, a tower body one 404 is fixedly installed on the top of the connecting base 401, a connecting ring one 405 is fixedly installed on the top of the tower body one 404, and a plurality of threaded rods 406 are fixedly and circumferentially installed on the surface of the connecting ring one 405.
[0033] Specifically, the mounting hole three 402 is mounted on the surface of the threaded rod two 302 to fix the connecting base 401, the movable groove 403 is sleeved outside the limiting nut 305 to facilitate the connection of the connecting base 401 and the mounting plate 301, and the connecting ring one 405 and the threaded rod three 406 are used for mounting and fixing the tower body two 5.
[0034] In one embodiment, the bottom of the tower body two 5 is fixedly provided with a connecting ring two 501, a plurality of mounting hole fours 502 are arranged on the surface of the connecting ring two 501, the plurality of mounting hole fours 502 are sleeved on the surfaces of the plurality of threaded rod threes 406, the top of the tower body two 5 is fixedly provided with a connecting ring three 503, and a plurality of threaded rod fours 504 are fixedly arranged on the surface of the connecting ring three 503.
[0035] Specifically, the connecting ring two 501 is attached to the surface of the connecting ring one 405, the mounting hole four 502 is sleeved on the threaded rod three 406, and the nut is fixed, the connecting ring three 503 and the threaded rod four 504 are used for mounting and fixing the tower head 6.
[0036] In one embodiment, the bottom of the tower head 6 is fixedly provided with a connecting ring four 601, a plurality of mounting hole fives 602 are arranged on the surface of the connecting ring four 601, the plurality of mounting hole fives 602 are sleeved on the surfaces of the plurality of threaded rod fours 504, and two groups of cross arms 603 are arranged on the surface of the connecting ring four 601.
[0037] Specifically, the connecting ring four 601 is attached to the surface of the connecting ring three 503, the mounting hole five 602 is sleeved on the threaded rod four 504, the nut is fixed, the tower head 6 is fixed, and the two cross arms 603 are a group and are arranged on both sides of the tower head 6.
[0038] Working principle: before using the device, first dig a foundation pit in the position to be installed, place the fixed bottom plate 1 horizontally at the bottom of the foundation pit, then insert the four embedded steel pipes 2 into the four installation holes one 102, make the bottom surface of the embedded steel pipe 2 inserted into the ground, then place the installation plate 301 on the top of the embedded steel pipe 2, make the installation hole two 303 correspondingly sleeved on the surface of the threaded rod one 202, screw the connecting threaded rod 304 into the threaded hole one 101, first screw the nut on the top of the threaded rod one 202, then fix the installation plate 301, adjust the two limiting nuts 305 on the surface of the connecting threaded rod 304, one rotates tightly on the bottom of the installation plate 301, and the other rotates tightly on the top of the fixed bottom plate 1, which strengthens the connection between the installation plate 301 and the fixed bottom plate 1, finally backfill the foundation pit, insert steel plates in the gap between the fixed bottom plate 1 and the installation plate 301 to strengthen the stability, backfill the ground to the same level as the bottom of the installation plate 301, then complete the fixed installation of the power iron tower base, avoid the influence of using concrete pouring on the soil, and improve the construction efficiency; after completing the base fixing, install the connecting base 401 on the surface of the installation plate 301, make the installation hole three 402 sleeved on the surface of the threaded rod two 302, use the nut to fix, then make the installation hole four 502 on the bottom of the tower body two 5 sleeved on the threaded rod three 406, install the nut to fix, finally make the installation hole five 602 on the bottom of the tower head 6 sleeved on the surface of the threaded rod four 504, install the nut to fix, then complete the assembly of the power iron tower, which is divided into three sections of tower body assembly 4, tower body two 5 and tower head 6, and is assembled, which is convenient for transportation and construction.
[0039] The above is only a preferred embodiment of the present application, and is not intended to limit the present application in other forms. Any skilled person in the art can modify or change the above disclosed technical content to equivalent embodiments applied to other fields, but any simple modification, equivalent change and modification of the above embodiments made according to the technical essence of the present application still belongs to the protection scope of the technical scheme of the present application.
Claims
1. An assembled electric power tower, characterized by, The utility model relates to a tower body two (5) are installed on the top of tower body assembly (4), and the tower head (6) is installed on the top of tower body two (5). The surface of the fixed bottom plate (1) is provided with four threaded holes (101), and the four ends of the fixed bottom plate (1) are provided with mounting holes (102).
2. The assembled electric power tower according to claim 1, characterized in that: The surface of the embedded steel pipe (2) is movably embedded in the inside of the mounting hole (102), and the top end of the embedded steel pipe (2) is provided with a threaded groove (201) on the surface.
3. The assembled electric power tower according to claim 1, characterized in that: The connecting assembly (3) comprises a mounting plate (301), a plurality of threaded rods (302) are fixedly installed on the top of the mounting plate (301), four mounting holes (303) are formed on the surface of the mounting plate (301), four threaded rods (304) are movably embedded on the surface of the mounting plate (301), two limiting nuts (305) are threadedly installed on the surface of each of the four threaded rods (304), and the four threaded rods (304) are respectively threadedly installed in the four threaded holes (101).
4. The assembled electric power tower according to claim 1, characterized in that: The tower body assembly (4) comprises a connecting base (401), a plurality of mounting holes (402) are formed on the surface of the connecting base (401), the plurality of mounting holes (402) are respectively sleeved on the surfaces of the plurality of threaded rods (302), a movable groove (403) is formed in the bottom of the connecting base (401), the movable groove (403) is sleeved on the surface of the top of the four threaded rods (304), a tower body (404) is fixedly installed on the top of the connecting base (401), a connecting ring (405) is fixedly installed on the top of the tower body (404), and a plurality of threaded rods (406) are fixedly and circularly installed on the surface of the connecting ring (405).
5. The assembled electric power tower according to claim 1, characterized in that: The bottom of the tower body two (5) is fixedly installed with a connecting ring (501), a plurality of mounting holes (502) are formed on the surface of the connecting ring (501), the plurality of mounting holes (502) are correspondingly sleeved on the surfaces of the plurality of threaded rods (406), a connecting ring (503) is fixedly installed on the top of the tower body two (5), and a plurality of threaded rods (504) are fixedly and circularly installed on the surface of the connecting ring (503).
6. The assembled electric power tower according to claim 1, characterized in that: The bottom of the tower head (6) is fixedly installed with a connecting ring (601), a plurality of mounting holes (602) are formed on the surface of the connecting ring (601), the plurality of mounting holes (602) are correspondingly sleeved on the surfaces of the plurality of threaded rods (504), and two groups of cross arms (603) are installed on the surface of the connecting ring (601).
7. The assembled electric power tower according to claim 1, characterized in that: