Manual tramper for corners after earthwork backfilling

By using PVC pipes and connecting mechanisms, the problems of heavy weight and significant vibration of manual compactors have been solved, resulting in a more labor-saving and comfortable compaction operation.

CN223607838UActive Publication Date: 2025-11-28CHINA RAILWAY NO 9 GRP NO 7 ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202521408434.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-07-07
Publication Date
2025-11-28
Estimated Expiration
2035-07-07

AI Technical Summary

Technical Problem

The wooden handles of existing manual compactors are heavy, and the vibration is transmitted to the hands, increasing the labor intensity and discomfort of the operators.

Method used

Using PVC pipes instead of solid wood handles, combined with T-shaped or parallel double-bar connection mechanisms, reduces the weight of the compactor and decreases vibration transmission.

Benefits of technology

Reduce the labor intensity of operators, improve hand comfort, and reduce fatigue during long-term work.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223607838U_ABST
    Figure CN223607838U_ABST
Patent Text Reader

Abstract

The utility model discloses a manual tramper at a corner after earthwork backfilling, which belongs to the technical field of earthwork tamping and comprises a tamping plate, a connecting mechanism is fixedly assembled at the top of the tamping plate, an assembly plate is detachably and fixedly connected to the bottom of the tamping plate, and auxiliary crushing blocks which are circumferentially and uniformly distributed are integrally formed at the bottom of the assembly plate. The whole connecting mechanism is made of the PVC pipe, and the PVC pipe is a hollow pipe, so that in the using process, the whole weight of the tramper can be reduced, the labor intensity of an operator during tamping operation on soil is reduced, the physical strength of the operator is saved, and the working efficiency of the operator is improved. And meanwhile, transmission of vibration to the hand of an operator in the using process can be reduced, and the hand comfort degree of the operator holding the device by hand during long-time repeated operation is improved.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to earthwork ramming technical field, concretely relates to a kind of earthwork backfilling after corner place manual tamper. BACKGROUND

[0002] In the process of earthwork backfilling, ramming equipment is needed to carry out ramming operation to backfilled earthwork, and in the corner place after earthwork backfilling, since the volume occupied by mechanical equipment is larger, so mainly the way that construction personnel hold manual tamper is used to carry out ramming treatment in corner place.

[0003] The common manual ramming equipment in current market is mainly composed of steel ramming plate and wooden handle, and the steel plate and handle are connected by fixing screw.However, in actual use process, the equipment has the following shortcomings: first, wooden handle is usually made of solid wood stick, so that the overall weight is larger.When handle and ramming plate are combined into an integral whole, the labor intensity of operator is significantly increased when using the equipment to carry out compaction operation on soil, and more physical strength is needed in compaction process.In addition, due to the solid structure of wood stick, the vibration felt by operator in use process will be directly transmitted to hand, and long-time repeated operation may affect the comfort of operator grasping handle.Therefore, we propose a kind of earthwork backfilling after corner place manual tamper. UTILITARY MODEL CONTENT

[0004] The utility model aims at providing a kind of earthwork backfilling after corner place manual tamper to solve the problems raised in the above background.

[0005] To achieve the above object, the utility model provides the following technical scheme: a kind of earthwork backfilling after corner place manual tamper, including ramming plate, the top of the ramming plate is fixedly equipped with connecting mechanism;

[0006] The bottom of the ramming plate is detachably fixedly connected with assembly plate, and the bottom of the assembly plate is integrally formed with auxiliary crushing block that is uniformly distributed in circle;

[0007] The connecting mechanism is T-shaped single-rod type connecting mechanism or parallel double-rod type connecting mechanism.

[0008] Preferably, the four corners of the ramming plate are integrally formed with assembly part, the top four corners of the assembly plate are integrally formed with assembly block, and the assembly block and assembly part are fixedly equipped with fixing screw.

[0009] Preferably, the connecting mechanism is T-shaped single-rod type connecting mechanism.

[0010] The connecting mechanism comprises a first base fixedly connected at the top center of the tamping plate, one end of the first PVC pipe fixedly connected at the top of the first base, and the first connecting seat fixedly connected at the top of the first PVC pipe.

[0011] Preferably, the first base is fixedly connected with the tamping plate through the first reinforcing frames uniformly distributed in a circle.

[0012] Preferably, the first PVC pipe is provided with the first rubber sleeve at the connection with the first base and at the connection with the first connecting seat.

[0013] Preferably, the outer end of the second PVC pipe is provided with the first rubber plug, and the outer wall of the second PVC pipe is sleeved with the first anti-skid sleeve.

[0014] Preferably, the connecting mechanism is a parallel double-rod connecting mechanism.

[0015] The connecting mechanism comprises a second base fixedly connected at the top center of the tamping plate, the second connecting seat fixedly connected at the top of the second base, and the third PVC pipe fixedly connected at the top of the second connecting seat in a left-right symmetry.

[0016] Preferably, the second base is fixedly connected with the tamping plate through the second reinforcing frames uniformly distributed in a circle.

[0017] Preferably, the second connecting seat is in a Y shape, and the second connecting seat is integrally formed with the connecting grooves in a left-right symmetry at the top, the third PVC pipe is inserted into the connecting grooves, and the second rubber sleeve is arranged between the third PVC pipe and the connecting grooves.

[0018] Preferably, the top of the third PVC pipe is provided with the second rubber plug, the side wall of the third PVC pipe is fixedly connected with the positioning blocks, the number of the positioning blocks on the side wall of each third PVC pipe is two, and the second anti-skid sleeve is arranged between the two positioning blocks.

[0019] Compared with the prior art, the manual tamping device for the earth backfilling corner has the following beneficial effects: compared with the traditional wooden handle, the connecting mechanism of the whole device is made of PVC pipes, the PVC pipe is a hollow pipe material, which can not only reduce the overall weight of the tamping device, reduce the labor intensity of the operator when tamping the soil, save the physical strength of the operator, but also reduce the transmission of vibration to the hands of the operator during use, and increase the hand comfort of the operator when holding the device for a long time. BRIEF DESCRIPTION OF DRAWINGS

[0020] Figure 1 It is a perspective view of the connecting mechanism and the assembly plate after assembly.

[0021] Figure 2 It is a perspective view of the connecting mechanism and the assembly plate after assembly.

[0022] Figure 3 It is a bottom view of the assembly plate.

[0023] Figure 4 It is a perspective view of the connecting mechanism and the assembly plate after assembly. Figure 1

[0024] Figure 5 It is a perspective view of the connecting mechanism and the assembly plate after assembly.

[0025] Figure 6 It is a perspective view of the connecting mechanism and the assembly plate after assembly.

[0026] Figure 7 It is a perspective view of the connecting mechanism and the assembly plate after assembly.

[0027] Figure 8 It is a perspective view of the connecting mechanism and the assembly plate after assembly.

[0028] In the figure: 1, tamping plate; 2, assembly part; 3, assembly plate; 4, assembly block; 5, auxiliary crushing block; 6, connecting mechanism; 61, first base; 62, first PVC pipe; 63, first connecting seat; 64, second PVC pipe; 65, first reinforcing frame; 66, first rubber sleeve; 67, first rubber plug; 68, second base; 69, second connecting seat; 610, third PVC pipe; 611, second reinforcing frame; 612, connecting groove; 613, second rubber sleeve; 614, second rubber plug; 7, first anti-skid sleeve; 8, positioning block; 9, second anti-skid sleeve. DETAILED DESCRIPTION

[0029] The technical solutions in the embodiments of the utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the utility model.

[0030] Embodiment one

[0031] Please refer to Figure 1 , Figure 2 , Figure 3 and Figure 4 ​The utility model provides a technical scheme: a manual tamper for earthwork backfilling rear corner, including tamper board 1, tamper board 1 is the steel sheet of thickness 15mm, the top fixed assembly of tamper board 1 is equipped with connecting mechanism 6, and the tamper board 1 can be driven to carry out up and down action through handheld connecting mechanism 6, thereby tampering the soil of earthwork backfilling rear corner and carries out the tampering treatment.

[0032] The assembly part 2 is integrally formed at the four corners of the tamper board 1, and the assembly part 2 is an inclined chamfer with a certain angle. The bottom of the tamper board 1 is equipped with an assembly plate 3. The top of the assembly plate 3 is integrally formed with an assembly block 4 corresponding to the position of the assembly part 2. The assembly block 4 and the assembly part 2 are detachably connected and fixed by a fixing screw. The assembly plate 3 is a steel plate with a thickness of 7mm, as shown in the figure, the bottom of the assembly plate 3 is integrally formed with auxiliary crushing blocks 5 evenly distributed in a circle. The edge of the auxiliary crushing block 5 is provided with a relatively sharp inclined chamfer. Figure 4

[0033] Working principle: if there are many stones in the area during the process of tampering the soil, and the process of crushing stones by the tamper board 1 is relatively laborious, the assembly plate 3 can be assembled at the bottom of the tamper board 1. During the up and down movement of the tamper board 1, the auxiliary crushing block 5 can crush the stones, thereby enhancing the crushing efficiency of the stones.

[0034] Embodiment two

[0035] Compared with embodiment one, the difference of the present embodiment is that:

[0036] Specifically, referring to Figure 1 , Figure 5 and Figure 6 , the connecting mechanism 6 is a T-shaped single rod connecting mechanism.

[0037] The connecting mechanism 6 includes a first base 61, which is welded and fixed at the center of the tamper board 1. The top of the first base 61 is fixedly assembled with one end of a first PVC pipe 62. The other end of the first PVC pipe 62 is fixedly assembled with a first connecting seat 63, which is in an inverted T shape. The left and right ends of the first connecting seat 63 are respectively fixedly connected with second PVC pipes 64.

[0038] ​The first PVC pipe 62 is detachably and fixedly connected with the first base 61 and the first connecting seat 63 through fixing screws, and the second PVC pipe 64 is also detachably and fixedly connected with the first connecting seat 63 through fixing screws. The first PVC pipe 62 is a PVC pipe with a pipe diameter of 90 mm, and the second PVC pipe 64 is a PVC pipe with a diameter of 50 mm. The PVC pipes are used to replace the traditional solid wooden handle and ramming plate 1, which not only reduces the overall weight of the rammer, making the operator more labor-saving during soil ramming, but also reduces the transmission of vibration to the handle during ramming compared with the solid wooden handle, making the operator more comfortable during soil ramming.

[0039] As shown in Figure 5 The first reinforcing frame 65 is welded and fixed between the side wall of the first base 61 and the ramming plate 1, which can increase the stability of the connection between the first base 61 and the ramming plate 1.

[0040] As shown in Figure 6 The outer side walls of the bottom end and the top end of the first PVC pipe 62 are respectively sleeved with the first rubber sleeve 66, and the first rubber sleeve 66 is located in the first base 61 and the first connecting seat 63, respectively. Since the first PVC pipe 62 is vertically arranged, the first rubber sleeve 66 arranged at the connection between the first PVC pipe 62 and the first base 61 and the first connecting seat 63 can increase the friction between them, thereby strengthening the connection stability of the first PVC pipe 62 with the first base 61 and the first connecting seat 63, avoiding loosening of the connection between the first PVC pipe 62 and the first base 61 and the first connecting seat 63 during repeated ramming of the soil with the rammer, and causing safety hazards.

[0041] As shown in Figure 6 The outer side end of the second PVC pipe 64 is inserted with the first rubber plug 67, which seals the end of the second PVC pipe 64 to protect the operator from being scratched on the hand during holding the second PVC pipe 64. The outer side wall of the second PVC pipe 64 is sleeved with the first anti-skid sleeve 7, which can enhance the stability of the operator during gripping the second PVC pipe 64.

[0042] Working principle: as Figure 5As shown in the utility model, when the corner of the earthwork backfill is tamped, the first base 61, the first PVC pipe 62, the first connecting seat 63 and the second PVC pipe 64 are sequentially assembled and fixed, in the process of tamping, the operator holds the first anti-skid sleeve 7 of the outer wall of the second PVC pipe 64 with both hands, drives the tamping plate 1 to reciprocate in the up-down direction through the second PVC pipe 64, and tamps the soil at the corner through the tamping plate 1.

[0043] Example three

[0044] Compared with example one, the difference of the utility model lies in that:

[0045] Specifically, referring to Figure 2 , Figure 7 and Figure 8 , the connecting mechanism 6 is a parallel double-bar type connecting mechanism.

[0046] The connecting mechanism 6 comprises a second base 68, the top of the second base 68 is welded and fixed with a second connecting seat 69, and the top of the second connecting seat 69 is fixed and assembled with a third PVC pipe 610 in left-right symmetry.

[0047] The second base 68 is composed of a fixed part and a connecting part, the fixed part is a steel pipe with a hollow inside, which reduces the overall weight of the second base 68, and the fixed part is welded and fixed with the tamping plate 1, the connecting part is a circular steel plate, and the connecting part is used for connecting and fixing with the second connecting seat 69, a second reinforcing frame 611 is welded and fixed between the second base 68 and the tamping plate 1 in a circumferential uniform distribution, the stability of the connection and fixation between the second base 68 and the tamping plate 1 is increased by arranging the second reinforcing frame 611, the second connecting seat 69 is in Y shape, the bottom of the second connecting seat 69 is welded and fixed on the surface of the connecting part of the second base 68, the top of the second connecting seat 69 is integrally formed with a connecting groove 612 in left-right symmetry, the connecting groove 612 is used for the insertion of the third PVC pipe 610, and the installation position of the third PVC pipe 610 is fixed by the fixing screw screwed on the side wall of the second connecting seat 69 after the third PVC pipe 610 is inserted into the connecting groove 612, and the third PVC pipe 610 is a PVC pipe with a diameter of 50 mm.

[0048] As shown in the utility model, Figure 8 The bottom of the third PVC pipe 610 is sleeved with a second rubber sleeve 613, and the second rubber sleeve 613 is located in the connecting groove 612, the stability of the connection and fixation between the third PVC pipe 610 and the second connecting seat 69 is increased by arranging the second rubber sleeve 613, and the connection between the third PVC pipe 610 and the second connecting seat 69 is prevented from loosening in the process of moving up and down.

[0049] The top of the third PVC pipe 610 is equipped with a second rubber plug 614. The second rubber plug 614 is arranged to close the top of the third PVC pipe 610. Since the top of the third PVC pipe 610 is the cutting position of the pipe, the second rubber plug 614 can prevent the top of the third PVC pipe 610 from scratching the operator during use of the tool.

[0050] The outer wall of the third PVC pipe 610 is fixedly attached with a positioning block 8 by glue. The positioning block 8 is annular. Each outer wall of the third PVC pipe 610 is provided with two positioning blocks 8. A second anti-skid sleeve 9 is arranged between the two positioning blocks 8. The second anti-skid sleeve 9 is sleeved on the outer wall of the third PVC pipe 610. The second anti-skid sleeve 9 can enhance the stability when the third PVC pipe 610 is gripped.

[0051] Working principle: Compared with the technical solution in example two, the third PVC pipe 610 vertically arranged in left-right symmetry is adopted instead of the second PVC pipe 64 arranged horizontally. Since the height of the operator is different, the height position of the second PVC pipe 64 is fixed in example two. The operators with different heights may be affected by the gripping height when they grip the second PVC pipe 64 to operate the ramming plate 1, and the comfort degree is reduced. The outer wall of the third PVC pipe 610 is provided with a vertical gripping area. The operator can select the appropriate gripping position of the third PVC pipe 610 according to his own height, so as to enhance the comfort degree in the operation process.

Claims

1. A manual tamper for corner areas after earthwork backfilling, comprising a tamper plate (1), characterized in that, The top of the ramming plate (1) is fixedly provided with a connecting mechanism (6); The bottom of the ramming plate (1) is detachably fixedly connected with an assembly plate (3), and the bottom of the assembly plate (3) is integrally formed with auxiliary crushing blocks (5) which are uniformly distributed in a circle; The connecting mechanism (6) is a T-shaped single-rod connecting mechanism or a parallel double-rod connecting mechanism.

2. A manual corner tamper for use after earthwork backfilling according to claim 1, characterised in that: The four corners of the ramming plate (1) are integrally formed with assembly portions (2), the top of the assembly plate (3) is integrally formed with assembly blocks (4) at the four corners, and the assembly blocks (4) and the assembly portions (2) are fixedly provided with fixing screws.

3. A manual corner tamper for use after earthwork backfilling according to claim 1, characterised in that: The connecting mechanism (6) is a T-shaped single-rod connecting mechanism; The first base (61) is fixedly connected with the ramming plate (1) and is fixedly connected with first reinforcing frames (65) which are uniformly distributed in a circle.

4. A manual corner tamper for use after earthwork backfilling according to claim 3, characterised in that: The connecting portions of the first PVC pipe (62) and the first base (61) and the connecting portions of the first PVC pipe (62) and the first connecting seat (63) are respectively provided with first rubber sleeves (66).

5. A manual compactor for corners after earthwork backfilling according to claim 3, characterized in that: The outer side of the second PVC pipe (64) is provided with a first rubber plug (67), and the outer side wall of the second PVC pipe (64) is sleeved with a first anti-skid sleeve (7).

6. A manual corner tamper for use after earthwork backfilling according to claim 3, characterised in that: The connecting mechanism (6) is a parallel double-rod connecting mechanism; 7. A manual corner tamper for use after earthwork backfilling according to claim 1, characterised in that: The second base (68) is fixedly connected with the ramming plate (1) and is fixedly connected with second reinforcing frames (611) which are uniformly distributed in a circle. The second connecting seat (69) is in the shape of Y, and the top of the second connecting seat (69) is integrally formed with connecting grooves (612) which are symmetrically distributed on the left and right sides, the third PVC pipe (610) is inserted into the connecting grooves (612), and the third PVC pipe (610) and the connecting grooves (612) are provided with second rubber sleeves (613).

8. A manual corner tamper for use after earthwork backfilling according to claim 7, characterised in that: The top of the third PVC pipe (610) is provided with a second rubber plug (614), the side wall of the third PVC pipe (610) is fixedly connected with positioning blocks (8), the number of the positioning blocks (8) on the side wall of each third PVC pipe (610) is two, and the two positioning blocks (8) are provided with a second anti-skid sleeve (9).

9. A manual corner tamper for use after earthwork backfilling according to claim 7, characterised in that: ​ 10. A manual compactor for corners after earthwork backfilling according to claim 7, characterized in that: ​