Environment-friendly exploration drilling machine inner pipe protection device

By using the connecting strips and lifting mechanism of the green exploration drilling rig inner pipe protection device, the problem of the exploration drilling rig inner pipe falling off was solved, and safe and efficient drilling operations were achieved.

CN223707557UActive Publication Date: 2025-12-23CHINA GEOLOGICAL SURVEY CHANGSHA NATURAL RESOURCES COMPREHENSIVE SURVEY CENT
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520590212.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-03-31
Publication Date
2025-12-23
Estimated Expiration
2035-03-31

AI Technical Summary

Technical Problem

After the exploration drilling rig has finished drilling, the inner tube is prone to falling off, causing damage and threatening the safety of the workers, as well as affecting the efficiency of the operation.

Method used

A green exploration drilling rig internal pipe protection device is adopted, including connecting strips, fixing mechanism and lifting mechanism. The internal pipe is connected through the fixing mechanism and connected to the external crane through the lifting mechanism to ensure a stable connection between the internal pipe and the retrieval device and prevent it from falling off.

Benefits of technology

To ensure that the inner tube and the retrieval device do not separate during the tilting and lowering process, the project can proceed safely and smoothly, improving operational efficiency and protecting the safety of workers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223707557U_ABST
    Figure CN223707557U_ABST
Patent Text Reader

Abstract

The utility model discloses a green exploration drilling machine inner pipe protection device which comprises a connecting strip, a fixing mechanism and a hoisting mechanism, the fixing mechanism is arranged at one end of the connecting strip, and a positioning piece is arranged at the end, away from the fixing mechanism, of the connecting strip; the end, provided with the positioning piece, of the connecting strip is bent towards the end, provided with the fixing mechanism, of the connecting strip, and the fixing mechanism is used for being detachably connected with the positioning piece. A hoisting mechanism is arranged on one side of the connecting strip away from two ends. According to the technical scheme provided by the utility model, the connecting strip is connected with the inner pipe through the fixing mechanism and the positioning piece, and then is connected with an external crane through the hoisting mechanism, so that the inner pipe is stably connected with the fisher, the inner pipe is prevented from being separated from the fisher in an inclined state, the normal proceeding of a project is ensured, and the production safety of surrounding workers is ensured.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The utility model relates to geological survey technical field, especially relates to green survey drilling machine inner tube protection device. BACKGROUND

[0002] In the geological exploration process, drive drilling tool from the underground drilling physical geological data core, mine core, rock cutting, liquid sample, gaseous sample etc.

[0003] The survey drilling machine is through the way of connecting of multiple inner tubes in turn, and carries out the underground drilling. After the drilling is finished, the survey drilling machine will take out each inner tube in turn through the fisher, and when the survey drilling machine takes out the inner tube to the wellhead through the fisher, the inner tube needs to be put down. At this time, the bottom end of the inner tube will abut against the ground, and then the inner tube is put down obliquely. In the process of putting down the inner tube obliquely, the inner tube and the fisher are easy to separate, resulting in the falling of the inner tube. Due to the length and weight of the inner tube, the fallen inner tube is easy to be damaged, and the kinetic energy of the fallen inner tube is large, which will threaten the safety of the surrounding operating staff, seriously affect the normal progress of the drilling operation, and reduce the operating efficiency. SUMMARY

[0004] The main purpose of the utility model is to provide green survey drilling machine inner tube protection device, which aims at solving the problem that the inner tube is easy to fall after the survey drilling machine takes out the inner tube to the wellhead through the fisher.

[0005] In order to achieve the above purpose, the technical scheme provided by the utility model is:

[0006] The green survey drilling machine inner tube protection device comprises a connecting strip, a fixing mechanism and a lifting mechanism, the fixing mechanism is arranged at one end of the connecting strip, and a positioning piece is arranged at the end of the connecting strip away from the fixing mechanism; the end of the connecting strip provided with the positioning piece is bent towards the end of the connecting strip provided with the fixing mechanism, and the fixing mechanism is used for detachably connecting the positioning piece; the lifting mechanism is arranged on the side of the connecting strip away from both ends.

[0007] Preferably, the connecting strip is arranged symmetrically along the lifting mechanism, and the lifting mechanism and the connecting strip are detachably connected.

[0008] Preferably, the lifting mechanism comprises a lifting ring and a connecting column, the lifting ring is connected to one end of the connecting column, and the end of the connecting column away from the lifting ring is detachably connected to the connecting strip.

[0009] Preferably, the connecting strip is provided with a connecting through hole on one side away from two ends; the hoisting mechanism comprises a limiting nut, an outer thread is arranged on one end of the connecting column away from the lifting ring, the limiting nut is located between the connecting through hole and two ends of the connecting strip, and one end of the connecting column away from the lifting ring is used for being screwed through the connecting through hole and the limiting nut.

[0010] Preferably, the connecting strip is provided with a first threaded through hole on one end away from the positioning member, the first threaded through hole extends along one end of the connecting strip to the other end of the connecting strip; the fixing mechanism comprises a screw rod and a handle, the handle is arranged on one side of the first threaded through hole away from the positioning member; one end of the screw rod is connected with the handle, and the other end of the screw rod is screwed with the first threaded through hole.

[0011] Preferably, the connecting strip is provided with a second threaded through hole on one end away from the first threaded through hole, and the second threaded through hole is coaxially arranged with the first threaded through hole; the positioning member comprises a positioning bolt, the positioning bolt is located on one side of the two threaded through holes away from the first threaded through hole, and the positioning bolt is screwed with the second threaded through hole and extends to between two ends of the connecting strip.

[0012] Preferably, the connecting strip is provided with hooks on one side away from between two ends of the connecting strip, and the hooks are inclined to one side away from the hoisting mechanism.

[0013] Preferably, the hooks are symmetrically arranged along the hoisting mechanism.

[0014] Compared with the prior art, the utility model has at least the following beneficial effects:

[0015] Through the fixing mechanism and the positioning member, the connecting strip is connected with the inner tube, and then the hoisting mechanism is connected with the external crane, so that the inner tube and the fishing tool are stably connected, the inner tube is prevented from being separated from the fishing tool in an inclined state, the normal engineering construction is ensured, and the production safety of surrounding workers is ensured. BRIEF DESCRIPTION OF DRAWINGS

[0016] In order to more clearly illustrate the technical scheme in the embodiments of the utility model or the prior art, the following will briefly introduce the drawings needed to be used in the embodiment or the prior art description, and obviously, the drawings in the following description are only some embodiments of the utility model, and for those skilled in the art, other drawings can be obtained according to the structures shown in these drawings without creating labor.

[0017] Fig. 1 It is a structural schematic view of the embodiment of the utility model green exploration drilling machine inner tube protection device;

[0018] Fig. 2 This is a schematic diagram of the structure when the connecting bar is inserted into the well to retrieve the cable.

[0019] Explanation of icon numbers:

[0020] 1-Connecting strip; 11-First threaded through hole; 12-Second threaded through hole; 13-Hook; 14-Connecting through hole;

[0021] 2-Fixing mechanism; 21-Screw; 22-Handle;

[0022] 3-Lifting mechanism; 31-Lifting ring; 32-Connecting column; 33-Limit nut;

[0023] 4-Locking bolts;

[0024] The realization of the purpose, functional features and advantages of this utility model will be further explained in conjunction with the embodiments and with reference to the accompanying drawings. Detailed Implementation

[0025] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments. Based on the embodiments of the present utility model, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the protection scope of the present utility model.

[0026] It should be noted that all directional indicators (such as up, down, left, right, front, back, etc.) in this utility model embodiment are only used to explain the relative positional relationship and movement of each component in a certain specific posture (as shown in the figure). If the specific posture changes, the directional indicator will also change accordingly.

[0027] Furthermore, in this utility model, the use of terms such as "first," "second," etc., is for descriptive purposes only and should not be construed as indicating or implying their relative importance or implicitly specifying the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include at least one of that feature. In the description of this utility model, "multiple" means at least two, such as two, three, etc., unless otherwise explicitly specified.

[0028] In this utility model, unless otherwise explicitly specified and limited, the terms "connection," "fixing," etc., should be interpreted broadly. For example, "fixing" can mean a fixed connection, a detachable connection, or an integral part; it can mean a mechanical connection or an electrical connection; it can mean a direct connection or an indirect connection through an intermediate medium; it can mean the internal communication of two components or the interaction between two components, unless otherwise explicitly limited. Those skilled in the art can understand the specific meaning of the above terms in this utility model according to the specific circumstances.

[0029] Furthermore, the technical solutions of the various embodiments of this utility model can be combined with each other, but only if they are based on the ability of those skilled in the art to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be considered that such combination of technical solutions does not exist and is not within the scope of protection claimed by this utility model.

[0030] This utility model proposes a green exploration drilling rig internal pipe protection device.

[0031] like Figs. 1-2 The green exploration drilling rig inner pipe protection device shown includes a connecting strip 1, a fixing mechanism 2, and a lifting mechanism 3. The fixing mechanism 2 is located at one end of the connecting strip 1, and a positioning element is located at the end of the connecting strip 1 away from the fixing mechanism 2. The end of the connecting strip 1 with the positioning element is bent toward the end of the connecting strip 1 with the fixing mechanism 2. The fixing mechanism 2 is used to detachably connect the positioning element. The lifting mechanism 3 is located on the side of the connecting strip 1 away from both ends.

[0032] The connecting strip 1 is connected to the inner pipe through the fixing mechanism 2 and the positioning component, and then connected to the external crane through the lifting mechanism 3, so that the inner pipe and the retrieval device are firmly connected, preventing the inner pipe from separating from the retrieval device when it is tilted, ensuring the normal progress of the project, and ensuring the production safety of the surrounding workers.

[0033] The connecting bar 1 is symmetrically arranged along the lifting mechanism 3, and the lifting mechanism 3 and the connecting bar 1 are detachably connected. The connecting bar 1 is symmetrically arranged along the lifting mechanism 3 to form a U-shape to ensure a stable center of gravity during operation.

[0034] The lifting mechanism 3 includes a lifting ring 31 and a connecting column 32. The lifting ring 31 is connected to one end of the connecting column 32, and the end of the connecting column 32 away from the lifting ring 31 is detachably connected to the connecting bar 1.

[0035] A connecting through hole 14 is provided on the side of the connecting strip 1 away from both ends; the lifting mechanism 3 includes a limiting nut 33, and the end of the connecting column 32 away from the lifting ring 31 is provided with an external thread. The limiting nut 33 is located between the connecting through hole 14 and both ends of the connecting strip 1. The end of the connecting column 32 away from the lifting ring 31 is used to pass through the connecting through hole 14 and the limiting nut 33 for threaded connection. The separate structure of the lifting mechanism 3 and the connecting strip 1 makes it easy for the connecting strip 1 to extend into the inner tube as a hook 13 to lift the fallen cable.

[0036] A first threaded through hole 11 is formed at the end of the connecting strip 1 furthest from the positioning member. The first threaded through hole 11 extends from one end of the connecting strip 1 toward the other end. The fixing mechanism 2 includes a screw 21 and a handle 22. The handle 22 is located on the side of the first threaded through hole 11 furthest from the positioning member. One end of the screw 21 is connected to the handle 22, and the other end of the screw 21 is threadedly connected to the first threaded through hole 11. The handle 22 adjusts the distance between the two ends of the screw 21 extending through the connecting strip 1, so as to facilitate the alignment of the screw 21 and the positioning member after the inner tube is inserted.

[0037] A second threaded through hole 12 is opened at the end of the connecting strip 1 away from the first threaded through hole 11. The second threaded through hole 12 and the first threaded through hole 11 are coaxially arranged. The positioning element includes a positioning bolt 4, which is located on the side of the second threaded through hole away from the first threaded through hole 11. The positioning bolt 4 is threadedly connected to the second threaded through hole 12 and extends to the two ends of the connecting strip 1. Since it is inconvenient to observe the screw 21 after it is inserted into the inner tube, the positioning bolt 4 is inserted into the inner tube first, then the screw 21 is aligned with the inner tube and the handle 22 is rotated so that the screw 21 abuts against the positioning bolt 4, thereby locking the inner tube and the retrieval device. The positioning bolt 4 and the second threaded through hole 12 are threadedly connected, which makes it easy to adjust the distance between the two ends of the connecting strip where the positioning bolt 4 extends, according to the actual use.

[0038] Hooks 13 are respectively installed on one side of the connecting bar 1 away from the two ends of the connecting bar 1, and the hooks 13 are tilted away from the lifting mechanism 3. The lifting mechanism 3 and the connecting bar 1 are separated, and then the external crane is connected through the fixing mechanism 2 and the positioning component. The connecting bar 1 is extended into the well so that the multiple hooks 13 cooperate to hook the cable. Finally, the external adjustment raises the connecting bar 1 so that the cable of the multiple hooks 13 is raised to the outside of the well.

[0039] Each hook 13 is symmetrically arranged along the lifting mechanism 3.

[0040] Specifically, six hooks 13 are provided on the outer side of the connecting strip 1.

[0041] The above description is only a preferred embodiment of the present utility model and does not limit the patent scope of the present utility model. All equivalent structural transformations made under the inventive concept of the present utility model using the contents of the present utility model specification and drawings, or direct / indirect applications in other related technical fields, are included within the patent protection scope of the present utility model.

Claims

1. A green exploration drilling rig internal pipe protection device, characterized in that, The device includes a connecting strip, a fixing mechanism, and a lifting mechanism. The fixing mechanism is located at one end of the connecting strip, and a positioning element is located at the end of the connecting strip away from the fixing mechanism. The end of the connecting strip with the positioning element bends toward the end of the connecting strip with the fixing mechanism, and the fixing mechanism is used to detachably connect the positioning element. The lifting mechanism is located on the side of the connecting strip away from both ends.

2. The green exploration drilling rig inner pipe protection device according to claim 1, characterized in that, The connecting strips are symmetrically arranged along the lifting mechanism, and the lifting mechanism and the connecting strips are detachably connected.

3. The green exploration drilling rig inner pipe protection device according to claim 2, characterized in that, The lifting mechanism includes a lifting ring and a connecting column. The lifting ring is connected to one end of the connecting column, and the end of the connecting column away from the lifting ring is detachably connected to the connecting strip.

4. The green exploration drilling rig inner pipe protection device according to claim 3, characterized in that, The connecting bar has a connecting through hole on one side away from both ends; the lifting mechanism includes a limiting nut, the connecting column has an external thread on one end away from the lifting ring, the limiting nut is located between the connecting through hole and both ends of the connecting bar, and the connecting column is used to pass through the connecting through hole and the limiting nut for threaded connection.

5. The green exploration drilling rig inner pipe protection device according to any one of claims 2-4, characterized in that, The connecting strip has a first threaded through hole at one end away from the positioning member, and the first threaded through hole extends from one end of the connecting strip to the other end of the connecting strip; the fixing mechanism includes a screw and a handle, the handle is disposed on the side of the first threaded through hole away from the positioning member; one end of the screw is connected to the handle, and the other end of the screw is threadedly connected to the first threaded through hole.

6. The green exploration drilling rig inner pipe protection device according to claim 5, characterized in that, The connecting strip has a second threaded through hole at one end away from the first threaded through hole, and the second threaded through hole and the first threaded through hole are coaxially arranged; the positioning element includes a positioning bolt, which is located on the side of the two threaded through holes away from the first threaded through hole, and the positioning bolt is threadedly connected to the second threaded through hole and extends to the two ends of the connecting strip.

7. The green exploration drilling rig inner pipe protection device according to any one of claims 2-4, characterized in that, Hooks are respectively provided on the side of the connecting bar away from the two ends of the connecting bar, and the hooks are tilted away from the lifting mechanism.

8. The green exploration drilling rig inner pipe protection device according to claim 7, characterized in that, Each of the hooks is symmetrically arranged along the lifting mechanism.