Wire erecting tool for overhead line

By using overhead line conductor erection tools, and employing traction ropes and winches for conductor deployment and tensioning, the problems of low construction efficiency and safety risks were solved, achieving an efficient and safe conductor erection process.

CN223771651UActive Publication Date: 2026-01-06SINOHYDRO ENG BUREAU 4
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520088419.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-01-15
Publication Date
2026-01-06
Estimated Expiration
2035-01-15

AI Technical Summary

Technical Problem

The existing overhead line conductor erection is inefficient, the construction quality is difficult to control, and there are safety risks associated with working at heights, especially under adverse weather conditions.

Method used

An overhead line conductor erection tool is used, including a tower frame, pulleys, traction rope, grounding pulley, and traction machine. The conductor is laid out and tightened by the traction rope and winch, reducing the number of people and time spent on high-altitude work.

Benefits of technology

It improved construction efficiency, reduced the time spent working at heights, improved the working environment, enhanced construction safety, and reduced the impact of climate on construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223771651U_ABST
    Figure CN223771651U_ABST
Patent Text Reader

Abstract

The utility model discloses an overhead line lead erecting tool, which relates to the technical field of power overhead lines and comprises an iron tower frame, pulleys are mounted on two sides of the top end of the iron tower frame, a traction rope is attached to the tops of the pulleys, a walking board is mounted at one end of the traction rope, and the traction rope is connected with one end of a lead through the walking board. The other end of the wire is connected with the pay-off machine; and the other end of the traction rope is connected with a traction machine. According to the overhead line lead erecting tool, an overhead lead is erected by adopting a traction method of the traction rope and the winching machine, so that the number of constructors for erecting the lead is reduced, and the continuity of on-site overhead line lead erecting is accelerated; and meanwhile, the sag is observed by using the total station, so that a guarantee is provided for the subsequent line tightening construction of the whole line, the overall construction time of a project is shortened, the direct cost investment of the project is reduced, certain economic and social benefits are generated, and the method has very strong practical guiding significance.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of overhead power line technology, specifically to a tool for erecting overhead power line conductors. Background Technology

[0002] Overhead lines mainly refer to exposed overhead lines, erected above the ground. They are power transmission lines that use insulators to fix the transmission conductors to towers standing upright on the ground to transmit electrical energy. They are relatively easy to erect and maintain, and have lower costs. However, they are easily affected by weather and environmental factors (such as strong winds, lightning strikes, pollution, ice, and snow), which can cause faults. At the same time, the entire transmission corridor occupies a large area of ​​land and is prone to causing electromagnetic interference to the surrounding environment. The main components of overhead lines include: conductors and lightning protection wires (overhead ground wires), towers, insulators, hardware, tower foundations, guy wires, and grounding devices.

[0003] Currently, the traditional construction method for overhead line conductor erection is to first erect the conductor manually and then tighten it. Both conductor laying and tightening are high-altitude operations, which make it difficult for personnel to move on the tower and are easily affected by rain and wind. This results in slow construction efficiency, difficulty in controlling construction quality, and a high risk of safety accidents such as falls from heights and being struck by objects from above.

[0004] To further improve the speed and quality of overhead line conductor erection and reduce the time spent by construction workers at height, our unit has summarized the conductor erection process using a winch and traction rope, based on the construction of the Guoneng Qingyu 900MW photovoltaic overhead line conductor. This method can reduce the conductor erection time, reduce the time workers spend at height, and improve construction efficiency, thus having certain advantages. Summary of the Invention

[0005] In view of the shortcomings of the prior art, this utility model provides an overhead line conductor erection tool, which solves the problems mentioned in the background art.

[0006] To achieve the above objectives, this utility model is implemented through the following technical solution: an overhead line conductor erection tool, including an iron tower, pulleys are installed on both sides of the top of the iron tower, a traction rope is attached to the top of the pulleys, a guide plate is installed at one end of the traction rope, the traction rope is connected to one end of the conductor through the guide plate, and the other end of the conductor is connected to a wire laying machine.

[0007] The other end of the traction rope is connected to the traction machine, and the middle of the traction rope passes through the top of the grounding pulley.

[0008] Optionally, the grounding trolley includes a base plate, a connecting seat is fixedly connected to the top of the base plate, the top of the connecting seat is connected to one end of the cable, and the other end of the cable is connected to a guide pulley.

[0009] Optionally, the cables are distributed in a crisscross pattern at equal intervals.

[0010] Optionally, the size of the guide pulley is consistent with the size of the pulley.

[0011] Optionally, the traction machine includes a traction roller shaft, both ends of which are fitted with limit discs, and both ends of the traction roller shaft pass through the top of two support plates respectively, with ground nails fixedly connected to the bottom edge of the support plates.

[0012] The outer edge of the limiting plate is provided with a toothed ring;

[0013] A drive shaft connected to the support plate is arranged parallel to the lower part of the traction roller shaft. A reduction motor connected to the support plate is provided at one end of the drive shaft. A transmission gear meshing with a gear ring is sleeved on the outside of the drive shaft. Two guide wheel sets are arranged parallel to the end of the support plate near the grounding trolley.

[0014] Optionally, the traction roller shaft is connected to one end of the traction rope.

[0015] Optionally, the guide wheel assembly consists of a positioning shaft, a ball shaft, and a guide wheel disk, with the ball shaft located in the middle of the guide wheel disk and the positioning shaft passing horizontally through the middle of the ball shaft.

[0016] Optionally, the central axes of the positioning shaft, ball shaft, and guide wheel disk coincide.

[0017] This utility model provides a tool for erecting overhead power line conductors, which has the following advantages:

[0018] This overhead line conductor erection tool does not require additional special equipment or special operations personnel. The wire laying is carried out by suspending a wire laying pulley on the overhead iron tower and using a traction rope and winch. The process is simple and easy to operate, and it is suitable for the construction of lines below 35kV.

[0019] Both conductor laying and tensioning are high-altitude operations. This method can reduce the number of workers required for high-altitude operations, effectively shorten the high-altitude operation time, improve the working environment, and make the construction safer.

[0020] It can effectively improve the work efficiency of construction workers, reduce the impact of climate on construction operations, and shorten the construction time of conductor erection. Attached Figure Description

[0021] Figure 1 This is a schematic front view of the utility model;

[0022] Figure 2 This is a partial schematic diagram of the China Railway tower frame of this utility model;

[0023] Figure 3This is a partially enlarged schematic diagram of the travel plate in this utility model;

[0024] Figure 4 This is an enlarged schematic diagram of the traction machine in this utility model;

[0025] Figure 5 This is an enlarged schematic diagram of the limiting plate in this utility model;

[0026] Figure 6 This is a side view of the traction machine in this utility model.

[0027] In the diagram: 1. Iron tower frame; 2. Traction rope; 3. Walking board; 4. Conductor; 5. Pulley; 6. Grounding pulley; 601. Base plate; 602. Connecting seat; 603. Cable; 604. Guide pulley; 7. Traction machine; 701. Traction roller; 702. Limiting plate; 703. Support plate; 704. Ground spike; 705. Gear ring; 706. Drive shaft; 707. Gear motor; 708. Drive gear; 709. Guide wheel assembly; 8. Cable laying machine. Detailed Implementation

[0028] The technical solutions of the present utility model will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present utility model. Obviously, the described embodiments are only some embodiments of the present utility model, and not all embodiments.

[0029] In the description of this utility model, unless otherwise stated, "a plurality of" means two or more; the terms "upper," "lower," "left," "right," "inner," "outer," "front end," "rear end," "head," "tail," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing this utility model and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of this utility model. In addition, the terms "first," "second," "third," etc., are used for descriptive purposes only and should not be construed as indicating or implying relative importance.

[0030] In the description of this utility model, it should be noted that, unless otherwise explicitly specified and limited, the terms "connected" and "linked" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium. Those skilled in the art can understand the specific meaning of the above terms in this utility model based on the specific circumstances.

[0031] Please see Figures 1 to 6This utility model provides a technical solution: an overhead line conductor erection tool, including a tower frame 1, with pulleys 5 installed on both sides of the top of the tower frame 1, a traction rope 2 attached to the top of the pulleys 5, a guide plate 3 installed at one end of the traction rope 2, the traction rope 2 being connected to one end of the conductor 4 through the guide plate 3, and the other end of the conductor 4 being connected to a wire laying machine 8.

[0032] The other end of the traction rope 2 is connected to the traction machine 7, and the middle of the traction rope 2 passes through the top of the grounding pulley 6.

[0033] In this embodiment, as Figure 1 As shown, the grounding trolley 6 includes a base plate 601, a connecting seat 602 is fixedly connected to the top of the base plate 601, the top of the connecting seat 602 is connected to one end of the cable 603, and the other end of the cable 603 is connected to a guide pulley 604.

[0034] In this embodiment, as Figure 1 As shown, the 603 cables are distributed in a crisscross pattern at equal intervals.

[0035] In this embodiment, as Figure 1 As shown, the dimensions of guide pulley 604 are the same as those of pulley 5.

[0036] In this embodiment, as Figure 1 As shown, the traction machine 7 includes a traction roller shaft 701, with limit plates 702 sleeved at both ends of the traction roller shaft 701. The two ends of the traction roller shaft 701 pass through the top of two support plates 703 respectively, and ground nails 704 are fixedly connected to the bottom edge of the support plates 703.

[0037] The outer edge of the limiting plate 702 is provided with a toothed ring 705;

[0038] A drive shaft 706 connected to a support plate 703 is provided parallel below the traction roller shaft 701. A reduction motor 707 connected to the support plate 703 is provided at one end of the drive shaft 706. A transmission gear 708 meshing with a gear ring 705 is sleeved on the outside of the drive shaft 706. Two guide wheel sets 709 are provided parallel to one end of the support plate 703 near the grounding trolley 6.

[0039] In this embodiment, as Figure 1 As shown, the traction roller shaft 701 is connected to one end of the traction rope 2.

[0040] In this embodiment, as Figure 1 As shown, the guide wheel assembly 709 consists of a positioning shaft, a ball shaft, and a guide wheel disc. The ball shaft is located in the middle of the guide wheel disc, and the positioning shaft runs horizontally through the middle of the ball shaft.

[0041] In this embodiment, as Figure 1 As shown, the central axes of the positioning shaft, ball shaft, and guide wheel disk coincide.

[0042] The method of using a tool for erecting overhead power line conductors is as follows:

[0043] Pulleys 5 are installed on both sides of the erected iron tower 1; a traction machine 7 is installed, and a grounding pulley 6 is installed between the traction machine 7 and the nearest iron tower 1, with the distance between the grounding pulley 6 and the traction machine 7 ranging from 5 to 10 meters; one end of the traction rope 2 is sequentially passed through the pulleys 5, guide pulleys 604, and guide wheel group 709 and then connected to the traction roller shaft 701; the other end of the traction rope 2 is connected to the conductor 4 through the walkway 3; the reduction motor 707 drives the transmission shaft 706 and the transmission gear 708 to rotate, and the traction roller shaft 701 winds up the traction rope 2 by the meshing of the transmission gear 708 and the gear ring 705; the traction rope 2 pulls the conductor 4 sequentially through multiple pulleys 5, forming the erection of the conductor 4.

[0044] Example: The Yumen "solar thermal energy storage + photovoltaic + wind power" demonstration project site is located within the Hongliuquan wind-solar-storage integrated energy demonstration base in Yumen City. The site is approximately 40 km southwest of Yumen City and approximately 22 km southeast of Huahai Town, Yumen City. The site has undulating terrain, with the ground sloping from southeast to northwest. The natural elevation of the site is between 1260 and 1395 m, with a comprehensive slope of approximately 1.6%, belonging to a gently sloping alluvial plain landform unit in front of the mountains.

[0045] This project has a planned installed capacity of 200MW, with a total of 40 wind turbines. Specifically, it will install 40 5.0MW wind turbines, numbered F1 to F40. Each turbine will be equipped with a box-type transformer. Eight 35kV overhead lines will connect to a newly built 110kV substation, and one additional 110kV line will connect to the 330kV Xiaojinwan substation. The project includes site roads, power collection lines, transmission lines, and other related ancillary facilities.

[0046] The Yumen "solar thermal energy storage + photovoltaic + wind power" demonstration project adopted the "winch + traction rope erection of conductors" method in the construction of the 110kV transmission line of the collection line project. This method solved the problem of tight construction period, shortened the construction period and reduced costs, and was highly recognized by the superior unit.

[0047] The above description is only a preferred embodiment of the present utility model, but the protection scope of the present utility model is not limited thereto. Any equivalent substitutions or changes made by those skilled in the art within the technical scope disclosed in the present utility model, based on the technical solution and inventive concept of the present utility model, should be included within the protection scope of the present utility model.

Claims

1. An overhead line conductor erection tool comprising a tower mast (1), characterized in that: The top end of the iron tower (1) is provided with a pulley (5) on both sides, the top of the pulley (5) is matched with a traction rope (2), one end of the traction rope (2) is provided with a walk plate (3), the traction rope (2) is connected with one end of a wire (4) through the walk plate (3), the other end of the wire (4) is connected with a wire laying machine (8). The other end of the traction rope (2) is connected with a traction machine (7), and the middle part of the traction rope (2) penetrates the top end of the ground trolley (6).

2. An aerial conductor stringing tool according to claim 1, wherein: The ground trolley (6) comprises a base plate (601), the top of the base plate (601) is fixedly connected with a connecting seat (602), the top end of the connecting seat (602) is connected with one end of a cable (603), and the other end of the cable (603) is connected with a guide pulley (604).

3. An aerial conductor erection tool as claimed in claim 2, characterised in that: The cable (603) is cross-shaped and equally spaced.

4. An aerial line conductor erection tool according to claim 2, characterized in that: The size of the guide pulley (604) is consistent with the size of the pulley (5).

5. An aerial line conductor erection tool according to claim 1, characterized in that: The traction machine (7) comprises a traction roller shaft (701), both ends of the traction roller shaft (701) are sleeved with a limiting disc (702), both ends of the traction roller shaft (701) penetrate the top of two support plates (703) respectively, and the bottom end edges of the support plates (703) are fixedly connected with ground nails (704). The outer edge of the limiting disc (702) is provided with a gear ring (705). A transmission shaft (706) connected with the support plate (703) is arranged in parallel below the traction roller shaft (701), one end of the transmission shaft (706) is provided with a speed reducer motor (707) connected with the support plate (703), the outer part of the transmission shaft (706) is sleeved with a transmission gear (708) engaged with the gear ring (705), and two guide wheel groups (709) are arranged in parallel at one end of the support plate (703) close to the ground trolley (6).

6. An overhead line conductor erection tool according to claim 5, characterised in that: The traction roller shaft (701) is connected with one end of the traction rope (2).

7. An aerial line conductor erection tool as claimed in claim 5, characterised in that: The guide wheel group (709) is composed of a positioning shaft, a ball shaft and a guide wheel disc, the ball shaft is located in the middle of the guide wheel disc, and the middle part of the ball shaft penetrates the positioning shaft horizontally.

8. An overhead line conductor erection tool according to claim 7, characterised in that: The central axes of the positioning shaft, the ball shaft and the guide wheel disc coincide with each other.