Simple operation system for pipe jacking construction
By designing a simple operating system and adopting hoisting and pipe jacking mechanisms, the high cost and low efficiency of traditional cranes for transporting materials have been solved, enabling efficient and low-cost pipe jacking construction that can adapt to complex environments and meet environmental protection requirements.
Patent Information
- Application Number
- CN202520676997.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-04-11
- Publication Date
- 2026-01-13
- Estimated Expiration
- 2035-04-11
AI Technical Summary
Traditional methods of using cranes to transport materials in pipe jacking construction suffer from high costs, low efficiency, and construction progress is easily restricted by weather and space, which significantly impacts construction costs and efficiency, especially in large-scale municipal projects.
A simplified operating system for pipe jacking construction was designed, including a hoisting mechanism and a pipe jacking mechanism. It adopts a simple design concept and utilizes a hoisting mechanism composed of columns, horizontal beams, track beams and electric hoists, combined with a pipe jacking mechanism using guide rails and equal-thrust hydraulic jacks, to achieve rapid material hoisting and efficient pipe jacking.
It significantly reduces construction costs and energy consumption, improves construction efficiency, adapts to complex environments, meets environmental protection requirements, and expands the application scope of pipe jacking construction.
Smart Images

Figure CN223794772U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to a pipe jacking construction technology field, and specifically is a pipe jacking construction simple operation system. BACKGROUND
[0002] In the continuous development of urban underground pipe network construction and maintenance, pipe jacking construction becomes a key technical means for ensuring the normal operation of the city and reducing the interference to ground transportation and environment due to its non-excavation characteristics. In the pipe jacking construction process, the transportation of various types of sporadic materials such as pipe jacking equipment and pipe materials is crucial. When facing a caisson construction scene, since the caisson usually has a certain height, how to safely and efficiently transport the materials to the bottom of the well becomes a big challenge.
[0003] At present, the conventional method is to use a crane to hoist the materials from the ground to the bottom of the well. In the case of small lifting operation task quantity, this method can still meet the demand. However, once the pipe jacking project is large in scale and long in construction period, the frequent use of the crane will lead to a sharp increase in the number of crane shifts. The cost of crane shifts is not small, which undoubtedly greatly increases the construction cost. For example, in some large municipal pipe jacking projects, due to the use of cranes to hoist materials, the mechanical shift cost accounts for a large proportion of the entire project cost, which seriously compresses the project profit space.
[0004] In addition, the crane operation also has efficiency problems. The hoisting speed of the crane is relatively limited and is greatly affected by factors such as weather and site space. In adverse weather conditions such as strong wind and heavy rain, crane operation may even be forced to stop, further delaying the construction progress. At the same time, if the space layout of the construction site is not wide enough, the parking and operation of the crane will also be limited, affecting the smooth progress of the hoisting operation.
[0005] In view of the high cost, low efficiency and other disadvantages exposed by the traditional use of cranes to hoist materials for pipe jacking construction, it is urgent to develop a new pipe jacking construction simple operation system. The system needs to effectively solve the material transportation problem, significantly reduce the construction cost and improve the construction efficiency under the premise of ensuring the construction quality, so as to adapt to the increasing demand for underground pipeline construction and promote the further innovation and development of pipe jacking construction technology. SUMMARY
[0006] The purpose of the utility model is to solve the above problems, and provide a pipe jacking construction simple operation system.
[0007] The specific scheme of the utility model is: a pipe jacking construction simple operation system, comprising: a caisson, a fixed platform is arranged at the upper end of the caisson, the fixed platform is a square concrete foundation, a hoisting mechanism is arranged at the upper part of the caisson, the hoisting mechanism is used for hoisting a steel pipe outside the caisson, a pipe jacking mechanism is arranged at the bottom of the caisson, and the pipe jacking mechanism is used for pipe jacking construction of the steel pipe.
[0008] The hoisting mechanism comprises:
[0009] Two parallel columns are arranged on the fixed table, and horizontal beams are arranged at the upper ends of the columns, the middle portions of the horizontal beams are fixedly connected with the columns, cross beams are arranged at the two ends of the horizontal beams, and the two ends of the cross beams are fixedly connected with the horizontal beams; track beams are arranged at the bottoms of the cross beams, one end of each track beam is located directly above the caisson, and the other end is located outside the caisson, electric hoists are arranged on the track beams, and the electric hoists can move on the track beams and hoist the pipelines.
[0010] Further, the pipe jacking mechanism comprises:
[0011] A guide rail is provided with an arc-shaped groove for positioning the steel pipe;
[0012] A foundation back wall is arranged on one side of the guide rail and connected with the caisson;
[0013] An equal-thrust hydraulic jack is arranged between the foundation back wall and the guide rail and used for pipe jacking construction of the steel pipe placed in the arc-shaped groove of the guide rail.
[0014] Further, two support tables are arranged outside the fixed table, two support columns corresponding to the columns are arranged on the support tables, and the upper ends of the support columns are fixedly connected with the horizontal beams.
[0015] Further, two inclined pull rods are arranged between the support columns and the columns, and the two inclined pull rods are cross-symmetrically arranged, the bottom end of one of the two inclined pull rods is fixedly connected with the column, the bottom end of the other inclined pull rod is fixedly connected with the support column, and the upper ends of the two inclined pull rods are fixedly connected with the horizontal beams.
[0016] Further, foundation bolts are arranged on the fixed table, and the columns are fixedly connected with the fixed table through the foundation bolts.
[0017] Further, the foundation bolts are L-shaped foundation bolts.
[0018] Further, two intermediate beams are arranged in the middle of the horizontal beams, one of the two intermediate beams corresponds to the support column, and the other intermediate beam corresponds to the column.
[0019] Further, the track beams are I-shaped steel.
[0020] The utility model has the following beneficial effects:
[0021] 1. Simple structure and convenient installation and debugging: The pipe jacking construction simple operation system of the utility model discards the complex structure of traditional equipment and adopts a simple design concept. For example, the hoisting mechanism is composed of upright columns, horizontal beams, cross beams and track beams arranged in parallel, and the connection of each component is clear and understandable. Compared with traditional large pipe jacking equipment, the installation process does not require professional personnel to spend a lot of time on complex assembly and debugging, greatly shortening the preparation time before construction, enabling the project to enter the construction phase faster, and significantly improving the construction efficiency.
[0022] 2. Significant cost advantage: From the equipment purchase and rental cost, the simple operation system has a simple structure, and the required materials are common and relatively low in price. Whether purchased or rented, the cost is much lower than that of traditional large equipment, providing a feasible solution for small projects with tight budgets. During the construction process, the labor cost is also reduced accordingly. At the same time, the system reduces the dependence on large mechanical equipment and reduces energy consumption costs, achieving effective control of costs in all aspects.
[0023] 3. Strong ability to adapt to complex construction environment: In space-limited areas such as old urban areas and narrow streets, traditional large pipe jacking equipment is difficult to operate due to its large size. The simple operation system has relatively small components, which are easy to assemble and operate in narrow spaces. In addition, in projects with strict noise and dust pollution control requirements, the noise and dust generated during the operation of the system are much lower than those of traditional equipment. For example, the pipe jacking mechanism uses equal-force hydraulic jacks, which can effectively reduce noise interference to the surrounding environment compared to the high noise of traditional equipment during operation, meet environmental protection requirements, and greatly expand the application range of pipe jacking construction technology in different complex environments.
[0024] 4. Improve construction efficiency: Through the coordinated operation of the optimized hoisting mechanism and pipe jacking mechanism, the simple operation system can realize fast hoisting and efficient pipe jacking. The electric hoist in the hoisting mechanism can move flexibly on the track beam and quickly lift the pipe, and the guide rail and equal-force hydraulic jack of the pipe jacking mechanism work closely to ensure accurate and efficient pipe jacking, effectively reducing the downtime and delay during construction, improving the construction efficiency, and ensuring that the project can be completed on time or even ahead of schedule. BRIEF DESCRIPTION OF DRAWINGS
[0025] Figure 1 is a front view of the utility model;
[0026] Figure 2 is Figure 1 A-A sectional view of the utility model;
[0027] Figure 3 is Figure 2 B-B sectional view of the utility model;
[0028] Fig. 1, caisson; 2, fixed platform; 3, hoisting mechanism; 301, stand; 302, horizontal beam; 303, cross beam; 304, track beam; 305, electric hoist; 306, support platform; 307, support column; 308, inclined rod; 309, intermediate beam; 4, pipe jacking mechanism; 401, foundation back wall; 402, equal force hydraulic jack; 403, guide rail; 5, steel pipe. DETAILED DESCRIPTION
[0029] The technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments in the present application, all other embodiments obtained by those skilled in the art without creative labor fall within the scope of protection of the present application.
[0030] It should be noted that if the embodiments of the present application involve directional indications (such as up, down, left, right, front, back, etc.), the directional indications are only used to explain the relative positional relationship, movement condition, etc. between the components in a certain specific posture (as shown in the drawings), and if the specific posture changes, the directional indications will also change accordingly.
[0031] In addition, if the embodiments of the present application involve descriptions of "first", "second", etc., the descriptions of "first", "second", etc. are only for description purposes, and cannot be understood as indicating or implying the relative importance of the indicated technical features or implicitly indicating the number of the indicated technical features. Therefore, the features limited by "first" and "second" can explicitly or implicitly include at least one of the features. In addition, the meaning of "and / or" appearing throughout the text includes three parallel schemes. Taking "A and / or B" as an example, it includes A scheme, or B scheme, or A and B schemes. In addition, the technical solutions of each embodiment can be combined with each other, but it must be based on the fact that a person skilled in the art can realize it, and when the combination of technical solutions appears contradictory or unachievable, it should be considered that the combination of technical solutions does not exist and is not within the scope of protection required by the present application.
[0032] Please refer to Figures 1-3 A simple operation system for pipe jacking construction, comprising: a caisson 1, a fixed platform 2 is arranged at the upper end of the caisson 1, the fixed platform 2 is a square concrete foundation, a hoisting mechanism 3 is arranged at the upper part of the caisson 1, the hoisting mechanism 3 is used for hoisting a steel pipe 5 outside the caisson 1, a pipe jacking mechanism 4 is arranged at the bottom of the caisson 1, and the pipe jacking mechanism 4 is used for pipe jacking construction of the steel pipe 5.
[0033] The hoisting mechanism 3 comprises:
[0034] Two parallel columns 301 are arranged on the fixed table 2, and horizontal beams 302 are arranged at the upper ends of the columns 301, the middle portions of the horizontal beams 302 are fixedly connected with the columns 301, cross beams 303 are arranged at the two ends of the horizontal beams 302, and the two ends of the cross beams 303 are fixedly connected with the horizontal beams 302; track beams 304 are arranged at the bottom of the cross beams 303, one end of each track beam 304 is located directly above the caisson 1, and the other end is located outside the caisson 1, and electric hoists 305 are arranged on the track beams 304, and the electric hoists 305 can move on the track beams 304 and hoist pipes.
[0035] In this embodiment, the pipe jacking mechanism 4 comprises:
[0036] A guide rail 403 is arranged, and the guide rail 403 is provided with an arc-shaped groove for positioning the steel pipe 5.
[0037] A foundation back wall 401 is arranged on one side of the guide rail 403 and connected with the caisson 1.
[0038] An equal-force hydraulic jack 402 is arranged between the foundation back wall 401 and the guide rail 403, and is used for pipe jacking construction of the steel pipe 5 placed in the arc-shaped groove of the guide rail 403.
[0039] In this embodiment, two support tables 306 are arranged on the outside of the fixed table 2, two support columns 307 corresponding to the columns 301 are arranged on the support tables 306, and the upper ends of the support columns 307 are fixedly connected with the horizontal beams 302.
[0040] In this embodiment, two inclined pull rods 308 are arranged between the support columns 307 and the columns 301, and the two inclined pull rods 308 are cross-symmetrically arranged, the bottom end of one of the two inclined pull rods 308 is fixedly connected with the column 301, the bottom end of the other inclined pull rod 308 is fixedly connected with the support column 307, and the upper ends of the two inclined pull rods 308 are fixedly connected with the horizontal beams 302.
[0041] In this embodiment, foundation bolts are arranged on the fixed table, and the columns 301 are fixedly connected with the fixed table through the foundation bolts.
[0042] In this embodiment, the foundation bolts are L-shaped foundation bolts.
[0043] In this embodiment, two intermediate beams 309 are arranged in the middle of the horizontal beams 302, one of the two intermediate beams 309 corresponds to the support column 307, and the other corresponds to the column 301.
[0044] In this embodiment, the track beams 304 are I-shaped steel.
[0045] The utility model has the following beneficial effects:
[0046] 1. Simple structure and convenient installation and debugging: The pipe jacking construction simple operation system of the utility model discards the complex structure of traditional equipment and adopts a simple design concept. For example, the hoisting mechanism 3 is composed of upright columns 301, horizontal beams 302, cross beams 303 and track beams 304 arranged in parallel, and the connection of each component is clear and understandable. Compared with traditional large pipe jacking equipment, the installation process does not require professional personnel to spend a lot of time on complex assembly and debugging, greatly shortening the preparation time in the early construction stage, enabling the project to enter the construction stage faster, and significantly improving the construction efficiency.
[0047] 2. Significant cost advantage: From the equipment purchase and rental cost, the simple operation system structure is simple, the required materials are common and relatively low in price, whether purchased or rented, the cost is much lower than that of traditional large equipment, providing a feasible solution for small projects with tight budgets. In the construction process, due to the shortened installation and debugging time, the labor cost is also reduced. At the same time, the system reduces the dependence on large mechanical equipment and reduces energy consumption costs, achieving effective control of costs in all aspects.
[0048] 3. Strong ability to adapt to complex construction environment: In space-limited areas such as old urban areas and narrow streets, traditional large pipe jacking equipment is difficult to enter the site due to its large size. The simple operation system, with its relatively small components, is easy to assemble and operate in narrow spaces. In addition, in projects with strict noise and dust pollution control requirements, the noise and dust generated by the system during operation are much lower than those of traditional equipment. For example, the pipe jacking mechanism 4 uses an equal-thrust hydraulic jack 402, which can effectively reduce noise interference to the surrounding environment compared to the high noise of traditional equipment during operation, meeting environmental protection requirements and greatly expanding the application range of pipe jacking construction technology in different complex environments.
[0049] 4. Improve construction efficiency: Through the coordinated operation of the optimized hoisting mechanism 3 and pipe jacking mechanism 4, the simple operation system can realize fast hoisting of materials and efficient pipe jacking. The electric hoist 305 in the hoisting mechanism 3 can move flexibly on the track beam 304 and quickly lift the pipe, and the guide rail 403 and equal-thrust hydraulic jack 402 of the pipe jacking mechanism 4 work closely to ensure accurate and efficient pipe jacking, effectively reducing delays and delays during construction, improving overall construction efficiency and ensuring that the project can be completed on time or even ahead of schedule.
Claims
1. A simple operation system for pipe jacking construction, comprising: The utility model provides a sinking well, which is characterized in that the upper end of the sinking well is provided with a fixed platform, the fixed platform is a square concrete foundation, the upper part of the sinking well is provided with a hoisting mechanism, the hoisting mechanism is used for hoisting a steel pipe outside to the inside of the sinking well, the bottom of the sinking well is provided with a pipe jacking mechanism, and the pipe jacking mechanism is used for pipe jacking construction of the steel pipe. The hoisting mechanism comprises: Two vertical columns are arranged on the fixed platform and arranged in parallel, the upper end of the vertical column is provided with a horizontal beam, the middle part of the horizontal beam is fixedly connected with the vertical column, the two ends of the horizontal beam are provided with cross beams, the two ends of the cross beam are fixedly connected with the horizontal beam, the bottom of the cross beam is provided with a track beam, one end of the track beam is located directly above the sinking well, the other end of the track beam is located outside the sinking well, an electric hoist is arranged on the track beam, and the electric hoist can move on the track beam and hoist a pipeline.
2. A simple operation system for pipe jacking construction according to claim 1, characterized in that: The pipe jacking mechanism comprises: A guide rail is provided with an arc-shaped groove, and the arc-shaped groove is used for positioning the steel pipe; A foundation back wall is arranged on one side of the guide rail and connected with the sinking well; An equal-thrust hydraulic jack is arranged between the foundation back wall and the guide rail and used for pipe jacking construction of the steel pipe placed in the arc-shaped groove of the guide rail.
3. A simple operation system for pipe jacking construction according to claim 1, characterized in that: Two support platforms are arranged outside the fixed platform, two support columns corresponding to the vertical columns are arranged on the support platforms, and the upper end of the support column is fixedly connected with the horizontal beam.
4. A simple operation system for pipe jacking construction according to claim 3, characterized in that: Two inclined rods are arranged between the support column and the vertical column, and the two inclined rods are arranged in cross symmetry, the bottom end of one of the two inclined rods is fixedly connected with the vertical column, the bottom end of the other inclined rod is fixedly connected with the support column, and the upper end of the two inclined rods is fixedly connected with the horizontal beam.
5. A simple operation system for pipe jacking construction according to claim 1, characterized in that: A foundation bolt is arranged on the fixed platform, and the vertical column is fixedly connected with the fixed platform through the foundation bolt.
6. A simple operation system for pipe jacking construction according to claim 5, characterized in that: The foundation bolt is an L-shaped foundation bolt.
7. A simple operation system for pipe jacking construction according to claim 3, characterized in that: Two middle beams are arranged in the middle of the horizontal beam, one of the two middle beams corresponds to the support column, and the other middle beam corresponds to the vertical column.
8. A simple operation system for pipe jacking construction according to claim 1, characterized in that: The track beam is an I-shaped steel.