Post-tensioning method underground garage waterproof plate column pier structure with bonded prestress
By using multiple column pier structures and T-shaped clip splicing methods, combined with positioning and reinforcement mechanisms, the problems of insufficient stress balance and complex splicing in existing technologies have been solved, thereby improving the stability and waterproofing performance of the underground garage waterproofing liner.
Patent Information
- Application Number
- CN202520204573.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-10
- Publication Date
- 2026-01-16
- Estimated Expiration
- 2035-02-10
AI Technical Summary
The existing post-tensioned bonded prestressed underground garage waterproof slab column-pier structure suffers from insufficient stress balance and redundancy when facing the multi-angle impact forces generated by frequent vehicle starts, stops, and turns, as well as uneven distribution of groundwater buoyancy. This leads to stress concentration in the waterproof slab and premature fatigue in local structures. Furthermore, the splicing is complex, and installation and maintenance are inconvenient.
It adopts a multi-column structure, combined with the splicing method of T-shaped clips and slots, and the sealing and fixing of sealing plates and blocks. Through the connection mechanism of positioning columns and positioning slots, reinforcing rings and reinforcing blocks, it enhances the load-bearing and force transmission performance, and achieves convenient splicing and sealing.
It achieves more uniform load distribution, improves structural stability and safety, simplifies splicing operations, ensures the overall waterproof performance of the waterproof membrane, avoids leakage, and enhances the shear resistance and overall stability of the column pier.
Smart Images

Figure CN223805570U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The application relates to the technical field of building engineering, in particular to a post-tensioning bonded prestressed underground garage waterproof slab column pier structure. BACKGROUND
[0002] The underground garage waterproof slab column pier is an important component of the underground garage structure, is mainly used for preventing underground water from seeping into the garage, and is the first line of defense for guaranteeing the dryness and normal use of the garage, needs to bear the pressure of underground water, and has good anti-seepage performance to prevent water seepage.
[0003] According to the search of the announcement No. CN203924109U, a post-tensioning bonded prestressed underground garage waterproof slab column pier structure is disclosed, and the technical scheme is that a column pier is arranged between the top plate and the bottom plate of the underground garage, the pier cap of the column pier is arranged in an inverted right quadrangular frustum shape, the side edges of the frustum of the pier cap are respectively perpendicular to the X-direction prestressed tendon and the Y-direction prestressed tendon of the bottom plate, and the X-direction prestressed tendon and the Y-direction prestressed tendon of the bottom plate both pass through the bottom of the pier cap.
[0004] According to the related technology in the above, the inventor considers that the post-tensioning bonded prestressed underground garage waterproof slab column pier structure has the problems that the stress balance and redundancy of the single column pier structure may be insufficient, the waterproof slab around the single column pier is prone to stress concentration under the conditions of frequent starting and stopping of vehicles, multi-angle impact force generated by turning and uneven distribution of underground water buoyancy, local structure is prematurely damaged due to fatigue, and once the column pier fails due to partial settlement of the foundation, construction defects of the column body and the like, the waterproof slab structure of the entire underground garage will face a great risk of instability, and the waterproof slab structure is inconvenient to splice, and complex process operation and professional equipment are often required, so that the installation and maintenance are not convenient, and the post-tensioning bonded prestressed underground garage waterproof slab column pier structure is needed to solve the above problems. Practical new type content
[0005] The application aims to provide a post-tensioning bonded prestressed underground garage waterproof slab column pier structure to improve the problems of stress balance and redundancy of the single column pier structure and inconvenience of splicing of the waterproof slab structure.
[0006] The post-tensioning bonded prestressed underground garage waterproof slab column pier structure provided by the application adopts the following technical scheme:
[0007] The post-tensioning method has a waterproof slab column pier structure of bonded prestressed underground garage, which comprises two slab bodies, the top end of the slab body is fixedly provided with a plurality of bottom discs in a rectangular distribution, the top surface of the bottom disc is inserted with a column body, the outer surface of the column body is fixedly provided with a plurality of side blocks in an annular distribution, the upper surface of the bottom disc is provided with a block groove matched with the side block, the lower end of the side block is fixedly provided with an insertion column, and the block groove is provided with a column groove matched with the insertion column.
[0008] By adopting the technical scheme, the connection structure of the column body and the bottom disc is formed, the plurality of column piers are accurately and stably installed, the bearing and force transmission performance are enhanced, and the deformation is reduced.
[0009] Optionally, one side of the slab body is fixedly provided with a clamping strip, the other side of the slab body is fixedly provided with a clamping plate, the outer side of the clamping plate is provided with a clamping groove matched with the clamping strip, and one side of the top surface of the clamping plate is matched with a sealing plate through a bolt.
[0010] By adopting the technical scheme, the clamping strip, the clamping groove and the sealing plate are matched to realize convenient splicing and good sealing of the slab body, and the slab body is waterproof and efficient.
[0011] Optionally, a plurality of reserved holes are symmetrically provided on both sides of the slab body, and a hole channel is provided between two corresponding reserved holes.
[0012] By adopting the technical scheme, the reserved hole and the hole channel assist the prestressed construction, improve the crack resistance and bearing capacity of the slab body, and cope with complex stress.
[0013] Optionally, the lower end of the column body is fixedly provided with a positioning column, and the bottom disc is provided with a positioning groove matched with the positioning column.
[0014] By adopting the technical scheme, the positioning column and the positioning groove ensure accurate installation of the column body and lay a stable connection foundation.
[0015] Optionally, the upper surface of the side block is connected with a reinforcing ring through a bolt.
[0016] By adopting the technical scheme, the reinforcing ring reinforces the connection part, improves the shear resistance and stiffness, and enhances the reliability of the column pier.
[0017] Optionally, the lower surface of the reinforcing ring is fixedly provided with a plurality of reinforcing blocks in an annular distribution, the upper surface of the bottom disc is fixedly provided with a limiting block, and the limiting block and the corresponding reinforcing block are connected through a bolt.
[0018] By adopting the technical scheme, the reinforcing block and the limiting block cooperate to strengthen the constraint and improve the durability of the column pier.
[0019] Optionally, the cross section shape of the clamping strip is T-shaped.
[0020] Through adoption of the above technical scheme, the T-shaped clamping strip is optimized for splicing guidance and anti-sliding, and the operation is simplified and stable.
[0021] Optionally, one side of the sealing plate is fixedly provided with a sealing block, and one side of the sealing block is in movable contact with the corresponding clamping strip.
[0022] Through adoption of the above technical scheme, the sealing block cooperates with the sealing plate to achieve airtight sealing, thereby guaranteeing long-term waterproof effect of the waterproof plate.
[0023] To sum up, the present application has at least one of the following beneficial technical effects:
[0024] 1. The present application can more evenly disperse various loads borne by the underground garage, which helps to resist external forces from different directions, and if one of the column piers has a problem, the other three column piers can still maintain the stability of the waterproof plate to a certain extent, thereby providing a guarantee for the safety of the underground garage, and the safety and stability are stronger.
[0025] 2. The present application adopts the splicing mode of the T-shaped clamping strip and the clamping groove, cooperates with the sealing plate and the sealing block for sealing and fixing, so that the splicing operation of the waterproof plate is relatively simple and fast, and at the same time, the splicing structure can effectively prevent underground water from seeping from the splicing gap, thereby ensuring the overall waterproof performance of the waterproof plate. BRIEF DESCRIPTION OF DRAWINGS
[0026] Figure 1 is a schematic diagram of the overall structure of the present application.
[0027] Figure 2 is an exploded view of the chassis profile and the column related structure of the present application.
[0028] Figure 3 is an exploded view of the connection structure between the plate bodies of the present application.
[0029] Figure 4 is another perspective exploded view of the connection structure between the plate bodies of the present application.
[0030] In the figure, 1 is a plate body; 11 is a reserved hole; 12 is a hole; 2 is a column; 21 is a chassis; 22 is a side block; 23 is a block groove; 24 is a plug-in column; 25 is a column groove; 26 is a positioning column; 27 is a positioning groove; 28 is a reinforcing ring; 29 is a reinforcing block; 210 is a limiting block; 3 is a clamping strip; 31 is a clamping plate; 32 is a clamping groove; 33 is a sealing plate; 34 is a sealing block. DETAILED DESCRIPTION
[0031] The following will be described in detail in combination with the accompanying drawings. Figure 1 - the accompanying drawings Figure 4 The present application will be further described in detail.
[0032] EMBODIMENT
[0033] The post-tensioning method has a waterproof slab column pier structure of the prestressed underground garage, referring to Figures 1-3 , including two slab bodies 1, the top end of the slab body 1 is fixedly provided with a plurality of bottom plates 21 distributed in a rectangular shape, the top surface of the bottom plate 21 is inserted with a column 2, a plurality of reserved holes 11 are symmetrically arranged on both sides of the slab body 1, and a hole 12 is arranged between two corresponding reserved holes 11, after the slab body 1 is spliced and the column pier is installed, the reserved holes 11 symmetrically arranged on both sides of the slab body 1 and the corresponding hole 12 are used to pass through the prestressed tendon, the implementation of the post-tensioning method with adhesion is the same as the technical content in the comparative case, therefore, this place will not be described in more detail, the slab body 1 is a waterproof slab body, the column 2 is a column pier structure body, the column 2 is installed on the bottom plate 21, a plurality of bottom plates 21 can be selectively inserted into the column 2, and the column pier layout is dynamically planned, so that the structure can better adapt to the complex and changeable use requirements as a whole, a plurality of column piers can more evenly disperse various loads borne by the underground garage, which helps to resist external forces from different directions, and if one of the column piers has a problem, the other three column piers can still maintain the stability of the waterproof slab to a certain extent, providing protection for the safety of the underground garage, and the safety and stability are stronger.
[0034] Referring to Figure 2 , the outer surface of the column 2 is fixedly provided with a plurality of side blocks 22 distributed in a ring shape, the upper surface of the bottom plate 21 is provided with a block groove 23 matched with the side block 22, the lower end of the side block 22 is fixedly provided with an insertion column 24, the block groove 23 is provided with a column groove 25 matched with the insertion column 24, the lower end of the column 2 is fixedly provided with a positioning column 26, and the bottom plate 21 is provided with a positioning groove 27 matched with the positioning column 26, the connection between the column 2 and the bottom plate 21 adopts a multiple positioning and reinforcing mechanism, in the initial installation, the cooperation between the positioning column 26 and the positioning groove 27 is like the tenon and mortise structure, which can accurately determine the center position of the column 2 on the bottom plate 21 and limit the horizontal displacement thereof, then, the combination of the side block 22 and the block groove 23 and the insertion of the insertion column 24 into the column groove 25 further constrain the degrees of freedom of the column 2 from multiple angles, so that the installation position of the column 2 on the bottom plate 21 is more accurate and stable, and this accurate assembly mode lays a solid foundation for the load bearing of the entire structure subsequently, compared with the traditional simple placement or rough positioning installation mode, the initial stability of the column pier structure is greatly improved.
[0035] Referring to Figure 2The upper surface of the side block 22 is connected with a reinforcing ring 28 through screw connection, the lower surface of the reinforcing ring 28 is fixedly provided with a plurality of reinforcing blocks 29 distributed in a ring shape, the upper surface of the base plate 21 is fixedly provided with a limiting block 210, the limiting block 210 is connected with the corresponding reinforcing block 29 through screw connection, the reinforcing ring 28 and the reinforcing blocks 29 are connected with the limiting block 210 of the base plate 21 through screw connection, forming a stable ring-shaped constraint system, the reinforcing ring 28 is similar to a hoop, tightly binding the column body 2 and the base plate 21 together, effectively enhancing the shear resistance and overall stability of the connecting part of the column body 2 and the base plate 21, when bearing the load transmitted from the upper structure, whether it is vertical pressure or horizontal shear force that may be generated, the connecting structure can effectively uniformly transmit and disperse the force, avoiding the structure damage caused by local stress concentration.
[0036] With reference to Figures 3-4 The side of the plate body 1 is fixedly provided with a clamping strip 3, the cross section of the clamping strip 3 is T-shaped, the other side of the plate body 1 is fixedly provided with a clamping plate 31, and the outer side of the clamping plate 31 is provided with a clamping groove 32 matched with the clamping strip 3, the side of the top surface of the clamping plate 31 is connected with a sealing plate 33 through screw connection, one side of the sealing plate 33 is fixedly provided with a sealing block 34, and the other side of the sealing block 34 is movably connected with the corresponding clamping strip 3, when the waterproof plates are spliced, the clamping strip 3 on one side of one plate body 1 is inserted into the clamping groove 32 on the other side of the other plate body 1, because the cross section of the clamping strip 3 is T-shaped, the clamping groove 32 is matched with the clamping strip 3, so that the two plate bodies 1 can be tightly connected in the horizontal direction and are not easy to be separated, then the sealing plate 33 on the side of the top surface of the clamping plate 31 is fixed through screw connection, and the sealing block 34 on the side of the sealing plate 33 is movably connected with the clamping strip 3, so as to further seal and fix the splicing part, preventing the gap from causing water leakage in the use process, thereby ensuring the overall waterproof performance of the waterproof plate, the splicing mode of the T-shaped clamping strip 3 and the clamping groove 32 is matched with the sealing and fixing of the sealing plate 33 and the sealing block 34, so that the splicing operation of the waterproof plate is relatively simple and fast, and the splicing structure can effectively prevent underground water from seeping from the splicing gap, ensuring the overall waterproof performance of the waterproof plate.
[0037] The implementation principle of the embodiment of the application is that the plate body 1 is a waterproof plate body, the column body 2 is a column pier structure body, the column body 2 is installed on the base plate 21, a plurality of base plates 21 can be selectively inserted into the column body 2, and the column pier layout is dynamically planned, so that the structure can better adapt to complex and changeable use requirements as a whole, a plurality of column piers can more evenly disperse various loads borne by the underground garage, which is helpful to resist external forces from different directions, and if one of the column piers has a problem, the other three column piers can still maintain the stability of the waterproof plate to a certain extent, providing protection for the safety of the underground garage, and the safety and stability are stronger.
[0038] The connection of the column 2 and the base plate 21 adopts a multiple positioning and reinforcing mechanism. In the initial installation, the cooperation of the positioning column 26 and the positioning groove 27 can accurately determine the center position of the column 2 on the base plate 21, and limit the horizontal displacement of the column 2. Subsequently, the cooperation of the side block 22 and the block groove 23 and the insertion of the insertion column 24 into the column groove 25 further restricts the degree of freedom of the column 2 from multiple angles, so that the installation position of the column 2 on the base plate 21 is more accurate and stable. This accurate assembly method lays a solid foundation for the subsequent load bearing of the entire structure. Compared with the traditional simple placement or rough positioning installation method, the initial stability of the column pier structure is greatly improved.
[0039] The reinforcing ring 28 and the reinforcing block 29 thereof are connected with the limiting block 210 of the base plate 21 through bolts, forming a stable ring-shaped restraint system. The reinforcing ring 28 is similar to a hoop, tightly binding the column 2 and the base plate 21 together, effectively enhancing the shear capacity and overall stability of the connection part of the column 2 and the base plate 21. When bearing the load transmitted from the upper structure, whether it is vertical pressure or horizontal shear force that may be generated, this connection structure can effectively transmit and disperse the force uniformly, avoiding the destruction of the structure caused by local stress concentration.
[0040] When splicing the waterproof plate, the clamping strip 3 on one side of one plate body 1 is inserted into the clamping groove 32 on the clamping plate 31 on the other side of the other plate body 1. Since the cross section of the clamping strip 3 is T-shaped, the clamping groove 32 cooperates with it, so that the two plate bodies 1 can be tightly connected in the horizontal direction and are not easy to be separated. Then the sealing plate 33 on one side of the top surface of the clamping plate 31 is fixed by bolts, and the sealing block 34 on one side of the sealing plate 33 is in movable contact with the clamping strip 3, further sealing and fixing the spliced part, preventing gaps from occurring during use and causing water leakage, thereby ensuring the overall waterproof performance of the waterproof plate. The splicing method of the T-shaped clamping strip 3 and the clamping groove 32, combined with the sealing and fixing of the sealing plate 33 and the sealing block 34, makes the splicing operation of the waterproof plate relatively simple and fast. At the same time, this splicing structure can effectively prevent groundwater from seeping from the splicing gap, ensuring the overall waterproof performance of the waterproof plate.
[0041] The embodiments of the specific implementation are the preferred embodiments of the present application, but do not limit the protection scope of the present application. The same parts are indicated by the same reference numerals. Therefore, any equivalent changes made according to the structure, shape, principle of the present application should be covered within the protection scope of the present application.
Claims
1. A waterproof post column pier structure of post-tensioned bonded prestressed underground garage, comprising two plate bodies (1), characterized in that: The top end of the plate body (1) is fixedly provided with a plurality of bottom plates (21) in rectangular distribution, the top surface of the bottom plate (21) is inserted with a column body (2), the outer surface of the column body (2) is fixedly provided with a plurality of side blocks (22) in annular distribution, the upper surface of the bottom plate (21) is provided with a block groove (23) matched with the side block (22), the lower end of the side block (22) is fixedly provided with an insertion column (24), and the block groove (23) is provided with a column groove (25) matched with the insertion column (24).
2. The post-tensioned bonded prestressed underground garage waterproof slab-column-pier structure according to claim 1, characterized in that: One side of the plate body (1) is fixedly provided with a clamping strip (3), the other side of the plate body (1) is fixedly provided with a clamping plate (31), the outer side of the clamping plate (31) is provided with a clamping groove (32) matched with the clamping strip (3), and one side of the top surface of the clamping plate (31) is matched with a sealing plate (33) through a bolt.
3. The post-tensioned bonded prestressed underground garage waterproof slab-column-pier structure according to claim 1, characterized in that: A plurality of reserved holes (11) are symmetrically provided on both sides of the plate body (1), and a hole channel (12) is provided between two corresponding reserved holes (11).
4. The post-tensioned bonded prestressed underground garage waterproof slab-column-pier structure according to claim 1, characterized in that: The lower end of the column body (2) is fixedly provided with a positioning column (26), and the bottom plate (21) is provided with a positioning groove (27) matched with the positioning column (26).
5. The post-tensioned bonded prestressed underground garage waterproof slab-column-pier structure according to claim 1, characterized in that: The upper surface of the side block (22) is connected with a reinforcing ring (28) through a bolt.
6. The post-tensioned bonded prestressed underground garage waterproof slab-column-pier structure according to claim 5, characterized in that: The lower surface of the reinforcing ring (28) is fixedly provided with a plurality of reinforcing blocks (29) in annular distribution, the upper surface of the bottom plate (21) is fixedly provided with a limiting block (210), and the limiting block (210) and the corresponding reinforcing block (29) are connected through a bolt.
7. The post-tensioned bonded prestressed underground garage waterproof slab column pier structure according to claim 2, characterized in that: The cross-sectional shape of the clamping strip (3) is T-shaped.
8. The post-tensioned bonded prestressed underground garage waterproof slab column pier structure according to claim 2, characterized in that: One side of the sealing plate (33) is fixedly provided with a sealing block (34), and one side of the sealing block (34) is in movable contact with the corresponding clamping strip (3).
Citation Information
Patent Citations
Bonded prestressed underground garage waterproof board pier structure adopting post-tensioning method
CN203924109U