Photovoltaic support assembly installation and maintenance platform for prefabricated pipe pile
By designing a prefabricated pipe pile photovoltaic support assembly installation and maintenance platform on the photovoltaic support, and utilizing the hangers, supports and tie rods to form a triangular structure, the problem of standing difficulties during photovoltaic assembly installation and maintenance is solved, enabling rapid platform construction and dismantling, and protecting the photovoltaic support.
Patent Information
- Application Number
- CN202520170513.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-25
- Publication Date
- 2026-01-23
- Estimated Expiration
- 2035-01-25
AI Technical Summary
The small size and large spacing of the photovoltaic support purlins make it difficult for workers to stand and operate when installing and maintaining photovoltaic modules, and the existing construction methods are not convenient for building construction platforms.
A photovoltaic support assembly installation and maintenance platform for precast pipe piles is designed. It adopts an upper and lower clamp arranged vertically, combined with a hanger, support and tie rod to form a triangular structure to build the platform assembly. The precast pipe piles are used as the force points to reduce the dependence on photovoltaic supports.
It enables rapid setup and disassembly of the platform, improves the convenience of construction, protects the anti-corrosion layer of the photovoltaic support, and reduces damage to the support.
Smart Images

Figure CN223823331U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model relates to photovoltaic construction technical field, concretely is a kind of photovoltaic support assembly installation and overhaul platform for prefabricated pipe pile. BACKGROUND
[0002] Ground photovoltaic power station component is all arranged on the photovoltaic component frame system with inclination, the highest photovoltaic support generally exceeds 2 meters, the usual construction method when worker is in photovoltaic component installation and maintenance is as follows: temporary construction platform is set up under photovoltaic support ground, and ground worker moves and places photovoltaic component to construction platform, and then worker on construction platform transfers photovoltaic component to the worker standing on the rafter of photovoltaic support, and the worker standing on the rafter of photovoltaic support fixes photovoltaic component to photovoltaic support, thereby completing the installation construction of photovoltaic component, but since the rafter of photovoltaic support is thin-walled cold-bending section steel with small size, the spacing between rafters is large, and the inclination is generally 20°~50°, so that it is very difficult for worker to stand and operate. SUMMARY
[0003] In order to solve the above problems, the utility model provides a kind of photovoltaic support assembly installation and overhaul platform for prefabricated pipe pile, structure is stable, simplifies platform erection and disassembly process, and high stability, the technical scheme adopted by the utility model is as follows:
[0004] A kind of photovoltaic support assembly installation and overhaul platform for prefabricated pipe pile, including upper hoop, lower hoop and at least one group of platform components, the upper hoop and lower hoop are arranged in upper and lower and are tightly installed on prefabricated pipe pile, the platform component includes hanger, support and pull rod, the hanger is vertically arranged and is installed on the upper hoop and lower hoop, the support is horizontally arranged and inner end is installed on the hanger, the pull rod is obliquely arranged and one end is connected with the hanger, and the other end is connected with the outer end of support, at least one wood template for treading is provided on the support, and the hanger, support and pull rod are combined into the structure with triangular side face.
[0005] The above-mentioned photovoltaic support assembly installation and overhaul platform for prefabricated pipe pile, the platform component is provided with two groups arranged left and right on prefabricated pipe pile, the left platform component is provided with left hanger, left support and left pull rod, and the right platform component is provided with right hanger, right support and right pull rod;
[0006] The left hanger is installed on the left side of the upper hoop and lower hoop, the inner end of the left support is installed on the lower part of the left hanger, one end of the left pull rod is connected with the upper part of the left hanger, and the other end is connected with the outer end of the left support, and at least two wood templates are installed on the left support;
[0007] The right hanger is installed on the right side of the upper hoop and lower hoop, the inner end of the right support is installed on the upper part of the right hanger, one end of the right pull rod is connected with the lower part of the right hanger, and the other end is connected with the outer end of the right support, and at least two wood templates are installed on the right support.
[0008] The utility model discloses a beneficial effect is: the structure simple, sufficient strength of the overhaul platform can be quickly built or disassembled, greatly facilitate the installation and overhaul of photovoltaic support and its component, utilize the pile foundation as the stress point completely, do not depend on photovoltaic support mounting, thereby reduce the damage to photovoltaic support, protect the outer anticorrosive layer of photovoltaic support. BRIEF DESCRIPTION OF DRAWINGS
[0009] Figure 1 It is side installation schematic drawing of the utility model embodiment;
[0010] Figure 2 It is overhead structure schematic drawing of the utility model embodiment.
[0011] In the drawing: 1, prefabricated pipe pile;2, left hanger;3, right hanger;4, upper hoop;5, lower hoop;6, right support;7, left support;8, left pull rod;9, right pull rod;10, square steel;11, wooden formwork. DETAILED DESCRIPTION
[0012] The technical scheme of the utility model will be explained in detail below in combination with the drawings. The following implementation is exemplary, and is intended to provide further description of the present application. Unless otherwise specified, all technical terms used have the same meaning as understood by those skilled in the art to which the present application belongs. It should be noted that the terms used are only for the purpose of describing the specific embodiments, and are not intended to limit the exemplary embodiments according to the present application.
[0013] The prefabricated pipe pile photovoltaic support component installation and overhaul platform of the embodiment is shown in Figure 1 and Figure 2 As shown, the platform component is provided with two groups arranged left and right on the prefabricated pipe pile 1, the left platform component is provided with a left hanger 2, a left support 7 and a left pull rod 8, and the right platform component is provided with a right hanger 3, a right support 6 and a right pull rod 9. The platform component is in a triangular structure, with high stability.
[0014] The left hanger 2 is installed on the left side of the upper hoop 4 and the lower hoop 5, the inner end of the left support 7 is installed on the lower part of the left hanger 2, one end of the left pull rod 8 is connected to the upper part of the left hanger 2 and the other end is connected to the outer end of the left support 7, at least two wooden formworks 11 are installed on the left support 7 for the staff to step on, square steels 10 are provided on both sides of the wooden formwork 11, the lower end of the square steel 10 is fixed on the left support 7, and then the wooden formwork 11 is connected with the square steel 10 to realize fixation.
[0015] The right hanger 3 is installed on the right side of the upper and lower hoops 4 and 5, the inner end of the right support 6 is installed on the upper part of the right hanger 3, the right pull rod 9 is connected to the lower part of the right hanger 3 at one end and to the outer end of the right support 6 at the other end, and at least two wooden formworks 11 are installed on the right support 6, and the installation of the wooden formworks 11 here is the same as that of the platform assembly on the left side.
[0016] The above is only the preferred embodiment of the present application, and it should be pointed out that those skilled in the art can make several changes or improvements without departing from the principles of the present application, and these changes or improvements should also be considered as the protection scope of the present application.
Claims
1. A photovoltaic racking assembly installation and maintenance platform for precast pipe piles, characterized by: The utility model relates to a prefabricated pipe pile climbing platform, which comprises an upper hoop (4), a lower hoop (5) and at least one set of platform components, the upper hoop (4) and the lower hoop (5) are arranged in an up-down manner and are tightly installed on a prefabricated pipe pile (1), the platform component comprises a hanger, a support and a pull rod, the hanger is vertically arranged and is installed on the upper hoop (4) and the lower hoop (5), the support is horizontally arranged and has an inner end installed on the hanger, the pull rod is obliquely arranged and has one end connected with the hanger and the other end connected with an outer end of the support, at least one wooden template (11) for treading is arranged on the support, and the hanger, the support and the pull rod are combined into a structure with a triangular side face.
2. The photovoltaic racking assembly installation and maintenance platform for precast piles according to claim 1, characterized in that: The platform component is provided with two sets arranged left and right on the prefabricated pipe pile (1), the left platform component is provided with a left hanger (2), a left support (7) and a left pull rod (8), and the right platform component is provided with a right hanger (3), a right support (6) and a right pull rod (9); The left hanger (2) is installed on the left side of the upper hoop (4) and the lower hoop (5), the inner end of the left support (7) is installed on the lower part of the left hanger (2), one end of the left pull rod (8) is connected with the upper part of the left hanger (2), the other end is connected with the outer end of the left support (7), and at least two wooden templates (11) are installed on the left support (7); The right hanger (3) is installed on the right side of the upper hoop (4) and the lower hoop (5), the inner end of the right support (6) is installed on the upper part of the right hanger (3), one end of the right pull rod (9) is connected with the lower part of the right hanger (3), the other end is connected with the outer end of the right support (6), and at least two wooden templates (11) are installed on the right support (6).