Fabricated shear wall structure with vertically connected flat joints

By using inverted trapezoidal grooves and C60 pads, combined with ultra-high performance concrete, the problems of insufficient grouting and unstable mechanical properties in prefabricated shear wall connections were solved, achieving an efficient and low-cost connection structure that improves shear strength and seismic performance.

CN223838354UActive Publication Date: 2026-01-27CHINA CONSTR FOURTH ENG DIV CORP LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202520393841.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-03-07
Publication Date
2026-01-27
Estimated Expiration
2035-03-07

AI Technical Summary

Technical Problem

Existing prefabricated shear wall connection methods suffer from problems such as incomplete grouting, complex and costly construction, and unstable mechanical properties of the connection parts.

Method used

The design employs inverted trapezoidal grooves and C60 spacers, combined with ultra-high performance concrete, to ensure smooth concrete flow during grouting, reduce rebar lap length, and improve the shear strength and seismic performance of the connection.

Benefits of technology

This achieves dense grouting, reduces construction complexity and cost, and improves the mechanical properties and seismic resistance of the connection parts.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN223838354U_ABST
    Figure CN223838354U_ABST
Patent Text Reader

Abstract

The utility model discloses a flat seam vertical connection assembly type shear wall structure which comprises an assembly type shear wall body, an inverted trapezoidal tooth groove is integrally formed in the lower portion of the assembly type shear wall body, a C60 cushion block is integrally arranged at the bottom of the inverted trapezoidal tooth groove, a ground beam is connected to the lower portion of the C60 cushion block, and the lower portion of the ground beam is connected with a horizontal beam. A grouting groove is formed in the shear wall body and comprises steel bars and filling slurry on the peripheries of the steel bars, and the filling slurry is concrete. According to the design of the trapezoid structure, concrete flowing in the grouting process is promoted, grouting compactness is guaranteed, dark part cavities are avoided, the shear strength of the connecting part is improved, the steel bar lap joint length is reduced in the construction process of the connecting structure, the construction steps are simplified, the construction cost is reduced, the construction period is shortened, ultra-high-performance concrete is adopted as a grouting material, and the construction cost is reduced. Compared with a cast-in-place structure, the anti-seismic performance of the shear wall is enhanced, and the shear wall has better anti-seismic capacity and durability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to a prefabricated shear wall structure with horizontal joints and vertical connections, and relates to the field of building structures. Background Technology

[0002] With the development of prefabricated building technology, prefabricated shear walls, as an important structural unit, have been widely used in modern high-rise buildings, industrial buildings, and other projects. Existing connection methods for prefabricated shear walls mainly include sleeve grouting connections, grout-anchored lap connections, and bolt connections.

[0003] While these connection methods can ensure the stability of shear walls to a certain extent, the following problems still exist:

[0004] (1) Incomplete grouting: Due to improper construction operations or structural problems, the flow of grouting material is often obstructed, resulting in voids in the dark cavity at the connection, which reduces the shear strength and stability of the shear wall.

[0005] (2) High construction cost and construction complexity: Existing common connection methods are difficult to balance low construction cost and construction process complexity. For example, sleeve grouting connection has stable performance, mature technology and wide application, but the process is complex and the technical requirements are high; grout anchor lap connection is simple and low cost, but the lap length of the steel bars is long and the application is strictly limited; bolt connection is easy to operate and controllable to install, which can greatly reduce temporary support and has high construction efficiency, but the construction cost is high.

[0006] (3) Unstable mechanical properties of the connection: Due to the limitations of the connection method, the mechanical properties of the connection often fail to meet the requirements of seismic resistance and shear resistance. Utility Model Content

[0007] This utility model provides a prefabricated shear wall structure with flat joint vertical connection to overcome the defects of existing prefabricated shear wall connection methods, such as incomplete grouting and unstable mechanical properties of the connection parts.

[0008] To solve the above-mentioned technical problems, this utility model provides the following technical solution:

[0009] This utility model discloses a prefabricated shear wall structure with a horizontal joint and vertical connection, including a prefabricated shear wall body. The lower part of the prefabricated shear wall body is integrally provided with an inverted trapezoidal groove. A C60 pad is integrally provided at the bottom of the inverted trapezoidal groove. A ground beam is connected below the C60 pad. A grouting groove is provided inside the shear wall body. The grouting groove includes reinforcing bars and surrounding filling grout, and the filling grout is concrete.

[0010] Furthermore, each of the inverted trapezoidal tooth sockets has an integrally formed cylindrical C60 pad at the bottom of the socket, with flow space left on the left and right sides of the C60 pad.

[0011] Furthermore, the C60 pad has a trapezoidal structure, which can effectively promote smooth concrete flow during grouting, prevent the formation of cavities in the dark, and effectively improve the mechanical properties of the connection.

[0012] Furthermore, the reinforcing bars include horizontal and vertical reinforcing bars of the wall that are lapped together perpendicularly, and the reserved lapped bars of the ground beam are lapped together with the vertical reinforcing bars and stirrups of the wall respectively.

[0013] The beneficial effects achieved by this utility model are as follows: the trapezoidal structure design promotes concrete flow during grouting, ensures dense grouting, avoids hidden cavities, and improves the shear strength of the connection parts; this connection structure reduces the lap length of steel bars during construction, simplifies construction steps, and reduces construction costs and time; the use of ultra-high performance concrete as grouting material enhances the seismic performance of the shear wall, and compared with cast-in-place structures, it has better seismic resistance and durability. Attached Figure Description

[0014] The accompanying drawings are provided to further illustrate the present invention and form part of the specification. They are used together with the embodiments of the present invention to explain the present invention, but do not constitute a limitation thereof. In the drawings:

[0015] Figure 1 This is a schematic diagram of the structure of this utility model;

[0016] Figure 2 This is a partially enlarged schematic diagram of the present invention;

[0017] Figure 3 This is a front view schematic diagram of the present invention;

[0018] Figure 4 This is a side view of the present invention.

[0019] In the diagram: 1. Prefabricated shear wall body; 2. Inverted trapezoidal groove; 3. C60 spacer block; 4. Ground beam; 5. Reinforcing steel; 51. Horizontal reinforcing steel of the wall; 52. Vertical reinforcing steel of the wall; 53. Stirrups; 54. Reserved lap joints of the ground beam; 6. Concrete. Detailed Implementation

[0020] The preferred embodiments of the present invention will be described below with reference to the accompanying drawings. It should be understood that the preferred embodiments described herein are for illustration and explanation only and are not intended to limit the present invention.

[0021] Example 1

[0022] like Figure 1-4 As shown, a prefabricated shear wall structure with vertically connected flat joints includes a prefabricated shear wall body 1. The prefabricated shear wall body 1 has an integrally formed inverted trapezoidal groove 2 at its lower part. A C60 pad 3 is integrally formed at the bottom of the inverted trapezoidal groove 2. A ground beam 4 is connected below the C60 pad 3. A grouting groove is provided inside the shear wall body 1. The grouting groove includes reinforcing bars 5 and surrounding filling grout, and the filling grout is concrete 6.

[0023] Each of the inverted trapezoidal tooth sockets 2 has an integrally formed cylindrical C60 pad 3 at the bottom of the tooth socket, with flow space left on the left and right sides of the C60 pad 3.

[0024] The C60 pad 3 has a trapezoidal structure, which can effectively promote the smooth flow of concrete 6 during the grouting process, fill it densely, prevent the formation of cavities in the dark, and effectively improve the mechanical properties of the connection part.

[0025] The reinforcing bars 5 include horizontal reinforcing bars 51 and vertical reinforcing bars 52 that are perpendicularly lapped together. The reserved lapped bars 54 of the ground beam are lapped together with the vertical reinforcing bars 52 and the stirrups 53 of the wall, respectively.

[0026] The vertical reinforcing bars 52 of the wall are lapped and connected to the reserved lapped bars 54 of the ground beam. The filling of concrete 6 can greatly reduce the lap length of the reinforcing bars. The superior bonding and anchoring performance of ultra-high performance concrete 6 ensures the strength and stability of the reinforcing bar connection. Moreover, the precast concrete frame structure based on ultra-high performance concrete 6 has better seismic performance than cast-in-place concrete structure.

[0027] It should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention. The terminology used in the description of this application is only for describing specific embodiments and is not intended to limit the exemplary embodiments according to this application. For ease of description, the dimensions of the various parts shown in the drawings are not drawn to actual scale. Techniques, methods, and devices known to those skilled in the art may not be discussed in detail, but where appropriate, such techniques, methods, and devices should be considered part of the specification. In all examples shown and discussed herein, any specific values ​​should be interpreted as merely exemplary and not as limitations. Therefore, other examples of exemplary embodiments may have different values. It should be noted that similar reference numerals and letters in the following drawings indicate similar items, and therefore, once an item is defined in one drawing, it does not need to be further discussed in subsequent drawings.

[0028] It should be noted that the terms "first," "second," etc., used in the specification and claims of this application are used to distinguish similar objects and not to describe a specific order or sequence. It should be understood that such use of data can be interchanged where appropriate so that embodiments of this application can be implemented in orders other than those illustrated or described herein, and the objects distinguished by "first," "second," etc., are generally of the same class and are not limited in number; for example, a first object can be one or more. Furthermore, in the specification and claims, "and / or" indicates at least one of the connected objects, and the character " / " generally indicates that the preceding and following objects are in an "or" relationship.

[0029] It should be noted that in the description of this application, the directional terms such as "front, back, up, down, left, right", "horizontal, vertical, horizontal" and "top, bottom" indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this application and simplifying the description. Unless otherwise stated, these directional terms do not indicate or imply that the device or element referred to must have a specific orientation or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation on the scope of protection of this application. The directional terms "inner" and "outer" refer to the inner and outer contours relative to the outline of each component itself.

Claims

1. A prefabricated shear wall structure with horizontal joints and vertical connections, characterized in that, The system includes a prefabricated shear wall body, with an inverted trapezoidal groove integrally provided at the bottom of the prefabricated shear wall body. A C60 pad is integrally provided at the bottom of the inverted trapezoidal groove, and a ground beam is connected below the C60 pad. A grouting groove is provided inside the shear wall body, and the grouting groove includes reinforcing bars and surrounding filling grout, which is concrete.

2. The prefabricated shear wall structure with horizontal joint vertical connection according to claim 1, characterized in that, Each of the inverted trapezoidal tooth sockets has an integrally formed cylindrical C60 pad at the bottom of the socket, with flow space left on the left and right sides of the C60 pad.

3. The prefabricated shear wall structure with horizontal joint vertical connection according to claim 2, characterized in that, The C60 pad has a trapezoidal structure, which can effectively promote the smooth flow of concrete during grouting, prevent the formation of cavities in the dark, and effectively improve the mechanical properties of the connection.

4. The prefabricated shear wall structure with horizontal joint vertical connection according to claim 1, characterized in that, The reinforcing bars include horizontal and vertical reinforcing bars of the wall that are lapped together perpendicularly, and the reserved lapped bars of the ground beam are lapped together with the vertical reinforcing bars and stirrups of the wall respectively.

5. The prefabricated shear wall structure with horizontal joint vertical connection according to claim 1, characterized in that, The filling grout in the concrete can reduce the lap length of the reinforcing bars, and the bonding and anchoring properties of the ultra-high performance concrete ensure the strength and stability of the reinforcing bar connection.